Questions and Answers a/o 15 Jun 17 @ 1520hrs
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation Number: W91SMC‐17‐R‐0004 Project Title: Repair Squadron Operations Facility Project Number: VDYD132014 Current a/o 15 Jun (1520hrs)
Questions and Answers
Number Spec Section Question Answer
1 07 22 00
Section 07 22 00, page 5, section 2.3.1 states “high density wood fiber” however, on page 6, section 3.2.2.1, the heading is “polyisocyanurate insulation” which is not the same as wood fiber and in the paragraph directly below it states “1/2” wood fiberboard, glass mat gypsum roof board…”
Paragraph 2.3.1. should be changed to read as follows: Provide 1/2" gypsum fiber roof board in accordance with ASTM C1278.
Remove reference to "wood fiberbaord in Paragraph 3.2.2.1.
1.a.
Can you please clarify what type of cover board is being requested as three different types of cover boards are listed here? (If it helps, you will get the best results out of a ½” Gypsum Fiber Roof Board ASTM C1278) -Section 07 54 19, page 8, section 2.1.1 states “minimum polymer thickness .060” and color to be “Décor Tan”. -Section 07 54 19, page 9, section 2.1.4 states “minimum polymer thickness .072”.
-Section 07 54 19, page 10, section 2.2 states “Fleece Backed .072 minimum” and directly below under item A it lists 60 mils thick Fleece Backed PVC
The design intent is to have a 60 mil PVC roof membrane with a fleece backing; for a total thickness of 72 mil minimum.
1.b.
Can you clarify what membrane is being specified? .060 or .072, minimum thickness or nominal thickness and Fleece Back or bare backed membrane?
The design intent is to have a 60 mil PVC roof membrane with a fleece backing; for a total thickness of 72 mil minimum.
1.c.
Regarding the color of “Décor Tan”; Décor is typically the name associated with the Sarnafil Décor Rib systems (simulating standing seam metal). Does this project contain any sections requiring this type of “rib” system?
No, the décor tan is the type of color to be used for the thermoplastic layer on the flat roof only. The standing seam roofs are a different color.
2 10 14 00
Missing Spec Info: Drawings for signage Included in prints but normal 10 14 00 spec section for signage not included in spec book. Request that an addendum be realesed regarding this issue. A specification section will be issued in an upcoming addendum.
Can Superintendent and Quality Control Manager be the same person? No
Can the prime contractor use a section inside the building as Site Office? Yes
Can we use the parking lot space next to the building as a laydown area?
The Government can section off a portion of the area as a laydown area, or the Contractor can use the GOV parking area to the east of the building.
Project Number: VDYD132014 Current a/o 15 Jun (1520hrs)
Questions and Answers
Is there any other specific information to be presented with the proposed schedule rather than tasks, starts & finish dates?
No, the items listed within the specificaitons regarding schedules is all that is required.
Is there a power source available at the building during construction phase for use by contractor/subcontractors?
Yes, the contractor can use the existing power coming into the building.
8.a.
My question is, I see no mention in the design, of the building gas and electric metering. Should I assume that the existing meters will remain and we will tie them into the new system?
PD102 shows removal of the gas meter and gas service. ED106 shows the locaiton of the existing electric meter that is to remain.
The controls for the elctric meter should remain and be integrated on the new system.
8.b. Do new meters need to be furnished and installed?
No. The gas meter is being permanently removed and the electric meter and water meter are to remain.
Are there existing Fire Sprinkler system as-builts available and released prior to bid?
Yes, reference Attachment titled Bldg. 5008 Fire Protection Plan (1 sheet) and Attachment titled Bldg. 5008 Fire Sprinkler System Piping Plan (1 sheet) (These attachments are posted with the Q&As on FBO)
Other than the SAFB Fire Marshal, are we required to submit to any other AHJ (i.e. Leidos or Corps of Engineers?)
No, the 126th CES and SAFB Fire Marshall are the only approving officials for fire protection. The Architect/Engineer Fire Protection Design Engineer will be reviewing the construction as well and providing input to 126CES.
Are we allowed to leave the fire sprinkler system out of service during the duration of construction?
Yes, however it needs to be coordinated with the 375th Base Fire Marshall.
Will this project be broken up in Phases or estimated flow working from N-S, E-W?
