Questions-Answers.docx

DOCX document 20 KB Posted

Attached to
FY25 OHARNG CJAG Culvert Project Federal contract opportunity
Solicitation number
W91364-25-B-A008
Issued by
Department of the Army Ohio Army National Guard

About this file

This document is a Questions and Answers file for the FY25 CJAG Culvert Project (Solicitation #W91364-25-B-A005) issued by the Ohio Army National Guard Purchasing & Contracting Office. The project involves removing and replacing existing culverts and implementing erosion protection measures at the Camp James A. Garfield Joint Military Training Center in Ravenna, OH. Key details include a bid opening date of August 28, 2025, at 11:00 am, with the contractor responsible for designing culvert plans for the base bid only. The design plans and specifications must be completed within 90 days of the Notice to Proceed, with review and approval processes involving the Department of Public Works, OHARNG Environmental Office, and US Army Corps of Engineers. Haul routes are specified in Attachment 3, and the total land disturbance is expected to be less than one acre, with potential additional stakeholder involvement if the disturbance exceeds that threshold.

View the file

Other files for this federal contract opportunity

Other files attached to FY25 OHARNG CJAG Culvert Project, newest first.
File Type Posted
Bid Opening Sign-in Sheet.pdf PDF
Bid Abstract1419.pdf PDF
Bid Abstract 1419A.pdf PDF
Questions-Answers.docx DOCX document
CJAG_Priority Structure Recommendations.pdf PDF
Att3_CJAG 2025 Culvert Sites_rev2.pdf PDF
SOW- CJAG 2025 Culverts_rev1.docx DOCX document
Questions-Answers.docx DOCX document
Specifications for Facility Management Electronic Deliverables.pdf PDF
Questions-Answers.docx DOCX document
CJAG 2025 Culvert Sites_Att 3 Rev.pdf PDF
Site Visit Sign In Roster.pdf PDF
Questions-Answers.docx DOCX document
CJAG 2025 Culvert Sites.docx DOCX document
Wage Determination.pdf PDF
Bid Form.docx DOCX document
Environmental Procedures.pdf PDF
Solicitation - W9136425BA008.pdf PDF
SOW- CJAG 2025 Culverts.docx DOCX document
CJAG 2025 Culvert_Construction Details.docx DOCX document
Instructions to Bidders.docx DOCX document
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ohio Army National Guard Purchasing & Contracting Office 2825 W. Dublin-Granville Rd.

Columbus, OH. 43235

SUBJECT: Questions/Answers TITLE: FY25 CJAG Culvert Project

SOL#: W91364-25-B-A005

Q&A:

Question #1: I am looking at this project and going through the documentation and noticed that the SAM posting says this is due on August 27th and the solicitation states it is due on August 28th. Can you please confirm that this is due on the 28th?

Answer #1: The bid opening date will be the 28th of August 2025 at 11:00 am. The SAM.gov posting will be corrected.

Question #2: Agencies will be weighing in on the approval process City, County, FEMA, Ohio EPA etc)?

Answer #2: The CJAG Department of Public Works (DPW) will review and approve the design plans and specifications. The OHARNG Environmental Office and the US Army Corps of Engineers (USACE), Pittsburgh District will be involved in the review and approval of the Pre-Construction Notification (PCN’s). USACE may share the PCN with the Ohio EPA, but this is not anticipated. The total land disturbance for this project is expected to be less than one acre. If the land disturbance increases to over one acre the Portage County Engineer’s Office and the Portage Soil and Water Conservation District will need to be involved in the process.

Question #3: Will the contractor be responsible for the design of plans alternate options or just plans for both base bid options? There are no current plans supplied for the options.

Answer #3: The contractor will only be responsible for providing designs for the culverts in the base bid. The culverts in the optional line items will not require design.

Question #4: Once awarded, what is the time frame required for having the survey and engineering completed?

Answer #4: Design plans and specifications for construction should be completed within 90 days of Notice to Proceed.

Question #5: Are there designated haul routes? During the pre-bid meeting, there were bridges crossed with 15 TON weight limits.

Answer #5: The haul routes are shown on the revised Site Plans. Please see Attachment 3