ATTACHMENT 0003 RFI from Move Vendors ANMC responses 13 OCT 2026.xlsx

XLSX spreadsheet 50 KB Posted

Attached to
ANC SE Expansion Moving Services
Solicitation number
W91QV126RA060
Issued by

About this file

This is a Request for Information (RFI) document containing 186 questions and answers from potential vendors regarding Arlington National Cemetery's (ANC) Southern Expansion moving services contract. The RFI addresses all aspects of relocating equipment, materials, and operations from the existing facilities to a new OPS Complex during the period February 1 – April 30, 2027.

Scope and Operational Requirements: The contractor must relocate equipment, furnishings, hazardous materials, and supplies from Buildings G, H, and other existing structures to new facilities. Key directorates being moved include Operations (G3), Safety, Interments, Facility Maintenance, Supply/Logistics (G4), and Engineering. The move encompasses approximately 22 personnel daily and includes specialized equipment such as fleet maintenance machinery, welding equipment, air compressors, server racks, and hazardous material containers. The contractor is responsible for all packing materials, labor, equipment rental (forklifts, cranes, dollies), inventory tracking with photographic documentation, and waste disposal. The government will provide preliminary inventory, coordinate disconnection/reconnection of utilities, supply access to restroom facilities and staging areas, and handle power-on testing of machinery post-installation. Vehicle access is limited to the 123 Gate and Joyce Street Gate, with operations restricted between 5 AM and 6 PM unless coordinated with the government representative. The Interment Operations directorate must remain partially operational, focusing only on above-ground inurnments, with normal operations expected to resume by February 22, 2027.

Hazardous Materials and Compliance: Contractors must comply with DOT, EPA RCRA, OSHA HAZWOPER, and U.S. Army Corps of Engineers (USACE) EM 385-1-1 requirements. Personnel require EPA RCRA Hazardous Waste training, OSHA HAZWOPER (29 CFR 1910.120), and OSHA HazCom certification. The contractor must verify hazardous materials inventory using Safety Data Sheets (SDS) provided by the government and coordinate with ANC Environmental staff for oversight. Licensed hazardous material carriers are required when DOT thresholds are exceeded (flammable liquids >119 gallons, corrosives >55 gallons, compressed gases >1,000 lbs, oxidizers >400 lbs). The contractor must develop an Environmental Compliance Plan, submit hazardous material manifests, and implement an emergency response plan. All disposal of packing waste and materials generated by the contractor is the contractor's responsibility.

Schedule, Pricing, and Contract Terms: The contract is firm-fixed-price with no cost adjustments for schedule extensions or weather delays. A 30-day pre-move consultation period is required at no charge, with two weeks of packing/preparation before February 1 and two weeks of post-move support contingency included within the February 1 – April 30 timeline. The move will not commence until the new OPS Complex is fully constructed and utilities are operational. Weather contingencies are built into the schedule, with extensions determined on a case-by-case basis. The contractor must provide staffing (at minimum: one Project Manager, one Scheduler, move leaders, and movers), though the 22-person estimate in the Performance Work Statement is for cost estimation only. No overtime will be paid or required. All materials, equipment, containers, labels, and barcode scanning equipment must be contractor-provided. This is a Small Business 100% set-aside with evaluation on Lowest Price Technically Acceptable (LPTA) basis. The contract includes multiple deliverables such as an Environmental Compliance Plan, detailed inventory with photographic evidence, floor plans showing final placement, and an Installation and Functional Test Report.

View the file

Other files

File Type Posted
Solicitation Amendment - W91QV126RA0600003.pdf PDF
ATTACHMENT 0003 RFI from Move Vendors ANMC responses 13 OCT 2026.xlsx XLSX spreadsheet
ATTACHMENT 0002 MICC PWS AUG 2025_Southern Expansion_ V5 2026 10-14 FINAL.pdf PDF
ATTACHMENT 0016 Move Routes-Access-Size.pptx PPTX presentation
Solicitation Amendment W91QV126RA0600003 SF 30.pdf PDF
Solicitation Amendment - W91QV126RA0600002 (1).pdf PDF
Solicitation Amendment W91QV126RA0600002 SF 30 (1).pdf PDF
ATTACHMENT 0009 Fac Maint Move Inventory.pdf PDF
ATTACHMENT 0006 Bldg_C_Furn-Combined (seating chart).pdf PDF
ATTACHMENT 0015 Storage options at Warehouse Bldg C.pdf PDF
ATTACHMENT 0017 Move Schedule Matrix NSC Move 2027.xlsx XLSX spreadsheet
ATTACHMENT 0008 ENG Move Inventory v2.pdf PDF
Solicitation Amendment W91QV126RA0600002 SF 30.pdf PDF
ATTACHMENT 0018 Service_Complex_Area V2 match.pdf PDF
ATTACHNENT 0007 Bldg_D_Furn-Combined (seating chart).pdf PDF
ATTACHMENT 0005 Bldg_B_Furn-Combined (seating chart).pdf PDF
ATTACHMENT 0013 Operations G3 Move Inventory.pdf PDF
ATTACHMENT 0004 Bldg_A_Furn_V2(seating chart).pdf PDF
Solicitation Amendment - W91QV126RA0600002.pdf PDF
ATTACHMENT 0011 G4 Bays Move inventory.pdf PDF
ATTACHMENT 0002 ANC PWS SE Expansion v5 FINAL.pdf PDF
ATTACHMENT 0010 Fleet Move Invenotry.pdf PDF
ATTACHMENT 0014 Safet yMove inventory.pdf PDF
ATTACHMENT 0012 Internment Ops Move Invenotry.pdf PDF
Solicitation Amendment W91QV126RA0600001 SF 30 (1).pdf PDF
Solicitation Amendment - W91QV126RA0600001 (1).pdf PDF
Solicitation - W91QV126RA060 FINAL.pdf PDF
ATTACHMENT 0002 ANC Access Roster Request for SE Expansion Moving Services Contract Recompete.xlsx XLSX spreadsheet
ATTACHMENT 0001 WAGE DETERMINATION.pdf PDF
MICC PWS AUG 2025_Southern Expansion_ v4 2026 08-11 FINAL.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI

