Amendment 0003.pdf
PDF 435 KB Posted
- Attached to
- Gates 2 and 3 Replacement, Ball Mountain Dam Federal contract opportunity
- Solicitation number
- W912WJ20B0022
About this file
This document is an amendment to a federal solicitation providing responses to contractor questions. The solicitation is for the Gates 2 and 3 Replacement project at the Ball Mountain Dam. The Army Corps of Engineers Engineering District New England is the contracting agency. The amendment allows for the use of composite stop logs containing fiberglass reinforcement. It clarifies that local hoisting systems will be required in addition to the overhead crane to remove gates from their pockets. The deadline to acknowledge receipt of the amendment is not extended.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Abstract.pdf | ||
| Amendment 0004.pdf | ||
| Amendment 0002.pdf | ||
| Gate House Lower Level.mp4 | MP4 file | |
| Gate House Door Walkthrough.mp4 | MP4 file | |
| Gate Chamber.mp4 | MP4 file | |
| Amendment 0001.pdf | ||
| Bridge Access.MOV | MOV file | |
| Virtual SIte Visit_no video.pptx | PPTX presentation | |
| Drawings.pdf | ||
| Specifications.pdf | ||
| Solicitation W912WJ20B0022.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose if this amendment is to provide responses to RFI’s. All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ20B0022
X 9B. DATED (SEE ITEM 11)
14-Aug-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
U0003
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
09-Sep-2020
CODE
US ARMY ENGR DISTRICT, NEW ENGLAND
696 VIRGINIA ROAD
CONCORD MA 01742-2751
W912WJ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912WJ20B0022
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS
The following have been added by full text:
AMENDMENT 0003 RFI'S
1. Inference to question 8 will the hydro unit completely shut off the flow of water to Gate 3 to allow servicing the gate?
Response: When hydro units are shut, all flow is stopped except for leakage that may occur along the gate seals. As stated in Specification Section 01 11 00 Part 1.3 “There is some leakage through the hydro-electric gate upstream of gate #3. The Contractor shall be responsible for managing all water resulting from the hydro-electric gate leakage.”
2. In reference Specification Section 01 11 00 Part 1.1 Paragraph 6 Will the overhead hoist reach each gate for disassembly/reassembly or will there need to be an additional hoisting systems to remove the gates from their current locations in addition to the in house crane?
Response: The overhead hoist does not reach directly above the gates. Local hoisting systems will be required to move gates from the gate pocked to the overhead hoist.
3. I have a question based on a previous RFI below. Please clarify if you could please.
Q) The specs indicate the stop logs are "Composite Plastic Timbers". Can the government expand on the specification requirement of the stop log material type? A previous RFI has requested Fiberglass material and that was denied. Can the government accept engineered composite fiberglass reinforced plastic (FRP)?
4. Contractors Comment "FRP is a well-known structural composite material solution. If you go through the product material specs they are essentially what you would find in a composite timber decking product (although higher material strengths). Many composite timber solutions include fiberglass as a material component."
Response: The answer to the previous RFI was not intended to prevent the utilization of composite timbers that include fiberglass reinforcing or other fiber reinforced polymers. Such timbers are acceptable.