This document is a Davis-Bacon Wage Determination for highway construction projects in Alaska, effective January 3, 2025. The wage determination establishes minimum hourly wage rates for various construction worker classifications across different regions of Alaska, with rates varying by job type and location. Key wage provisions include: Executive Order 14026 requires contractors to pay at least $17.75 per hour for contracts entered into on or after January 30, 2022, while Executive Order 13658 requires $13.30 per hour for contracts awarded between January 1, 2015 and January 29, 2022. The document provides detailed wage rates for workers such as carpenters ($43.34/hour), cement masons ($44.43/hour), electricians ($44.44/hour), and multiple laborer classifications with rates ranging from $36.00 to $47.36 per hour, depending on specific job responsibilities and geographic location within Alaska.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
"General Decision Number: AK20250002 01/03/2025
Superseded General Decision Number: AK20240002
State: Alaska
Construction Type: Highway
Counties: Alaska Statewide.
HIGHWAY CONSTRUCTION PROJECTS
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).
|If the contract is entered |� Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |� The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $17.75 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2025. | |If the contract was awarded on|� Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |� The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $13.30 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours performing on that | | | contract in 2025. |
The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.
Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/03/2025
SUAK2023-001 08/08/2022
Rates Fringes
CARPENTER
North of 63 Latitude........$ 43.34 27.92 South of N63 Latitude.......$ 43.34 28.46
CEMENT MASON/CONCRETE FINISHER...$ 44.43 22.13
ELECTRICIAN
Inside Journeyman Wireman (Technician)................$ 44.44 29.72
IRONWORKER
Fence Barrier Installer.....$ 37.99 35.63 Guardrail Installer.........$ 38.99 35.63 Guardrail Layout Man........$ 38.73 35.63 Signalman, Stage Rigger, Structural, Ornamental, and Reinforcing.............$ 41.49 35.63
LABORER (North of N 63 Latitude and east of W138 longitude) Group 1.....................$ 36.00 32.56 Group 2.....................$ 37.00 32.56 Group 3.....................$ 37.90 32.56 Group 3A....................$ 41.78 32.56 Group 3B....................$ 47.36 28.51
LABORERS CLASSIFICATIONS
GROUP 1: Asphalt Worker (shoveler, plant crew); Brush Cutter;
Carpenter Tender; Choke Setter, Hook Tender, Rigger, Signaler;
Concrete Labor (curb & gutter, chute handler, curing, grouting, screeding); Crusher Plant Laborer; Demolition Laborer; Ditch Digger; Dumper; Environmental Laborer (hazard/toxic waste, oil spill); Fence Installer; Fire Watch Laborer;
Flagger; Form Stripper; General Laborer; Guardrail Laborer, Bridge Rail Installer; Hydro-seeder Nozzle person; Landscaper or Planter; Laying of Mortarless Decorative Block (retaining walls, flowered decorative block 4 feet or less - highway or landscape work); Material Handler; Pneumatic or Power Tools;
Portable or Chemical Toilet Servicer; Pump Person or Mixer Person; Railroad Track Laborer; Sandblast, Pot Tender; Saw Tender; Slurry Work; Steam Cleaner Operator; Steam Point or Water Jet Operator; Storm Water Pollution Protection Plan Worker (SWPPP Worker-erosion and sediment control Laborer);
Tank Cleaning; Utiliwalk & Utilidor Laborer
GROUP 2: Burning & Cutting Torch; Cement or Lime Dumper or Handler (sack or bulk); Choker Splicer; Chucktender (wagon, air-track & hydraulic drills); Concrete Laborer (power buggy, concrete saws, pumpcrete nozzle person, vibrator person);