IDQuestionDepartmentProposed Responsible RespondentComment Resolution (due 12 OCT )POC to Verify
1Which gate(s) will be designated for contractor vehicle access during the move period (Feb 1 – Apr 30, 2027)?G2ENG-Angela Pedersen to coordinate w/G2For the contrators 123 Gate and the Joyce Street gatePM
2Are there separate gates for large vehicles (semi-trucks, flatbed trucks) vs. standard moving vans?G2ENG-Angela Pedersen to coordinate w/G2No all contractor traffic should be moving through the 123 Gate and Joyce Street GatePM
3What are the maximum vehicle dimensions (length, width, height) allowed on-site roads and through gates?G2ENG-Angela to coordinate w/G2Dictated by turn radius; box truck is preferred; 18-wheeler is maximum allowablePM
4Will dedicated contractor parking be provided for 22 personnel daily, and if so, location/capacity?ENG, G3Rosil Saldana to coordiante with Angela Pederse.Personal vehicle parking is limited. Contactor is responsible for transporting employees to the move site.
5Are there restrictions on vehicle movement times (early morning/evening constraints)?G2Steve Hendley and G2 cooridnation.The existing service complex opens at 5am. Operational closure is 6PM. Outisde of that, cooridnaion needed with Gov Rep.G3, COS
6What are the exact dimensions of the laydown/storage area provided for staging moving equipment?ENG, G3Staging area will be provided. MOver needs to inform of sizing.PM -ALL to sort thorugh. Daily basis? Chief Mc Queen - ask users
7Are covered storage areas available for weather protection of packing materials and equipment?ENG/FMWeather protected staging will be provided.PM -ALL to sort thorugh. Daily basis? Chief Mc Queen - ask users
8Will 24/7 access be provided, or are there specific hours (tied to 0800-1700 operations)?G2G2- Chris GreenNo 24/7 access; Service complex opens at 5am. Operational closure is 6PM. Outisde of that, cooridnaion needed with Gov Rep.G3, COS
9Are there loading dock specifications for the existing OPS Complex and new facility (dimensions, weight capacity)?ENGThere is no need to access loading loads for existing OPS complex. Access points and dimensions provided.PM - New Facillity
10Will government provide barriers/signage to prevent interference with cemetery operations?IO, G3Steve HendleyNo anticipated impacts to cemetery operations; No barriers or signage will be provided; Contractors will use designated gates and any closed roads will be clearly identified.
11Will contractor personnel have access to restroom facilities at both existing and new OPS complexes?ENGRosil Saldana (COR)Yes
12Are there water hookups available for equipment washing/spill containment?ENGRosil Saldana (COR)NoPM
13What is the electrical capacity available for contractor equipment charging stations?FMAnwar277V and 480V available.
14Which gate(s) will be designated for contractor vehicle access during the move period (Feb 1 – Apr 30, 2027)?ENG/G2For the contrators 123 Gate and the Joyce Street gate
15For Building A (Storage): Can you provide an itemized list of shelving units, cabinet types, and special storage configurations?ENGAngela PedersenFloor Plan and schedule of the furnishings being provided as part of the RFI. New purchases to be located at new complex will be handled with Directorate POC
16For Building B (Maintenance Shops): What are the specifications for fixed vs. portable equipment (tire changer dimensions, drill press tonnage, welding equipment)?ENGAngela PedersenFloor Plan and schedule of the furnishings being provided as part of the RFI. New purchases to be located at new complex will be handled with Directorate POC
17For Building C (Warehouse): Are there hazardous material storage restrictions beyond Building G & H?ENG, SafetyAngela PedersenFloorplan and schedule of the furnishings will be provided in Amendment. FLEET and Safety for Haz Mat HandlingALL directorates to confirm if NEW purchase, if it will fit on the desingated location or new location
18For interment operations materials (concrete liners, tomb covers, tents, canopies, tarps): What are the total quantities and dimensions?IOSteve HendleyInvenotry Matrix being provided as part of the RFI
19Are there any items that must be disassembled, and what reassembly verification will be required?ALLALL "Column I" addedINventory being provided.
20Buildings G & H: Can you provide an inventory of hazardous materials with DOT shipping classifications?Safety/EVAngela Pedersen and Mark UpshawNo. Gov’t does not provide; contractor verifies materials with ANC Environmental oversight. Safety has purview of the transportation.Safety
21What is the total weight and volume of hazardous materials requiring certified transport?Safety/EVMark Upshaw and Beatriz (Fleet)DOT thresholds — flammable liquids >119 gal/package; corrosives >55 gal/package; compressed gases >1,000 lbs; any explosives/PIH gases; radioactive above Type A limits; oxidizers >400 lbs/package. Contractor must calculate totals via inventory. (coordnation with EV and SAfety if the case)Safety
22Are there specific EPA or OSHA certifications beyond DOT requirements for contractor and personnel?Safety/EVMark Upshaw and John RedmondYes. Contractor personnel require EPA RCRA Hazardous Waste training, OSHA HAZWOPER (29 CFR 1910.120), and OSHA HazCom training. Because ANC is a military installation under the jurisdiction of the Department of the Army, contractors are governed by both OSHA (29 CFR 1910/1926) and the much more stringent U.S. Army Corps of Engineers (USACE) Safety and Health Requirements Manual (EM 385-1-1).Safety
23Will government provide secondary containment systems, or is contractor responsible?Safety/EVMark UpshawNo need to dispose empty containers nor residual materilsSafety
24What is the acceptable method for disposal of empty containers and residual materials?Safety/EVMark UpshawHaz and Non-Haz disposal will be handled by the agnecy
25For specialized equipment (welding equipment, air compressors, etc.), are original manufacturer specifications available?FMChief McQueen (FM )and Beatriz (fleet)No, original manufacturer specifications available
26Will machinery require operational testing post-installation, and who is responsible?ENGRosil Saldana (COR)Provided in the Move Inventory Matix
27Are there power requirements (3-phase, single-phase, amperage) for equipment in the new facility?ENGRosil Saldana (COR)Not applicable. The contracor is not required to do equipment connections.
