Attach3-Vol_2_Specs.pdf
PDF 2 MB Posted
- Attached to
- Repair Maintenance Hangar, B102 Federal contract opportunity
- Solicitation number
- W9136419B7001
About this file
This federal contract opportunity notice solicits bids for Project No. PBXP 132166 to repair and renovate Building 102 at Mansfield Air National Guard Base in Mansfield, Ohio. Work includes demolition, fire protection and suppression systems, mechanical, plumbing and electrical upgrades, renovating exterior brick and metal siding, replacing windows and doors, and meeting energy efficiency and antiterrorism force protection goals. The construction duration is 577 calendar days from notice to proceed. There are no options or additive bid items. The solicitation is set aside for small businesses with a NAICS code of 236220 and $36.5 million size standard. The magnitude is between $10-25 million. A pre-bid conference is July 30, 2019 at 10:00 am. The bid opening is August 23, 2019 at 1:00 pm. Interested parties must register in SAM and check the FedBizOpps website for solicitation documents and any amendments. The Department of the Army Ohio Army National Guard issued this opportunity notice.
Specifications-Vol 2
View the file
Other files for this federal contract opportunity
Show all 50
Repair Maintenance Hangar, B102 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
T Y P E B - 3 F I N A L
Repair MX Hangar Project Number PBXP132166
Volume 2 – Specifications (1 of 4)
Prepared for
179th Civil Engineering Squadron Ohio Air National Guard
Mansfield Lahm ANG Base
February 2019
CH2MHILL– HDR JV
241 Taylor Street, Suite 100
Dayton, Ohio, 45402
REPAIR MX HANGAR
MANSFIELD, OHIO
PW\DENOOl\6698 16
FEBRUARY 2019
SEALS PAGE
00 01 07 - 1
SECTION 00 01 07
SPECIFICATIONS
DIVISION 01 - GENERAL REQUIREMENTS
DIVISION 03 - CONCRETE
DIVISION 04 - MASONRY
DIVISION 05 - METALS
Digitally Signed on
February 5, 2019
Dennis Pearson
PW\DENOOl\6698 16
FEBRUARY 2019
00 01 07 - 2
DIVISION 02 - EXISTING CONDITIONS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
DIVISION 08 - OPENINGS
DIVISION 09 - FINISHES
DIVISION 10 - SPECIALTIES
John Baudry
PW\DEN001\669816
FEBRUARY 2019
00 01 07 - 3
DIVISION 21 – FIRE SUPPRESSION
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
DIVISION 33 - UTILITIES
Carl Osberg
PW\DEN001\669816
FEBRUARY 2019
00 01 07 - 4
DIVISION 22 – PLUMBING
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
Darren Magley
PW\DEN001\669816
FEBRUARY 2019
00 01 07 - 5
DIVISION 26 – ELECTRICAL
Lisa H. Coppinger
PW\DEN001\669816
FEBRUARY 2019
00 01 07 - 6
DIVISION 27 - COMMUNICATIONS
Tim E. Sears
PW\DEN001\669816
FEBRUARY 2019
00 01 07 - 7
DIVISION 03 - CONCRETE
DIVISION 31 – EARTHWORK
DIVISION 32 – EXTERIOR IMPROVEMENTS
Amanda Thompson
END OF SECTION
PROJECT TABLE OF CONTENTS Page 1
PROJECT TABLE OF CONTENTS
VOLUME 2
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 22 00.00 10 PRICE AND PAYMENT PROCEDURES
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 33 29 SUSTAINABILITY REPORTING
SUPPLEMENT: SUBMITTAL REGISTER
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 QUALITY CONTROL
01 45 35 SPECIAL INSPECTIONS, TESTS, AND OBSERVATIONS FOR
STRUCTURAL SYSTEMS
SUPPLEMENT: SPECIAL INSPECTION RECORD
SUPPLEMENT: SPECIAL INSPECTION DAILY REPORT
SUPPLEMENT: SPECIAL INSPECTION DISCREPANCY NOTICE
SUPPLEMENT: SPECIAL INSPECTION FINAL REPORT
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 PROJECT IDENTIFICATION
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 91 00.15 TOTAL BUILDING COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
02 82 13.00 10 ASBESTOS ABATEMENT
02 84 16 HANDLING OF LIGHTING BALLASTS AND LAMPS CONTAINING PCBs
AND MERCURY
VOLUME 3
DIVISION 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
03 42 13.00 10 PLANT-PRECAST CONCRETE PRODUCTS FOR BELOW GRADE
CONSTRUCTION
DIVISION 04 - MASONRY
04 20 00 UNIT MASONRY
DIVISION 05 - METALS
05 12 00 STRUCTURAL STEEL
05 21 00 STEEL JOIST FRAMING
05 30 00 STEEL DECKS
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 51 00 METAL STAIRS
05 51 33 METAL LADDERS
05 52 00 METAL RAILINGS
PROJECT TABLE OF CONTENTS Page 2
