EXHIBIT 2 - PROPOSED RD Notes and Details.pdf
PDF 274 KB Posted
- Attached to
- BGQ VORTAC Road Repair (Big Lake)
- Solicitation number
- 697DCK-25-R-00304
About this file
This document is a technical drawing exhibit detailing proposed roadway construction notes and details for a Federal Aviation Administration (FAA) project in Alaska. The drawing provides comprehensive technical specifications for roadway construction, including typical roadway section materials, construction and demolition notes, and grading requirements. Key technical details include geotextile placement, surface course specifications, erosion control measures, utility protection protocols, and specific guidelines for grading, drainage, and fill materials. The drawing includes precise instructions for contractors regarding site preparation, utility protection, safety standards, material storage, debris management, and maintaining existing site conditions during construction. The technical notes emphasize verifying existing conditions, maintaining proper drainage, and ensuring uniform grading with specific elevation and gap tolerances for roadway and fencing installations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
$F
IL
ES
$D
AT
E$ $T
IM
E$
$N
AM
E$
A
B
C
D
E
F
G
H
8 7 6 5 4 3 2 1
H
G
F
E
D
C
12345678
REVDRAWING NO
DATE JCN
APPROVED BY
ISSUED BY
CHECKED
DRAWN
DESIGNED
SUBMITTED BY
REVIEWED BY
FEDERAL AVIATION ADMINISTRATION
DEPARTMENT OF TRANSPORTATION
REV APPROVED
DATE DESCRIPTION JCN REDLINE
DATE APVD
A
8" SURFACE COURSE
18" BASE COURSE
EXISTING SUBGRADE COMPACTED TO
REACH PROCTOR DENSITY OF 95% PER
ASTM D698
PROPOSED ROADWAY MATERIALS SECTION (TYP)
NOT TO SCALE
GENERAL NOTES:
1. FIELD VERIFY ALL DIMENSIONS, MEASUREMENTS, STRUCTURES, PROJECT BOUNDARIES, AND
LAYOUT BEFORE PROCEEDING WITH THE WORK TO AVOID UNREASONABLE DELAYS TO THE
PROJECT SCHEDULE. INFORMATION CONTAINED WITHIN THESE DRAWINGS WITH REGARD TO
EXISTING CONDITIONS IS PROVIDED FOR THE CONVENIENCE OF THE CONTRACTOR. ALL
ATTEMPTS HAVE BEEN MADE TO ACCURATELY REPRESENT THE EXISTING BUILDING AND AREAS
SURROUNDING THE PROJECT AREA PER FAA EXISTING AS-BUILTS AND FIELD VERIFICATION.
2. ANY DISCREPANCIES FOUND BETWEEN THE DRAWINGS AND SPECIFICATIONS AND SITE
CONDITIONS OR ANY INCONSISTENCIES OR AMBIGUITIES IN THE DRAWINGS OR
SPECIFICATIONS SHALL BE IMMEDIATELY REPORTED TO THE CONTRACTING OFFICER'S
REPRESENTATIVE (COR) IN WRITING. THE COR WILL CORRECT SUCH INCONSISTENCIES OR
AMBIGUITIES IN WRITING. DO NOT PERFORM WORK BEFORE VERIFICATION AND AFTER
DISCOVERY OF SUCH INCONSISTENCIES OR AMBIGUITIES WITHOUT THE COR AUTHORIZATION .
ANY WORK DONE AFTER DISCOVERY OF SUCH DISCREPANCIES WITHOUT REPRESENTATIVE'S
PRIOR AUTHORIZATION WILL BE CONSIDERED TO BE DONE AT RISK.
3. LOCATE AND PROTECT ALL UTILITIES, LANDSCAPING, TREES, PERMANENT STRUCTURES, AND
ANY OTHER EXISTING INFRASTRUCTURE THAT ARE NOT OF RECORD OR SHOWN ON THE PLANS.
ANY DAMAGES TO PREVIOUSLY MENTIONED ELEMENTS DURING CONSTRUCTION SHALL BE
IMMEDIATELY REPAIRED OR REPLACED AT THE CONTRACTOR'S EXPENSE. UNLESS APPROVED
BY THE COR, REPAIRS OR REPLACEMENTS SHALL BE MADE TO A CONDITION EQUAL TO OR
BETTER THAN THE EXISTING AND APPROVED BY THE COR.
4. THE CONTRACTOR SHALL OBTAIN ANY REQUIRED PERMITS FOR CONSTRUCTION PRIOR TO THE
START OF CONSTRUCTION.