28For fleet maintenance equipment, are there vehicle lifts or ramps that require disassembly?FleetBeatriz (fleet)No
29PWS lists Operations (G3), Safety, Internments, Facility Maintenance, Supply/Logistics (G4), and ENG. What is the expected duration for each phase?ENGRosil SAldana (COR), Contract G32 weeks of packing prior Feb 1st. Then 4 weeks of moving calendar days, with 1 week on the backend for contingency
30What are overlap periods between phases (can multiple directorates move simultaneously)?ENGRosil Saldana (COR) Contratcts, G3Schedule of relocaion being attached/provided
31Which facilities must remain fully operational during the move (e.g., Interment Operations)?ALLCoordination by ALLBuilding 123 will need to remain operational and the bay area will need to remain partially operational as IO will still be performing Columbarium services. Schedule of reloation being provided as part of the RFI.
32Will contractor be responsible for decommissioning utilities (water, electrical, HVAC) after move completion?ENGGovernment will be responsible for decommissioning utilites
33Post-move cleanup: What level is required (sweep/mop vs. deep clean)?Angela PedersenNone; buildings will be demolished
34Will furniture/fixtures remaining be marked by government, or must contractor identify them?ENGRosil Saldana coordained with Angela PedersenFurniture/fixtures, shelving, air compressors, hoists, steel, will remain; any furniture moving will be marked by the Government
35Are there asbestos survey reports available for the existing facility?Safety/EVJohnJohn Checking with Deborah
36Will the new OPS Complex be fully constructed and utilities operational by February 1, 2027?ENGAngela PedersenMove will not take place OPS complex is fully constructed and utilities operations.
37Are there final punch-list items or construction contractors still on-site restricting mover access?ENGMike Horace - Angela PedersenYes. Intent is for construction to be complete. However thre may be exceptions. The Mover will be infomed of exceptions
38Will flooring, HVAC, and electrical systems be fully tested before contractor mobilization?ENGAngela PedersenYes. Intent is for construction to be complete. However thre may be exceptions. The Mover will be infomed of exceptions
39Are floor plans available showing designated placement areas for each directorate?ENGRosil Saldana (COR) coordiate w/Angela for last versionYes. Will Be provided
40Which cemetery operations must continue uninterrupted during the move (funeral services, interments, maintenance)?ENGInterment Directorate will remain operational focusing on inurnments (ABOVE GROUND) only. Return to normal operations focasted, currently, as 22 Feb. 2027. Schedule of relocation being provided as part of the RFI.
41Are there specific no-move windows (funerals scheduled, visitation hours)?G2/G3/ENGNo 24/7 access; no impacts to funeral schedule aticipated. Service complex opens at 5am. Operational closure is 6PM. Outisde of that, cooridnaion needed with Gov Rep.
42What is the protocol if an emergency occurs during moving activities?G2Chris Green - Rosil SaldanaCall 911-then notify COR-then notify ANMC G3
43Will government provide cemetery maps showing no-access zones?ENGRosil Saldana coordained with Angela PedersenYes, from esisitng OPS complex using temp access road into Joyce St. Contractor may not use the tunnel.PENDING confirmation from G3 and G2
44What is the contingency plan for inclement weather, snow/ice, or extended utility outages affecting the move?G3John FreelandInclement weather will require extensions to the projected move timeline. Impact to be determined on case basis.
45Does government hold any weather contingency days, or is the 88-day period a hard deadline?G3John FreelandWeather contingencies are built within the schedule.
46What cost/schedule adjustments apply if completion cannot be met by April 30, 2027?MICCAmber PeeblesThere will be no cost adjustment. This is a firm fixed price contract.
47Will government provide a single point of contact (POC) for each directorate?ENGRosil SaldanaYes, at kick-off meeting. Each Directorate will have a primary and secondary POC.
48Should contractor provide pre-move orientation for government staff on packing/handling procedures?ENGRosil Saldana/ContractesYes, expectation is to cover at the post-award conference
49Will government personnel assist in identifying items and placement, or is contractor fully responsible?ENGALLInventory Matrix will be provided as part of the RFI. Contractor will coordinate oversite of items to be moved with Directorate POCs.
50Will contractor provide standard moving boxes, or does government have preferred suppliers/specifications?ENGContractor is responsible for supplying all materials that they will need for the move
51Are eco-friendly or cost-optimized packing materials acceptable?ENGRosil SaldanaPrice saving should be optimized while ensuring no damage to equipment being moved
52What is the expected waste volume (styrofoam, packaging cardboard) for off-site disposal?ENGMark UpshawContractor determines waste volume
53Will contractor purchase labels for inventory tracking, or will government supply labeling system?ENGRosil Saldana coordinate with G4Contractor will provide labels for inventory tracking
54For items requiring specialized rigging (heavy machinery): Is equipment rental included in fixed price or reimbursable at actual cost?FMRosil Saldana coordinate with CSENo reimburseable costs; all costs are fixed price
55Are there any items requiring third-party specialized handling (calibration, realignment)?ENGRosil SaldanaNo
56Will government cover insurance for high-value equipment during transport, or is this contractor responsibility?ENGCES and MICCRefer to PWS; Government is not providing insurance.
57For hazardous material transport, will contractor contract certified HazMat movers?Safety/EVMark UpshawContractor must provide licensed HazMat carriers when DOT thresholds are exceeded.
58Will government approve contractor’s choice of subcontractors, or are pre-approved vendors required?MICCAmber PeeblesThere is no requirement to have subcontractors. The only requirement regarding subcontractor is in accordance with FAR 52.219-14
59Are there small/disadvantaged business preferences for subcontractor selection?MICCAmber PeeblesThere is no requirement to have subcontractors. The only requirement regarding subcontractor is in accordance with FAR 52.219-15
