Amd_03,_W912UM19R0008.pdf
PDF 2 MB Posted
- Solicitation number
- W912UM19R0008
About this file
This is a performance work statement for an indefinite delivery indefinite quantity construction security monitoring services contract in the Republic of Korea. Key details include providing temporary physical security infrastructure, equipment, and monitoring services at construction sites to comply with Intelligence Community Directive 705. Services include overall program management, site security, access control, secure storage and shipping of materials, and surveillance by cleared American guards, construction technicians, and local nationals. The base period of performance is one year with four one-year options and a six-month extension. Pricing is fixed for labor categories and temporary equipment. The solicitation number is W912UM19R0008.
Amendment#03, W912UM19R0008, IDIQ, CSM Services, Korea
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04 EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
a. The purpose this amendment is to revise PWS, solicitation and extended proposal due date and question closing date.
b. Request for proposal will be extended from 29 August 2019 to 6 September 2019, 1000hours (Korea Standard Time).
c. Questions submission date closing is in ProjNet is extended by noon, 27 August 2019(Korea Standard Time).
d. All other terms and condition of the solicitation remains the same.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 81
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 26-Aug-2019
16B. UNITED STATES OF AMERICA 15C. DATE SIGNED 15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer) (Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912UM19R0008
X 9B. DATED (SEE ITEM 11)
24-Jul-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
26-Aug-2019
CODE
CONTRACTING DIVISION
U.S. ARMY CORPS OF ENGINEERS
FAR EAST DISTRICT
UNIT #15546
APO AP 96271
W912UM 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODE CODE
EMAIL:TEL:
W912UM19R0008
SECTION F 30 BLOCK 14 CONTINUATION PAGE
See the confirmed copy of the solicitation.
SEE ADDENDUM
(No Collect Calls)
W912UM19R0008 24-Jul-2019
b. TELEPHONE NUMBER
315-755-6929
8. OFFER DUE DATE/LOCAL
TIME
10:00 AM 6 Sep 2019
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
W912UM9. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
WON S CHUNG
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED ORX
SMALL BUSINESS
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
CONTRACTING DIVISION
U.S. ARMY CORPS OF ENGINEERS
FAR EAST DISTRICT
UNIT #15546
APO AP 96271
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE15. DELIVER TO CODE 16. ADMINISTERED BY
SEE SCHEDULE
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
FAX:
TEL: 82-503-355-6091
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
$20,500,000
NAICS:
561612
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF88
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
Section SF 1449 - CONTINUATION SHEET
ITEM NO SUPPLIES/SERVICES MAX
QUANTITY
UNIT UNIT PRICE MAX AMOUNT
0001 1 Job CSM Services
FFP
Construction Security Monitoring Services, Republic of Korea
The contractor shall perform the work in accordance with Performance Work
Statement (PWS).
The Base Ordering Period is 12 months from the date of award.
MAX
NET AMT
UNIT UNIT PRICE MAX AMOUNT
1001 1 Job OPTION CSM Services
FFP
Construction Security Monitoring Services, Republic of Korea
The Ordering Period under this CLIN is 12 months from the last day of the Base
Ordering period.
UNIT UNIT PRICE MAX AMOUNT
1002 1 Job OPTION CSM Services
FFP
Construction Security Monitoring Services, Republic of Korea
The Ordering Period under this CLIN is 12 months from the last day of the 1st
Optional Ordering period.
UNIT UNIT PRICE MAX AMOUNT
1003 1 Job OPTION CSM Services
FFP
Construction Security Monitoring Services, Republic of Korea
The Ordering Period under this CLIN is 12 months from the last day of the 2nd
UNIT UNIT PRICE MAX AMOUNT
1004 1 Job OPTION CSM Services
FFP
Construction Security Monitoring Services, Republic of Korea
The Ordering Period under this CLIN is 12 months from the last day of the 3rd
UNIT UNIT PRICE MAX AMOUNT
1005 1 Job OPTION CSM Services (Up to 6 Months Extension)
FFP
Construction Security Monitoring Services, Republic of Korea
The contractor shall perform the work in accordance with Performance Work
Statement (PWS).
Ordering Period(s) shall be as stated in any exercise(s) of the option under Clause
52.217-8, Option to Extend Services of this Contract, not to exceed 6 months from the last day of previously exercised optional ordering period.
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
2001 1 Job Contract Manpower Reporting
FFP
Refer to Manpower Reporting Requirement within PWS
PRICE SCHEDULE
Price schedule will be set forth in this Indefinite Delivery Indefinite Quantity (IDIQ) contract. The contract period of performance (POP) consists of one twelve month base year with four twelve month option years to be exercised at the discretion of the Government. Labor categories and equipment listed below are based on the PWS stated in this contract.