5. DESIGN, CONSTRUCT, AND MAINTAIN ALL SAFETY DEVICES. SAFETY DEVICES SHALL CONFORM
TO ALL LOCAL, STATE. AND FEDERAL SAFETY AND HEALTH STANDARDS, LAWS, AND
REGULATIONS.
6. EXISTING VEHICULAR ACCESS TO THE SITE SHALL BE KEPT IN SERVICES DURING THE COURSE
OF CONSTRUCTION UNLESS OTHERWISE AGREED UPON DURING THE PRE-CONSTRUCTION
CONFERENCE. A PLAN SHOWING THE PROPOSED LOCATIONS OF STAGING, STORAGE OF
MATERIALS, AND VEHICLES ON SITE TO BE SUBMITTED TO THE COR FOR REVIEW, COMMENT,
AND/OR APPROVAL PRIOR TO THE START OF CONSTRUCTION. DUE TO THE LIMITED SPACE ON
SITE, COORDINATE WITH THE COR FOR ADDITIONAL AREAS REQUIRED FOR MATERIAL AND
EQUIPMENT STORAGE.
7. STAGING AND STORAGE OF CONSTRUCTION MATERIAL AND EQUIPMENT SHALL BE LIMITED TO
THE CONSTRUCTION STAGING AREA. CONSTRUCTION STAGING AND PARKING AREA SHALL BE
DETERMINED AT THE PRE-CONSTRUCTION CONFERENCE. MATERIALS SHALL BE NEATLY
STORED AND PROTECTED AT ALL TIMES. UPON COMPLETION OF WORK, RESTORE AREAS BACK
TO ITS ORIGINAL PRE-CONSTRUCTION CONDITION. THIS SHALL INCLUDE ANY AREAS OUTSIDE
OF THE STAGING AND STORAGE AREAS USED FOR CONSTRUCTION ACTIVITIES AND
MOVEMENTS.
8. PROVIDE SANITARY TOILET FACILITIES WITH WATER FOR THE WORKERS AND COR. ENSURE
FACILITIES ARE PROPERLY SECURE TO WITHSTAND WEATHER AND CONSTRUCTION ACTIVITIES.
9. PROVIDE ENCLOSED DUMPSTERS FOR DISPOSAL OF CONSTRUCTION DEBRIS WITHIN THE AREA
DESIGNATED BY THE COR AT THE PRE-CONSTRUCTION CONFERENCE. THE AREA AROUND THE
DUMPSTERS SHALL BE KEPT CLEAN AND FREE OF EXCESS DEBRIS AND DUST DURING
CONSTRUCTION. ALL DEBRIS SHALL BE REMOVED. ANY WASTE THAT CAN ATTRACT WILDLIFE
SHALL BE REMOVED FROM THE SITE DAILY. FAA DUMPSTERS SHALL NOT BE USED.
CONSTRUCTION DEBRIS MUST BE REMOVED DAILY.
10. SHUTDOWN AND CUTOVERS OF ENVIRONMENT AND ELECTRICAL SYSTEMS SHALL BE
PERFORMED BY FAA PERSONNEL, IF NECESSARY FOR CONSTRUCTION ACTIVITIES. ALL
PREPARATORY WORK FOR SHUTDOWN AND CUTOVER SHALL BE SCHEDULED AND
COORDINATED WITH THE COR A MINIMUM OF 30 WORKING DAYS IN ADVANCE.
11. THE CONTRACTOR SHALL PROVIDE TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES
TO PREVENT EROSION OR DISPLACEMENT OF SOILS AND DISCHARGE OF SOIL - BEARING
RUNOFF OR AIRBORNE DUST TO ADJACENT PROPERTIES AND WALKWAYS. REMOVE
TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES AFTER WORK IS COMPLETED AND
SITE IS STABILIZED.
CONSTRUCTION NOTES:
1. ELEVATION DENOTED AS "MATCH" ARE INTENDED TO MEET EXISTING GRADE ELEVATIONS.
VERIFY ELEVATIONS AT TIE-INS AND PATCH POINTS PRIOR TO BEGINNING CONSTRUCTION.
2. ADEQUATE DRAINAGE SHALL BE MAINTAINED AT ALL TIMES DURING CONSTRUCTION. ANY
DRAINAGE FEATURE OR STRUCTURE DISTURBED DURING CONSTRUCTION SHALL BE RESTORED
TO EXISTING CONDITIONS OR BETTER SUBJECT TO THE APPROVAL OF THE RE.