60What inventory format is required (Excel, PDF, government-provided system)?ENGThere is no government-provided inventory system; contractor will provide inventory in excell or PDF.
61For each item, are the following required: Description, Building of Origin, Destination Building, Condition (Pre/Post-move), Photographic Evidence?ENGRosil SaldanaYes, Contractor must provide inventory of item, origin, destination, condition, and photos
62Will government provide bar-code scanning equipment, or must contractor provide?ENGG4/CES?Contractor must provide all barcode scanning equipment and labels
63During the move, if additional items are identified for relocation, what is the approval/pricing process?ENGCES and MICCContractor will communicate to COR, and COR will communicate with Contracting Officer for approval
64If government identifies damaged items during unpacking, what is the damage claim/dispute resolution process?MICCAmber PeeblesAll damages will be documented with photos, provided to Contractor Officer, and communicated to Contractor with request for adjustment
65Are there cost allowances for minor scope changes?MICCAmber PeeblesContracting Officer will assess scope determinations for potential modifications to contract
66Post-move: Will contractor be required to provide photographic verification of final placement?ENGYes; photographic evidence required
67Is a final floor plan marking actual placement locations (vs. planned) required?ENGRosil SAldana (COR) confirm w/AngelaContractor will provide photographic evidence of final placement locationsPM
68Will contractor attend final walkthrough and sign-off with government, or is this government-only?ENGYes, Contractor will attend final walkthrough with government (COR and directorate POCs)
69What is the timeline for ANC badge issuance? Can expediting be arranged for pre-move mobilization?G2G2/Chris GreenOnce the contract is awarded the COR can coordinate with ANMC G2 for processing of contractor badging- contractors will be required to receive their badges from the JBMHH Visitor Control Center prior to beginning operations. All personnel, including subcontractors, are subject to US background checks.
70Are there restrictions on photography/video recording on-site for equipment documentation?ENGRosil SaldanaNone.
71Does government have a certified environmental contractor for hazardous material verification?Safety/EVMark UpshawNo. The government does not provide a certified environmental contractor for hazardous material verification. The contractor is responsible for verifying hazardous/regulated materials and coordinating with ANC Environmental staff for oversight. Certified HazMat movers must be utilized if DOT thresholds are exceeded.
72What documentation is required for the Environmental Compliance Plan (Deliverable #0)?Safety/EVMark UpsahwHazardous material inventory/classification; SDS sheets; handling/packaging/transport procedures; contractor certifications (DOT, EPA RCRA, OSHA HAZWOPER/HazCom); manifests; emergency response plan; and confirmation of compliance with ANC policy.
73Are there soil/groundwater contamination concerns at the existing OPS Complex?Safety/EVCJ and Mark UpshawThere are no concerns at this time. Once tanks are removed, the soil will be tested for contamination per the tank removal contract and DEQ requirements.
74Will government Safety Officer conduct pre-move safety orientation, or is contractor responsible?Safety/EVJohn RedmondThe Contractor is primarily responsible for conducting the pre-move safety orientation for their own personnel and subcontractors. However, this is done in close coordination with, and after a joint meeting with, the government's representatives which should include the ANMC Safety Manager.
75How are near-misses documented vs. reportable incidents (for “zero reportable incidents” requirement)?Safety/EVJohn RedmondUnder both EM 385-1-1 and Army Regulation 385-10, contractors working on Army installations will notify the on-site Contractor Site Safety and Health Officer (SSHO) and the Contracting Officer’s Representative (COR) or Contracting Officer (KO) and local Safety Office of any near miss or mishap.
76Are there specialty workers’ compensation coverage requirements for hazardous material handling?MICCAmber PeeblesFirm Fixed Price contract
77PWS mentions 30-day pre-consultation period at no charge. Does this mean: 30 days prior to Feb 1 (starting Jan 2), OR 30 days after Feb 1 mobilization (planning before physical move starts March 2)?ENGRosil Saldana coordinate with G3Move Schedule attached as part of RFI
78Can multiple planning meetings occur during this period without additional fees?ENGRosil SaldanaYes. This is a fixed price.
79Are there preferred start dates for each directorate’s move?ENGRosil Saldana Coordiane with G3Move Schedule attached as part of RFI
80What is the minimum notice required before moving each directorate (1 week, 48 hours)?ENGRosil SaldanaMove plan will be followed, and finalized
81Will government provide a master schedule, or must contractor develop and obtain approval?ENGRosil SaldanaGovernment Phased Move Schedule being provided as part of this RFI
82What does “fully operational” mean for the 2-week contingency period at end of contract?ENGRosil SaldanaAll items have been moved and have been verified with Contactor and Government walk-through
83Who is responsible for power-on and initial testing of machinery at new location?ENGRosil to coordiante with AngelaGovernment is powering on and testing machinery; not a contractor responsibility
84Will government provide an existing inventory, or must contractor conduct initial inventory during pre-move?ENGRosil SaldanaGovernment will provide a prelinimary invetory which selected Vendor will have to validate and provide final inventory list
85Will government provide condition assessments (photos) for damage claim verification?ENGCES and MICCContractor will communicate to COR, and COR will communicate with Contracting Officer for approval
86Are there items considered “government property” with special accountability requirements?ENGRosil Saldana (COR)Yes. To be cooridnated with the Property Book Officer
87What is the insurance deductible for contractor-caused damage?MICCAmber PeeblesIn accordance with FAR 52.236-7: "Permits and Responsibilities (Deviation Date)

