CJAG 2025 Culvert Sites_Att 3 Rev.pdf

PDF 2 MB Posted

Attached to
FY25 OHARNG CJAG Culvert Project Federal contract opportunity
Solicitation number
W91364-25-B-A008
Issued by
Department of the Army Ohio Army National Guard

About this file

This document is an Attachment 3 - Site Plans for a federal contract (PN 3924007 CJAG 2025 Culvert Repairs) located in Ravenna, Ohio. The project involves multiple culvert repair and replacement tasks across different locations, including Base Bid and Optional Tasks: Task A involves replacing a 6' x 6' x 32' concrete box culvert on Smalley Road; Task B replaces a 48" x 162' RCP culvert with a catch basin; Option 2 includes erosion repairs at several sites involving rip rap installation; Option 3 covers Road 5C culverts with replacement of 18" x 40' and 12" x 30' culverts; Option 4 addresses Magazine Road culverts with multiple replacement and modification requirements; and Option 5 involves replacing twin 30" x 42' culverts on Randall Road.

The site plans include detailed geospatial coordinates for each task location, specified culvert dimensions, and installation requirements such as headwall and flared end installations. The main gate is located at 8451 State Route 5, Ravenna, OH, and the document includes a haul routes map showing the project area boundaries. Each task involves specific culvert infrastructure improvements, with most tasks requiring complete culvert replacement, installation of structural ends or headwalls, and in some cases, additional modifications like catch basin removal or roadside ditch rerouting.

View the file

Other files for this federal contract opportunity

Other files attached to FY25 OHARNG CJAG Culvert Project, newest first.
File Type Posted
Bid Opening Sign-in Sheet.pdf PDF
Bid Abstract1419.pdf PDF
Bid Abstract 1419A.pdf PDF
Questions-Answers.docx DOCX document
CJAG_Priority Structure Recommendations.pdf PDF
SOW- CJAG 2025 Culverts_rev1.docx DOCX document
Att3_CJAG 2025 Culvert Sites_rev2.pdf PDF
Specifications for Facility Management Electronic Deliverables.pdf PDF
Questions-Answers.docx DOCX document
Questions-Answers.docx DOCX document
Questions-Answers.docx DOCX document
Site Visit Sign In Roster.pdf PDF
Questions-Answers.docx DOCX document
CJAG 2025 Culvert Sites.docx DOCX document
SOW- CJAG 2025 Culverts.docx DOCX document
CJAG 2025 Culvert_Construction Details.docx DOCX document
Instructions to Bidders.docx DOCX document
Wage Determination.pdf PDF
Bid Form.docx DOCX document
Environmental Procedures.pdf PDF
Solicitation - W9136425BA008.pdf PDF
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PN 3924007 CJAG 2025 CULVERT REPAIRS

ATTACHMENT 3 – SITE PLANS

Overall Site Plan

OPTION 3, Task E:

Road 5C Culverts

OPTION 4, Task

F: Magazine Rd

Culverts

BASE BID, Task A:

Smalley Rd Box

Culvert

BASE BID, Task B:

Smalley Rd - Area

1A Culvert

Main Gate:

8451 State Route 5, Ravenna, OH

OPTION 5, Task

G: Randall Rd

Culvert

OPTION 2, Task

D: Erosion

Repairs

BASE BID, Task A: Smalley Rd Box Culvert

(41.215351, -81.112647)

Design and construct replacement of 6’ x 6’ x 32’ long concrete box culvert.

BASE BID, Task B: Smalley Rd at Area 1-A

(41.220903, -81.064154)

Design and construct replacement of 48” x 162’ RCP culvert and catch basin.

OPTION 2, Task D: NFR 2.52

41.191962, -81.144529

Install rip rap to protect against erosion and scour along east abutment at inlet and outlet.

OPTION 2, Task D: NFR 1.32

41.191953, -81.121933

Install rip rap to protect each abutment at inlet and at eroded sections of ditch.

OPTION 2, Task D: GLR2

41.212077, -81.089277

Install rip rap at inlet and outlet to protect against erosion and scour.

OPTION 2, Task D: GLR3

41.214409, -81.086743

Install rip rap at inlet and outlet to protect against erosion and scour.

OPTION 3, Task E: Road 5C Culverts

(41.189370, -81.130198)

Replace 18” x 40’ culvert. Install half-height headwalls each end.

Replace 12” x 30’ culvert.

OPTION 4, Task F: Magazine Rd Culverts

a. Replace 18” x 38’ culvert.

Install flared ends each end.

Remove 18” x 34’ culvert and catch basin and replace with swale.

b. Replace 18” x 52’ culvert.

d. Replace 42” RCP x 54’ culvert. Install full-height headwalls each end. Catch basin to be removed. Reroute roadside ditches to inlet.

c. Replace 18” x 38’ culvert.

Remove 18” x 34’ culvert and (2) catch basins and replace with swale.

OPTION 5, Task G: Randall Road Twin Culvert

41.2074, -81.0297

Replace twin 30” x 42’ culvert. Install half-height headwalls each end.

Haul Routes

Main Gate:

8451 State Route 5, Ravenna, OH

1603720950.ctr Polygonal Line

1603720950.ctr Polygonal Line

1603720950.ctr Polygonal Line

1603720950.ctr Polygonal Line

1603720950.ctr Line

1603720950.ctr Polygonal Line