Price Schedule for Base Year
Labor Categories
Item Description Unit Security Contractor
Security Program Manager (on-site) Hour
Site Security Manager Hour
Site Security Coordinator Hour
Lead Construction Surveillance Technician (CST) Hour
Lead Cleared American Guard (CAG) Hour
Cleared American Guard Hour
Construction Surveillance Technician Hour
Local National (LN) Guard Hour
LN Administrative Assistant (on-site) Hour
Construction Security Temporary Equipment (CSTE) List
FE-6 Perimeter Security Fence (incl. Gates) LF
Complete Fence Protection System LF
Vehicle Access Control Sally Port Each
Guard Tour Patrol system (complete with 20 RFID sensors 2 handheld data collectors) 1 System
- Additional RFID Sensor Each
- Additional Handheld Data Collector Each
Portable intrusion detection unit Each
Walk through Metal Detector Each
Handheld Metal Detector Each
Package X-Ray Inspection system Each
Pallet X-Ray Inspection system Each
Vehicle Inspection mirror Each
Digital Badging System (complete with 500 badges) 1 System
- Additional 500 - ID Cards Lot
- Additional 500 - Laminating Pouches Lot
- Additional 500 - 30” bead chain necklaces Lot
- Additional 500 - 20 ¾” removable vinyl strap clips Lot
Biometric (Iris) ID System (complete) 1 System
- Additional Enrollment Optical Unit Each
- Additional Remote Optical Unit Each
Portable Radio communication system
- Radio Each
- Rechargeable Battery pack Each
- Holster with belt clip or loop Each
- Multi unit charging station Each
Secure Storage Containers
- Class 6, single lock, two drawer, legal size file Each
- Class 6, map and plan container with plan hold rack Each
- Key control containers with tags Each
Locking devices
- Environmental Padlock Each
- Padlock with changeable combination Each
- High Security exterior padlock Each
- Cypher Door Lock Each
- Heavy duty Slide bolt Each
- Slide bolt with #12 double door strike Each
- Slide bolt with #13 mortise floor strike Each
- Slide bolt with #14 surface mount strike Each
- 6 foot length of hardened steel heavy duty chain Each
SSM Support items
- Field Engineer tool kit: provide 1 Each
- Handheld flashlight with batteries Each
- Electronic Logging Device Each
- Handheld portable megaphone with batteries Each
- 2TB (minimum) RAID 1 external Hard drive Each
- Green / Red spray paint (can) Each
SSM personnel Support items
- Digital SLR Cameras Each
- External flash unit Each
- 55-105 Lenses for camera Each
- Flash memory Data card Each
- Laptop Computer Each
- Rugged external hard drive Each
Price Schedule for 1st Option Year
Security Program Manager (on-site) Hour
Site Security Manager Hour
Site Security Coordinator Hour
Lead Construction Surveillance Technician (CST) Hour
Lead Cleared American Guard (CAG) Hour
Cleared American Guard Hour
Construction Surveillance Technician Hour
FE-6 Perimeter Security Fence (incl. Gates) LF
Complete Fence Protection Microwave LF
Complete Fence Protection LF
Vehicle Access Control Sally Port Each
Guard Tour Patrol system (complete with 20 RFID sensors 2 handheld data collectors) 1 System
- Additional RFID Sensor Each
- Additional Handheld Data Collector Each
Portable intrusion detection unit Each
Walk through Metal Detector Each
Handheld Metal Detector Each
Package X-Ray Inspection system Each
Pallet X-Ray Inspection system Each
Vehicle Inspection mirror Each
Digital Badging System (complete with 500 badges) 1 System
- Additional 500 - ID Cards Lot
- Additional 500 - Laminating Pouches Lot
- Additional 500 - 30” bead chain necklaces Lot
- Additional 500 - 20 ¾” removable vinyl strap clips Lot
Biometric (Iris) ID System (complete) 1 System
- Additional Enrollment Optical Unit Each
- Additional Remote Optical Unit Each
Portable Radio communication system
- Radio Each
- Rechargeable Battery pack Each
- Holster with belt clip or loop Each
- Multi unit charging station Each
Secure Storage Containers
- Class 6, single lock, two drawer, legal size file Each
- Class 6, map and plan container with plan hold rack Each
- Key control containers with tags Each
Locking devices
- Environmental Padlock Each
- Padlock with changeable combination Each
- High Security exterior padlock Each
- Cypher Door Lock Each
- Heavy duty Slide bolt Each
- Slide bolt with #12 double door strike Each
- Slide bolt with #13 mortise floor strike Each
- Slide bolt with #14 surface mount strike Each
- 6 foot length of hardened steel heavy duty chain Each
SSM Support items
- Field Engineer tool kit: provide 1 Each
- Handheld flashlight with batteries Each
- Electronic Logging Device Each
- Handheld portable megaphone with batteries Each
- 2TB (minimum) RAID 1 external Hard drive Each
- Green / Red spray paint (can) Each
SSM personnel Support items
- Digital SLR Cameras Each
- External flash unit Each
- 55-105 Lenses for camera Each
- Flash memory Data card Each
Price Schedule for 2nd Option Year
Security Program Manager (on-site) Hour
Site Security Manager Hour
Site Security Coordinator Hour
Lead Construction Surveillance Technician (CST) Hour
Lead Cleared American Guard (CAG) Hour
Cleared American Guard Hour
Construction Surveillance Technician Hour
FE-6 Perimeter Security Fence (incl. Gates) LF
Complete Fence Protection System LF
Vehicle Access Control Sally Port Each
Guard Tour Patrol system (complete with 20 RFID sensors 2 handheld data collectors) 1 System
- Additional RFID Sensor Each
- Additional Handheld Data Collector Each
Portable intrusion detection unit Each