(a) The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work.

(b) The Contractor shall be responsible for all damages to persons or property that occur as a result of the Contractor's fault or negligence.

(c) The Contractor shall be responsible for all materials delivered and work performed until completion and acceptance of the entire work, except for any completed unit of work which may have been accepted under the contract."

88Are there specific high-value items requiring documented special handling procedures?Fleet, FMNo
89The PWS estimates 22 personnel (1 PM, 1 Scheduler, 2 Foremen, 15 Movers). Can contractor propose alternative staffing if more cost-effective?ENGRosil SaldaanaYes, estimates in PWS are only estimates
90Will overtime be required on weekends/federal holidays if delays occur, and at what rates?MICCAmber PeeblesOvertime will not be required nor will the Government pay overtime for commercial service type contract .
91Are equipment rental costs (forklifts, cranes, dollies) included in fixed price or Will contractor provide transportation for personnel between staging areas, or will government provide?MICCAmber PeeblesProvide as a Fixed Price (itemized). Government will not provide any transportation for Contractor personnel
92Are travel expenses for key personnel included in labor rates or separate line items?MICCAmber PeeblesThis is a firm fixed price contract. Travel expenses are not included in labor rates.
93Will contractor bill for equipment mobilization/demobilization separately or inclusive?MICCAmber Peeblesinclude as part of fixed price but itemize.
94Given Feb 1 – Apr 30 timeline and potential weather delays, what is protocol for cost changes due to schedule extensions?ENGCES and MICCAccounted for in the PWS
95Are fuel price escalation clauses acceptable, or is price fixed regardless of market changes?MICCAmber PeeblesFixed price. Itemize
96Confirm tagging system rules (yellow, green, brown).ENGRosil SaldanaYellos for internal packing and relocation, red for divesting
97Who performs electrical disconnect for the yard flammable container?ENGGovernment performs electrical disconnect
98Provide hazmat container sizes/weights (22 units).Safety/EVJohn RedmondThese will be new/packaged to be moved to the NSC
99Confirm red toolboxes exclusion.IO/Fleet/FM/GOV will move Snap On Tool Boxes
100Confirm yellow cranes exclusion.FleetFleetCranes will NOT be moved
101Request facility oversight and sign-off for Parts Room Bay.FleetMover will pack and move with government oversite.
102Provide final layout of new location.ENGRosil Saldana coord with Angela PedersenFloor Plan and Items to Move Matirx.
103Confirm staging areas at new site.ENGRosil Saldana coord with Angela PedersenStaging area will be provided. Mover to supply proposed site based on their vehicles and equipment.
104Provide hazmat handling requirements by ANC policy.Safety/EVMark Urpshaw coord with John RedmondHazard Communication (HAZCOM) Program Enclosure to the ANMC Safety SOP will be provided but contractor will also follow all applicapble standards and regulations for hazmat handling as well.
105Confirm if an Eye Wash Temporary Station needs to be provided to the site during relocation operation.ENGAngela PedersenNot required; Eye wash stations are currently located at old and new facilitiesPM
106Confirm Roll off container for debris can be utilized, if yes provide staging area for containers and Relocating equipment.Safety/EVUpshawDisposal after the move of boxes, wrappers, is the responsibility of the Mover. Staging area will be provided. However, ANC needs estimated size from vendor.
107Confirm Names to all Bays from the walkthrough site visit.ENGRosil SaldanaBay namecloture is informal. Site layout with buiding provided as part of the RFI.
108Confirm Funeral procedures to prevent interruption of ANC and Contractor workflow cease work durations.IOSteve HendleyNo impacts to funerals aticipated.
109Confirm a funeral schedule be provided with dates and times on a weekly basis.ENGFuneral services will be at the columbariums only during the initial move period. No columbariums located near where the move will be taking place. No aticipated impact from hte move to funerals that will be conducted.
110Was attendance at the September 17 site visit mandatory for proposal eligibility, or may an offeror submit without attending?MICCAmber PeeblesNo
111If attendance was mandatory, will the Government offer another visit or other method to obtain the necessary site information?MICCAmber PeeblesNo.
112May a prime offeror rely on a qualified small-business moving subcontractor's relevant experience, licenses, fleet and past performance in its technical response, subject to all applicable subcontracting limitations?MICCAmber PeeblesThe government will accept proposals however the limitations on subcontracting apply and this will be a firm-fixed-price contract, so it is best to consider all risks involved.
113Please confirm that the current proposal deadline remains October 8, 2026, at 4:00 p.m. Eastern.MICCAmber PeeblesYes
114This is a nonbinding clarification request. A to Z will not prepare final pricing until eligibility and access requirements are confirmed.MICCAmber PeeblesThis will be a firm fixed price contract
115The SF1449 cover shows September 23, 2026, at 4:00 PM; Section L and the current SAM notice show October 8 at 4:00 PM. Please confirm the controlling offer deadline and that Eastern daylight time applies to the September/October deadlines and September 17 visit. 2. Section L identifies CLIN 0001 performance February 1-April 30, 2027, but the price instructions refer to a base year and evaluating the six-month extension at half of the last year's price. Please specify the required quoted period and exact option evaluation calculation.MICCAmber PeeblesAnswer: Offers are now due 23 October at 4PM (EST) Answer: There will be no six-month extension pricing. Just require a base year for CLIN 0001 performance February 1-April 30, 2027.
116Is September 17 site attendance required for eligibility or optional? We understand the access roster is due September 16 at 2:00 PM and have not committed attendees.MICCAmber PeeblesIt is not required just recommended.
117For a small-business prime coordinating appropriately qualified subcontractors, please confirm the applicable limitations-on-subcontracting/personnel-cost requirements and treatment of similarly situated small-business performers. Answer: We understand the proposed PM and foremen must each document three commercial/industrial relocations and the integration plan must identify specialist calibration/recommissioning roles; no teammate history would be represented as Aroi's own. FAR 52.219-14 Limitations on Subcontracting: "(1) Services (except construction), it will not pay more than 50 percent of the amount paid by the Government for contract performance to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 50 percent subcontract amount that cannot be exceeded. When a contract includes both services and supplies, the 50 percent limitation shall apply only to the service portion of the contract."MICCAmber PeeblesClarification to Technical Plan Evaluation requirements. The Evualution Criteria listed as Subcontractor Integration Plan has been removed.
