Amendment 0006. Proposal Due date is revised to Friday July 29 2016 at 02 00 P.M. Local Time
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
F6G3CE6036A001
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
PROJECT NO. CRWU 06-2003
Buckley Air Force Base, Aurora, CO
This amendment is issued to incorporate bid addendum 4 as described in Block 14 Continuation page.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 26-Jul-2016
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9133L-16-R-0043
X 9B. DATED (SEE ITEM 11)
17-Jun-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
26-Jul-2016
CODE
NGB-AQ - W9133L
111 SOUTH GEORGE MASON DR
BLDG. 2, 4TH FLOOR
ARLINGTON VA 22204-1373
W9133L 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9133L-16-R-0043
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 06
CHANGES TO THE DRAWINGS
P111 - REMOVE this drawing and REPLACE with drawing P111 dated 7/25/2016. This drawing was revised to moved floor penetrations for the plumbing pipe to the east wall, so pipe will be enclosed in chase.
P302- REMOVE this drawing and REPLACE with drawing P302 dated 7/25/2016. This drawing was revised to moved floor penetrations for the plumbing pipe to the east wall, so pipe will be enclosed in chase.
M105- REMOVE this drawing and REPLACE with drawing M dated 7/25/2016105. This drawing was revised to moved floor penetrations for the plumbing pipe to the east wall, so pipe will be enclosed in chase.
M300- REMOVE this drawing and REPLACE with drawing M300 dated 7/25/2016. This drawing was revised to moved floor penetrations for the plumbing pipe to the east wall, so pipe will be enclosed in chase.
The following changes are made to the drawings without reissuance.
A111 - ADD "pipe/ conduit chase that is 1’ – 6” deep at east wall between room A102 and A103. Wall shall be an S1 wall type."
E007 - CHANGE fire pump feeder labels from “XFMR-FPC1, XFMR-FPC2” to “DISC-FPC1, DISC-FPC2”
E110 - CHANGE fire pump feeder labels from “XFMR-FPC1” to “DISC-FPC1” and XFMR-FPC2” to “DISC-
FPC2”
E403, DETAIL 3 - ADD Note "1. For all new columns, route #3/0 AWG bare copper to rebar in the new foundation at each column and connect with exothermic weld."
CORRECTION TO AMENDMENT 0004 CHANGES TO THE SPECIFICATIONS
REPLACE
"6. Section 014510, CONTRACTOR QUALITY CONTROL, Paragraph 3.2. B.2. CQC System Manager: The
7. CQC system manager shall be a graduate engineer, graduate architect, or a graduate of construction management, with a minimum of 5 years of construction experience OR a construction person with a minimum of 10 years of experience working on projects similar in size and scope to this project. In addition to the above experience and education requirements, it is recommended the CQC system manager have completed the course entitled "Construction Quality Management for Contractors" prior to start of field work. For further information contact the USACE Omaha District (402-221-4269). The USACE Omaha District partners with the Rocky Mountain/ABC to offer this training course. For more information on
W9133L-16-R-0043 these classes, please contact Karen Pavone at (303-832-5812) or kpavone@abcrmc.org”
WITH
"6. Section 014510, CONTRACTOR QUALITY CONTROL, Paragraph 3.4. B.2. CQC System Manager: The CQC system manager shall be a graduate engineer, graduate architect, or a graduate of construction management, with a minimum of 5 years of construction experience OR a construction person with a minimum of 10 years of experience working on projects similar in size and scope to this project. In addition to the above experience and education requirements, it is recommended the CQC system manager have completed the course entitled "Construction Quality Management for Contractors" prior to start of field work. For further information contact the USACE Omaha District (402-221-4269). The USACE Omaha District partners with the Rocky Mountain/ABC to offer this training course. For more information on these classes, please contact Karen Pavone at (303-832-5812) or kpavone@abcrmc.org”
SECTION 00010 - SOLICITATION CONTRACT FORM
The required response date/time has changed from 28-Jul-2016 02:00 PM to 29-Jul-2016 02:00 P.M.