53.243Amendment U0003 is issued prior to receipt of the bids and does hereby become a part of the contract documents and in case of conflict it shall supersede original project manual and drawings. Each bidder shall be responsible for issuing information contained herein to sub-contractors and suppliers to ensure that his/her proposal covers all work required by the contract documents including this addendum. Each bidder shall acknowledge receipt of this addendum on the proposal form where indicated.

View the file

Other files

File Type Posted
W912TF-11-R-0502 U0008.pdf PDF
W912TF-11-R-0502 U0007.pdf PDF
W912TF-11-R-0502 U0006.pdf PDF
W912TF-11-R-0502 U0005.pdf PDF
IF102.dwg DWG drawing
IF502.dwg DWG drawing
IF201.dwg DWG drawing
IF501.dwg DWG drawing
IF601.dwg DWG drawing
IF001.dwg DWG drawing
IF101.dwg DWG drawing
IF103.dwg DWG drawing
IF503.dwg DWG drawing
W912TF-11-R-0502 U0004.pdf PDF
RFI 4.11.2011.pdf PDF
AD-A2.pdf PDF
AD-M5.pdf PDF
AD-A1.pdf PDF
W912TF-11-R-0502 U0002.pdf PDF
AD-S1.pdf PDF
Furniture CAD Files.zip ZIP file
QUESTIONS RECEIVED AS OF 0900 3.24.2011.pdf PDF
SBTeamingArrangements.ppt PPT presentation
Preproposal conference March 2011.ppt PPT presentation
Joint Ventures and SB Teaming.pdf PDF
W912TF-11-R-0502 BUISNESS CARDS PART 1.pdf PDF
W912TF-11-R-0502 SITE VIST BUISNESS CARDS PART 2.pdf PDF
W912TF-11-R-0502 SITE VISIT SIGN IN SHEETS.pdf PDF
W912TF-11-R-0502 U0001.pdf PDF
Amendment U0001 Drawings.pdf PDF
W912TF-11-R-0502 RFI No. 01.pdf PDF
Exhibit C REVISED MARCH 18 2011.docx DOCX document
Drawings Dated 08 Dec 2010 Part One.pdf PDF
Drawings Dated 08 Dec 2010 Part Two.pdf PDF
024116 FL - STRUCTURE DEMOLITION BLDG 259 HAZMAT REPORT.pdf PDF
018113. 13 LEEDChecklist.pdf PDF
SpecsSBD120810.pdf PDF
Exhibit B SSS Feb 11.docx DOCX document
W912TF-11-R-0502.pdf PDF
Exhibit A SSS Jan 11.docx DOCX document
Exhibit C SSS Feb 11.docx DOCX document
Exhibit D and F Feb 11.docx DOCX document
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F8N3CE0173A003 SZCQ089023

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

Amendment U0003 is issued prior to receipt of the bids and does hereby become a part of the contract documents, and in case of conflict, it shall supersede original project manual and draw ings. Each bidder shall be responsible for issuing information contained herein to sub-contractors and suppliers to ensure that his/her proposal covers all w ork required by the contract documents including this addendum.

Each bidder shall acknow ledge receipt of this addendum on the proposal form w here indicated.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 6

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 07-Apr-2011

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912TF-11-R-0502

X 9B. DATED (SEE ITEM 11)

09-Mar-2011

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

07-Apr-2011

CODE

FA6291 NEW HAMPSHIRE AIR NATIONAL GUARD

NGNH-PFO-PC JOINT CONTRACTING

302 NEWMARKET ST

PEASE ANGB

NEWINGTON NH 03803-0157

W912TF 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912TF-11-R-0502

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time has changed from 14-Apr-2011 02:00 PM to 21-Apr-2011 02:00 PM.

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT U0003

1. Question: The spread footing at Column Line 3 which runs from M to K-lines on SB101 is noted as Type Q. Graphically, in plan this footing scales to only 28'x6' which is significantly less than the 30'- 2"x8" of a Type Q. Please verify this is a Type Q footing?

Response 1: The spread footing at Column Line 3 from M to K-lines is a Type Q footing with the dimensions of 30 feet-2 inches by 8 feet.

2. At K-Line between 3.6 and 9 Line, what wall section are we to referring to? What are the footing elevations at this location?

Response 2: Wall section is similar to Detail 6/SB501 with top of wall =101.33 feet, except refer to

Detail 1/SB501 for reinforcing and dimensions. Bottom of footing = 97.00 feet.

