W912QR25R0052_Specs_Vol1-0000.pdf
PDF 9 MB Posted
- Attached to
- DTA Manned/Unmanned Tactical Vehicle Lab
- Solicitation number
- W912QR25R0052
About this file
This file is a Solicitation for a Design-Bid-Build construction project for the Manned/Unmanned Tactical Vehicle Lab (MUMT) at the Detroit Arsenal in Warren, Michigan. The solicitation (W912QR25R0052) seeks a contractor to construct a single-story, approximately 31,800 square foot research and development facility for ground transport equipment testing. The project will include high and lower bay areas with specialized features such as bridge cranes, vibration-isolation seismic mass foundations, hydraulic and power infrastructure, and integrated systems like Intrusion Detection and Energy Monitoring Control Systems.
The solicitation is issued by the U.S. Army Corps of Engineers Louisville District, with a full and open procurement approach. The estimated contract value is $30,000,000, with a NAICS code of 236220 and a size standard of $45,000,000. Key submission details include: electronic proposal submission through PIEE Solicitation Module by 16 Jun 2025, a 90-day offer validity period, and requirements for a performance and payment bond. Contractors must be properly registered in the System for Award Management (SAM) and meet small business guidelines. The contract includes a 850-calendar day performance period, with work to commence within 10 calendar days of award.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation For Manned/Unmanned Tactical Vehicle Lab (MUMT), Detroit Arsenal, Detroit, MI
P2: 506474
Design-Bid-Build
Specifications - Vol 1 of 3 (Div 00-07) Certified Final Design
12 May 2025
W912QR25R0052
ARIMS: 200A
Disposition: Maintain for 15yrs after construction
W912QR25R0052_Specs_Vol1-0000
Request for Proposal for the Manned/Unmanned Tactical Vehicle Lab for the Ground Vehicle Systems Center at Detroit Arsenal located in Warren, MI.
The magnitude of construction listed in FAR 36.204(h) is more than $10,000,000.00.
NAICS Code 236220. Size Standard $45,000,000. Please note that business size in the System for Aw ard Management (SAM) is determined by the NAICS code. If the vendor size is not listed correctly for a particular NAICS code in SAM, the business w ill be considered other than a small business.
This is a Full and Open procurement.
PLEASE NOTE: SAM is completely free of charge for both registrants and users.
STEPHANIE DREES 502-315-3270
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
12-May-2025
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________850 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________FAR 52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________16 Jun 2025 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.
B. An offer guarantee is, X is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______90 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
U. S. ARMY ENGINEER DISTRICT, LOUISVILLE
600 DR. MARTIN LUTHER KING, JR. PLACE
ROOM 821
LOUISVILLE KY 40202-2239
W912QR
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
01:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: 502.315.7494 TEL: FAX:
W912QR25R0052 72
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
Section 00 10 00 - Solicitation
PRICE BREAKOUT SCHEDULE
00 10 00
PRICE BREAKOUT SCHEDULE
OFFEROR'S NAME: ___________________________________________
CONTRACT LINE-ITEM SCHEDULE
Line Item No. Description Unit Amount
BASE PROPOSAL
0001. Primary Facility: All work, materials, and labor Job $ required to construct the Manned Unmanned Tactical Vehicle Lab Building; includes all Base Proposal construction work required within a line five feet outside of the building, except that work covered by Item No.0002.
0002. Secondary Facility: All work, materials, and labor required to construct Supporting Facilities; includes Job $ all Base Proposal construction work required outside a line five feet outside of the building, except that work covered by Item No. 0001.
Total Base Proposal $
TOTAL PROPOSAL $
NOTES FOR CONTRACT LINE ITEM (CLIN) SCHEDULE
NOTE NO. 1. To better facilitate the receipt and proposal process, all modifications to proposals are to be submitted on copies of the latest Contract Line Item (CLIN) schedules as published in the solicitation or the latest amendment thereto. In lieu of indicating additions/deductions to line items, all Offerors should state their revised prices for each item.
NOTE NO. 2. Offerors must insert a price on all numbered items including options of the CLIN Schedule. Failure to do so may result in the offer being unacceptable.