Culvert Pipe Laborer; Cured In place Pipelayer; Environmental Laborer (asbestos, marine work); Foam Gun or Foam Machine Operator; Gunite Operator; Hod Carrier; Jackhammer/Chipping Gun or Pavement Breaker; Laser Instrument Operator; Laying of Mortarless Decorative Block (retaining walls, flowered decorative block over 4 feet - highway or landscape work);
Mason Tender & Mud Mixer (sewer work); Pilot Car; Plasterer, Bricklayer & Cement Finisher Tender; Power Saw Operator; Railroad Switch Layout Laborer;
Sandblaster; Scaffold Building & Erecting; Sewer Caulker;
Thermal Plastic Applicator; Timber Faller, Chainsaw Operator, Filer; Timber person
GROUP 3: Bit Grinder; Camera/Tool/Video Operator; Guardrail Machine Operator; High Rigger & Tree Topper; High Scaler;
Multiplate; Plastic Welding; Slurry Seal Squeegee Person
GROUP 3A: Asphalt Raker, Asphalt Belly Dump Lay Down; Drill Doctor (in the field); Driller (including, but not limited to wagon drills, air-track drills, hydraulic drills); Pioneer Drilling & Drilling Off Tugger (all type drills); Pipelayers;
Powder person (Employee Possessor); Storm Water Pollution Protection Specialist (SWPPP Specialist)
GROUP 3B: Driller (including, but not limited to wagon drills, air-track drills, hydraulic drills; over 5,000 hours); Grade Checking (setting or transferring of grade marks, line and grade, GPS, drones); Pioneer Drilling & Drilling Off Tugger (all types of drills; over 5,000 hours);
Stake Hopper
LABORER (South of N 63 Latitude and west of W138 longitude) Group 1.....................$ 36.00 32.56 Group 2.....................$ 37.00 32.56 Group 3.....................$ 37.90 32.56 Group 3A....................$ 41.78 32.56 Group 3B....................$ 47.36 28.51
LABORERS CLASSIFICATIONS
GROUP 1: Asphalt Worker (shoveler, plant crew); Brush Cutter;
Carpenter Tender; Choke Setter, Hook Tender, Rigger, Signaler;
Concrete Labor (curb & gutter, chute handler, curing, grouting, screeding); Crusher Plant Laborer; Demolition Laborer; Ditch Digger; Dumper; Environmental Laborer (hazard/toxic waste, oil spill); Fence Installer; Fire Watch Laborer;
Flagger; Form Stripper; General Laborer; Guardrail Laborer, Bridge Rail Installer; Hydro-seeder Nozzle person; Landscaper or Planter; Laying of Mortarless Decorative Block (retaining walls, flowered decorative block 4 feet or less - highway or landscape work); Material Handler; Pneumatic or Power Tools;
Portable or Chemical Toilet Servicer; Pump Person or Mixer Person; Railroad Track Laborer; Sandblast, Pot Tender; Saw Tender; Slurry Work; Steam Cleaner Operator; Steam Point or Water Jet Operator; Storm Water Pollution Protection Plan Worker (SWPPP Worker-erosion and sediment control Laborer);
Tank Cleaning; Utiliwalk & Utilidor Laborer
GROUP 2: Burning & Cutting Torch; Cement or Lime Dumper or Handler (sack or bulk); Choker Splicer; Chucktender (wagon, air-track & hydraulic drills); Concrete Laborer (power buggy, concrete saws, pumpcrete nozzle person, vibrator person);
Culvert Pipe Laborer; Cured In place Pipelayer; Environmental Laborer (asbestos, marine work); Foam Gun or Foam Machine Operator; Gunite Operator; Hod Carrier; Jackhammer/Chipping Gun or Pavement Breaker; Laser Instrument Operator; Laying of Mortarless Decorative Block (retaining walls, flowered decorative block over 4 feet - highway or landscape work);
Mason Tender & Mud Mixer (sewer work); Pilot Car; Plasterer, Bricklayer & Cement Finisher Tender; Power Saw Operator; Railroad Switch Layout Laborer;
Sandblaster; Scaffold Building & Erecting; Sewer Caulker;
Thermal Plastic Applicator; Timber Faller, Chainsaw Operator, Filer; Timber person
GROUP 3: Bit Grinder; Camera/Tool/Video Operator; Guardrail