3. Concrete Pad note f. on C503 refers to Motorcycle Parking Pad. Cannot find on the drawings, could the location and size be provided?

Response 3: The motorcycle parking pads have been eliminated from the project. Delete Concrete Pad Note 1f on Sheet C503, Site Details.

4. 3/CL101 has a stoop detail which differs from 6/SB502. Please clarify which should govern?

Response 4: Detail 3, Sheet CL101 applies only to the stoop with Keynote #13 on Sheet CS101 as this stoop will be removed as part of a future building addition.

5. Specification Section 111916 specifies two types of detention gun lockers. Please define how many are required and where they will be installed. Drawing AE108, Room A116 indicates a Note #8 that indicates two Munition Cabinets. Are we to assume that one of each type of gun locker is required?

Response 5: Provide two (2) gun lockers in Room A116. Delete tilt-out pistol lockers and change type of remaining gun locker. See changes to Specification Section 111916 listed further below.

6. SS 113100, Part 2.3 - Icemakers; please clarify where this appliance is required.

Response 6: Provide one (1) icemaker in the Water Jugs Room (Room 122). See attached Sketch AD-A2 for revised location. Provide freestanding icemaker in lieu of under-counter icemaker specified. See changes to Specification Section 113100 listed further below. Newly specified icemaker will require an increase in ventilation in the room. See attached sketch AD-M5.

7. Specification Section 124130 specifies recessed mounted frames are required for the roll-up mats.

No slab recesses have been indicated on the structural or architectural plans. Please confirm that recessed frames are required and that the mats that are scheduled in Rooms 105, 110, 114, are to extend from wall to wall. Are we to assume Vestibule 101 is a similar layout to Vestibule 103 as shown on 3/AE403?

Response 7: Provide surface mounted frames. See changes to Specification Section 124130 listed further below. Mats are to extend from wall to wall. Yes, Vestibule 101 is a similar layout to Vestibule 103; see 1/AE102.

1. Specification Section 092900 Gypsum Board, Part 2.4, Item C specifies acoustically enhanced gypsum board and Part 3.3, A.9 indicates include this product as indicated on the drawings. Drawing

AE001 indicates the wall types for the project and does not specifically mention that "acoustically enhanced" drywall is required. Please clarify which wall types are required to get this product. Is it required at all the acoustic rated walls (ND, NE, NG, 1F, 1H, 3A, 3C)?

Response 1: Acoustically enhanced drywall is not required. Resilient channel construction achieves intended STC rating; delete paragraphs 092900 2.4, C and 3.3, A, 9 in their entirety.

2. Acoustic rated wall types ND, NE, NG, 1F, 1H, 3A and 3C are shown to get "resilient sound isolation clips" per Wall Type detail on AE001. Please specify a manufacturer and model # for these isolation clips.

Response 2: Kinetics “IsoMax” or an approved equivalent from another manufacturer.

1. Refer to drawing P103, at Corridor 104, the gas piping size as it continues to Mech Room 125 is shown as 1-1/4 inch. Yet on detail 1/P403, the piping is shown as 2 inches. Please identify the correct pipe size to the Mechanical Room.

Response 1: The correct size is 1-1/4 inch.

2. The Fire Alarm drawings FA101 through FA104, FA501, and E001 show symbols Klaxon devices. I can not find product numbers or specifications for Klaxon devices. Drawing FA501 Drawing notes asks that the Klaxon devices be connected to the Fire Alarm Panel and the appropriate circuits be provided. Who is supplying the information on the Klaxon devices and who is responsible for providing the Klaxon devices?

Response 2: Klaxon devices are specified in section 283176, 2.17, D. They shall be provided by the same Contractor who provides the fire alarm system. Refer to specification 283176, 3.1, C.

SPECIFICATIONS

1. SECTION 111916, DETENTION GUN LOCKERS

a. Paragraph 1.3, A, 2: Delete paragraph in its entirety.

b. Paragraph 2.2, A: Change to read as follows: “Products: Subject to compliance with requirements provide Universal Weapons Rack, Model No. UWRC 4284 by Spacesaver

Corporation or an approved equivalent from another manufacturer.”

c. Paragraph 2.2, B: Change to read as follows: “Cabinet: Fully welded lockable cabinet with bi-fold retractable doors and perforated doors and sides. Provide storage for up to seventy

(70) M9 pistols. Provide and include accessories and components to configure cabinet for storage of pistols, including weapons brackets, pistol supports, back panels and appurtenances. Accessories that are to come into contact with the weapons are to be powder-coated, vinyl-dipped, rubber, or thermoplastic-coated for weapon protection.”

d. Paragraph 2.2, C: Change to read as follows: “Size: 42 inches wide by 16 inches deep by 84 inches high.”

e. Paragraph 2.2, E: Change “surface” to “floor.”

f. Section 2.3: Delete section in its entirety.