--END OF CLIN SCHEDULE—
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
Section 00 21 00 - Instructions
ELECTRONIC PROPOSAL SUBMISSION
ELECTRONIC PROPOSAL SUBMISSION
Proposals: ALL SUBMISSIONS TO THIS PROPOSAL ANNOUNCEMENT SHALL BE SUBMITTED
ELECTRONICALLY THROUGH THE PROCUREMENT INTEGRATED ENTERPRISE ENVIRONMENT
(PIEE) SOLICITATION MODULE. No paper copies, CD-ROMs or facsimile submissions will be accepted.
Electronic Proposal Submission is required through the PIEE-SOLICITATION MODULE (https://piee.eb.mil/). Instructions for uploading proposals are as follows:
1. Register in PIEE:
a. Navigate to https://piee.eb.mil/
b. Select Register [top right]
c. Select Vendor
d. Create a User ID and Password and follow the prompts [next]
e. Create Security Questions [next]
f. Complete your User Profile Information [next]
g. Complete your Supervisor or Approving Official Information [next]
h. Complete Roles
i. Step 1. Select SOL-Solicitation
ii. Step 2. Select Proposal Manager
iii. Step 3. Click Add Roles
iv. Step 4. Fill in our Location Code (CAGE Code) [next]
i. Provide a justification for your registration [next]
j. Follow the remaining prompts to submit your registration
2. Log into PIEE and select the Solicitation Icon.
3. Enter search criteria to find the solicitation. (Search Criteria can be the complete solicitation number, Solicitation Open Date, Response Due Date, Product or Service Code, NAICS, Set Aside code, Place of Performance Zip Code, Contracting Office DODAAC, or Status)
4. The search results display. Select the Solicitation Number link to open the solicitation.
5. The solicitation displays. The information is view only.
6. Scroll down to see the Contract Information and Attachments. The Attachments can be viewed by selecting the File link. Scroll back up to the top of the screen and click the Offer tab.
7. Click the Offer tab to Add and review current offers on the Solicitation. Click the Add button to add an offer to the Solicitation.
8. Select the applicable Cage Code for which submitting the proposal for. The list is prefiltered based on the Cage in the Proposal Manager’s profile.
9. It is important that interested parties CAREFULLY ensure their electronic files adhere to the following naming convention:
a. W912QR25R00052-FIRMNAME-VOLUME I
b. W912QR25R00052-FIRMNAME-VOLUME II
Each file name shall begin with the solicitation number followed by the firm’s name and a brief file description. Please see examples above.
File Organization: Although hard copies are not accepted, each file shall be clearly indexed, and logically assembled. Font size shall be 11 or larger. Pages shall be letter sized (larger page sizes (such as 11x17 foldouts, etc.)
will be counted as two pages. Proposals shall be in a narrative format, organized and titled so that each section of the proposal follows the order and format of the factors. Information presented should be organized soas to pertain to only the evaluation factor in the section that the information is presented. Information pertaining to more than one evaluation factor should be repeated in each section for each factor.
Upload Completion & Deadline: Interested parties shall submit responses no later than the date specified on the solicitation document. The time & date of proposal receipt will be the upload completion delivery time & date recorded within PIEE-Solicitation. Do not assume that electronic submission will occur instantaneously. Large files (e.g. 10MB or more) will take some time to upload. Offerors should time their upload effort with prudence by not waiting until the last few minutes—this will allow for unexpected delays in the transmittal process. Offerors are encouraged to keep a copy of the upload confirmation for their record. Submissions after the deadline will be considered late and will be processed in accordance with FAR 15.208.
Electronic Files: Files shall be in their native format (i.e. doc, xls, ppt, etc.), or if in pdf format, shall be in searchable text. Text and graphics portfolios of the electronic copies shall be in a format readable by Microsoft Office or Adobe applications. Data submitted in a spreadsheet format shall be readable by MS Excel (all cells and formulas should be unlocked). Any information, presented in a proposal that the Offeror wants safeguarded from disclosure to other parties must be identified and labeled in accordance with the requirements of Provision “FAR 52.215-1, Instructions to Offerors – Competitive Acquisition (Nov 2021),” subparagraph (e), which is found in 00 21 00 Instructions of the RFP. The Government will endeavor to honor the restrictions against release requested by Offerors, to the extent permitted under United States law and regulations.