There will be no phases for this building in terms of occupants. All occupants will be out of the buildng at the time of construction and left to the contractor to decide on how best to complete the work.
13 Please confirm that the building will be unoccupied during construction. Yes, building will be unoccupied
Please confirm that we are to replace all the existing solder link sprinkler heads to ne QR type throughout?
Drawing FPD101 indicates which sprinkler heads may remain in the same location. Contractor shall comply with NFPA 13 for modifications. It is not the design intent to replace heads in rooms that don't require any sprinkler modifications such as Lunge 140, OG Support 140, and Vestibules 100 & 138, Classified Tele. Room 120, and Toilet 122.
Project Number: VDYD132014 Current a/o 15 Jun (1520hrs)
Questions and Answers
Are we additionally required to utilize the UFC-3-600-01 (Ver.
11/28/2016) along with NFPA 13 standards for redesign? Yes
Please confirm that this is a "Buy American"/domestic material only project.
All applicable Federal Acquisition Regulation (FAR) clauses and requirements regarding the Buy American Act are listed within the Solicitation.
Other than shown; is the intent of the FP SOW to reuse the existing sprinkler head outlets as much as possible for redesign and leave all existing branchlines, mains, riser assembly & backflow to remain unchanged/as-is?
It is the intent to utilize the existing piping to the extent possible, however, as indicated in the drawings, many of the branches and heads need to be modified to fit the new floor plan and ceiling grid.
The riser assembly and backflow preventer are expected to remain unchanged/as-is.
Are we required to recalculate the existing system for the new floor layouts/renovations?
Yes. In accordance with specification 21 1313.00 10, paragraph 1.2, the contractor is responsible for design of the sprinkler layout including hydraulic calculations.
Are there an HIGH security areas that have lead lined walls/ceiling that require special pipe penetrations (i.e. transition to CPVC or other special fittings) No, there are no lead-lined walls.
Making the bid due at 1 PM on Monday essentially means all sub bids will have to be received by Friday in order to prepare the bid and transport to Peoria by 1 PM. Equipment suppliers are notorious for holding their bids until the last minute for fear of having their numbers shopped. Even if we direct our subs to submit on Friday, the majority of mechanical and electrical numbers won’t come in until Monday morning, delaying preparation of the proposals and forcing contractors to choose between quality and expedience to deliver the proposals. If the bid turn-in time was changed to 4 PM, this would allow time for bids to be received on Monday morning and proposals finalized properly to ensure best value pending
Project Number: VDYD132014 Current a/o 15 Jun (1520hrs)
Questions and Answers
This project will be bid by a large number of local contractors with bids provided by local suppliers. Making delivery of the proposals to Peoria @ 1 PM creates a hardship for these contractors to prepare and submit their best value proposals. This process will reward the contractors who can afford the additional manpower and cost to have proposals. If the bids could be delivered to Scott AFB, it would provide additional time to ensure the small businesses bidding this project have the additional time to receive quotes and ensure best value is presented. The proposal due date location remains the same.
The framing details are unclear on existing framing. Seeing the original design drawings would assist in takeoff and construction of the new framing. Are the structural and architectural as-builts available for the building? pending
Reference section 2.5.2.2. Subfactor 1 Experience and Capability:
Please list which Key Personnel roles can be shared. In example, can the Superintendent also perform as the Site Safety and Health Officer if qualified? No, Key Personnel roles cannot be shared.