Walk through Metal Detector Each
Handheld Metal Detector Each
Package X-Ray Inspection system Each
Pallet X-Ray Inspection system Each
Vehicle Inspection mirror Each
Digital Badging System (complete with 500 badges) 1 System
- Additional 500 - ID Cards Lot
- Additional 500 - Laminating Pouches Lot
- Additional 500 - 30” bead chain necklaces Lot
- Additional 500 - 20 ¾” removable vinyl strap clips Lot
Biometric (Iris) ID System (complete) 1 System
- Additional Enrollment Optical Unit Each
- Additional Remote Optical Unit Each
Portable Radio communication system
- Radio Each
- Rechargeable Battery pack Each
- Holster with belt clip or loop Each
- Multi unit charging station Each
Secure Storage Containers
- Class 6, single lock, two drawer, legal size file Each
- Class 6, map and plan container with plan hold rack Each
- Key control containers with tags Each
Locking devices
- Environmental Padlock Each
- Padlock with changeable combination Each
- High Security exterior padlock Each
- Cypher Door Lock Each
- Heavy duty Slide bolt Each
- Slide bolt with #12 double door strike Each
- Slide bolt with #13 mortise floor strike Each
- Slide bolt with #14 surface mount strike Each
- 6 foot length of hardened steel heavy duty chain Each
SSM Support items
- Field Engineer tool kit: provide 1 Each
- Handheld flashlight with batteries Each
- Electronic Logging Device Each
- Handheld portable megaphone with batteries Each
- 2TB (minimum) RAID 1 external Hard drive Each
- Green / Red spray paint (can) Each
SSM personnel Support items
- Digital SLR Cameras Each
- External flash unit Each
- 55-105 Lenses for camera Each
- Flash memory Data card Each
Price Schedule for 3rd Option Year
Security Program Manager (on-site) Hour
Site Security Manager Hour
Site Security Coordinator Hour
Lead Construction Surveillance Technician (CST) Hour
Lead Cleared American Guard (CAG) Hour
Cleared American Guard Hour
Construction Surveillance Technician Hour
FE-6 Perimeter Security Fence (incl. Gates) LF
Complete Fence Protection System LF
Vehicle Access Control Sally Port Each
Guard Tour Patrol system (complete with 20 RFID sensors 2 handheld data collectors) 1 System
- Additional RFID Sensor Each
- Additional Handheld Data Collector Each
Portable intrusion detection unit Each
Walk through Metal Detector Each
Handheld Metal Detector Each
Package X-Ray Inspection system Each
Pallet X-Ray Inspection system Each
Vehicle Inspection mirror Each
Digital Badging System (complete with 500 badges) 1 System
- Additional 500 - ID Cards Lot
- Additional 500 - Laminating Pouches Lot
- Additional 500 - 30” bead chain necklaces Lot
- Additional 500 - 20 ¾” removable vinyl strap clips Lot
Biometric (Iris) ID System (complete) 1 System
- Additional Enrollment Optical Unit Each
- Additional Remote Optical Unit Each
Portable Radio communication system
- Radio Each
- Rechargeable Battery pack Each
- Holster with belt clip or loop Each
- Multi unit charging station Each
Secure Storage Containers
- Class 6, single lock, two drawer, legal size file Each
- Class 6, map and plan container with plan hold rack Each
- Key control containers with tags Each
Locking devices
- Environmental Padlock Each
- Padlock with changeable combination Each
- High Security exterior padlock Each
- Cypher Door Lock Each
- Heavy duty Slide bolt Each
- Slide bolt with #12 double door strike Each
- Slide bolt with #13 mortise floor strike Each
- Slide bolt with #14 surface mount strike Each
- 6 foot length of hardened steel heavy duty chain Each
SSM Support items
- Field Engineer tool kit: provide 1 Each
- Handheld flashlight with batteries Each
- Electronic Logging Device Each
- Handheld portable megaphone with batteries Each
- 2TB (minimum) RAID 1 external Hard drive Each
- Green / Red spray paint (can) Each
SSM personnel Support items
- Digital SLR Cameras Each
- External flash unit Each
- 55-105 Lenses for camera Each
- Flash memory Data card Each
Price Schedule for 4th Option Year
Security Program Manager (on-site) Hour
Site Security Manager Hour
Site Security Coordinator Hour
Lead Construction Surveillance Technician (CST) Hour
Lead Cleared American Guard (CAG) Hour
Cleared American Guard Hour
Construction Surveillance Technician Hour
FE-6 Perimeter Security Fence (incl. Gates) LF
Complete Fence Protection System LF
Vehicle Access Control Sally Port Each
Guard Tour Patrol system (complete with 20 RFID sensors 2 handheld data collectors) 1 System
- Additional RFID Sensor Each
- Additional Handheld Data Collector Each
Portable intrusion detection unit Each
Walk through Metal Detector Each
Handheld Metal Detector Each
Package X-Ray Inspection system Each
Pallet X-Ray Inspection system Each
Vehicle Inspection mirror Each
Digital Badging System (complete with 500 badges) 1 System
- Additional 500 - ID Cards Lot
- Additional 500 - Laminating Pouches Lot
- Additional 500 - 30” bead chain necklaces Lot
- Additional 500 - 20 ¾” removable vinyl strap clips Lot
Biometric (Iris) ID System (complete) 1 System
- Additional Enrollment Optical Unit Each
- Additional Remote Optical Unit Each
Portable Radio communication system
- Radio Each
- Rechargeable Battery pack Each
- Holster with belt clip or loop Each
- Multi unit charging station Each
Secure Storage Containers
- Class 6, single lock, two drawer, legal size file Each
- Class 6, map and plan container with plan hold rack Each
- Key control containers with tags Each
Locking devices