10. Upload the attachments that comprise the proposal by selecting Choose Files link.
11. After entering all necessary information enter a Signature Date an Click the Signature button.
12. The Sign Document pop-up will be displayed requiring the user to enter a Digital Pin and One Time Password (OTP). Click the Sign and Submit button to continue.
13. After successfully adding the Proposal a success message of the submission will be displayed and the proposal displayed collapsed. Users may expand and view all their proposals on a Solicitation.
The Procurement Integrated Enterprise Environment (PIEE) help desk may be reached by calling telephone number 866-618-5988 for assistance.
PROJNET INSTRUCTIONS
OFFEROR'S QUESTIONS AND COMMENTS
Technical inquiries and questions relating to proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at http://www.ProjNet.org/ProjNet. As noted below, offerors shall not submit their proposals via ProjNet. Offerors shall submit their proposals in accordance with the provisions stated in the solicitation.
To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into system.
The Solicitation Number is: W912QR25R0052
The Bidder Inquiry Key is: S9E6HC-EW2428
Specific Instructions for ProjNet Bid Inquiry Access:
1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
2. Identify the Agency. This should be marked as USACE.
3. Key. Enter the Bidder Inquiry Key listed above.
4. Email. Enter the email address you would like to use for communication.
5. Select Continue. A page will then open stating a user account was not found and will ask you to create one using the provided form.
6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.
7. Select Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.
Specific Instructions for Future ProjNet Bid Inquiry Access:
1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your
2. Secret Question and Secret Answer to log in.
3. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
4. Identify the Agency. This should be marked as USACE.
5. Key. Enter the Bidder Inquiry Key listed above.
6. Email. Enter the email address you used to register previously in ProjNet.
7. Select Continue. A page will then open asking you to enter the answer to your Secret Question.
8. Enter your Secret Answer and click Login. Once this is completed you are now logged into the
9. system.
From this page you may view all bidder inquiries or add an inquiry.
Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.
Offerors are requested to review the specification in its entirety and to review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.
The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.
Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.
NOTES:
1. Offerors shall not submit their proposals via ProjNet, but in accordance with the provisions stated in the solicitation. Any questions regarding acceptable means of submitting offers shall be made directly to the Contract Specialist identified in the solicitation.
2. Government responses to technical inquiries and questions relating to proposal procedures or bonds that are submitted to ProjNet in accordance with the procedures above are not binding on the Government unless an amendment is issued on Standard Form 30. In the case of any conflicts, the solicitation governs. Any changes or revisions to the solicitation will be made by formal amendment. Government responses will be limited to:
(a) Notice that an amendment will be issued; (b) Reference to an existing requirement contained in the solicitation; or (c) Notice that a response is not necessary.
3. The ability to enter technical inquiries and questions relating to proposal procedures or bonds will be disabled ten (10) calendar days prior to the closing date stated in the solicitation. No Government responses will be entered into the ProjNet system within five (5) calendar days prior to the closing date stated in the solicitation.
Section 00 22 00 - Supplementary Instructions
EVALUATION CRITERIA
PROCEDURES FOR SUBMITTAL OF OFFERS AND PROPOSAL EVALUATION CRITERIA
1. Overview.
1.1 The intent of this solicitation is to select one contractor for the construction of a new Manned/Unmanned Tactical Vehicle Lab for the Ground Vehicle Systems Center at Detroit Arsenal (DTA), located in Warren, MI. The basis of award is the Best Value Trade-Off Process. The Contracting Officer will award a firm fixed price contract to the responsible offeror whom the Source Selection Authority (SSA) determines conforms to the solicitation, is fair and reasonable, and offers the best overall value to the Government, all factors considered. The Government reserves the right to accept other than the lowest priced offer or to reject all offers.
