Appendix G Cost Estimate Approval Process.docx

DOCX document 12 KB Posted

Attached to
Mobile Crane Maintenance and Repairs for Army Test Center
Solicitation number
W91ZLK-22-R-0011
Issued by

About this file

This combined synopsis/solicitation requests proposals for mobile crane maintenance and repair services for the Army Test Center. The solicitation is set aside for small businesses and contemplates award of a firm-fixed-price contract using simplified acquisition procedures. Offerors must provide pricing for base and option years using the attached schedule of services. Proposals are due by 3:00 PM Eastern time on March 18, 2022 and shall include separate technical/management and price volumes. The technical volume must demonstrate relevant experience and qualifications. Evaluation will be based on lowest price among technically acceptable proposals. The place of performance is the Army Test Center in Aberdeen Proving Ground, Maryland including off-site locations. The period of performance is one base year plus two one-year options.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPENDIX G

COST ESTIMATE APPROVAL PROCESS

An approved written cost estimate is required prior to performing any maintenance repair work.

The maintenance contractor shall prepare a written cost estimate within 48 hours of receiving notification of an open work order. The repair cost estimate shall include all elements contained in the form at Appendix F.

The repair cost estimate shall be submitted electronically via e-mail to the QA/COR. When electronic submission is unavailable, the contactor shall prepare a hard copy and hand carry the estimate to the QA/COR.

The QA/COR shall make a repair recommendation and determines the Maintenance Expenditure Limit (MEL). MEL is a computation to accurately make cost-effective repair or buy decisions.

The COR signs the Estimate Form then notifies the maintenance contractor when the cost estimate is approved, deferred, or when a turn-in decision is made.

Cost estimates under $500.00 or unique situations may be approved on-site by the QA and/or telephonically by the COR. An Estimate Form shall be prepared within 24 hours of the completed work. The estimate shall be marked “COR/QA ON-SITE APPROVAL”.