2. SECTION 113100, RESIDENTIAL APPLIANCES

a. Paragraph 2.3, A: Change to read as follows: “Basis-of-Design Product: Subject to compliance with requirements, provide product indicated below or an approved equivalent from another manufacturer. Manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:”

b. Paragraph 2.3, A: Delete list of manufacturers and add the following list:

“1. Hoshizaki America, Inc.

2. Manitowoc Food Service Group.

3. Scotsman Ice Systems.”

c. Paragraph 2.3, B: Change to read as follows: “Commercial Icemaker.”

d. Paragraph 2.3, B, 1: Change to read as follows: “Basis-of-Design Product: Manitowoc, Indigo

Series 322 Ice Cube Machine, Model No. ID-0322A with Bin B-320.”

e. Paragraph 2.3, B, 2: Change type from “Undercounter” to “Freestanding, Air Cooled, making cubed type ice, Energy Star model.”

f. Paragraph 2.3, B, 3, a: Change Width from “457 mm (18 inches)” to “559 mm (22 inches)”

g. Paragraph 2.3, B, 3, b: Change Depth from “610 mm (24 inches)” to “863 mm (34 inches)”

h. Paragraph 2.3, B, 3, c: Change Height from “386 mm (33-5/8 inches)” to “1511 mm (59-1/2 inches)”

i. Paragraph 2.3, 4, a: Change to read as follows: “Ice Production: 152 kgs (335 lbs) per day.”

j. Paragraph 2.3, 4, b: Change to read as follows: “Bin Storage: 95 kgs (210 lbs).”

k. Paragraph 2.3, 5, a: Change to read as follows: “Bin Level Control with Programmable Ice

Production”

l. Paragraph 2.3, 5, b: Change to read as follows: “Anti-microbial inhibitor.”

m. Paragraphs 2.3, 5, c and 2.3, 5, d: Delete paragraphs in their entirety.

n. Paragraph 2.3, 6: After “steel” add “with clear coat.”

3. SECTION 124130, ENTRANCE FLOOR MATS AND FRAMES

a. Paragraph 1.3, A, 1: Change “recess-mounted” to “surface mounted.”

b. Paragraph 1.7, A: Change to read as follows: “Coordinate size and location of structural elements that may interfere with floor mat installation.”

c. Paragraph 2.1, A: Change to read as follows: “Subject to compliance with requirements, provide ARDEN Entrance Mating Systems “M-650RS” with F-5 Frame or an approved equivalent product from another manufacturer. Manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:”

d. Paragraph 2.1, C: Delete paragraph in its entirety.

e. Add section 2.2: FRAMES.

f. Add paragraph 2.2, A to read as follows: “Surface-Mounted Frames:”

g. Add paragraph 2.2, A, 1 to read as follows: “Tapered Frames: Tapered serrated flexible black plastic extrusions, not less than 1-1/2 inches wide.”

h. Paragraph 2.2, B: Delete paragraph in its entirety.

i. Paragraph 3.2, A: Change “recess-type” to “surface-type.”

j. Paragraph 3.2, A, 1: Delete paragraph in its entirety.

k. Section 3.3: Delete section and subsequent paragraph(s) in their entirety.

4. SECTION 275123, INTERCOMMUNICATIONS AND PROGRAM SYSTEMS

a. Paragraph 3.4, D: Change “ET101, ET102, and ET104” to “FA101, FA102, and FA104.”

DRAWINGS

1. SHEET AE401, ENLARGED PARTIAL FIRST FLOOR PLANS

a. Detail 5: See attached Sketch AD-A2 for revised ice machine location and casework plan.

2. SHEET AE742, INTERIOR ELEVATIONS

a. Detail 1: See attached Sketch AD-A2 for revised casework elevation.

3. SHEET MH101, FIRST FLOOR MECHANICAL DUCTWORK PLAN SOUTH

a. Detail 1: Change ductwork in Water Jugs (Room 122) per attached Sketch AD-M5.

AMENDMENT U0003 ATTACHMENTS

1. Sketch AD-A2

2. Sketch AD-M5

(End of Summary of Changes)