Machine Operator; High Rigger & Tree Topper; High Scaler;
Multiplate; Plastic Welding; Slurry Seal Squeegee Person
GROUP 3A: Asphalt Raker, Asphalt Belly Dump Lay Down; Drill Doctor (in the field); Driller (including, but not limited to wagon drills, air-track drills, hydraulic drills); Pioneer Drilling & Drilling Off Tugger (all type drills); Pipelayers;
Powder person (Employee Possessor); Storm Water Pollution Protection Specialist (SWPPP Specialist)
GROUP 3B: Driller (including, but not limited to wagon drills, air-track drills, hydraulic drills; over 5,000 hours); Grade Checking (setting or transferring of grade marks, line and grade, GPS, drones); Pioneer Drilling & Drilling Off Tugger (all types of drills; over 5,000 hours);
Stake Hopper
LINE CONSTRUCTION
Line Installer..............$ 50.78 33.42 Powderperson................$ 61.44 34.53 Power Journeyworker Line (including Equipment Operator)...................$ 63.44 34.59 Tree Trimmer................$ 40.71 29.27
PAINTER (Region 1: North of N 63 Latitude) Brush and Roller............$ 36.08 25.45 Sandblast and Spray.........$ 36.60 25.45
PAINTER (South of N 63 Latitude) Brush, Roll and Spray.......$ 33.22 26.30 Sandblast and Structural Steel Painter...............$ 34.57 26.30
PILEDRIVER PERSON
Piledriver, Sheet Stabber...$ 43.34 27.92 Piledriver-Welder...........$ 48.90 27.92
PLUMBER/PIPEFITTER (First Judicial District)...............$ 41.50 28.12
PLUMBER/PIPEFITTER (North of N 63 Latitude)...................$ 46.06 30.70
PLUMBER/PIPEFITTER (South of N 63 Latitude)...................$ 41.00 28.70
POWER EQUIPMENT OPERATOR
Group 1.....................$ 47.74 27.15 Group 1A....................$ 49.64 27.15 Group 2.....................$ 46.91 27.15 Group 3.....................$ 46.13 27.15 Group 4.....................$ 39.42 27.15
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
Group 1: Asphalt Roller: Breakdown, Intermediate, and Finish;
Back Filler; Barrier Machine (Zipper); Beltcrete with Power Pack & similar conveyors; Bending Machine; Boat Coxswain;
Bulldozer; Cableways, Highlines & Cablecars; Cleaning Machine;
Coating Machine; Concrete Hydro Blaster; Cranes (45 tons & under or 150 feet of boom & under (including jib & attachments)), (a) Hydralifts or Transporters, (all track or truck type), (b) Derricks, (c) Overhead; Crushers; Deck Winches, Double Drum; Ditching or Trenching Machine (16 inch or over); Drag Scraper, Yarder, and similar types; Drilling Machines, Core, Cable, Rotary and Exploration; Finishing Machine Operator, Concrete Paving, Laser Screed, Sidewalk, Curb & Gutter Machine; Grade Checker and/or Line and Grade including Drone; Helicopters; Hover Craft, Flex Craft, Loadmaster, Air Cushion, All-Terrain Vehicle, Rollagon, Bargecable, Nodwell, & Snow Cat; Hydro Ax, Feller Buncher & similar; Hydro Excavation (Vac-Truck and Similar); Loaders (2 1/2 yards through 5 yards, including all attachments): (a) Forklifts (with telescopic boom & swing attachment), (b) Front End & Overhead, (2-1/2 yards through 5 yards), (c) Loaders, (with forks or pipe clamp), (d) Loaders, elevating belt type, Euclid & similar types); Material Transfer Vehicle (Elevating Grader, Pickup Machine, and similar types);
Mechanic, Bodyperson, Electrical; Micro Tunneling Machine;
Mixers: Mobile type with hoist combination; Motor Patrol Grader; Mucking Machine: Mole, Tunnel Drill, Horizontal/Directional Drill Operator and/or Shield; Off-Road Hauler (including Articulating and Haul Trucks); Operator on Dredges; Piledriver Engineer, L.B. Foster, Puller or similar paving breaker; Plant Operator (Asphalt & Concrete); Power Plant, Turbine Operator 200 k.w & over (power plants or combination of power units over 300 k.w.); Remote Controlled Equipment; Scraper (through 40 yards); Service Oiler/Service Engineer; Shot Blast Machine; Shovels, Backhoes, Excavators with all attachments, and Gradealls (3 yards & under);