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
6 61 16 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
7 21 13 BOARD AND BLOCK INSULATION
07 27 10.00 10 BUILDING AIR BARRIER SYSTEM
07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS
07 42 63 FABRICATED WALL PANEL ASSEMBLIES
07 60 00 FLASHING AND SHEET METAL
07 81 00 SPRAY-APPLIED FIREPROOFING
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 33 23 OVERHEAD COILING DOORS
08 39 54 BLAST RESISTANT DOORS
08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS
08 60 45 TRANSLUCENT PANEL SYSTEMS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
08 91 00 METAL LOUVERS
DIVISION 09 - FINISHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 30 10 CERAMIC, QUARRY, AND GLASS TILING
09 65 00 RESILIENT FLOORING
09 67 23.15 FUEL RESISTIVE RESINOUS FLOORING, 3-COAT SYSTEM
09 90 00 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 11 00 VISUAL DISPLAY UNITS
10 14 00.20 INTERIOR SIGNAGE
10 21 13 TOILET COMPARTMENTS
10 22 26.13 ACCORDION FOLDING PARTITIONS
10 28 13 TOILET ACCESSORIES
10 44 16 FIRE EXTINGUISHERS
10 51 13 METAL LOCKERS
10 99 99 MISCELLANEOUS SPECIALTIES - DRAFT (SMOKE) CURTAINS
DIVISION 14 - CONVEYING EQUIPMENT
14 21 23 ELECTRIC TRACTION PASSENGER ELEVATORS
DIVISION 21 - FIRE SUPPRESSION
21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION
21 13 20.00 20 FOAM FIRE EXTINGUISHING FOR AIRCRAFT HANGARS
21 30 00 FIRE PUMPS (PACKAGED)
PROJECT TABLE OF CONTENTS Page 3
VOLUME 4
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC
23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING
CONTROL SYSTEMS
23 11 25 FACILITY GAS PIPING
23 23 00 REFRIGERANT PIPING
23 54 19 BUILDING HEATING SYSTEMS, WARM AIR
23 64 26 CHILLED, CHILLED-HOT, AND CONDENSER WATER PIPING SYSTEMS
23 81 00.00 20 UNITARY AIR CONDITIONING EQUIPMENT
DIVISION 26 - ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 13.00 40 MEDIUM-VOLTAGE CABLES
26 05 71.00 40 LOW VOLTAGE OVERCURRENT PROTECTIVE DEVICES
26 08 00 APPARATUS INSPECTION AND TESTING
26 12 19.00 40 PAD-MOUNTED, LIQUID-FILLED, MEDIUM-VOLTAGE TRANSFORMERS
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 24 13 SWITCHBOARDS
26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION
26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS
26 41 00 LIGHTNING PROTECTION SYSTEM
26 51 00 INTERIOR LIGHTING
26 56 00 EXTERIOR LIGHTING
26 60 13.00 40 LOW-VOLTAGE MOTORS
VOLUME 5
DIVISION 27 - COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
27 51 23.10 INTERCOMMUNICATION SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
DIVISION 31 - EARTHWORK
31 05 19 GEOTEXTILE
31 23 00.00 20 EXCAVATION AND FILL
31 32 11 SOIL SURFACE EROSION CONTROL
PROJECT TABLE OF CONTENTS Page 4
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 05 33 LANDSCAPE ESTABLISHMENT
32 11 16.16 BASE COURSE FOR RIGID AND SUBBASE COURSE FOR FLEXIBLE
PAVING
32 11 23 AGGREGATE BASE COURSE
32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS
32 13 11 CONCRETE PAVEMENT FOR AIRFIELDS AND OTHER HEAVY-DUTY
PAVEMENTS
32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE
FACILITIES
32 13 73 COMPRESSION JOINT SEALS FOR CONCRETE PAVEMENTS
32 16 13 CONCRETE SIDEWALKS, STOOPS, AND CURBS AND GUTTERS
32 17 24.00 10 PAVEMENT MARKINGS
32 31 13.53 HIGH-SECURITY CHAIN LINK FENCES AND GATES
32 92 23 SODDING
33 11 00 WATER UTILITY DISTRIBUTION PIPING
33 16 15 WATER STORAGE STEEL TANKS
33 30 00 SANITARY SEWERS
33 40 00 STORM DRAINAGE UTILITIES
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
-- End of Project Table of Contents --
SECTION 01 11 00 Page 1 PW\DEN001\669816
PART 1 GENERAL
1.1 SUBMITTALS
SECTION 01 11 00
SUMMARY OF WORK
08/15
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Utility Outage Requests
Utility Connection Requests
Borrow Permits
Excavation Permits
Welding Permits
Burning Permits
Salvage Plan; G
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The work includes, but is not limited to, the items listed below and incidental related work. See design drawings and specifications for a full description of the work to be performed.
