Water_Treatment_Services-RFP_Changes.docx
DOCX document 17 KB Posted
- Attached to
- Water Treatment Services
- Solicitation number
- 26-001-ITB - Services
- Issued by
- Bell County, Kentucky
About this file
Water Treatment Services RFP Changes Document
This document presents amendments to the Water Treatment Services Request for Proposal issued by the Kenton County Airport Board (KCAB) for the Cincinnati/Northern Kentucky International Airport (CVG) in Hebron, Kentucky. The RFP solicits proposals for comprehensive water treatment services across multiple airport facilities, including professional testing, chemical provision, equipment operation and maintenance, and consulting services. The proposal deadline is February 5, 2026 at 2:00 pm Eastern Time, with questions due by January 26, 2026 at 11:59 pm and answers posted by January 29, 2026 at 11:59 pm. Interviews are scheduled for the week of February 16, 2026. The contract term runs from March 1, 2026 through February 28, 2029, with KCAB retaining options to renew for two additional one-year periods. The amendments remove certain facilities (Fire Training and KCAB Cargo Building) from service scope and provide detailed specifications for chillers, cooling towers, and water consumption data across three major facility areas: the Main Terminal Facility, Concourse B Facility, and CVG Centre Facility, with annual condenser water make-up consumption recorded at 12,472,900 gallons (Main Terminal), 1,375,000 gallons (Concourse B), and 3,127,100 gallons (CVG Centre) from August 2024 to August 2025.
The contractor must maintain a Certified Water Technologist on staff, provide certified laboratory capabilities within 24-hour travel distance, and possess at least 10 years of experience treating similar-sized hydronic systems. Required deliverables include monthly site visits, quarterly Legionella testing across 16 buildings, annual equipment inspections, staff training, and specialized laboratory analysis, supported by contractor-furnished equipment including electronic metering pumps and cloud-based monitoring applications. The contractor must provide 24/7 emergency response within four hours of notification. Insurance requirements include commercial general liability coverage ranging from $2,000,000 to $10,000,000, automobile liability, workers' compensation, and unemployment insurance, with KCAB named as an additional insured. Annual price adjustments are permitted based on the Consumer Price Index for the Cincinnati/Northern Kentucky metropolitan area, capped at three percent of the current annual contract price. Kentucky resident bidders receive statutory preference in accordance with Kentucky Revised Statutes, with preferences equal to those offered by their home state. KCAB affirms compliance with Title VI of the Civil Rights Act of 1964 and commitment to full and fair opportunity for disadvantaged business enterprises.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Water_Treatment_Services.pdf | ||
| System_Requirements.xlsx | XLSX spreadsheet | |
| Equipment_&_Systems_by_Building.docx | DOCX document | |
| Proposed_Water_Treatment_Services_Contract.pdf | ||
| Notice_to_Bidders.pdf | ||
| KCAB_Water_Management_Program.pdf | ||
| Water_Treatment_Services-RFP_Changes.docx | DOCX document | |
| Resident_&_Non-Resident_Bidder_Affidavits.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Water Treatment Services B.1.18 Remove Fire Training and KCAB Cargo Bldg. from list C.1.2 Main Terminal Facility Chiller Plant Review Chiller York 1300-ton water cooled chiller, 3,995 lbs. of R-134a water cooled chiller, Condenser flow 3,900 GPM @17.6’, in 85ºF out 94.3ºF Evaporator flow 1,950 @ 10.9’, in 57ºF, out 41ºF York 1300-ton, 1958 lbs. of R-134a water cooled chiller, Condenser flow 6,000 GPM @ 25’, in 85ºF out 94.6ºF- Evaporator flow 3,000 @ 22’, in 57ºF out 41ºF Cooling Towers Cells CT-1 to CT-4 – induvial cells – Marley cooling tower, Cross flow pattern, 2,000 GPM, entering water 95ºF, exiting water 85ºF with a wet bulb of 78ºF. Cell CT-5 – induvial cells – Marley cooling tower, Cross flow pattern, 2,295 GPM, entering water 95ºF, exiting water 85ºF with a wet bulb of 78ºF.
C.1.3 Remove, there is no plate and frame there C.1.4 Airport Chilled Water Production This is the primary facility used to supply chilled water to the airport central chilled water system. The airport utilizes a water side economizer due to the exhaust from the planes which encircle the buildings.
41ºF to 75ºF outdoor air temperature: The chilled water is supplied by a 1,300-ton chiller to produce the needed chilled water.
75ºF to 95ºF outdoor air temperature: The chilled water is supplied by one or two 1300-ton chillers to produce the needed chilled water.
C.1.5 Condenser Water Annual Make-up Water Consumption The Main Terminal condenser water make-up from August 2024 until August 2025 was recorded on the airport meter as consuming 12,472,900 gallons of water.
C.1.6 Central Chiller Water Annual Make-Up Water Consumption The Main Terminal is the only central chilled water system make-up point for the facility. From August 2024 until August 2025 the make-up water consumption was recorded on the airport meter as 20,230 gallons of water.
C.2.2 Preconditioned Air System York 400-ton air cooled chiller, 685 lbs. of R134a C.2.3 Remove, there is no Condenser Water makeup in A con C.3.2 Concourse B Facility Chiller Plant Review 2- Carrier 400-ton chillers R134a – (these chillers are for the PCA system but share the cooling towers with the 2500-ton chiller) Condenser Flow 1,200 GPM Evaporator Flow 1,185 GPM York 2500-ton chiller R134a Condenser 6,000 GPM Evaporator 3,750 GPM C.3.4 Remove, there is no plate and frame.
C.3.5 Airport Chilled Water Production Concourse “B” chiller plant and cooling tower are used as a back-up chilled water plant in the event of a Terminal 3 chiller has an outage or failure.
76°F to 95°F outdoor air temperature the chilled water is supplied by a 2,500-ton chiller to produce the needed chilled water.
C.3.6 Condenser Water Annual Make-Up Water Consumption The Concourse “B” condenser water make-up from August 2024 until August 2024 was recorded on the airport meter as consuming 1,375,000 gallons of water C10.2 CVG Centre Facility Chiller Plant Equipment Chillers 2-York 450 ton, 930 lbs. each of R-134a water cooled chiller, Condenser flow 1,350 GPM @ 18.7’, in 85ºF out 94.1ºF, Evaporator flow 900 @ 23.1’, in 57ºF out 45ºF.
Cooling Towers 2-Marley 450-ton, Gear drive tower fan on a VFD, Condenser flow 1,350, in 94.1ºF out 85ºF.
Cooling Towers Sump under Towers The approximate dimensions are 14’ wide by 48’ long with a normal pool depth of 6’.
The make-up water is added at 5’ and stopped at 7’. The approximate volume of the cooling tower sump is 30,000 gallons.
CVG Centre Chilled Water Production:
CVG Centre chiller plant and cooling tower are a standalone chilled water plant located in the lower level of the CVG Centre.
55ºF and below outdoor air temperature The office facilities utilize an air-side economizer to provide the needed chilled water. This facility computer room utilizes a glycol loop and dry-coolers to provide the needed cooling to the Package Air Condition units.
56ºF to 95ºF outdoor air temperature The chilled water is supplied by one 450-ton chiller to produce the needed chilled water.
Condenser water annual make-up water consumption The CVG Centre condenser water make-up from August 2024 until August 2025 was recorded on the airport meter as consuming 3,127,100 gallons of water