PreProposal_Conference_Slides_.pdf
PDF 3 MB Posted
- Solicitation number
- W912SV-14-R-0001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RTI_Amendment_6.pdf | ||
| Q A_Dated_25_June_2014.pdf | ||
| Q A_Dated_30_May_2014.pdf | ||
| RTI_Amendment_5.pdf | ||
| Q A_Dated_16_May_2014.pdf | ||
| Q A_Dated_16_May_2014.pdf | ||
| RTI_Amendment_4.pdf | ||
| Amendment_3.pdf | ||
| REVISED_EXHIBIT_H.xlsx | XLSX spreadsheet | |
| Q A_Dated_23_April_2014.pdf | ||
| PreProposal_Conference_SignIn_Sheet2_.pdf | ||
| PreProposal_Conference_SignIn_Sheet1.pdf | ||
| Q A_Dated_15_April_2014.pdf | ||
| Amendment_2.pdf | ||
| Q A_Dated_7_April_2014.pdf | ||
| EXHIBIT_B_RTI.pdf | ||
| EXHIBIT_H.xlsx | XLSX spreadsheet | |
| EXHIBIT_F.pdf | ||
| RTI_Amendment_1.pdf | ||
| EXHIBIT_C_RTI.pdf | ||
| EXHIBIT_D_RTI.pdf | ||
| Exhibit_G_TEP_SAMPLE.pdf | ||
| EXHIBIT_A_RTI.pdf | ||
| RTI_Solicitation.pdf | ||
| RTI_Brand_Name_Justification_Revised.pdf | ||
| RTI_Brand_Name_Justification.pdf |
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRE-PROPOSAL CONFERENCE
17 April 2014
17 April 2014
USPFO Massachusetts
INTRODUCTION
CW2 Erika Reinikainen-Rovinelli : Contracting Officer (USPFO
P & C)
MAJ Shawn Brown: Contract Specialist (USPFO P & C)
MAJ Jonathan Carney: COR (MAARNG- FMO)
Mr. William R Pettingell: Project Manager (MAARNG- FMO)
Base + Options 1-4
540 Days after NTP
Construct a Regional Training
Institute (RTI)
Magnitude-$10,000,000-
25,000,000
One Firm-fixed Price
Contract Will Be Awarded
Project is being solicited 100% Small
Business Set Aside
The Contract Will Be Awarded Using
Source Selection Tradeoff
Procedures (FAR Part 15)
Evaluation Factors – Technical, Past
Performance and Price
The project is for the construction of a new Regional Training Institute (RTI) building and billeting facility.
The Contractor will provide all labor, materials, equipment, and supervision necessary to perform all work required in strict accordance with the detailed requirements of the technical provisions.
Provide all materials, labor and equipment to construct one 25,913 square foot Educational Facility.
Provide all materials, labor and equipment to construct one 32,125 square foot Billeting Facility.
On The Web - https://www.fbo.gov Solicitation Exhibits Questions & Answers Document Amendments Check Regularly & Refresh Web Page Plans & Specifications- must be registered and have password on FBO https://www.fbo.gov/
Export Controlled Materials Company must be certified (via an approved DD Form 2345) by the Joint Certification Program (JCP) administered by the DLA
Logistic Information Service (DLIS). Instructions may be found on their website:
http://www.logisticsinformationservice.dla.mil/jcp/Default.aspx
Questions about this program or DD Form 2345 should be addressed to U.S./Canada Joint Certification Office, DLA Logistics
Information Services (DLIS), Federal Center, 74 Washington
Avenue North, Battle Creek, MI 49017-3084. The Joint Certification
Office may be contacted by telephone at: 1-(800) 352-3572; or email: jcp-admin@.dla.mil http://www.logisticsinformationservice.dla.mil/jcp/Default.aspx mailto:jcp-admin@.dla.mil mailto:jcp-admin@.dla.mil
The U.S./Canada Joint Certification Program (JCP) office reported to this office that once a company is certified with the JCP office (normally 7 to 12 business days), the company should contact FBO to have them add their JCP number to their FBO account. JCP has indicated that they are currently experiencing a three (3) week delay in addition to the normal waiting period.
CONSTRUCTION PERIOD
IS 540 DAYS AFTER NOTICE
TO PROCEED
The Government Intends to Award
Without Discussions and There May
Not Be a Chance for Discussions, Corrections, or Revised Proposals
Offerors Are Strongly Cautioned To
Carefully Read The Requirements Of
The Solicitation And Comply
Accordingly
Section 00110 Of The RFP Details The
Submission Requirements and
Instructions
Be familiar with FAR Provision 52.215-1, Instructions to Offerors - Competitive
Acquisition
2 Volumes Are Required
VOL 1 – Price/Cost Proposal
Pro forma documents
Pricing information
VOL 2 – Two Parts
Part 1- Technical Capability Proposal
Part 2- Past/Present Performance Info
Offeror portion of SF1442 Section 00010 – Pricing Info – All Line items Exhibit D (Option Information) Section 00600 – Representations and
Certifications (R&C) Complete R&Cs in SAM on the web Complete and Return DoD R&Cs in
Section 00600 Complete & Include Supplemental
Information-Section 00110 Paragraph 3.4.1.2
Part I-Technical Capability
Comprised of two (2) sub factors:
Experience & Capability
LEED® Experience with building to US
Green Building Council (USGBC) LEED®
Standards
Technical Capability Ratings:
ACCEPTABLE: Proposal meets the minimum requirements.
UNACCEPTABLE: Proposal does NOT clearly meet the minimum requirements.