a. Asbestos, lead paint, PCB, and mercury abatement.
b. Demolition of exterior walls and interior partitions.
c. Demolition of existing two-story mezzanine in hangar bay.
d. Select demolition of existing structure, finishes, equipment, and utilities.
e. Site work including installation of new oil water separator, new sidewalks, and drive access to the new shop spaces.
f. Installation of new interior partitions, and anti-terrorism (AT) compliant exterior walls, doors, and windows.
g. Construction of a new two-story mezzanine within the hangar bay, including a new elevator.
SECTION 01 11 00 Page 2 PW\DEN001\669816
h. Installation of new high expansion foam and sprinkler fire suppression systems, including exterior water storage tanks and pump house.
i. Installation of new compressed air lines, air handling equipment, stratification fans, and ductwork.
j. Electrical upgrades and new transformer.
k. Installation of new WLAN infrastructure and intercom upgrades.
l. Repair and restoration of hangar metal wall panels.
m. Relocation of government furnished equipment from other buildings on base to this project.
1.2.2 Location
The work is located at existing building 102 at Mansfield Lahm Air National
Guard Base, Ohio. The exact location will be shown by the Contracting
Officer.
1.3 CONTRACT DRAWINGS
Design drawings accompany this specification and are a part thereof.
Five sets of full size contract drawings, maps, and specifications will be furnished to the Contractor without charge. Reference publications will not be furnished. Immediately check furnished drawings and notify the
Government of any discrepancies.
1.4 WORK RESCHEDULING
Allow for a maximum of 5 calendar days in the construction schedule where construction activity is prohibited due to operations. Government will provide 24 hour notification each time the restrictions are invoked.
Normal duty hours for work are from 6:00 a.m. to 4:30 p.m., Monday through
Friday. Requests for additional work requires written approval from the
Contracting Officer 7 days in advance of the proposed work period.
1.5 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
SECTION 01 11 00 Page 3 PW\DEN001\669816
1.6 ON-SITE PERMITS
1.6.1 Utility Outage Requests and Utility Connection Requests
Schedule work to minimize outages. For utility outages and connections required during the execution of work that affect existing systems, schedule outside the regular working hours or on weekends, as approved by the Contracting Officer. Schedule utility outages and connections to minimize disruptions to the Government. No additional payment will be provided for utility outages and connections required to be performed outside the regular work hours.
Submit requests for utility outages and connections in writing to the
Contracting Officer for approval at least 14 calendar days in advance of the time required. In each request, state the system involved, area involved, approximate duration of outage, and the nature of work involved.
1.6.2 Borrow, Excavation, Welding, and Burning Permits
ACTIVITY SUBMISSION DATE
Burning Permits 3 calendar days prior to work
Excavation Permits 14 calendar days prior to work
Welding Permits 3 calendar days prior to work
Post permits at a conspicuous location in the construction area.
Burning of trash or rubbish is not permitted at on project site.
1.7 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation, and comply with
Installation requirements for locating and marking underground utilities.
Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.
Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating
Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities, and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.7.1 Notification Prior to Excavation
Notify the Contracting Officer at least 15 days prior to starting excavation work.
SECTION 01 11 00 Page 4 PW\DEN001\669816
1.8 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT
Pursuant to Contract Clause "FAR 52.245-1, Government Property", the
Government will furnish the following materials and equipment for installation by the Contractor:
DESCRIPTION QUANTITY
Test Stand Chiller 1
Quantities indicated for the above-listed items marked with an asterisk are estimates. It is the intention of the Government to furnish all quantities of the asterisk items required to complete the work as specified, and the various quantities will be adjusted when necessary. Quantities stated for the above items not marked with an asterisk are all that will be furnished by the Government. Provide any additional quantities that are required.
1.8.1 Delivery Schedule
Notify the Contracting Officer in writing at least 30 calendar days in advance of the date on which equipment are required. Pick up equipment no later than 30 calendar days after such date.
1.9 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area.
Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Use a system of property control that is approved by the Contracting Officer. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
-- End of Section --
SECTION 01 11 00 Page 5 PW\DEN001\669816
1.1 SUBMITTALS
SECTION 01 14 00
WORK RESTRICTIONS
11/11 submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance with
Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
Government Guard Services; G
Medical Plan; G
Contractor Regulations; G
Transportation of Personnel, Materials, and Equipment; G
Purchase Orders; G
List of Contact Personnel; G
Personnel List; G
Vehicle List; G
Statement of Acknowledgement Form SF 1413; G
1.2 SPECIAL SCHEDULING REQUIREMENTS
a. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.
b. The adjacent fire station and associated drive access will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.
c. Permission to interrupt any Activity roads, railroads, or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Ohio Laws
a. Persons operating a motor vehicle onto the installation will have a valid state motor vehicle operator’s license and proof of insurance in their possession.
b. Ohio Motor Vehicle Laws are applicable while on the 179th Airlift Wing.
SECTION 01 11 00 Page 6 PW\DEN001\669816
c. The speed limit on the installation is fifteen (15) miles per hour unless otherwise posted. Speed limits are enforced by the use of Laser
Speed Measuring Devices (LSMD).
d. Drivers must comply with all posted traffic signs.
e. Vehicle restraints (seat belts) must be worn on base in compliance with
Ohio law.
f. Local law enforcement agencies have proprietary jurisdiction with the
179AW. That is, criminal offenses having occurred within the jurisdiction of the 179AW may be investigated by either military and/or civilian law enforcement agencies.
1.3.1.2 Background Checks
a. Contractors, sub-contractors, any their employees are required to have a nationwide criminal background check conducted before being granted authority for “un-escorted entry” onto the 179th Airlift Wing. Only
Federal Government personnel are authorized to escort non-cleared contractor personnel onto base.
b. It is the primary contractor’s responsibility to ensure information is provided for nationwide criminal background checks are conducted on all employees (e.g. primary contractor and subcontractor employees) who will be working on the 179 Airlift Wing installation and it’s jurisdictions for. Information is provided through submission of Base Access Form.
c. Contractor background check information must be submitted to the 179 SFS before any contracted employees will be allowed access onto the installation unless prior arraignments have been made through coordination with the the 179 AW Contracting Office.
d. If a contractor employee has an active warrant, the employee will be denied access to the installation and local law enforcement will be contacted by the 179th Security Forces Squadron.
e. The 179th SFS/S-5 Section may deny access and access credentials to the
179th Airlift Wing Air National Guard Base, based on information obtained during identity vetting that indicates the individual may present a threat to the good order, discipline and morale of the installation. This memorandum will serve as guidance, and approval to deny entry. Upon request, the 179th SFS S-5 section will review on a case by case basis, if the personal being vetted have an objection. The
179th SFS S5 section will not disclose criminal history information to the contractors, due to law enforcement sensitive information.
f. Contractors, sub-contractors, and their employees will enter and exit the installation through the Main Gate located at 1947 Harrington-
Memorial Road.
g. Contractors will be added to the Entry Authority List once vetted.
Contractors working on the installation longer than 30 days should come get a DBIDs Credential from the SF building on Tuesdays from 0900-1100.