- Environmental Padlock Each
- Padlock with changeable combination Each
- High Security exterior padlock Each
- Cypher Door Lock Each
- Heavy duty Slide bolt Each
- Slide bolt with #12 double door strike Each
- Slide bolt with #13 mortise floor strike Each
- Slide bolt with #14 surface mount strike Each
- 6 foot length of hardened steel heavy duty chain Each
SSM Support items
- Field Engineer tool kit: provide 1 Each
- Handheld flashlight with batteries Each
- Electronic Logging Device Each
- Handheld portable megaphone with batteries Each
- 2TB (minimum) RAID 1 external Hard drive Each
- Green / Red spray paint (can) Each
SSM personnel Support items
- Digital SLR Cameras Each
- External flash unit Each
- 55-105 Lenses for camera Each
- Flash memory Data card Each
Price Schedule for 6 Months Extension Option Period
Security Program Manager (on-site) Hour
Site Security Manager Hour
Site Security Coordinator Hour
Lead Construction Surveillance Technician (CST) Hour
Lead Cleared American Guard (CAG) Hour
Cleared American Guard Hour
Construction Surveillance Technician Hour
FE-6 Perimeter Security Fence (incl. Gates) LF
Complete Fence Protection System LF
Vehicle Access Control Sally Port Each
Guard Tour Patrol system (complete with 20 RFID sensors 2 handheld data collectors) 1 System
- Additional RFID Sensor Each
- Additional Handheld Data Collector Each
Portable intrusion detection unit Each
Walk through Metal Detector Each
Handheld Metal Detector Each
Package X-Ray Inspection system Each
Pallet X-Ray Inspection system Each
Vehicle Inspection mirror Each
Digital Badging System (complete with 500 badges) 1 System
- Additional 500 - ID Cards Lot
- Additional 500 - Laminating Pouches Lot
- Additional 500 - 30” bead chain necklaces Lot
- Additional 500 - 20 ¾” removable vinyl strap clips Lot
Biometric (Iris) ID System (complete) 1 System
- Additional Enrollment Optical Unit Each
- Additional Remote Optical Unit Each
Portable Radio communication system
- Radio Each
- Rechargeable Battery pack Each
- Holster with belt clip or loop Each
- Multi unit charging station Each
Secure Storage Containers
- Class 6, single lock, two drawer, legal size file Each
- Class 6, map and plan container with plan hold rack Each
- Key control containers with tags Each
Locking devices
- Environmental Padlock Each
- Padlock with changeable combination Each
- High Security exterior padlock Each
- Cypher Door Lock Each
- Heavy duty Slide bolt Each
- Slide bolt with #12 double door strike Each
- Slide bolt with #13 mortise floor strike Each
- Slide bolt with #14 surface mount strike Each
- 6 foot length of hardened steel heavy duty chain Each
SSM Support items
- Field Engineer tool kit: provide 1 Each
- Handheld flashlight with batteries Each
- Electronic Logging Device Each
- Handheld portable megaphone with batteries Each
- 2TB (minimum) RAID 1 external Hard drive Each
- Green / Red spray paint (can) Each
SSM personnel Support items
- Digital SLR Cameras Each
- External flash unit Each
- 55-105 Lenses for camera Each
- Flash memory Data card Each
Note: Workers Compensation Insurance (Defense Base Act)
The cost of Defense Base Act Insurance:
The United States Department of Labor has waived the application of the Defense Base Act to all Contractor employees covered under the compulsory workers’ compensation laws of the Republic of Korea. The waiver remains in effect until March 31, 2021. The Contractor is under no obligation to provide Defense Base Act insurance coverage to these employees. The Contractor certifies that its price for this Contract or Task Order does not include costs of Defense Base Act insurance coverage for its employees covered under the compulsory workers’ compensation laws of the Republic of Korea.
If the Contractor has obtained Defense Base Act insurance coverage for its employees covered under the compulsory workers’ compensation laws of the Republic of Korea, the Contractor certifies that its costs of the insurance have not been included in its price for the work under this Contractor or Task Order.
The United States Department of Labor waiver does not apply to any employee who:
a) Is a citizen of the United States of America; or
b) Is a lawful resident of the United States of America; or
c) Was hired in the United States of America.
Where the Contractor is required to obtain DBA insurance coverage for any of its employees, it may include its costs of the coverage in its price for the Contract or Task Order. The Contractor shall procure DBA insurance coverage commercially only from a United States Department of Labor authorized insurance carrier. The United
States Department of Labor publishes a list of insurance carriers that are currently authorized to write coverage under the Defense Base Act. If Defense Base Act coverage is required for any employee, it is the Contractor’s responsibility to locate and contact a carrier, and arrange coverage. The list of currently authorized carriers is found at: http://www.dol.gov/owcp/dlhwc/lscarrier.htm.
PERIOD OF PERFORMANCE
Contract Period Period of Performance Remarks
Base Year One Year 12 Months from the date of contract award.
1st Option year One Year 12 Months from the last day of base period.
2nd Option year One Year 12 Months from the last day of option period one.
3rd Option year One Year 12 Months from the last day of option period two.
4th Option year One Year 12 Months from the last day of option period three.