1.2 This project is for the design/bid/build construction of a new Ground Transport Equipment Building to support eight tactical vehicle integration labs. Project includes associated vehicle parking with vehicle integration labs, bench lab, and engineering-design space to enable the integration of technology required for the transformation of current combat systems to manned-unmanned systems to meet the Army’s strategic program delivery requirements, information systems, fire pump and alarm systems, Intrusion Detection System (IDS) installation, Cybersecurity and Energy Monitoring Control Systems (EMCS) connection. Sustainability and energy enhancement measures are included. Supporting facilities include site development, utilities and connections, lighting, paving, parking, walks, curbs and gutters, storm drainage, information systems, landscaping and signage. Heating and air conditioning will be provided by self-contained systems for the entire facility. Measures in accordance with the Department of Defense (DoD) Minimum Antiterrorism for Buildings standards will be provided. Comprehensive building and furnishings related interior design services are required.
1.3 The estimated target ceiling for contract award is $30,000,000 based on the funds made available for this project. The Government cannot guarantee that additional funds will be available for award. Offerors are under no obligation to approach this ceiling.
2. Submittal of offers.
2.1 Offerors submitting proposals for this project should limit submissions to data essential for evaluation of proposals so that a minimum of time and monies will have been expended in preparing information required herein. However, in order to be effectively and equitably evaluated, the proposals must include information sufficiently detailed to clearly describe the offeror's capability for successfully completing the solicited project. Requirements stated in this Request for Proposal (RFP) are minimums. Proposals should follow in the order of sequence set forth in the RFP. Information provided out of sequence may not be evaluated and may result in the offeror’s disqualification from award.
2.2 All submissions to this proposal announcement shall be submitted electronically and shall be submitted no later than the time and date specified in Block 13 of Standard Form 1442. Please refer to and follow the instructions specified in the Electronic Proposal Submission Instructions, attached herein.
2.3 Offerors are required to submit a proposal consisting of the information identified in paragraphs 2.4 and 2.5 below. All proposal materials shall be submitted electronically with a table of contents and section dividers. The sections should parallel the submission requirements identified herein.
2.4 Volume I shall be submitted electronically in accordance with the Proposal Submission Instructions in Section 00 21 00 and include the following information:
Volume I – Factor I: Past Performance Volume I – Factor II: Management Plan Volume I – Factor III: Small Business Participation Plan
*NOTE: Failure to place the required submission information under the appropriate tab may result in a lower rating if the evaluators cannot readily find the appropriate information. Any specified page limits will be strictly adhered to and enforced. Information submitted that exceeds the specified limit will not be evaluated.
2.5 Volume II shall be submitted electronically in accordance with the Proposal Submission Instructions in Section 00 21 00 and include the following information:
Volume II – Tab A: Standard Form 1442 and Price Breakout Schedule Volume II – Tab B: Joint Venture Agreements Volume II – Tab C: Evidence of Ability to Obtain Bonding and Proof of Financial Ability Volume II – Tab D: Pre-Award Information Volume II – Tab E: Subcontracting Plan
NOTE: Failure to place the required submission information under the appropriate tab may result in a lower rating if the evaluators cannot readily find the appropriate information.
3. Proposal Evaluation Process.
3.1. A Source Selection Evaluation Board (SSEB) comprised of representatives of the Corps of Engineers, User/Customer, and other required personnel will evaluate the proposals. Offerors are advised that the technical evaluation and rating of proposals will be conducted in strict confidence. Technical proposals (Volume I) will be reviewed and rated without knowledge of the price offered. The number and identities of offerors are not revealed to anyone not involved in the evaluation and award process or to other offerors.
Proposals will be evaluated based on the factors described herein, and the basis of award is a Best Value Trade-Off, as stated above.
3.2 The evaluation process essentially consists of four parts: proposal compliance review and responsibility review, technical evaluation, price evaluation, and price/technical trade-off analysis.
3.2.1 Proposal Compliance Review: This is an initial review to ensure that all required forms and certifications are complete and that the offeror is financially capable of sustaining performance under the contract and is able to obtain the required level of performance and payment bonds from an acceptable surety.