SECTION 01 11 00 Page 7 PW\DEN001\669816
1.3.1.3 Installation Entry
a. Construction and delivery vehicles will be subject to vehicle inspection daily and privately owned vehicles will be inspected at random in accordance with Department of Defense and Air Force directives.
b. Contractor employees must possess valid picture identification such as a state-issued driver’s license or state-issued identification card at all times while on the installation. This picture identification must include, as a minimum, the physical description of the individual (i.e., height, weight, date of birth, eye and hair color), a picture of the individual, and the individual’s signature.
c. At the time contractors initially come to the pre-construction meeting;
they will be given copies of contractor access instructions/forms and other documentation to be used by the 179th Security Forces Squadron to generate a Contractor Entry Authority Lists (CEALs).
d. Vehicles owned by your firm will be permitted entry to 179 AW, Mansfield
Lahm Airport (ANG) Base, provided they are listed on the Contractor
Entry Authority List. Vehicles used in one time delivery of materials or by subcontractors do not need to be included on this list.
e. It is the sole responsibility of the contractor to renew through adding or deleting employees to the CEAL. Please keep this in mind for employees you may dismiss from your company.
1.3.1.4 Prohibited Items
No person shall bring or possess any of the following items while on the
179th Airlift Wing, Mansfield Ohio Air National Guard Base:
a. Weapons. In the interest of public safety, the items listed below are considered dangerous weapons.
b. Instruments capable of propelling a projectile by compressed air, gasses, springs, or other mechanical or physical means. Such weapons include, but are not limited to, firearms, paint ball guns, pellet guns, BB guns, blowguns, bows and arrows, underwater spear guns, hunting slingshots, and throwing spears.
c. An instrument, which has the capacity to inflict death and from the manner in which it is used is likely to produce or may easily and readily produce death. The following instruments are included in, but not limited to, this category. Knives in excess of 3 inches, spring-loaded knives (switchblades), swords, blackjacks, metal knuckles, "Nunchacku" fighting sticks, kung-fu stars, boomerangs, chains
(wrapped), and billy clubs. Possession of these items are expressly prohibited.
d. Explosive Material: Consists of but is not limited to, ammunition, gunpowder, firecrackers, and similar items.
e. Narcotics or drugs in any quantity except for those prescription drugs issued by a licensed pharmacist based on written prescription from a licensed medical doctor for health care purposes.
f. Drug paraphernalia and any contents contained therein.
SECTION 01 11 00 Page 8 PW\DEN001\669816
g. Alcoholic beverages, which includes but is not limited to beer in open containers no matter what the quantity, is strictly prohibited from being consumed on the base and/or job site.
1.3.1.5 Medical Emergencies
a. If an employee is injured or has a medical emergency notify Base Defense
Operations Center (BDOC) 911 or (419)520-6260.
o If calling from an on-base phone dial the 3-digit extension 911.
o If calling from a cell phone you must dial the entire prefix (419)
520-6260.
o Dialing 9-1-1 from a cell phone will ring in to the local area civilian 911 center.
b. You may contact BDOC in person or by phone by dialing (419)520- 6260/6259. Contractors may also make contact with any Security Forces patrols (vehicles/foot) at any time.
1.3.1.6 Severe Weather
a. Severe weather watches/warnings and safety instructions are announced over the installation public address system. Contractors are required to listen to these announcements and to follow the directions made over the public address system, made by the contracting officer’s representative, or by Emergency Personnel/Security Forces members.
b. Contractors are to seek shelter, secure their job site(s) and consider ceasing all outside activity immediately. Contractors will need to follow all safety instructions announced over the public address system or by authorized personnel.
c. Lightning warnings are declared when there is lightning within five (5) miles of the installation. Contractors are to cease all outside activity immediately and will seek shelter inside a building(s) or vehicle. Contractors will remain inside the building/vehicle until the lightning warning has been cancelled.
1.3.1.7 Photography
a. Photography of the Aircraft, Aircraft Parking Ramp or any security device or practices is strictly prohibited.
1.3.1.8 Restricted and Controlled Areas and Posted Sentries
a. Entering a “RESTRICTED AREA” (i.e. Aircraft Parking Ramp) or a
“CONTROLLED AREA” (i.e. aircraft hangars, marked facility, etc) without the permission of the Installation Commander is a CRIMINAL OFFENSE.
b. Posted Sentries are armed and have legal authority on the installation, much the same as a civilian police officer’s authority off-base.
