Exhibit 1 is a Project Plan Overview for the BGQ VORTAC Road Repair project located near Big Lake, Wasilla, Alaska. The project involves rehabilitating 64 miles of road on FAA-owned land, with specific grade and elevation requirements. Key technical specifications include matching existing grades at the project start and end points, maintaining vertical grade limitations of 10% favorable and 6% adverse grades, and raising the roadway centerline profile by 1'-6" above the existing elevation.

The project scope includes grading and compacting the existing roadway, installing geotechnical materials, clearing vegetation within 20 feet of the roadway edges, removing and replacing existing culverts with 18" HDPE culverts, and installing culvert marker posts. The project is set aside for small businesses, with an estimated cost between $500,000 and $1,000,000 and a projected performance period of 90 calendar days. An optional site visit is scheduled for July 10, 2025, and proposals are due by July 24, 2025, at 3:00 PM EDT.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENTS

EXHIBIT 1

PROJECT PLAN OVERVIEW

Start Project Intersection of Access Road and W Camp Dr

Match Existing Grade at intersection and transition road elevation up to proposed roadway elevation within the first 100-feet of roadway shown in Exhibit 2.

Vertical Grade Limitations:

Favorable Grade – 10% Adverse Grade - 6%

Match Existing Grade at location coordinated with Project COR within last 100-feet of roadway rehabilitation.

Vertical Grade Limitations:

Favorable Grade – 10% Adverse Grade - 6%

Raise roadway centerline profile to 1’-6” above existing centerline elevation. See Project Statement of Work and Exhibit 2 for more details.

End Project Coordinate project end.

Exact location to be coordinated in the field with COR.