Waste Diversion Plan.xlsx
XLSX spreadsheet 20 KB Posted
- Attached to
- 32214 Chavez Switchgear Replacement Albuquerque, NM Federal contract opportunity
- Solicitation number
- 47PH0622R0018
About this file
This document contains a federal contract opportunity notice and related project file. The General Services Administration, Public Buildings Service is seeking a construction contractor to replace electrical switchgear at the Dennis Chavez Federal Building in Albuquerque, New Mexico for between $1 million to $5 million. The project includes design and replacement of the main 3000A 277/480V electrical gear in the basement, removing plaza drains above the switchgear room, adding a new tapered insulation and waterproofing system, and demolishing and replacing the existing switchgear egress door and sink. The contractor must be a general construction firm under NAICS 238210 with a size standard of $16.5 million. The project is anticipated to take 210 calendar days from notice to proceed and will require work in an occupied federal courthouse with minimal disruptions. This is a 100% service-disabled veteran-owned small business set-aside solicitation, with the proposal due date of June 24, 2022 and a pre-proposal conference scheduled for June 6, 2022. Prospective contractors must register in the System for Award Management and monitor the solicitation website for any amendments.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF30 Amendment 05.pdf | ||
| SF30 Amendment 04.pdf | ||
| SF30 Amendment 03.pdf | ||
| SF30 Amendment 02.pdf | ||
| SF30 Amendment 01.pdf | ||
| Drawing 8.pdf | ||
| Drawing 3.pdf | ||
| GSA527.pdf | ||
| Project Manual 101920.pdf | ||
| Drawing 12.pdf | ||
| Past Performance Questionnaire.pdf | ||
| Drawing 11.pdf | ||
| Drawing 10.pdf | ||
| Drawing 9.pdf | ||
| Drawing 2.pdf | ||
| SF1442 47PH0622R0018.pdf | ||
| Drawing 13.pdf | ||
| Drawing 7.pdf | ||
| Drawing 6.pdf | ||
| Drawing 5.pdf | ||
| Drawing 4.pdf | ||
| Drawing 1.pdf | ||
| Bid Schedule Template.xlsx | XLSX spreadsheet | |
| Vendor Fitness Determination Training Manual.pdf |
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Waste Diversion Plan
: +christopher.clever@gsa.gov +walter.tersch@gsa.gov
(For consideration as an alternate). Anticipated sections match Actual to the right for 1:1 comparison.
-Jake Begnaud - WPIDBB Fine with either, will defer to +walter.tersch@gsa.gov Seems like it only boils down to estimating method or not.
-Christopher Clever - PCBL That's correct.
| -Jake Begnaud - WPIDBB | Project Waste Management Plan | Submittal Type: | Waste Diversion Plan (Anticipated): | Waste Diversion Report (Final) : | |||
| The general info in these gray cells replicates onto the Report tabs. | |||||||
| Project Name: | Chavez Switchgear Replacement | ECC (estimated construction cost): | Project Manager: | SethSutherland | ePM/ePMX Project # : | 32214 | |
| Project Short Description: | PM email or phone: | seth.sutherland@gsa.gov | gBUILD Project # : | NA | |||
| Building Number: | Service Center / Field Office: | Budget Activity: | (list all applicable) | RWA # : | NA |
Anticipated Waste Diversion Plan To be filled out and submitted Pre-Construction, with final Construction Documents (PM or contractor populates this pink section) Actual Waste Diversion Report To be submitted during Project Close-Out (Reports tab figures auto-populate this green section)
| Material* | |||||
| (see weight conversion factors below) | Diversion Method | Target Diversion Rate for each material, by weight | |||
| (Change to actual target(s) as needed) | Diverted (lbs) | Landfilled (lbs) | Total C&D material weight (Diverted + Landfilled) (lbs) | Diversion |
Rate
| Reuse* | Recycle or Compost | Donation | ||||||
| Asphalt | 50% | 0 | 0 | 0 | n/a | |||
| Brick, Masonry, and Tile | 50% | 0 | 0 | 0 | n/a | |||
| Cardboard | 50% | 0 | 0 | 0 | n/a | |||
| Carpet, including Padding | 50% | 0 | 0 | 0 | n/a | |||
| Ceiling tile | 50% | 0 | 0 | 0 | n/a | |||
| Concrete | 50% | 0 | 0 | 0 | n/a | |||
| Drywall/ sheetrock (unpainted) | 50% | 0 | 0 | 0 | n/a | |||
| Metals | 50% | 0 | 0 | 0 | n/a | |||
| Painted wood, drywall, or plywood | 50% | 0 | 0 | 0 | n/a | |||
| Reusable items | 50% | 0 | 0 | 0 | n/a | |||
| Roofing | 50% | 0 | 0 | 0 | n/a | |||
| Soil, Rock, Land Clearing Debris | 50% | 0 | 0 | 0 | n/a | |||
| Wood (unpainted) | 50% | 0 | 0 | 0 | n/a | |||
| Other: ____________________ | 50% | 0 | 0 | 0 | n/a | |||
| Other: ____________________ | 50% | 0 | 0 | 0 | n/a | |||
| Other: ____________________ | 50% | 0 | 0 | 0 | n/a | |||
| Total**: | 0 | 0 | 0 | n/a |
| Reuse is encouraged. Please list any items such as cabinets, doors, shelves, bricks, framing lumber, siding, fill material, misc. millwork, etc. planned for reuse. | |||
| Item | Reuse Onsite | Reuse Offsite | Off-Site Recipient or Salvage/ Deconstruction Company |
| Volume-to-Weight Conversion Factor Reference Table |
| If a hauler reports materials by volume, this table enables conversion to weight, for reporting actual diversion and disposal. |
| Asphalt paving: 1 cubic yard = 773 lbs | Dirt or sand: 1 cubic yard = 929 lbs |
| Asphalt or composite roof shingles: 1 cubic yard = 731 lbs | Fiberglass insulation, loose: 1 cubic yard = 17 lbs |
| Brick, laid flat: 1 flat square foot = 20 lbs | Mixed (composite) C&D material: 1 cubic yard = 417 lbs |
| Brick, loose: 1 cubic yard = 3,200 lbs. (1 cubic foot = 120 lbs) | Sheetrock (drywall), loose: 1 cubic yard = 393.5 lbs |
| Ceramic tile, scrap, loose: 1 cubic yard = 1,214 lbs | Rock, crushed: 1 cubic yard = 2,570 lbs |
| Concrete: 1 cubic yard = 860 lbs | Wood: 1 cubic yard = 169 lbs |
| *Only non-hazardous materials need to be included in this document. C&D mandates governing GSA exclude hazardous materials such as asbestos or lead-containing paint. |
| **At substantial completion, the final number of (a) diverted tons, and (b) total non-hazardous C&D material tons must be reported via the ePMXpress Project Detail tab. ePMXpress powers GSA's tracking metrics. |