1.3.1.9 Personnel Entry Approval
Failure to obtain entry approval will not affect the contract price or time of completion.
SECTION 01 11 00 Page 9 PW\DEN001\669816
1.3.1.10 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.3.2 Working Hours
Regular working hours must consist of a period established by the
Contracting Officer, between 6:00 a.m. and 4:30 p.m., Monday through
Friday, excluding Government holidays.
1.3.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the
Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer.
1.3.4 Occupied and Existing Buildings
The Contractor shall be working in an existing building and around existing buildings which are occupied. Do not enter the buildings without prior approval of the Contracting Officer.
The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.
Provide dust covers or protective enclosures to protect existing work that remains and Government material during the construction period.
Leave attached equipment in place, and protect it against damage, or temporarily disconnect, relocate, protect, and reinstall it at the completion of the work.
The Government will remove and relocate other Government property in the areas of the buildings scheduled to receive work.
1.3.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required paragraph WORK OUTSIDE REGULAR HOURS.
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, and compressed air are considered utility cutovers pursuant to the paragraph WORK
OUTSIDE REGULAR HOURS.
d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, SECTION 01 11 00 Page PW\DEN001\669816 including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.
e. Connection to Existing Sanitary Sewer Line: Provide positive verification that the existing line conveys sanitary sewer; verify line is not incorrectly connected to a storm drain. Obtain Installation's
Sanitary Sewer Connection Permit 2 weeks prior to connection and in accordance with Section 33 30 00 SANITARY SEWERS.
SECTION 01 22 00.00 10 Page 1 PW\DEN001\669816
1.1 REFERENCES
SECTION 01 22 00.00 10
PRICE AND PAYMENT PROCEDURES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM A615/A615M (2016) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete
Reinforcement
ASTM C127 (2015) Standard Test Method for Density, Relative Density (Specific Gravity), and
Absorption of Coarse Aggregate
ASTM C128 (2015) Standard Test Method for Density, Relative Density (Specific Gravity), and
Absorption of Fine Aggregate
1.2 SUBMITTALS
used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section
01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with
Section 01 33 00 SUBMITTAL PROCEDURES:
SD-03 Product Data
Weight Certificates
1.3 SINGLE JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING PROPOSAL SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
SECTION 01 22 00.00 10 Page 2 PW\DEN001\669816
1.3.1 Mobilization and Demobilization
1.3.1.1 Payment
Payment will be made for costs associated with mobilization and demobilization, as defined in Special Clause PAYMENT FOR MOBILIZATION AND
DEMOBILIZATION.
1.3.1.2 Unit of Measure
Unit of measure: Job.
1.3.2 Structure No. 1
1.3.2.1 Payment
Payment will be made for costs associated with operations necessary for construction of the structure at Station XX+XX.
1.3.2.2 Unit of Measure
1.3.3 Structure No. 2
1.3.3.1 Payment
Payment will be made for costs associated with operations necessary for construction of the structure at Station YY+YY.
1.3.3.2 Unit of Measure
1.4 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING PROPOSAL SCHEDULE and described below. The unit price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
1.4.1 Excavation
1.4.1.1 Payment
Payment will be made for costs associated with excavation for the structure, which includes performing required excavation and other operations incidental thereto, Contractor-furnished disposal area(s) and disposition of excess excavated material and unsuitable and frozen materials.
1.4.1.2 Measurement
The total quantity of excavated material for which payment will be made will be the theoretical quantity between the ground surface as determined by a survey and the grade and slope of the theoretical cross sections indicated. No allowance will be made for overdepth excavation or for the
SECTION 01 22 00.00 10 Page 3 PW\DEN001\669816 removal of any material outside the required slope lines unless authorized.
1.4.1.3 Unit of Measure
Unit of measure: Cubic yard.
1.4.2 Riprap
1.4.2.1 Payment
Payment will be made for costs associated with furnishing, transporting, stockpiling (if applicable), placing, and constructing the stone protection as specified.