3.2.2 Technical Evaluation: The SSEB will evaluate and rate the Volume I proposals against the RFP requirements. Factor I – Past Performance will be rated using Tables 1 and 2 below. The rating will be based on overall confidence in performance, with the final confidence assessment rating based on the extent of recent, relevant past experience and the quality of the offeror’s performance. Factor II – Management Plan will be rated using Table 3 below. Factor III – Small Business Participation Plan will be rated using Table 4 below.
3.2.3 Price Evaluation: The SSEB and Contracting Officer/SSA will evaluate price proposals independent of the technical evaluation. The SSEB will not have access to price information until completion of the technical evaluation.
3.2.4 Price/Technical Trade-off Analysis: After all the above evaluations are complete, the Contracting Officer/SSA will compare the relative advantages and disadvantages of technical proposals and compare prices. The Source Selection Authority (SSA) will then consider all factors to select the proposal offering the best value to the Government.
4. Proposal Information and Related Evaluation Factors.
4.1 Proposals will be evaluated in accordance with the factors and sub factors below, listed in relative order of importance. All evaluation factors, other than cost or price, when combined are considered approximately equal to price. The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a cost or price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.
4.2 Volume I – Factor I – Past Performance 1st
4.3 Volume I – Factor II –Management Plan 2nd
4.4 Volume I – Factor III – Small Business Participation Plan 3rd
4.5 Volume II - Price and Pro Forma Information
Tab A Standard Form 1442 and Price Breakout Schedule Not Rated
Tab B Joint Venture Agreement Not Rated
Tab C Evidence of Ability to Obtain Bonding and Not Rated Proof of Financial Ability
Tab D Pre-Award Information Not Rated
Tab E Subcontracting Plan Acceptable / Unacceptable
4.6 Ratings:
Evaluators will apply the adjectival rating for the definition that most closely matches the evaluation.
TABLE 1
Past Performance Relevancy Ratings Rating Description Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.
Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.
Somewhat Relevant Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.
Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.
TABLE 2
Performance Confidence Assessments
Rating Description Substantial Confidence Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.
Satisfactory Confidence Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.
Neutral Confidence No recent/relevant performance record is available or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned. The offeror may not be evaluated favorably or unfavorably on the factor of past performance.
Limited Confidence Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.
No Confidence Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will successfully perform the required effort.
TABLE 3
Technical / Risk Assessment Ratings Adjectival Rating Description Outstanding Proposal indicates an exceptional approach and understanding of the requirements and contains multiple strengths, and risk of unsuccessful performance is low.
Good Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength, and risk of unsuccessful performance is low to moderate.
Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.
Marginal Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high.
Unacceptable Proposal does not meet the requirements of the solicitation, and thus, contains one or more deficiencies, and/or risk of unsuccessful performance is unacceptable. Proposal is unawardable.
TABLE 4
Small Business Ratings
Rating Description
Acceptable Proposal clearly meets the minimum requirements of the solicitation.
Unacceptable Proposal does not clearly meet the minimum requirements of the solicitation.
4.7 Definitions
1. Deficiency. A material failure of a proposal to meet a Government requirement or a combination of significant weaknesses in a proposal that increases the risk of unsuccessful contract performance to an unacceptable level. See FAR 15.001.
2. Strength. An aspect of an offeror’s proposal that has merit or exceeds specified performance or capability requirements in a way that will be advantageous to the Government during contract performance.
3. Significant Strength. An aspect of an offeror’s proposal that has appreciable merit or appreciably exceeds specified performance or capability requirements in a way that will be appreciably advantageous to the Government during contract performance.
4. Weakness. A flaw in the proposal that increases the risk of unsuccessful contract performance. See
FAR 15.001.
5. Significant Weakness. A flaw in the proposal that appreciably increases the risk of unsuccessful contract performance. See FAR 15.001.
6. Uncertainty. Any aspect of a non-cost/price factor proposal for which the intent of the offeror is unclear (e.g., more than one way to interpret the offer or inconsistencies in the proposal indicating that there may have been an error, omission, or mistake).
7. Clarification. Limited exchanges between the Government and offerors that may occur when award without discussions is contemplated. See FAR 15.306(a)(1).