118For the plumbing equipment/materials identified in the PWS, is the Contractor required to disconnect or reconnect any existing plumbing pipes, fittings, or connections as part of the relocation, or is the Contractor only responsible for moving the plumbing shop equipment and materials? If so, what type of materials are these (e.g., pipes, tools, etc.)?...) The shop folks will disconnect prior to the move.ENG/FMDalwuan Williams/CW2 McQueenRespective shops and sections will disconnect prior move.
119For the electrical shop equipment identified in the PWS, is the Contractor required to disconnect or reconnect any hardwired electrical equipment, wiring, or electrical connections during the relocation, or is the Contractor only responsible for moving the electrical shop equipment and materials? If so, what type of materials are these, (ie wires, connectors..etc) The shop folks will disconnect prior to the move.ENG/FMDalwuan Williams/CW2 McQueenANC electricains will disconnect all equipment wiring before move
120Can this task be completed before the 88 days or must we adhere strictly to that timeline?ENGRosil SaldanaYes. Shedule of Move being provided as part of the RFI
121Are we allowed to take videos and photos at the site visit?ENGRosil SaldanaYes for cost estimate purpose only.
122Please provide an itemized inventory of all hazardous or regulated materials to be relocated, including: •Material type, contents, and hazard classification, •Container quantities, dimensions, and weights, •Applicable Safety Data Sheets (SDS), •Identification of the responsible party for:
oPreparing, packaging, sealing, and labeling
oManifesting and transportation •Confirmation whether a separately licensed hazardous-material carrier is requiredSafety/EVJohn Redmond and ALLANMC has inventory lists and SDS sheets for all chemicals. Each section should provide the quantity and dimensions of each that will be transported. Clearer after Vendor selection
123Provide the current logistics plan and available drawings for the new facility, including: Vehicle entrances and gate clearances, Road and surface conditions, truck turning and maneuvering areas’, Loading/unloading locations, Overhead and vertical clearances, Building entrances and door dimensions, Interior travel paths, ramps, elevation changes, Floor-loading limitations, Restrictions affecting moving vehicles, forklifts, lifts, rigging, or material-handling equipmentENGAngela PedersenFloor Plan and schedule of the furnishings being provided as part of the RFI. New purchases to be located at new complex will be handled with Directorate POC. Access and opening dimensions provided.
124Confirm whether a pre-move walkthrough will be provided once the new facility is sufficiently complete, prior to finalizing the moving plan, staffing, equipment, and scheduleENGAngela PedersenPossible.
125If the new facility cannot be inspected before proposal submission, provide required bidder assumptions for:
•Access and unloading
•Interior movement and final placement
•Temporary storage or staging
•Remobilization or second handling Clarify how differing site conditions or construction delays will be addressed post-award.ENGFloor Plan and Items to Move Matirx provided as parti of this RFI
126Provide a final itemized inventory organized by building, room. Bay, or storage area. Identify whether each item is:
•Relocated
•Disposed
•Excluded
•Left in place Include elevations and locations for heavy or oversized items.ENGRosil Saldana with ALL to update marixFloor Plan and Items to Move Matirx will be provided
127Confirm which party will supply pallets, pallet boxes, reusable crates/totes, rolling bins, carts, and other containers. If contractor-provided, supply required quantities, specifications, delivery dates, staging requirement, and return schedule. Clarify whether government-owned containers onsite may be used.ALLALL - Recommending they do the packing and supplying all packing materialsMover will provide all packing materials. GOV owned containers are not for mover use.
128Clarify responsibility for:
•Packing and move preparation - contractor
•De-palletizing and unpacking - contractor
•Reassembly and final placement - contractor
•Removal of packing materials and debris - contractor
•Handling loose tools, hardware, parts, and supplies stored in shelves, drawers, cabinets, bins, and workstations. Confirm whether small items may remain in existing containers or require separate inventory and packing.ALLALL - Modification of Inventory MetrixResponsibility of hte contractor. With exceptions by directorate and their oversite.
129Provide dimensions, weights, elevations, and handling requirements for all heavy or fragile property, including:
•Two heavy servers stored on elevated pallet rack
•Stone, masonry, and concrete products
•Steel cabinets and storage units
•Shop machinery and fabrication equipment
•Snowplows and attachments
•Large tires and vehicle components
•Specialty or heavy equipment. Include lifting points, center-of-gravity data, manufacturer instructions, and handling restrictions.ALLALL - Modification of Inventory MetrixINventory being provided.
130Confirm responsibility of lowering heavy items stored on elevated racks. If contractor-responsible, provide:
•Required lift height
•Estimated load weights
•Confirmation of aisle widths, overhead clearances, floor conditions, and access routes suitable for rated equipment and certified operators.G4G4 - This pertains to you bay in Bldg 129.Yellow tag will be moved by Mover.
131Clarify whether items stored on existing pallets may be transported as-is or must be re-palletized. Identify responsibility for:
•Inspecting pallets
•Replacing damaged pallets
•Securing and wrapping loads
•Confirming pallet weights/dimensions
•Preparing loads for safe transportIO/Fleet/FM/ALL - modification of inventory MatrixRecommend that contractor is responsible for palletizing any items that they are moving. If they deem the pallet to be in sound condition that responsibility is on them.
132Identify all motirzed equipment and confirm whether each will be transported or operated under its own power. Clarify requirements for:
•Fuel removal or reduction
•Fluid containment
•Battery disconnection/removal
•Mechanical preparation
•Loading/transport
•Destination recommissioning
IO/Fleet/FM/ALL - modification of inventory MatrixContractors may NOT opperate GOV owned equipment. Inventory Matrix provided as part of the RFI
133Identify all equipment requiring utility disconnection/reconnection (electrical, gas, compressed, air, exhaust, ventilation, plumbing, fuel). Clarify which work must be performed by: •Government personnel
•Licensed trades
•Manufacturer-authorized technicians
•Specialty riggers
•Moving contractorENGRosil SaldanaDisconnection by respective Section prior relocation
134Confirm whether storage systems are included in the relocation or only their contents. If included, clarify responsibility for:
•Unloading
•Dismantling
•Component labeling
•Transportation
•Reassembly
•Anchoring
•Inspection and approval at destinationALLAll - Modificaton of Inventory MetrixStorage systems not to be relocated. Exeption: 1) of IO/QA who has 4 storag e cabinets. 2) Total of 4 HazMat containers to be relocated.
135Confirm whether the entire structure or only its contents are included. If relocating the structure, provide:
•Manufacturer/model
•Dimensions and empty weight
•Anchoring details
•Lifting points
•Utility connections
•Manufacture relocation instructions
•Destination pad/foundation requirements. Confirm responsibility for emptying, disconnecting, unanchoring, rigging, lifting, transporting, placing, reconnecting, and anchoring.ALLALL - Modification of Inventory MetrixStorage systems not to be relocated. Exeption: 1) of IO/QA who has 4 storag e cabinets. 2) Total of 4 HazMat containers to be relocated. (need to verify specs of these
136Provide procedure for documenting, tracking, and signing off on tagged property from pickup through final placement. Identify the authorized government representative responsible for verification and acceptance.ALLAll- Modification of Inventory matrixProcedure, tracking of property will be part of the fixed price by Mover.
137Provide all requirement for contractor personnel and vehicles, including:
•Background screening
•Badging and identification
•Personnel/vehicle information submissions
•Escort requirements
•Processing/approval lead times
•Site safety orientation
•Equipment-operator certifications
•Hazardous-material training
•Required PPEG2/SafetyG2/SafetyAll contractors must be vetted through the JBMHH Visitor Control Center and issued a badge in order to conduct work on ANC property. Vehicle information is required to be obtained by the COR in order to provide contractor vehicle passes. Escorts will only be required for afterhours work being performed (if any). The vetting process is alloted a 72 hour turn around time. See PWS Section 1.6.7.2. All required Safety training including operator certifications, hazardous material training and required PPE will be per the contractors Accident Prevention Plan and will be the responsibility of the contractor.
138Does the Government require certified calibration of shop machinery after reinstallation – that is, a calibration performed and certified by a qualified party? – or Is the requirement satisfied by reinstalling the equipment in its designated location, reconnecting it, and demonstrating that it powers on and functions, documented in the Installation and Functional Test Report?IO/FM/FleetHendley/McQueenNo.
139Could the Government identify which specific items of equipment require certified calibration, and whether any calibration certificates must be provided to the Government?IO/FM/FleetNot applicable.
140Will the Government provide an inventory or list of the hazardous materials to be relocated from Buildings G and H, and if so, at what point?Safety/EVANMC has inventory lists and SDS sheets for all chemicals. Each section should provide the quantity and dimensions of each that will be transported. Clearer after Vendor selection
141Does the Government classify the pesticides stored in Building G as hazardous material for purposes of the HMTA transportation requirements in this PWS?Safety/EV/HORTANMC has inventory lists and SDS sheets for all chemicals. Each section should provide the quantity and dimensions of each that will be transported. Clearer after Vendor selection.Follow up w/ HORT
142Are compressed gas cylinders present among the items to be relocated, and if so, does the Government expect the contractor to transport them, or will they be handled separately by the Government or another party?Fleet/Safety/EVBeatriz/JohnTo be relocated by Move Contractor.
143IO/FM/FleetMark UpshawHazardous waste will be divested through DLA and is not part of the move contract.
144Are auto lifts within the scope of items to be relocated under this contract? If they are, could the Government identify their number, type and location, since they do not appear in the PWS item list? If they are not, will an offeror whose Technical Rigging Narrative does not address auto lifts be evaluated as technically acceptable under Standard 3A?FleetBeatrizVehicle lifts are not part of the move contract
145Inventory: Please provide an inventory by building or department, including quantities, dimensions, weights, available photographs, and identification of items that will remain or be moved by government personnel.AllAll- Modification of Inventory matrixIventory being provided.
146Packing and unpacking: Please confirm whether the contractor must pack and unpack all office, shop, warehouse, and supply contents, including desk contents, files, tools, parts, and loose materials on shelving. Section 5.2 requires delivering packing materials to the customer but does not clearly identify any government packing responsibilities. If government personnel will pack or unpack any items, please identify those items and quantities.ALLDiscussion neededThe mover is not resposible for moving desk, cubbile partitions, shelving nor containers unless specifically identified.
147Heavy machinery: Please provide the makes, models, weights, dimensions, and handling requirements for machinery requiring relocation, including auto lifts, welding equipment, compressors, and carpentry machinery. Which items require specialized rigging or manufacturer-certified technicians?ALLAll- Modification of Inventory matrixINventory being provided.
148Equipment disconnection and installation: Does the contractor’s scope include electrical, plumbing, compressed-air, and gas disconnections and reconnections; floor anchoring; calibration; and certification? Please identify responsibilities assigned to government personnel or the construction contractor and confirm whether destination utility connections will be ready before equipment arrives.IO/Fleet/FM/Respective shops and sections will disconnect prior move.
149Staffing: Section 5.1 identifies one project manager, one scheduler, two foremen, and 15 movers/laborers, totaling 19 personnel, but states a total of 22. Please clarify the intended total and whether staffing levels are estimates or mandatory minimums. May staffing vary by move phase?ENGRosil Saldanad (COR)The personnel listed in the PWS was for cost estiamtion purposes. Contracor will provide the necessary manpower for the move. ANC believes there needs to be at least a Project Manager, a Scheduler, move leadres, and movers.
150Performance schedule: Please reconcile the 30-day pre-move consultation requirement in Section 1.6.23 with the solicitation requirement that all move phases begin no earlier than February 1, 2027. Are the two weeks of initial planning and two weeks of post-move support included within February 1–April 30, 2027? Please also clarify the conflicting references to 88 and 90 days.ENGRosil Saldana (COR)ANC has refined the scheduled/phased move. It is anticipated that packing/preparation will be conducged by the moved during a 2 week period before 1 February. There will be {#} number of days for training [what type]. Then the physical move will beging Feb [ #]. Scheudle phase is attached
151Facility readiness and delays: Please provide anticipated availability dates for each destination building. How will government-directed schedule changes, construction delays, standby, remobilization, temporary storage, and additional handling be addressed if destination facilities are unavailable as scheduled?ENGRosil Saldana (COR)Move will not begin until occupncy has been granted