1.4.2.2 Measurement
Measure riprap for payment by the ton (2,000 pounds) by weighing each truckload to the nearest 0.1 ton, and the final quantity of the whole sum is rounded to the nearest whole ton. Weigh the riprap for payment on approved scales before being placed in the work. Quarry weights will not be accepted. Use scales of sufficient length to permit simultaneous weighing all axle loads. Scales must be inspected, tested and sealed as directed to assure accuracy with 0.5 percent throughout the range of the scales. Certify scales located at the site of the work as to accuracy by an acceptable scales company representative prior to weighing any riprap.
Scales will be checked and certified before riprap hauling and rechecked and recertified whenever a variance is suspected. Furnish the scales. If commercial scales are readily available in close proximity, 10 miles of site of work, the Contracting Officer may approve the use of the scales.
Weigh riprap in the presence of the Government representative. The
Contracting Officer may elect to accept certified weight certificates furnished by a public weighmaster in lieu of scale weights at the jobsite.
1.4.2.3 Unit of Measure
Unit of measure: Ton (2,000 pounds).
1.4.3 Deformed Steel Bars for Concrete Reinforcement
1.4.3.1 Payment
Payment will be made for costs associated with furnishing, transporting, delivering, and placing deformed steel bars for concrete reinforcement, which includes steel in laps as indicated or as required. No payment will be made for the additional steel in laps which are authorized for the convenience of the Contractor. No separate payment will be made for accessories; include payment in the contract unit price for the items of work to which the accessories are incidental.
1.4.3.2 Measurement
The measured lengths of deformed steel bars for concrete reinforcement will be converted to weights for the size of bars listed by the use of the nominal weights per lineal foot specified in ASTM A615/A615M.
1.4.3.3 Unit of Measure
Unit of measure: Per pound in place.
SECTION 01 22 00.00 10 Page 4 PW\DEN001\669816
1.4.4 Bituminous Base Course
1.4.4.1 Measurement
Bituminous Base Course will be measured for payment based upon the number of tons (2,000 pounds) of bituminous mixture used in the accepted work.
Weigh the bituminous mixture after mixing, no deductions will be made for the weight of bituminous material incorporated in the mix. Quantities of paving mixtures called for in bid schedule are based on aggregates having a specific gravity of 2.65 as determined according to apparent specific gravity paragraphs in ASTM C127 and ASTM C128. Correct the tonnage of bituminous base course mixtures to compensate for the difference in the tonnage of mixtures used in the project, when specific gravities of aggregates used are more than 2.70 and less than 2.60. The tonnage paid for is the number of tons used, proportionately corrected for specific gravities using 2.65 as the base correctional factor.
1.4.4.2 Unit of Measure
Unit of measure: Ton (2,000 pounds).
1.4.5 Bituminous Materials
1.4.5.1 Payment
Payment will be made for costs associated with bituminous materials.
1.4.5.2 Measurement
Bituminous materials will be measured for payment based upon the number of tons (2,000 pounds) of the material used in the accepted work.
1.4.5.3 Unit of Measure
Unit of measure: Tons (2,000 pounds).
1.5 CONTAMINATED SOIL REMOVAL
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING PROPOSAL SCHEDULE and described below. The unit price and payment made for each item listed must constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
1.5.1 Unit of Measure
Unit of measure: Cubic yard.
3.1 CONTRACT COST BREAKDOWN
The Contractor must furnish within 30 days after the date of Notice to
SECTION 01 22 00.00 10 Page 5 PW\DEN001\669816
Proceed, and prior to the submission of its first partial payment estimate, a breakdown of its single job pay item or items which will be reviewed by the Contracting Officer as to propriety of distribution of the total cost to the various accounts. Any unbalanced items as between early and late payment items or other discrepancies will be revised by the Contracting
Officer to agree with a reasonable cost of the work included in the various items. This contract cost breakdown will then be utilized as the basis for progress payments to the Contractor.
SECTION 01 30 00 Page 1 PW\DEN001\669816
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements
Manual used, a designation following the "G" designation identifies the office that will review the submittal for the Government.Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance with accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
View Location Map; G
Progress and Completion Pictures; G
1.3 VIEW LOCATION MAP
Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.
1.4 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600 x 1200 x 24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work.
Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten views from points located by the Contracting
Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures. Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file. Include a date designator in file names. Cross reference submittals in the appropriate daily report. Photographs provided are for unrestricted use by the Government.
SECTION 01 30 00 Page 2 PW\DEN001\669816
1.5 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 LIABILITY, during the entire period of performance under this contract. Provide other insurance coverage as required by Ohio law.