8. Adverse Past Performance. Past performance information that supports a less than satisfactory rating on any evaluation. Adverse past performance that must be addressed with Offerors includes unfavorable comments received from sources such as those received from respondents from past performance questionnaires or interviews that have not been finalized within a formal rating system.
5.0 Volume I – Factor I: Past Performance
5.1 Submission Requirements:
5.1.1 Provide descriptions of up to three (3) projects substantially complete or completed by the Prime
Contractor within the last five (5) years (from the solicitation issue date) that are similar to this project in size and scope. Projects completed more than five (5) years before the solicitation issue date may be considered for evaluation purposes but may lessen the overall relevancy rating for that project. Projects are considered substantially complete if they can be used for their intended purpose. An Indefinite Delivery Indefinite Quantity (IDIQ) contract may be submitted only if a single task order could be considered similar to this project. Task orders may not be combined in order for the project to be considered similar.
NOTE: Renovation projects will NOT be considered similar in size or scope to the solicited requirement.
5.1.2 Projects considered similar in size would be new construction of 20,000 square feet or greater
5.1.3 Projects considered similar in scope to this project would include the following features:
a) New construction of an industrial, research, development, testing, maintenance and/or manufacturing facility that includes associated office/admin space.
NOTE: Warehouses and office/admin facilities will NOT be considered similar in scope.
5.1.4 The prime contractor must have self-performed at least 15 percent of the direct contract labor (including testing and layout personnel), exclusive of other general conditions or field overhead personnel, material, equipment, or subcontractors to be considered similar.
5.1.5 Additional consideration may be given for projects that contain the following features:
a) High bay space with bridge cranes to support industrial vehicle research, development, testing, and maintenance activities.
b) Previous USACE experience.
5.1.6 The following information shall be provided for each project:
a) Project Title, Location, and Contract Number/Unique Identifier.
b) Current percentage of construction complete and the date it was or will be complete.
a. For projects that are not yet complete, provide description of work remaining to be completed.
c) Scope of the project, to include purpose/use of facility.
d) Size of the project, differentiate square footage of new construction versus renovation if the project includes both.
e) Role of firm: Provide a description of the type of work performed and the percentage of work that was self-performed.
f) Dollar value of the project.
g) Customer primary point of contact (POC) and alternate POC (name, relationship to project, agency/firm affiliation, city, state, current and correct phone number, and current and correct email address).
5.1.7 Provide two references for all the projects identified in paragraph 5.1.1, 5.1.2 and 5.1.3. Reference information must include project name, location, owner's name, point of contact, telephone number, and email address.
For this factor, also include any ratings, letters, awards, etc. that support past performance on these projects. Any of this information that is submitted shall clearly identify to which of the submitted projects it pertains. A sample Past Performance Questionnaire is attached for your convenience. If used, the Past Performance Questionnaire must be submitted by the offeror with the proposal submission and not sent directly to the agency from the reference. For each project, the offeror may provide information on problems encountered on the identified contracts and the offeror’s respective corrective action.
NOTE: For purposes of evaluating past performance, the Prime Contractor is defined as the contractor identified in Block 14 of the Standard Form 1442. Projects performed by contractors other than the offeror, including, but not limited to, teaming partners, subcontractors, sister or parent companies, and affiliates will not be evaluated for past performance, unless those other contractors are part of a joint venture offeror as demonstrated by a signed joint venture agreement. If more than one contractor is listed in Block 14, then a signed joint venture must be submitted with the proposal and the joint venture shall be registered as such in the System for Award Management (SAM). However, each party of the Joint Venture (JV) must submit their own Unique Entity Identifier Number (formerly known as DUNS) with the JV proposal. Projects performed by other contractors than the offeror, such as teaming partners or subcontractors, will not be evaluated for past performance, unless those other contractors are part of a JV offeror as demonstrated by a signed JV agreement. If the offeror represents the combining of two or more companies as a JV for the purpose of this RFP, each company in the JV may submit project examples, but the total submitted by the JV will not exceed three (3).