Sideboom (under 45 tons); Sub Grader (Gurries & similar types); Tack Tractor; Truck Mounted Concrete Pump, Conveyor/Tele-belt, & Creter; Wate Kote Machine
Group 1A: Camera/Tool/Video Operator (Slipline); Electrical Mechanic, Mechanic (over 10,000 hours); Cranes (over 45 tons or 150 feet including jib & attachments) (a) Clamshells & Draglines (over 3 yards), (b) Tower Cranes; Licensed Water/Waste Water Treatment Operator; Loaders (over 5 yards);
Motor Patrol Grader, Dozer, Grade Tractor (finish: when finishing to final grade and/or to hubs, or for asphalt);
Power Plants (1000 k.w. & over); Profiler, Reclaimer, and Roto- Mill; Quad; Scrapers (over 40 yards); Screed; Shovels, Backhoes, Excavators with all attachments (over 3 yards);
Sidebooms (over 45 tons); Slip Form Paver, C.M.I. & similar types; Topside (Asphalt Paver, Slurry machine, Spreaders, and similar types)
Group 2: Boiler ? Fireperson; Cement Hogs & Concrete Pump Operator; Conveyors (except those listed in Group I); Hoists on Steel Erection, Towermobiles & Air Tuggers;
Horizontal/Directional Drill Locator; Locomotives, Rod & Geared Engines; Mixers; Screening, Washing Plant; Sideboom (cradling rock drill, regardless of size); Skidder; Trenching Machines (under 16 inches); Water/Waste Water Treatment Operator
Group 3: ""A"" Frame Trucks, Deck Winches; Bombardier (tack or tow rig); Boring Machine; Brooms, Power (sweeper, elevator, vacuum, or similar); Bump Cutter; Compressor; Farm Tractor;
Forklift, Industrial Type; Gin Truck or Winch Truck (with poles when used for hoisting); Hoists, Air Tuggers, Elevators;
Loaders: (a) Elevating-Athey, Barber Greene & similar types,
(b) Forklifts or Lumber Carrier (on construction job sites),
(c) Forklifts, (with tower), (d) Overhead & Front End, (under 2-l/2 yards); Locomotives: Dinkey (air, steam, gas & electric) Speeders; Mechanics, Light Duty; Oil, Blower Distribution;
Posthole Digger, Mechanical; Pot Fireperson (power agitated);
Power Plant, Turbine Operator, (under 200 k.w.); Pumps, Water;
Roller (other than Asphalt); Saws, Concrete; Skid Hustler; Skid Steer (with all attachments); Stake Hopper; Straightening Machine; Tow Tractor
Group 4: Crane Assistant Engineer/Rig Oiler; Parts & Equipment Coordinator; Spotter; Steam Cleaner; Swamper (on trenching machines or shovel type equipment)
TRUCK DRIVER
Group 1.....................$ 46.84 27.32 Group 1A....................$ 48.19 27.32 Group 2.....................$ 45.51 27.32 Group 3.....................$ 44.64 27.32 Group 4.....................$ 44.02 27.32 Group 5.....................$ 43.22 27.32 Group 1: Air/Sea Traffic Controllers; Boat Coxswain; Captains & Pilots (air & water); Deltas, Commanders, Rollagons, & similar equipment (when pulling sleds, trailers or similar equipment); Dump Trucks (including rockbuggy, side dump, belly dump, & trucks with pups) over 40 yards up to & including 60 yards; Fueler; Helicopter Transporter; Liquid Vac Truck/Super Vac Truck; Material Coordinator or Purchasing Agent; Oil Distributor Truck; Ready-mix (over 12 yards up to & including 15 yards) (over 15 yards to be negotiated); Semi with Double Box Mixer; Tireperson, Heavy Duty/Fueler; Water Wagon (250 Bbls and above) Group 1A: Dump Trucks (including rockbuggy, side dump, belly dump & trucks with pups) over 60 yards up to & including 100 yards (over 100 yards to be negotiated); Jeeps (driver under load); Lowboys, including tractor attached trailers & jeeps, up to & including 12 axles (over 12 axles or 150 tons to be negotiated); Tireperson Heavy Duty (earthmover tires, i.e.