6 Months Extension Period 6 Months 6 Months from the last day of option period four.
REVISED PWS, 26 AUG 19
PERFORMANCE WORK STATEMENT (PWS)
FOR
INDEFINITE DELIVERY INDEFINITE QUANTITY (IDIQ)
CONSTRUCTION SECURITY MONITORING (CSM) SERVICES CONTRACT, REPUBLIC OF KOREA
Revision: 26 August 2019
TABLE OF CONTENTS
1.0 GENERAL
1.1 PURPOSE
1.2 BACKGROUND
1.3 SCOPE
2.0 PERFORMANCE REQUIREMENTS
2.1 GENERAL
2.2 OVERALL CONSTRUCTION SECURITY PROGRAM MANAGEMENT
2.3 CONSTRUCTION SITE TEMPORARY PHYSICAL SECURITY
2.4 CONSTRUCTION SECURITY MONITORING SUPPORT EQUIPMENT
2.5 CONSTRUCTION SECURITY MONITORING SERVICES
2.6 CONSTRUCTION MATERIAL SECURE SHIPPING
2.7 SITE SECURITY PERSONNEL (SSP) QUALIFICATIONS AND DUTIES
2.8 CONSTRUCTION SECURITY MONITORING OPERATIONS
2.9 CONSTRUCTION SECURITY RECORDS AND DOCUMENTATION
2.10 QUALITY CONTROL PROVISIONS
2.11 GENERAL SHIPPING AND TRANSPORTATION
2.12 PLACE OF PERFORMANCE
2.13 PERIOD OF PERFORMANCE
3.0 EXECUTION
3.1 GENERAL SECURITY PROCEDURES
3.2 TEMPORARY ENCLOSURES
3.3 SECURE STORAGE AREA (SSA)
3.4 ACCESS CONTROL FACILITY
3.5 VEHICLE ACCESS CONTROL FACILITY
3.6 CONSTRUCTION MATERIAL SECURE SHIPMENT
3.7 DECERTIFICATION FACILITY
3.8 CONSTRUCTION SECURITY TECHNICAL EQUIPMENT (CSTE) AND CONTROLS
3.9 SECURITY LIGHTING SYSTEM
3.10 EMERGENCY POWER
3.11 SSM SUPPORT EQUIPMENT
3.12 NOTIFICATION SYSTEMS
3.13 GENERAL ELECTRICAL REQUIREMENTS
4.0 CONTRACT ADMINISTRATION
4.1 CONTRACT LIASON
4.2 MANPOWER REPORTING REQUIREMENT
4.3 COUNTER INTELLIGENCE AND SECURITY AWARENESS
4.4 DISCLOSURE OF INFORMATION
4.5 OPERATIONS SECURITY (OPSEC) REQUIREMENTS
4.6 INFORMATION SECURITY REQUIREMENTS
4.7 DELIVERABLES
4.8 TRAVEL
4.9 CONSTRAINTS
4.10 GOVERNMENT ADMINISTRATION
4.11 MODIFICATIONS TO THE CONTRACT
4.12 PERFORMANCE REQUIREMENTS SUMMARY (PRS)
5.0 CSTE EQUIPMENT SPECIFICATIONS
5.1 CSTE EQUIPMENT LIST
5.2 ACCESS SCREENING SYSTEM SPECIFICATIONS
5.3 PERSONNEL IDENTIFICATION SYSTEM SPECIFICATIONS
5.4 FENCE PROTECTION SYSTEM SPECIFICATIONS
5.5 GUARD TOUR WATCHCLOCK SYSTEM SPECIFICATIONS
5.6 OUTDOOR MOTION DETECTION SYSTEM SPECIFICATIONS
5.7 INTERIOR INTRUSION DETECTION SYSTEM SPECIFICATIONS
5.8 PORTABLE INTRUSION DETECTION SYSTEM SPECIFICATIONS
5.9 CONSTRUCTION VIDEO SURVEILLANCE SYSTEM SPECIFICATIONS
5.10 ACCESS CONTROL FACILITY VIDEO SURVEILLANCE SYSTEM SPECIFICATIONS
5.11 PORTABLE COMMUNICATIONS SYSTEM SPECIFICATIONS
5.12 SECURE STORAGE CONTAINER SPECIFICATIONS
5.13 LOCKING DEVICE SPECIFICATIONS
5.14 SITE SECURITY MANAGER SUPPORT ITEM SPECIFICATIONS
5.15 SSM PERSONNEL SUPPORT ITEM SPECIFICATIONS
1.0 GENERAL
1.1 PURPOSE
A. The purpose of this requirement is to provide temporary construction security infrastructure, equipment, and services as well as construction security surveillance services to support secure construction projects in accordance with (IAW) the Intelligence Community Directive (ICD) 705 and Department of Defense (DoD) policies. Infrastructure and services will be required at construction sites will primarily support the Yongsan Relocation Program in the Far East District
(POF), South Korea, with the capability to provide same/similar services for other customers within the POF area of responsibility.