Subfactor 1
Limited to ten (10) pages
Demonstrate experience with building to perform a project of this magnitude & complexity
If no such experience indicate in detail how offeror plans to overcome this lack of experience
Subfactor 2 – (USGBC) LEED® Experience building to (USGBC) LEED® standards
Demonstrate that key construction personnel have experience in LEED®
If no experience, offeror must explain how they will overcome the lack of experience
Exhibit A- Part 1- Performance Relevancy Questionnaires – Use Exhibit Format!
Complete not more than 5 forms for Relevant
Contracts Completed Or Substantially Completed (75%) In The Last Five Years
Exhibit A-Part 2 – Describe compliance with FAR 52.219-8, Utilization of Small Businesses
Send Questionnaires for the Exhibit A Projects to your references
“Do This Early” – must be rec’d by the Contracting Office by the closing date.
If You Do Not Have Relevant Past Performance
And Are Using Experience Of Key Personnel, Predecessor Companies Or Subcontractors To
Obtain This Ensure You Clearly State This In
The Proposal
To Be Considered Subcontractor Must
Complete the Information and Consent Form -
Exhibit B
• Proposal Due 1300 Hours (1:00 P.M.) on 19 May 2014.
• Proposal Must Be Signed By an authorized Officer Of Your Company.
• NO Facsimile Or Electronic Offers.
• Send or deliver to: (follow instructions in
Sec 00110)
USPFO- MA Purchasing & Contracting
Massachusetts Army National Guard
2 Randolph Road
Hanscom AFB, MA
• OFFERORS MUST REQUEST ACCESS TO
THE BASE NLT 72 HOURS PRIOR TO BID
CLOSING DATE (as described in Section
00100, Para 5).
• LATE PROPOSALS DUE TO DELAYS AT
THE BASE ENTRANCE WILL NOT BE AN
EXCUSABLE DELAY
PLAN ACCORDINGLY FOR BASE ACCESS!!!
Reference Questionnaires Are Also Due By This Time And Date
Send Reference Questionnaires Out
EARLY!
Return to KO Via E-mail at:
erika.l.reinikainenrovinelli.mil@mail.mil
Exhibit A- Performance Relevancy Questionnaire
PART 1 (NTE 3) PART 2 (1) (submit with Vol 2 – Past Performance (PP))
Exhibit B-Subcontractor/Teaming Partner/Key Personnel Info & Consent Form (if applicable) (submit with Vol 2 PP)
Exhibit C- Reference Questionnaire Package Exhibit D- Option Information Form (submit with Vol 1 Pricing )
EXHIBIT F– FORWARD PRICING
AGREEMENT RATES FOR MODIFICATIONS
EXHIBIT G – SAMPLE EVALUATED TOTAL
OFFER METHOD
EXHIBIT H - EVALUATED TOTAL OFFER
CALCULATION
Process Is Detailed In RFP Section 00120
Carefully Review Section 00120 When Preparing Proposal
Comply With Section 00100 And 00110 Requirements
Failure To Furnish A Complete Proposal May Result In Elimination From Consideration
Best Value Is Defined As An Award
Based On The Greatest Overall Benefit
In Response To The Requirement.
Award Is Based On Price And Other
Non-cost Related Factors.
• Technical and Past/Present Performance are approximately equal to each other and when combined are approximately equal to the Price
Factor.
1. Technical will be evaluated first, Price
Factor second and Past Performance last.
2. If an offeror is deemed unacceptable, no further competition will take place.
3. If Price is determined to be reasonable & realistic, the offer will continue in the competition for a PP evaluation.
Submit a Complete Proposal In
Accordance With Instructions – Use
Formats Provided
Prime Contractors are responsible for coordination among the divisions with subcontractors
• Award is contemplated to be made without discussions- Do Not anticipate a chance to make corrections or changes
• Your first proposal will probably be your only proposal!!
• Read the solicitation requirements carefully!!
• Consider using Section 00120 to “rate” yourself before submitting the proposal-is it complete??
When Using A Subcontractor To
Obtain/Enhance Relevancy Provide
Subcontractor Consent Form, Exhibit
B, Or it Will Not Be Considered
Award In This Process Does Not
Necessarily Mean The Lowest Price
Wins
All amendments will be posted on the FBO web site
Check site regularly for changes & refresh the page
After closing no information will be available until award Awards will be posted to the web Results should be announced in approximately 90 days FAR 52.219-14 Limitations on Subcontracting Apply-
Small Business must perform 15% of cost of contract, not including the cost of materials with its own employees
• Questions Must Be Submitted Via Email To:
shawn.m.brown4.mil@mail.mil and erika.l.reinikainenrovinelli.mil@mail.mil.
• All questions and requests for information (RFI) must be received NOT LATER THAN the fifth working day prior to closing and will be posted not later than two working days prior to closing.
• The Contracting Officer Reserves The Right To Address
Questions Received After The Fifth Day Prior To Solicitation
Closing With Those Offers Deemed Compliant and/or To Be
In The Competitive Range If Discussions Are Deemed
Necessary
• Do Not Call Technical Personnel Or A&E- This Will Only
Delay Getting An Answer
• All Questions, On A Non-Attribution Basis, And The Answers Will Be Posted To The Web Site:
https://www.fbo.gov/
• If Necessary Addendums, Issued By An
Amendment, Will Also Be Posted
• Check Web Site Regularly And Don’t Forget To Refresh Web Page
• https://www.fbo.gov
• https://www.acquisition.gov/
• https://www.sam.gov/
• http://www.wdol.gov/wdol/scafiles/ davisbacon.ma.html
1:00:59 p.m.
(1:01:00 is LATE)
19 May 2014
DON’T FORGET TO HAVE REFERENCES SENT IN BY THIS TIME &
DATE
Important information to know before we begin our site visit.