2026 GFEBS Solicitation Questions_Answers update 4.02.2026 v2.pdf
PDF 280 KB Posted
- Solicitation number
- W91CRB-26-R-A014
About this file
This is a Questions and Answers document for the 2026 GFEBS (General Fund Enterprise Business System) Solicitation that clarifies two key issues raised by potential contractors.
The document confirms that the 30-day phase-in period is a separate contract period distinct from the 12-month base year. Additionally, it addresses a typographical error in the solicitation regarding submission requirements for Volume 3: Factor 3 - Cost/Price, clarifying that contractors should follow the instructions provided in section L rather than the conflicting language that incorrectly specified both hard and electronic copies. The government issued an amended solicitation on the morning of April 3, 2026 to correct this error.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2026 GFEBS Solicitation Questions/Answers
1. Could you please confirm if the 30-day phase-in period is separate from the 12-month base year?
Yes, the government confirms that the 30-day phase-in period is separate from the 12-month base year.
2. I just noticed the solicitation requires both hard and electronic copies of files for Volume 3: Factor 3 - Cost/Price (see text from the amended solicitation below). Is that correct?
No, this is a typo error. It is supposed to be read as is in section L, Volume 3: Factor 3 - Cost/Price, section a. Please follow instructions in section L. The government will issue an amended solicitation in the morning of 4/3/2026 to fix this error.