1.2 BACKGROUND
A. It is the intent to have an IDIQ type contract with specific Task Orders issued on a project by project basis to support construction security requirements. Delivery periods will vary based on projects and defined in each Task Order. U.S. Government Intelligence Community sponsored construction projects are subject to overarching and unique program considerations. The infrastructure, equipment, and services being acquired will be critical to ensuring that these construction projects comply with the requirements defined in the ICD 705, "Physical and
Technical Security Standards for Sensitive Compartmented Information Facilities", and the DoD
5105.21-M-Volumes 1,2,3, "Sensitive Compartmented Information Administrative Security
Manual", dated October 2012. In addition, the ICD 705 has several implementing documents to include ICS 705-I, ICS 705-2 and the "IC Technical Specifications for Construction and
Management of Sensitive Compartmented Information Facilities (SClF), IC Tech Spec for
ICD/ICS 705," dated 23 April 2012 and known as the Tech Specs. Documents available at www.odni.gov
1.3 SCOPE
A. The Contractor shall be capable of providing a turn-key construction security and construction security monitoring program which shall include all aspects of physical, personnel, technical, and procedural security as required for supported secure projects to fully comply with ICD 705 and ensure successful accreditation of the secure facility. For Operational Security (OPSEC) purposes, contract documents will refer to projects under the purview of the ICD 705 as Secure Work Areas
(SWA) in lieu of Sensitive Compartmented Information Facilities (SCIF) but the terms shall be interchangeable. The contract scope shall include the full range of construction security program management, administrative, construction surveillance operations, including demobilization and closeout. The scope of this contract also includes subject matter expertise on construction surveillance, technical surveillance, Temporary Electronic Security System (TESS) design, installation and operation.
B. Infrastructure and Equipment: The construction security infrastructure shall include but not be limited to temporary security offices, fencing and gates, personnel screening equipment, temporary lighting, intrusion detection systems and closed circuit television (CCTV), as well as temporary utilities to support these systems. Construction security surveillance support equipment shall include but not be limited to items such as personnel badging equipment and supplies, material screening equipment such as pallet x-rays and ultrasound scanners, as well construction surveillance supplies such as cameras, locks, tools, notebooks, and Automated Data Processing
(ADP) equipment as required to process and record construction security surveillance activities and events.
C. Construction Security Monitoring Services: Construction security monitoring services personnel shall include Site Security Manager (SSM), Site Security Coordinator (SSC), Cleared American
Guards (CAGs), Construction Surveillance Technicians (CSTs), and Local National Guards
(LNGs), as well as administrative support to manage all aspects of the construction security program.
2.0 PERFORMANCE REQUIREMENTS
2.1 GENERAL
A. The following paragraphs describe the support tasks that shall be required throughout the contract life. The contractor shall provide necessary resources and knowledge to support the listed tasks.
Specific objectives shall be dependent on the basic contract and/or the Task Order written against the basic contract. The contractor shall complete all required tasks while controlling and tracking performance and goals in terms of costs, schedules, and resources. The overall guiding documents for US-Only Secure Facility construction and Construction Surveillance and Security that shall be followed for this contract are the Intelligence Community Directive 705 (ICD 705) Series
Documents. Construction Surveillance project components and subcomponents framework shall be consistent at the Task Order level, but specific implementation requirements may vary significantly based on Government sponsoring agency or department and/or Government
Accrediting Office (AO) and Cognizant Security Authority (CSA).
2.2 OVERALL CONSTRUCTION SECURITY PROGRAM MANAGEMENT
A. The Contractor shall be capable of providing a turn-key construction site temporary physical security and construction security monitoring program which shall include all aspects of physical, personnel, technical, and procedural security as required for supported secure projects to fully comply with ICD 705 and ensure successful accreditation of the secure facility. At a minimum, the contractor shall be capable of providing all infrastructure, personnel, and processes for construction site physical security, construction site access control, secure shipping, receipt, and storage of construction materials, and monitoring of construction activities to ensure that the facility is constructed in a manner to prevent technical compromise.
B. The Contractor shall maintain strict compliance with this PWS and other terms and conditions contained herein in order to monitor and detect unauthorized access to internal controlled areas during the construction period and to deter the implantation of clandestine surveillance devices or systems by construction workers into the structure being constructed or its surroundings. Many of the services will be required on a continuing basis beyond initial construction. The Contractor shall furnish all personnel, equipment, and supplies required to provide construction site security monitoring IAW with all applicable rules, laws and regulations as stated in this PWS or as further identified in the specific project Task Order. Depending on the specific Task Order and the location, it is the sole responsibility of the Contractor to arrange for the housing of contract personnel covered by this contract. The Contractor shall comply with all applicable local regulations and standards.
C. The contractor shall be required to comply with all training and deployment requirements, country clearances as required by each Task Order as required for contract performance. These requirements will typically be country specific or Area of Operations (AOR) specific. The contractor shall provide its employees and any sub-contractors the support infrastructure to meet the requirements of this contract.
D. Contractor employees shall be required to follow Government established procedures contained in referenced regulations, project specific Construction Security Plans (CSP), and each Task Order.
Additionally, U.S. Citizen Contractor employees shall be required to adhere to Government regulations and Government policies including, but not limited to those regarding relationships, and reporting contracts, marriage, cohabitation or equivalent bonds with foreign nationals.
E. Cleared contractor personnel shall notify the COR and SSM of any suspicious behavior or occurrences that may occur at any time. This includes any foreign contact that suggests they may be the target of an attempted exploitation by a foreign intelligence service. Cleared contractor personnel shall be required to report adverse information regarding themselves or other cleared employees to the COR for notification to trustworthiness or reliability of the employee and suggests that the person’s ability to safeguard classified information may be impaired or that person may be subject to exploitation.
F. Briefings: The Government reserves the right to conduct briefings and debriefings for persons at all levels of involvement in performance of work. Required briefings/debriefings include, but are not limited to, the following:
1. Cleared U.S. citizen Contractor personnel at all levels may be required to attend debriefing when returning from the host country.