3. SURFACES AROUND THE FACILITY SHALL BE GRADED TO PROVIDE POSITIVE DRAINAGE AWAY
FROM BUILDINGS AND PAVEMENTS.
4. REMOVE STANDING WATER FROM THE PROJECT WORK LIMITS AS NECESSARY TO PROTECT
SUBGRADE, SUBBASE, AND/OR BASE COURSE OF NEW PAVEMENT, SURROUNDING CONDITIONS
TO REMAIN, OR OTHER COMPLETED WORKS.
5. TOP ELEVATION OF ALL UTILITY STRUCTURES TO REMAIN SHALL BE ADJUSTED TO MATCH
FINISHED GRADE ELEVATION.
6. FINISHED GRADE SHALL BE SLOPED AT A UNIFORM SLOPE BETWEEN ANY SPOT ELEVATIONS.
7. FINISHED GRADES SHALL MATCH EXISTING GRADES UNLESS OTHERWISE NOTED. IF MATCHING
EXISTING GRADES CONFLICT WITH ANY NOTES ON THIS SHEET COORDINATE WITH RESIDENT
ENGINEER FOR DIRECTION PRIOR TO PERFORMING CONSTRUCTION ACTIVITIES.
8. THE MAXIMUM ACCEPTABLE GAP UNDER FENCING FROM FIRM GROUND IS 2 INCHES. THE
MAXIMUM ACCEPTABLE GAP UNDER A GATE FROM FIRM GROUND IS 4 INCHES.
9. FILL MATERIALS SHALL NOT BE PLACED ON FROZEN SOILS, ON FROST-HEAVED SOILS; AND/OR
ON EXCESSIVELY WET SOILS. BORROW FILL MATERIALS SHOULD NOT CONTAIN FROZEN
MATERIALS AT THE TIME OF PLACEMENT, AND ALL FROZEN OR FROST-HEAVED SOILS SHOULD
BE REMOVED PRIOR TO PLACEMENT OF STRUCTURAL FILL OR OTHER FILL SOILS AND
AGGREGATES. EXCESSIVELY WET SOILS OR AGGREGATES SHOULD BE SACRIFICED, AERATED,
AND MOISTURE CONDITIONED.
DEMOLITION NOTES:
1. CALL UNDERGROUND SERVICE ALERT AT LEAST TWO DAYS PRIOR TO EXECUTING
DIGGING/EXCAVATION OPERATIONS.
2. RESTORE ANY MONUMENTATION AND/OR BENCHMARKS THAT ARE DISTURBED OR DESTROYED
BY DEMOLITION OR CONSTRUCTION OPERATIONS. SUCH POINTS SHALL BE REFERENCED AND
REPLACED WITH APPROPRIATE MONUMENATION BY A LICENSED SURVEYOR.
GEOTEXTILE
3.0 % 3.0 %
ACCESS ROAD
LEGEND
EXISTING GROUNDEG
TYPICALTYP
FINISHED GRADEFG
UNLESS NOTED OTHERWISEUNO
CENTER LINECL
CL
SEE PROJECT STATEMENT OF WORK FOR PROPOSED ROADWAY WIDTH
CATCH
EG,
TYP
APPROXIMATED
EG
TYP
PROPOSED TYPICAL ROADWAY SECTION
NOT TO SCALE
GEOTEXTILE
SEE PROPOSED
ROADWAY MATERIALS
SECTION (TYP)
0'-8" BELOW EG,
TYP
RAISE ROADWAY AT
CENTERLINE 1'-6", TYP UNO
(SEE EXHIBIT 1 FOR
ADDTIONAL INFORMATION)
SURFACE
COURSE
GRADE
AutoCAD SHX Text
EDM:
AutoCAD SHX Text
ISSUED FOR:
AutoCAD SHX Text
EXHIBIT 2
AutoCAD SHX Text N/A
AutoCAD SHX Text 04/2025
AutoCAD SHX Text
MANAGER, AJW-B20
AutoCAD SHX Text
PROGRAM REPRESENTATIVE, AJW-B720
AutoCAD SHX Text
PROPOSED ROADWAY
AutoCAD SHX Text
NOTES AND DETAILS
AutoCAD SHX Text
ALASKA
AutoCAD SHX Text
TECHNICAL SERVICES
AutoCAD SHX Text
NDP
AutoCAD SHX Text
NAS DEFENSE PROGRAMS
AutoCAD SHX Text
TECHNICAL SERVICES PROGRAM
AutoCAD SHX Text
CONTRACT DOCUMENT
| Sheets and Views |
| EXHIBIT2 |
File details come from the government source that posted it. Updated .