loader, scraper, haul truck)
Group 2: All Deltas, Commanders, Rollagons, & similar equipment; Batch Trucks (8 yards & up); Batch Trucks (up to & including 7 yards); Boom Truck/Knuckle Truck (over 5 tons);
Cacasco Truck/Heat Stress Truck; Construction and Material Safety Technician; Dump Trucks (including articulating end dump, rockbuggy, side dump, belly dump, & trucks with pups) over 20 yards up to & including 40 yards; Gin Pole Truck, Winch Truck, Wrecker (truck mounted ""A"" frame manufactured rating over 5 tons); Mechanics; Partsperson; Ready-mix (up to & including 12 yards); Stringing Truck; Turn-O-Wagon or DW-10 (not self loading)
Group 3: Boom Truck/Knuckle Truck (up to & including 5 tons);
Dump Trucks (including articulating end dump, rockbuggy, side dump, belly dump, & trucks with pups) over 10 yards up to & including 20 yards; Expeditor (electrical & pipefitting materials); Gin Pole Truck, Winch Truck, Wrecker (truck mounted ""A"" frame manufactured rating 5 tons & under); Greaser ? Shop; Semi or Truck & Trailer; Thermal Plastic Layout Technician; Traffic Control Technician; Trucks/Jeeps (push or pull)
Group 4: Air Cushion or similar type vehicle; All Terrain Vehicle; Buggymobile; Bull Lift & Fork Lift, Fork Lift with Power Boom & Swing Attachment (over 5 tons); Bus Operator (over 30 passengers); Cement Spreader, Dry; Combination Truck- Fuel & Grease; Compactor (when pulled by rubber tired equipment); Dump Trucks (including rockbuggy, side dump, belly dump, & trucks with pups) up to & including 10 yards;
Dumpster; Expeditor (general); Flat Beds, Dual Rear Axle; Foam
Distributor Truck Dual Axle; Front End Loader with Fork;
Grease Truck; Hydro Seeder, Dual Axle; Hyster Operators (handling bulk aggregate); Loadmaster (air & water operations); Lumber Carrier; Ready-mix, (up to & including 7 yards); Rigger (air/water/oilfield); Tireperson, Light Duty;
Track Truck Equipment; Truck Vacuum Sweeper; Warehouseperson;
Water Truck (Below 250 Bbls); Water Truck (straight); Water Wagon, Semi
Group 5: Buffer Truck; Bull Lifts & Fork Lifts, Fork Lifts with Power Boom & Swing; Attachments (up to & including 5 tons); Bus Operator (up to 30 passengers); Farm Type Rubber Tired Tractor (when material handling or pulling wagons on a construction project); Flat Beds, Single Rear Axle; Foam Distributor Truck Single Axle; Fuel Handler (station/bulk attendant); Gear/Supply Truck; Gravel Spreader Box Operator on Truck; Hydro Seeder, Single axle; Pickups (pilot cars & all light-duty vehicles); Rigger; Swamper; Tack Truck; Team Drivers (horses, mules, & similar equipment)
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)).
The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.
Union Rate Identifiers
A four-letter identifier beginning with characters other than
""SU"", ""UAVG"", ?SA?, or ?SC? denotes that a union rate was prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.
0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.
Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification.
Union Average Rate Identifiers
The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE:
UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio.
The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.
A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.
Survey Rate Identifiers
The ""SU"" identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007 6/27/2024. SU indicates the rate is a single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier.
?SU? wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1).
State Adopted Rate Identifiers
The ""SA"" identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007 01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.
The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the ?SA? identifier took effect under state law in the state from which the rates were adopted.
WAGE DETERMINATION APPEALS PROCESS
1) Has there been an initial decision in the matter? This can be:
a) a survey underlying a wage determination
b) an existing published wage determination
c) an initial WHD letter setting forth a position on a wage determination matter
d) an initial conformance (additional classification and rate) determination
On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of Wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mail to:
Branch of Wage Surveys Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations.
Requests can be submitted via email to BCWD-Office@dol.gov or by mail to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).
Requests for review and reconsideration can be submitted via email to dba.reconsideration@dol.gov or by mail to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210.
END OF GENERAL DECISION"