2. Management personnel shall be required to attend special security briefings/debriefings concerning reporting requirements on unusual incidents, activities, or information relating to project security.
3. Visitors to the project site shall be required to attend an appropriate security briefing by the SSM or other USAG Humphreys security management personnel.
2.3 CONSTRUCTION SITE TEMPORARY PHYSICAL SECURITY
A. The Contractor shall be capable of providing a turn-key solution for temporary physical security and associated intrusion detection when required by a particular Task Order. A temporary physical security system may include but not be limited to temporary security offices, fencing and gates at the site perimeter as well as the Secure Storage Area (SSA), personnel screening equipment, temporary lighting, intrusion detection systems and closed circuit television (CCTV), as well as temporary utilities to support these systems.
B. Installed temporary physical security measures may be required to be changed and reconfigured during the course of the work.
C. When requested as part of a Task Order, the contractor shall develop a project specific comprehensive temporary physical security system including design, installation, maintenance, and removal, and submit to the Government for approval. Temporary Physical Security System components not covered by the price schedule shall be negotiated at the time of Task Order award.
D. Required temporary physical security items may include:
1. Temporary Enclosures
2. Secure Storage Area (SSA)
3. Jobsite Decertification Facility
4. Access Control Facility (ACF)
5. Vehicle Access Control and Screening Facility (VACF)
6. Site Security Manager (SSM) & Security Operations Offices
7. Construction Security Temporary Equipment (CSTE) and Controls
8. Security Lighting System
9. Emergency Power
10. Locking Devices and Secure Containers
2.4 CONSTRUCTION SECURITY MONITORING SUPPORT EQUIPMENT
A. The Contractor shall be capable of providing equipment and tools required to support construction security monitoring functions when required by a particular Task Order. Construction security monitoring support equipment shall include but not be limited to items such as personnel badging equipment and supplies, material screening equipment such as pallet x-rays and ultrasound scanners, as well construction surveillance supplies such as cameras, locks, tools, notebooks, and
Automated Data Processing (ADP) equipment as required to process and record construction security surveillance activities and events.
B. When requested as part of a Task Order, the contractor shall develop a project specific Bill of
Materials (BOM) of construction security monitoring support equipment and submit to the
Government for approval. Construction Security Monitoring Support Equipment not covered by the price schedule shall be negotiated at the time of Task Order award.
C. Required construction security monitoring support equipment items may include (Refer to Section
5.0 for equipment specifications):
1. Walk through Metal Detector
2. Handheld Metal Detector
3. Package X-Ray Inspection system
4. Pallet X-Ray Inspection system
5. Vehicle Inspection mirror
6. Digital Badging System
7. Biometric ID system with
8. Complete Fence Protection System
9. Guard Tour Watchclock system
10. Outdoor Motion Detection System
11. Interior Intrusion Detection System
12. Lookout portable intrusion detection units
13. Construction Video Surveillance System
14. Access Control Facility Video Surveillance System
15. Portable Radio communication system
16. Secure Storage Containers
17. Locking devices as follows
18. SSM Support Automated Data Processing (ADP)
19. SSM personnel Support ADP, tools, and Photographic equipment
20. FE-6 Perimeter Security Fence
21. FE-6 Gate 20’
22. Fence Penetration System
2.5 CONSTRUCTION SECURITY MONITORING SERVICES
A. Five types of Site Security Personnel (SSP) will be required for this contract: Site Security manager (SSM), Site Security Coordinator (SSC), Cleared American Guards (CAGs), Construction Surveillance Technicians (CSTs), and Local National Guards (LNGs). Depending on the Task Order, the Contractor will be required to provide one type of SSP or any combination of types of SSPs. In addition to the SSP listed above, the contractor shall provide an on-site Project
Manager (PM) for each task order. The PM shall be the single interface for the Government for the task order and any support personnel as required in the execution of the task order. A SSM may serve as the PM. A Lead CST may serve as an SSC.
B. Key Personnel: The Contractor shall submit resumes of key personnel (PM, SSM, SSC, Lead CAG and Lead CST) proposed for this IDIQ contract and for the sample Task Order and each Task
Order. For Task Orders, the Government shall have twenty one (21) calendar days to review resumes and approve or reject candidates. If rejected, the contractor shall then have fourteen (14) calendar days to propose suitable replacements. The Contractor shall notify the Contracting Officer prior to replacing Government approved key personnel, and shall demonstrate that the qualifications of the proposed replacement personnel are equal to or better than the qualifications of the personnel being replaced. Key personnel changes shall not be allowed without Government approval.
C. Prior to incurring any costs relative to the assignment of SSP, the Contractor shall ensure that the individual meets the standards and qualifications set forth in the contract. The contractor will adhere to all pertinent rules, regulations and standards of the United States Government. These regulations include but are not limited to, Status of Forces Agreements (SOFA), Department of
State regulations (DOS), Department of Defense (DOD) requirements and any and all other Laws of the local jurisdictions where work is executed. A TOP SECRET Facility clearance shall be required for this contract. These rules and regulations will vary depending on the areas where the various construction projects are being conducted.
D. The contractor shall appoint a Security Manager to oversee clearance requirements of contractor personnel performing work under this contract. The Security Manager shall be responsible for tracking the security requirements for all personnel (subcontractors included) utilized on this
E. The Contractor shall comply with all applicable national laws unless specifically authorized in writing to do otherwise by the Contracting Officer.