24 How many days are allotted for Material Submittal Reviews? pending
25 What are the security requirements regarding the REAL ID Act?
Refer to: http://www.scott.af.mil/News/Article- Display/Article/931808/real-id-act-enforced-at-scott-afb-sept-15/ and refer to the Attachment titled REAL ID Act 20170607 (1 page)
26 07 22 00
Roof and Deck Insulation - Part 2; 2.3 PROTECTION BOARD: 2.3.1:
HIDH DENSITY WOOD FIBER BOARD - Substitution Request allowing JM's 2 perlite HD Coverboards: Johns Manville manufacturers, in Rockdale, Illinois, a RetroPlus and DuraBoard Perlite Fiber board, based off the updated ASTM C 728 Type 3. Both boards exceed Wood Fiber Board, for lower moisture content and water resistance. Johns Manville does not make a Wood Fiber Board. pending
Project Number: VDYD132014 Current a/o 15 Jun (1520hrs)
Questions and Answers
27 07 22 00
Roof and Deck Insulation - Part 2; 2.3 PROTECTION BOARD: 2.3.1:
HIDH DENSITY WOOD FIBER BOARDSubstitution Request for the Invinsa Coverboard: JM Invinsa High Density Coverboard. A High Density Poly ISO board, that is 150 psi, and has a coated glass facer on both sides. The data sheet attached, as compared to a WFB or Perlite board, exceed in all categories, the performance over the specified. It is manufactured in Jacksonville, FL pending
28 07 54 19
POLYVINYL - CHLORIDE ROOFING PART 2 PRODUCTS;
2.1 MATERIALS; 2.1.1 PVC ROOF MEMBRANE - Johns Manville PVC
60 mil min FB Sandstone ES; JM and Cooley Group, have a strategic partnership, to manufacturer PVC. Which is manufactured in Pawtucket, RI & Lancaster, SC; Allowing JM PVC FB pending
Are non-US made products, allowed in the construction of U.S.
properties?
All applicable Federal Acquisition Regulation (FAR) clauses and requirements regarding the Buy American Act are listed within the Solicitation.
30 09 29 00
2.1.14 calls for 15lb asphalt moisture barrier over gypsum sheathing.
Where will this be required? pending
What's the difference between keynote 4/A102 on additive bid items and the keynote 5/A101 in the base bid? pending
Do rooms 143, 142, 153 need to be framed, hung and taped to the tall ~32' roof deck since there's no ceiling in these rooms? If so what gauge and type of steel studs should be used? pending
Since there won't be another walk thru of the existing space, can keynote 11/A101 be confirmed that the existing walls at perimeter of open storage area go to the deck? pending
What does comment "frame metal studs around utilities, see partition type" stated on detail 9/A751 and many other details mean? Is this above and beyond industry standard framing practices? pending
Project Number: VDYD132014 Current a/o 15 Jun (1520hrs)
Questions and Answers
S001 - 4.2.H calls for wall studs to be at a minimum 600S62-68 which is 14ga material however S201 shows typ. head and sill material to be 600S137-54 which is 16ga. Is 16ga sufficient or does it need to be 14ga per S001? pending
G400 note says "Concrete backer board up to tile height only. Provide moisture resistant gypsum board above". There is no moisture resistant gypsum board in the specs, only water resistant gypsum boarding board 09 29 00 2.1.3 which is more expensive and requires a skim coat of mud. Can a specification be given for the moisture resistant gypsum board? pending
G400 wall type P2d states "W/WIRE MESH IN WALL" is this the same mesh as noted in P0c wall type? Should this mesh at room 204 be installed all the way up to the ~32' roof deck above or just to above ceiling height? pending
38 Is it required to have a RCDD on staff and submit credentials? pending
39 01 45 00
Paragraph 3.4.1. requires a Safety and Health Manager as part of the CQC organization. Does this manager need to be on site full time and may he perform duties other than safety and health?
Refer to Spec Section 01 45 00, para. 3.4.1. regarding requirements of the CQC staff and refer to Question #23 above.
40 01 50 00
This specification does not indicate who is to pay for the use of temporary power and water during construction. Will the GC have to pay a metered charge or is the government supplying these utilities free of charge? pending
41 01 91 00 Please confirm tha the General Contractor is responsible for hiring the commissioning agent for the project. pending
Sheet D101: Keynote 14 states to remove wall coverings and prep to paint. Will the walls at this keynote require a skim coat finish as part of prepping for paint? pending
Project Number: VDYD132014 Current a/o 15 Jun (1520hrs)
Questions and Answers
Please clarify if all non-cased doors are to receive new hardware per the door schedule of sheet A900. The demo and architectural drawings do not appear to mention anything about providing new hardware at existing doors, but the door schedule specifies a hardware set for all reused doors. pending
Please clarify if door 115 is to receive a new door and frame. This door is marked as a reused door on the door schedule, but the demo drawings (D101) shows this door as being removed and replaced with a new door and frame. Please clarify and provide opening size if a new door is required. pending
