This document outlines requirements for providing temporary restroom facilities at Mansfield Lahm Air National Guard Base in Ohio as part of Project Number PBXP 132166 for repair of an aircraft maintenance hangar. Key requirements include furnishing all equipment, labor, materials, and facilities to support a minimum of 60 people with surge capacity for 160, with separate facilities for males and females. Each stall must include a shower, sink, and toilet and be lockable from the interior. Heating, ventilation and air conditioning must be provided. The contractor is responsible for utilities connection and provision of sewage and potable water services. The period of performance is estimated at 18 months. The contractor must comply with all environmental, safety, and waste disposal regulations and properly maintain the site.
Statement of Work for temp facilities
View the file
Other files for this federal contract opportunity
Show all 50
Repair Maintenance Hangar, B102 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Requirements/Specifications
PBXP132166: PROVIDE TEMPORARY RESTOOM FACILITIES
MANSFIELD-LAHM ANG BASE, OHIO
SPECIFICATION PARAGRAPH
General Requirements 1
Requirement Description 2
Site 3
1. GENERAL REQUIREMENTS
1.1. The contractor shall furnish all equipment, labor, material, and appurtenances to provide equipment-related facilities in accordance with this scope of work and associated specifications to provide supporting temporary restrooms for the duration of the project
PBXP132166: REPAIR MX HANGAR. This requirement shall include all accessories, parts, and equipment necessary to provide fully functioning temporary facility. Only U.S. manufactured equipment shall be utilized for this project.
1.2. The location for this requirement is within the Mansfield Lahm ANG Base, Mansfield, Ohio.
1.3. The contractor shall not exceed the stated equipment requirements without prior approval from the Contracting Officer.
1.4. The contractor shall protect all government property from damage. Any damages incurred in the pursuance of this project shall be replaced and/or restored to the original condition acceptable to the Base Civil Engineer.
1.5. The contractor shall comply with the provisions of the Occupational Safety and Health Act of
1972 and all provisions thereto.
1.6. The contractor shall maintain a clean and safe installation site at all times to prevent damage to the buildings, utilities, or any other systems that may be affected. This is also intended to protect building occupants and nearby aircraft from potential hazards associated with the proposed work. This shall include dust, debris, and waste created in the performance of installation and requisite ancillary maintenance of temporary installed facilities.
1.7. Material Safety Data Sheets (MSDSs) shall be provided as part of the submission process for chemicals to be used as part of this requirement. MSDS shall be provided prior to installation.
1.8. Green Procurement: reasonable efforts shall be made to provide environmentally friendly alternatives for all materials required for the requirement.
1.9. The contractor shall field verify all dimensions. The dimensions provided by the government are only approximations and they are not responsible for their precision or accuracy. This includes, but is not limited to drawings, schedules, and statement of requirements.
1.10. The contractor shall be responsible for all defects, damages, and serviceability of the restrooms.
1.11. All trash, waste, and construction debris generated from this project shall become the responsibility of the contractor and shall be removed from the base at no extra cost to the
Government. The disposal of these materials shall follow the appropriate Federal and State laws. This includes the disposal or recycling of hazardous and infectious materials.
1.12. Coordination will be required with the Contracting Officer Representative (COR), for project
PBXP 132166, Repair Maintenance Hangar, Bldg. 102.
1.13. Point of Contact (POC) for this project is Maj Kiet Chung at (419) 520-6156. The Contracting
Officer (KO) for this project is Gordon Strom at (419) 520-6390.
2. REQUIREMENT DESCRIPTION
2.1. Supported Personnel: The restrooms shall be adequate to support a minimum of 60 people and a surge capacity of 160, one weekend a month. The facilities shall be serviced, cleaned, and supplied a minimum once a week and after each regularly scheduled drill period for the entirety of the period of performance (POP) for Project Number PBXP132166: REPAIR MX
HANGAR. Separate units shall be provided for males and females. Current estimated period of performance for project is 18 months.
2.2. Required Facilities: Facilities shall be capable of being locked and secured from the interior to provide security of the users in each stall. Each stall shall be a shower, sink, and toilet combination. Heating, ventilation, and air conditioning shall be provided.
2.3. Available Utilities: Electrical utilities are available for use at the proposed location. The location of the temporary shower, toilet, and sink combination is adjacent to buildings 108, 110, and 112. Contractor shall be responsible for temporary connection to the electrical utility. Contractor shall be responsible for providing service of sewage and potable water.
3. SITE MAINTENANCE REQUIREMENTS
3.1. Foreign Object Damage (FOD): Debris and tool accountability shall be maintained by the contractor for the duration of the project. Proper housekeeping shall be practiced to mitigate damage to aircraft from loose aggregate and/or equipment.
3.2. Site Restoration: No earthwork is expected to occur as part of this project. Impacts outside of the grounds outside of the project scope shall be repaired and/or restored at no additional cost to the government. Proper environmental and sediment control shall be practiced.
Vegetated areas shall be reseeded, as appropriate.
4. ENVIRONMENTAL AND SEDIMENT CONTROL
4.1. Contractor shall comply with all applicable environmental laws and regulations, related to installation, use, and continued maintenance of facilities.
4.2. Waste Management: All trash, waste, and construction debris generated from this project shall become the responsibility of the contractor and shall be removed from the base at no extra cost to the Government. The disposal of these materials shall follow the appropriate
Federal and State laws. This includes the disposal or recycling of hazardous materials.
4.3. Tracking and Reporting: Contractor shall track all Construction, demolition, and debris
(CD&D), and Hazardous Materials (HAZMAT) as required by local Air Wing Instructions (AWI) and Environmental Management Office (EMO) policies. Contractor shall utilize the respective tracking form and inventory provided.
4.4. HAZMAT Use and Storage: Items may not be disposed of on installation property. Any fines and/or violations shall be the sole responsibility, of the Contractor. Applicable Safety Data
Sheets shall be submitted as part of the submittal process. Quantities of expected storage, usage, and container sizes shall be reported as part of the Installation’s HAZMAT tracking program.
4.5. Erosion and Sediment Control: Impacts outside of the grounds of the facilities installation site shall be repaired and/or restored at no additional cost to the government. Proper environmental and sediment control shall be practiced. Best Management Practices (BMPs) shall be utilized for earthwork for erosion and sediment control. The “Rainwater and Land
Development Guide” by the Ohio Department of Natural Resources is available for download at http://soilandwater.ohiodnr.gov/water-conservation/stormwater-management.
Vegetated areas shall be restored and reseeded, as appropriate.