5.2 Evaluation Criteria:
5.2.1 The SSEB will first evaluate the relevancy of recent past performance identified in the proposal in response to paragraph 5.1 above. By using the criteria identified above, the SSEB will determine how relevant a past project is when compared to the scope, size, and magnitude of effort and complexities of the solicited project. A relevancy rating will be assigned to each submitted project using the Past Performance Relevancy Ratings table above.
5.2.2 The SSEB will next review how well the offeror performed on those projects. The Government reserves the right to check any or all cited references to verify supplied information and to assess owner satisfaction.
The Government also reserves the right to not contact the provided references. In addition to the information submitted by the offeror, the Government reserves the right to review any other sources of relevant information for evaluating past performance, including projects other than those submitted by the offeror. The Government reserves the right to review past performance information retrieved through the Past Performance Information Retrieval System (PPIRS), including Contractor Performance Assessment Reporting System (CPARS), using all CAGE/Unique Entity Identifier numbers. Other sources may include, but are not limited to, past performance information retrieved from inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the offeror.
5.2.3 The SSEB will review all past performance information collected and determine the quality of the offeror’s performance, general trends, and usefulness of the information and incorporate this information into the performance confidence assessment. The SSEB will assign a final, overall Performance Confidence rating, using the ratings in the Performance Confidence Assessment table above, based on the SSEB’s assessment of (1) the degree of the offeror’s recent, relevant experience, and (2) how well the offeror performed that experience.
6.0 Volume I – Factor II: Management Plan
6.1 Submission Requirements:
Provide a management plan narrative that describes how you’ll successfully deliver the project. The Management Plan shall at a minimum include the following information:
Discuss the key members of your project delivery team (e.g. PM, Superintendent, Quality Control Team, SSHO), and how they’ll work together to streamline construction and delivery of this project.
Identify significant challenges/areas of risk specific to this project and provide your plan for mitigating these risk/constraints during contract performance.
Discuss the key subcontractors you will utilize to accomplish this work and how they will be managed.
Discuss the key considerations and milestones associated with the construction schedule and how you’ll execute the work to deliver the project within the period of performance.
Discuss plan for managing construction to achieve LEED Silver requirement.
There is a page limit of eight (8) single sided, 8.5” x 11” pages, using a minimum font size of 11 and a minimum margin of one-half inch on all sides for this factor. Any information that exceeds these page limits will not be evaluated.
6. 2 Evaluation Criteria:
Narratives will be evaluated based on the level of understanding of the work and the involvement the contractor will have in the management, oversight, control, and coordination of the work performed during construction of the project. Narratives that demonstrate a clear understanding of the project requirements and provide a thorough approach for successfully managing the solicited project and/or mitigating project specific risk items, may be rated more favorably by the SSEB.
The offeror’s organizational chart will be evaluated based on the clarity, adequacy, capabilities, and strengths for successfully managing the solicited project.
7.0 Volume I – Factor III: Small Business Participation Plan
7.1 Submission Requirements
ALL OFFERORS ARE REQUIRED TO SUBMIT A SMALL BUSINESS PARTICIPATION PLAN. The Small Business Participation Plan shall be based on the offeror’s best effort and is required to address each of the following areas individually:
The extent to which the small business programs listed in FAR 19 (small business, small disadvantaged business, woman-owned small business, HubZone, service disabled veteran owned small business, etc.) are specifically identified in the Small Business Participation Plan.
The extent of participation of such firms in terms of the value of the total acquisition in %’s for the base year and for each individual option year; the extent of commitment to use such firms (for example, enforceable commitments, i.e., teaming agreements signed, are to be considered more heavily than non-enforceable ones).
The complexity and variety of the work small firms are to perform on this acquisition.
The practicality of the Small Business Participation Plan, i.e., aggressive goals.
The Small Business Participation Plan shall be organized as follows:
(1) Prime Contractor type of business (check all that apply):
( ) Large ( ) Small (also check type of small business) ( ) Small Non-Disadvantaged Business ( ) Small Disadvantaged Business ( ) Woman-Owned Small Business ( ) HUBZone Small Business ( ) Veteran Owned Small Business ( ) Service Disabled, Veteran Owned Small Business
(2) Percentage of your participation as a prime contractor: __________________ %
NOTE: Small Business primes’ self-performance counts as Small Business Participation, and small business primes may achieve small business participation goals through their own performance/participation as a prime and/or through subcontracting to other small businesses.