F. The Contractor shall be responsible for assuring that all SSP are in good physical health and are physically able to perform the activities and functions required by this PWS as determined by the
Contractor's medical doctor. Site security personnel may be required to undergo a Government psychological evaluation in order to be qualified for deployment to certain designated posts.
G. All personnel shall:
1. Possess binocular vision correctable to 20/20 (Snellen) and close vision correctable to Saiger No.4 type tests for both eyes.
2. Be free of color blindness.
3. Have normal fields of vision and good depth perception (approximately 100 degrees laterally).
4. Be in good health without conditions which would interfere with the performance of assigned duties, or meeting country and AOR specific requirements.
5. Receive a physical examination performed by a licensed and American Medical
Association (AMA) certified physician to include medical and drug screening.
6. The Contractor shall provide a certificate attesting to final results, pass/fail, of this examination for each proposed contract person to the Contracting Officers
Representative (COR).
H. As specified in each Task Order, the contractor will be required to travel to locations OCONUS in the Republic of Korea. Contractor employees who deploy to locations that require immunizations shall do so in accordance with Department of Defense Instruction (DoDI) 6205.4 Department of the Army, and local immunization requirement.
I. The Contractor shall ensure that all personnel possess the necessary security clearances to perform their respective functions or shall be clearable. Clearable shall be defined as having a current favorably adjudicated security clearance of the required level needed for their proposed position.
J. All personnel performing work on this contract shall be initiated for a reciprocal Top Secret or
Secret Clearance based on their proposed position, their most recent Defense Security Service personnel security clearance and successful completion of a suitability review. Personnel performing under this contract shall not travel to OCONUS until after the reciprocal clearance and suitability review package has been completed. Suitability determinations will usually be completed within three weeks of receipt of the most recent Report of Investigation (ROI).
K. If during the course of performance of the contract, an individual is determined to no longer meet security requirements for the proposed position, the Contractor shall be responsible for replacing the individual at contractor expense.
L. Contractor personnel shall be required to adhere to all applicable USFK, 8th Army, and USAG
Humphreys, field management rules, regulations and standard operating procedures regarding site access, off duty behavior and other administrative matters.
M. Contractor personnel roles shall be assigned IAW qualification requirements established in the
PWS for their assigned role and shall not be used interchangeably unless qualified for both roles and with prior approval from the COR.
N. Non-cleared or non-US contractor personnel shall be escorted at all times when on the construction site.
O. The Contractor shall establish and maintain close, continuous, and responsive contact with the
COR and other designated US Government project management personnel.
P. The Contractor shall obtain all visas as required for work in OCONUS project sites. The contractor shall notify the COR immediately of any problems meeting personnel requirements due to the inability to obtain or delay in obtaining or extending a visa.
Q. Contractor SSP shall be required to participate in security briefings as required by the Government.
The Government shall review and approve resumes of new Key Personnel prior to their employment with the Contractor. Key personnel shall be defined as supervisory or management level contract personnel to include the SSM, SSC, Lead CAG, Lead CST, and PM. Any replacements shall meet or exceed qualifications of proposed management personnel in original contractor's proposal.
R. The Contractor shall adhere to the latest version of the EM 385-1-1 (Engineer Manual), U.S. Army
Corps of Engineers Safety and Health Requirements Manual (2014), as well as any updates to the manual, in the performance of this contract. The Contractor shall provide all required personal protective equipment (PPE) as required to perform the work under this contract in accordance with
EM 385-1-1.
S. The contractor shall ensure that all personnel performing under this contract manifest a neat and professional appearance consistent with the position and duties.
2.6 CONSTRUCTION MATERIAL SECURE SHIPPING
A. The Contractor shall be capable of providing a CONUS based Secure Shipment Certification Team when required by a particular Task Order. Establishment and operation of the Central Receiving
Point (CRP), provision of the shipping containers, and the actual shipping will be by others.
2.7 SITE SECURITY PERSONNEL (SSP) QUALIFICATIONS AND DUTIES
A. Project Manager (PM).
1. Project Manager (PM) is the single focal point of contact for the Government and all contract activities related to construction security and shall be responsible for implementing all aspects of the construction security program.
The PM shall be responsible for all matters related to processes, operations, schedules, logistics, reporting, briefing and any other administrative matters.
2. The PM shall have at least 10 years experience in at least one of the following areas of expertise: Program Management-Security field, Construction security surveillance, Technical Surveillance Countermeasures, Industrial or Government security involving counterintelligence, construction quality assurance, or hands on supervisory construction experience. PM shall have a minimum 3 years experience managing DOD or other Federal Government Construction security program and a minimum 2 years experience managing construction security program for projects performed outside the U.S. and its territories. The PM's experience shall include the completion of a minimum of one similar project completed within past 5 years.
3. The PM shall be a U.S. Citizen possessing a Top Secret security clearance.
B. Site Security Manager (SSM):
1. The SSM acts as the single point of contact regarding security on the project or construction site and is responsible for implementing all aspects of the
Construction Security Plan (CSP). SSMs shall maintain direct contact with the
COR who will be responsible for project security. All security policy decisions shall be approved by the COR.
2. The SSM shall have at least 10 years experience in at least one of the following areas of expertise: Construction security surveillance, Technical Surveillance
Countermeasures, Industrial or Government security involving counterintelligence, construction quality assurance, or hands on supervisory construction experience with at least 3 years as an SSM on a project exceeding
$10mm. In addition, the SSM shall have successfully…