Amendment 0004.pdf

PDF 361 KB Posted

Attached to
Gates 2 and 3 Replacement, Ball Mountain Dam Federal contract opportunity
Solicitation number
W912WJ20B0022
Issued by
Department of the Army Corps of Engineers Engineering District New England

About this file

This amendment modifies solicitation W912WJ20B0022 for the Gates 2 and 3 Replacement project at Ball Mountain Dam. The scope of work involves replacing gates 2 and 3 and associated hydraulic equipment. The amendment provides responses to contractor questions. Draining, cleaning, and flushing of hydraulic systems will only be required for gates 2 and 3 and associated piping and cylinders. No power is available at the intake structure, and the existing monorail system is property of the hydropower owner and cannot be utilized by the contractor.

View the file

Other files for this federal contract opportunity

Other files attached to Gates 2 and 3 Replacement, Ball Mountain Dam, newest first.
File Type Posted
Bid Abstract.pdf PDF
Amendment 0003.pdf PDF
Amendment 0002.pdf PDF
Gate Chamber.mp4 MP4 file
Gate House Door Walkthrough.mp4 MP4 file
Gate House Lower Level.mp4 MP4 file
Amendment 0001.pdf PDF
Bridge Access.MOV MOV file
Virtual SIte Visit_no video.pptx PPTX presentation
Specifications.pdf PDF
Solicitation W912WJ20B0022.pdf PDF
Drawings.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to provide responses to RFI’s. All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 11-Sep-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ20B0022

X 9B. DATED (SEE ITEM 11)

14-Aug-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

11-Sep-2020

CODE

US ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA ROAD

CONCORD MA 01742-2751

W912WJ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912WJ20B0022

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS

The following have been added by full text:

AMENDMENT 0004 RFI'S

1) What power source is provided on site on the intake structure and also in the gate house?

Response: 110 Volt power is available in the gate house, and no power is available at the intake.

2) Is there any information that you can provide on the monorail system? We intend to carry stop logs from access road to the gate house using the monorail.

Response: The monorail system at the intake is property of the hydropower owner and cannot be utilized by the Gates 2 and 3 Replacement contractor.

3) In the spec, we are required to clean and flush the system. Are we required to drain the entire system or cap it and drain only the parts we need to remove?

Response: Draining, cleaning, and flushing of the hydraulic system will only be required for the lines and hydraulic equipment for gates 2 and 3. This includes cylinders, piping, and at the power unit per Specifications Section 35 05

40.14. Draining, cleaning, and flushing shall only be performed on the systems associated with the gate currently being worked, as the other gate will still be in service.

(End of Summary of Changes)