152Move phases and operational requirements: Please identify required move dates and maximum allowable downtime for each shop or department. Technical Exhibit 1 requires machinery to be operational within two days of arrival. Does this mean calendar or working days, and how will this requirement apply when utilities or other government-provided prerequisites are unavailable?ENGRosil Saldana (COR)Will provide a Move Inventeroy Matrix and Move schedule
153Hazardous materials: Please provide the types, quantities, container sizes, and safety data sheets for hazardous materials to be handled. Identify which materials require relocation or disposal and who is responsible for draining, decontamination, and preparation for transport.Safety/EVJohn Redmond - UpshawANMC has inventory lists and SDS sheets for all chemicals. Each section should provide the quantity and dimensions of each that will be transported. Clearer after Vendor selection
154Disposal: Section 5.1 references placing expendable items into existing designated dumpsters, while Section 5.2 references transportation to the Defense Logistics Agency, dumpsites, or recycling facilities. Please identify the items and quantities for disposal, destinations, and responsibility for dumpsters, hauling, and disposal fees.Safety/EVMark UpshawANMC will addess transportation to DLA. If the move contractor will generate waste (eg. boxes, plastic, etc) it is the responsibilty of the contractor to provide theri disposal.
155Access and work hours: Please provide available floor plans, loading locations, door clearances, floor-load limits, approved travel routes, and staging areas for both complexes. What funeral-related restrictions or work stoppages should bidders anticipate? May evening or weekend work be approved?ENG/ALLAngela Pedersen/and ALL1) Angela working/dimension clerances 2) Rosil send RFI to ALL for laydown area since FLeet, IO, FM are main usesrs.
156Invoicing: May the contractor invoice monthly or upon completion of accepted move phases, or is invoicing permitted only after final completion? If partial invoicing is allowed, please identify the required milestones and supporting documentation.MICC
157Price submission: Please clarify the references to “Base Year,” “last year,” and the six-month extension in the pricing instructions for this approximately three-month relocation. Should bidders submit one total job price only, or also provide fully burdened labor rates and a breakdown of equipment, materials, and subcontract costs?ENGRosil Saldana (COR)This is fixed price to be awarded DEc 2026
158Insurance: Please specify the required insurance types and minimum coverage limits, including coverage for property in transit, machinery rigging, and hazardous-material handling.MICC
159Please clarify if ANC will have a forklift for us to use OR do we have to provide our own forklift.ENGRosil SaldanaMove contractor may not use GOV equipment. Contractor will have to cost rentar/purchase.
160Please provide a count of the grey containers in Bldg. 1350 since we couldn't see the containers behind the first row.FMMcQueenNeed response
161Will ANC provide the final Government-approved inventory of the items included in the move? This should include equipment, materials, machinery, attachments, crates, palletized freight, shop contents, and the applicable contents of Buildings 13–15 and Building 1350.ENGRosil Saldana (COR)Will provide a Move Inventeroy Matrix
162Will ANC identify any hazardous or regulated materials included in the move, including chemicals, solvents, automotive fluids, aerosols, paints, oils, and other regulated substances? If available, will ANC provide the applicable SDS information?Safety/EVMark Upshaw/RedmondANMC has inventory lists and SDS sheets for all chemicals. Each section should provide the quantity and dimensions of each that will be transported. Clearer after Vendor selection
163Will ANC provide the quantities and contents of the 55-gallon drums, oil kegs, fluid containers, pails, spill/recovery containers, and similar liquid-storage items included in the move? Will ANC indicate which containers are full, partially full, or empty?Safety/EVALL: what are these?ANMC has inventory lists and SDS sheets for all chemicals. Each section should provide the quantity and dimensions of each that will be transported. Clearer after Vendor selection
168Will ANC confirm the final quantity and types of tires and wheel assemblies included in the move, including oversized agricultural, earthmover, truck, trailer, turf, and skid-steer tires? If available, will ANC provide approximate weights for mounted wheel assemblies?IO/Fleet/FM/All- Modification of Inventory matrixInventory Matrix being provided as part of the RFI
169Will ANC identify the on-site staging and laydown areas that will be available during the move? Will ANC identify any restrictions on temporarily placing loaded pallets, crates, bins, equipment, or vehicles in these areas?ALLUsers to determine thisWill be proided.
170Will ANC confirm that each destination area will be cleared, accessible, and ready to receive materials when deliveries are scheduled? Will ANC identify any destination-specific access restrictions, receiving hours, or preparation requirements?ENGAngela PedersenFloor Plan and schedule of the furnishings being provided as part of the RFI. New purchases to be located at new complex will be handled with Directorate POC
171Will ANC identify any items that will need to be unpacked, uncrated, assembled, placed, or positioned at their destination, including items associated with the mobile shelving/parts areas?ALLAll- Modification of Inventory matrixINventory being provided.
172Will ANC clarify the requirements for disposal, recycling, or removal of packing materials, scrap, pallets, crates, damaged materials, and other waste generated during the move? If applicable, will ANC identify any Government-approved recycling or disposal locations?Safety/EVMark UpshawDisposal after the move of boxes, wrappers, is the responsibility of the Mover
173Will ANC confirm whether there are any requirements or restrictions regarding truck types, trailer lengths, liftgates, flatbeds, box trucks, tractor-trailers, or other transportation equipment used for the move?ENGRosil Saldana (COR)Vendors to provide.
174Will ANC identify any requirements for protecting floors, walls, doors, loading areas, landscaping, or other facility surfaces during the move? Will ANC identify any known site conditions that could affect the movement of heavy equipment or palletized materials?ENGOnly Administrative Building
175Will contractor be able to utilize an ANC forklift at the site to load the trucks with materials on pallets?ENGRosil Saldana (COR)Move contractor may not use GOV equipment. Contractor will have to cost rentar/purchase.
176Is contractor responsible for moving the hazardous materials located in the outside storage building being relocated?Safety/EVAll - Mark Upshaw/John RedmondANMC has inventory lists and SDS sheets for all chemicals. Each section should provide the quantity and dimensions of each that will be transported. Clearer after Vendor selection
177Is contractor responsible for unpacking the Parts Room into final destinations?FleetBeatrizYes.

This is the start of the file's text. The full file is on GovTribe.