1.6 FIRST TIER CONTRACTOR REQUIREMENTS FOR ASBESTOS CONTAINING MATERIALS
Accomplish all contract requirements of Section 02 82 13.00 10 ASBESTOS
ABATEMENT, assigned to the Private Qualified Person, Designated Competent
Person, directly with a first-tier subcontractor.
1.7 SUPERVISION
1.7.1 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.
1.7.2 Superintendent Qualifications
The project superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
For routine projects where the superintendent is permitted to also serve as the Quality Control (QC) Manager as established in Section 01 45 00.00 10
QUALITY CONTROL, the superintendent must have qualifications in accordance with that section.
1.7.2.1 Duties
The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.
The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.7.3 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
SECTION 01 30 00 Page 3 PW\DEN001\669816
1.8 PRECONSTRUCTION CONFERENCE
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form
1354" Submittal. Major subcontractors who will engage in the work must also attend.
1.9 PARTNERING
To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, the Contractor and their Subcontractors. Key personnel from the Supported Command, the End User (who will occupy the facility), the Government Design and Construction team and Subject Matter
Experts, the Installation, the Contractor and Subcontractors, and the
Designer of Record will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project that is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule.
The Contracting Officer will provide additional information on the
Partnering Process and a list of key and optional personnel who should attend the Partnering meeting, at time of Pre-Construction Conference.
1.9.1 NOT USED
1.9.2 Informal Partnering
The Contracting Officer will organize the Partnering Sessions with key personnel of the project team, including Contractor personnel and
Government personnel.
The Initial Partnering session should be a part of the Pre-Construction
Meeting. Partnering sessions will be held at a location agreed to by the
Contracting Officer and the Contractor (typically a conference room provided by the Base Resident Engineer office or the Contractor). The
Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by the
Contracting Officer. The Partners will determine the frequency of the follow-on sessions, at no more than 3 to 6 month intervals.
SECTION 01 30 00 Page 4 PW\DEN001\669816
1.10 ELECTRONIC MAIL (E-MAIL) ADDRESS
Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 days after contract award, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats.
Multiple email addresses are not allowed.
It is the Contractor's responsibility to make timely distribution of all
Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of any changes to this email address.
SECTION 01 32 01.00 10 Page 1 PW\DEN001\669816
SECTION 01 32 01.00 10
PROJECT SCHEDULE
02/15
AACE INTERNATIONAL (AACE)
AACE 29R-03 (2011) Forensic Schedule Analysis
AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
Project Scheduler Qualifications; G
Preliminary Project Schedule; G
Initial Project Schedule; G
Periodic Schedule Update; G
1.3 PROJECT SCHEDULER QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.
SECTION 01 32 01.00 10 Page 2 PW\DEN001\669816
2.1 SOFTWARE
The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.
2.1.1 Government Default Software
The Government intends to use Primavera P6.
2.1.2 Contractor Software
Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.
2.1.2.1 Primavera
If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system.
2.1.2.2 Other Than Primavera
If the contractor chooses software other than Primavera P6, that is compliant with this specification, provide for the Government's use two licenses, two computers, and training for two Government employees in the use of the software. These computers will be stand-alone and not connected to Government network.Computers and licenses will be returned at project completion.
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to
FAR Clause 52.236-15, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule.Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path
Method (CPM) of network calculation to generate all Project Schedules.
Prepare each Project Schedule using the Precedence Diagram Method (PDM).
3.2 BASIS FOR PAYMENT AND COST LOADING
The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.
SECTION 01 32 01.00 10 Page 3 PW\DEN001\669816
3.2.1 Activity Cost Loading
Activity cost loading must be reasonable and without front-end loading.
Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.
3.2.2 Withholdings / Payment Rejection
Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.
In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.
Less than 2 percent of all non-procurement activities may have Original
Durations (OD) greater than 20 work days or 30 calendar days.
3.3.3 Procurement Activities
Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.3.4 Mandatory Tasks
Include the following activities/tasks in the initial project schedule and all updates.
a. Submission, review and acceptance of SD-01 Preconstruction Submittals
(individual activity for each).
b. Submission of mechanical/electrical/information systems layout drawings.
c. Long procurement activities.
d. Submission and approval of O & M…