Please clarify if the work in existing auditorium 102, storage 110A and mechanical 136 are in the contractor’s scope. Drawing D101 shows these areas hatched as not in scope per the demo plan legend, but these rooms appear to have demo keynotes with work required in them. pending
Please clarify if toilet partitions and urinal screens are to be metal or HDPE. The section 102113 part 2.3 paragraph E. appears to call for HDPE material but drawing A800 Keynote 7 calls for metal. pending
Please provide the location of the 18” grab bars (002A) shown in the toilet accessories schedule on sheet A800 as none appear to be listed on the drawings. pending
Please confirm that each shower in the locker rooms will require a shower soap dish (mark 006 of the toilet accessories schedule on sheet A800). There currently only appears to be soap dishes at the waste receptacles. The dishes are shown on the interior building elevators but don’t appear to be called out. Please also provide call outs for shower rods as these don’t appear to be indicated. pending
Please clarify if the fire extinguisher cabinet in corridor 110 is to be removed and replaced. This shown as an existing cabinet in the life safety drawings (G500) but the floor plans (A101) appear to indicate a new cabinet. pending
Project Number: VDYD132014 Current a/o 15 Jun (1520hrs)
Questions and Answers
Please clarify what size is required for the fire extinguishers specified in section 104416. Part 2.1.1 paragraph C indicates a type ABC fire extinguisher but doesn’t indicate what size is intended (10 lbs, 20lbs, etc.) pending
Please provide location and sizing of the dressing mirrors specified in section 102813 part 2.2.3. Paragraph B as these mirrors do not appear to be shown in the drawings. pending
Plan Sections 5/6/S503, Section 3/4/S504 and Details 1/2/3/A702
Areas of Concern: The brick wall between the windows is less than 2 foot. After we remove existing jacks from both sides of window's there will not be anything holding the existing brick or stone column in place, all the brick ties will be disconnected. If the brick lintel above the windows that holds up the upper band of brick is loose and setting on masonry that is a lot of weight on a unsecure column . There is not a good way to re-connect the brick or stone back to the new stud work .
Also the gyp sheathing will be in pieces and there will be no continuous vaper barrier. pending
Plan Sections 5/6/S503, Section 3/4/S504 and Details 1/2/3/A702
Another question is the brick lintel secured to the existing stud work? If so this will cause a multitude of problems. pending
Plan Sections 5/6/S503, Section 3/4/S504 and Details 1/2/3/A702
If we demo the existing wall and reframe with a heaver stud with new sheathing and a vapor barrier this will give us a better structural wall , if we use the correct gage of studs we should not need to use the extra bracing as shown on details 5 &6 / S503. For these elevations: - West wall between column D and G -South wall between 1 and 7 -East wall from G to G.5 pending
Project Number: VDYD132014 Current a/o 15 Jun (1520hrs)
Questions and Answers
Demolition Key Notes 4 and 6 on Sheet ED101 call to protect in place the device, breaker and conduit. In all probability these devices are fed from other devices that are to be demolished. It is unknown at this point what will be required to keep these devices operational, whether it be 10' or 50' of conduit/wire. How are we to estimate an unknown condition like this? Will this be addressed on an individual basis by change order at that time? pending
Will the contractor be required to dispose of the lamps and ballast and absorb that cost, or will the lamps and ballasts be recycled by the Government? pending
Detail D on Sheet E102 shows 2 vehicle loops. Detail 1 shows 4 vehicle loops. Which detail is correct? pending
The card reader at the entry on Sheet E102 isn't shown on the access control drawings and isn't shown to have cabling going back into the building. Does this card reader only tie into the gate controller? If not, please provide the requirements for this card reader. pending
There is a floor box shown in Room 121 on Sheet E301. This floor box isn't shown on Sheet E101. Is this floor box required and, if so, is power required at this location. pending
Is there a specification for the motion detector shown on Sheets E 301 and E304? pending
Is the contractor to provide the communication racks and vertical wire managers shown on Sheet E302? pending
Are we to provide all of the patch panels and horizontal wire managers shown on Sheet E302 or just the quantity needed for what we will be installing, plus the one spare patch panel that is identified? pending
63 27 10 00
Specification 27 10 00-2.4.4 calls for the contractor to provide patch cords at the patch panels. What length patch cords are required?
Nothing in the spec is calling for patch cords at the workstation. Is this a requirement and, if so, what length patchcord is required? pending
Project Number: VDYD132014 Current a/o 15 Jun (1520hrs)
Questions and Answers
Is the equipment currently in place in Room 132 to terminate the 25 pair copper and 24 strand fiber optic cable or will we need to provide patch panels in Room 132? pending