(3) Percentage of total contract value of subcontracts planned for:
% of Total Contract
Value Large % Total Small % Small Non-Disadvantaged % Small Disadvantaged % Small Woman Owned % Small HUB Zone % Small Veteran Owned % Small Service Disabled Veteran Owned %
Each percentage above shall be accompanied by detailed supporting documentation regarding individual commitments.
NOTE: The sum of the percentages of Small Non-Disadvantaged and Small Disadvantaged should equal the entries for the Total Small; however, the sum of all of the percentages need not equal 100% since the prime is not included and individual subcontractors may be counted towards more than one category.
(4) List principal supplies/services (be specific) to be subcontracted to:
Name of
Company Type of
Service/Supply Large Small Non-Disadvantaged Small Disadvantaged Small Woman Owned Small HUB Zone Small Veteran Owned Small Service Disabled Veteran Owned
(5) Prior Performance Information: Provide any information substantiating the offeror’s track record of utilizing small business on past contracts.
(6) For Large and Small Businesses provide descriptive information for all small business categories. Any information concerning long-term relationships with Small Business subcontractors, such as mentor-protégé relationships, should be provided.
(7) Extent of Commitment: Provide documentation regarding enforceable commitments to utilize any small business category as defined in FAR Part 19 as subcontractors.
(8) Small Business Subcontracting Plan: Each Large Business Offeror shall provide a Small Business Subcontracting Plan that contains all of the elements required by FAR Clause 52.219-9 Alt II. This Plan shall be submitted separately from the Small Business Participation information required above which applies to both Large and Small Businesses.
The Subcontracting Plan is not a requirement for evaluation in source selection but rather a requirement for award to a Large Business. The approved Small Business Subcontracting Plan will be incorporated into any resultant contract(s).
7.2 Evaluation Criteria:
ALL OFFERORS ARE REQUIRED TO SUBMIT A SMALL BUSINESS PARTICIPATION PLAN.
The Small Business Participation Plan will be evaluated based on the offeror’s best efforts, the level of small business commitment that is being demonstrated for the proposed acquisition, and the prior level of commitment to utilizing small businesses in performance of prior contracts. The Small Business Participation Plan must meet the minimum Total Small Business Participation goal of 15% of the total contract value (through collective small business participation from any type of small business or sub-category small business).
Pursuant to DFARS PGI 215.304(c), the following elements will be considered in evaluating an offeror’s Participation Plan:
The extent to which such firms, as defined in FAR Part 19, are specifically identified in plans;
The extent of commitment to use such firms (enforceable commitments will be weighted more heavily than non-enforceable ones);
The complexity and variety of the work such firms are to perform;
The realism of the plans;
Past performance of offerors in complying with the requirements of the Subcontracting Plan Goals for such firms and monetary targets for participation;
The extent of participation of such firms in terms of the proposed subcontracted value; and
The extent to which the offeror provides detailed explanations/documentation supporting the proposed participation percentages, or lack thereof. The Department of Defense (DOD) has established small business goals to help ensure small business receives a fair proportion of DOD awards.
8.0 Volume II - Price and Proforma Information
8.1 Tab A - Standard Form 1442 and Proposal Price Breakout Schedule.
8.1.1 Submission Requirements:
The offeror shall complete and submit Standard Form 1442 and Section 00 10 00, Proposal Price Breakout Schedule.
8.1.2 Evaluation Criteria:
The price will be evaluated on base proposal plus all options. The price will be evaluated for fairness and reasonableness through the use of a price analysis. Price will also be checked for unbalancing of line items.
Offerors are cautioned to distribute costs appropriately.
8.2 Tab B – Joint Venture Agreements
8.2.1 Submission Requirements:
If more than one contractor is listed in Block 14, or the offeror listed in Block 14 is a joint venture (JV), then a signed JV agreement must be submitted with the proposal and the offeror shall be registered in the System for Award Management (SAM) as a legal entity separate from the individual joint venture members. However, each member of the JV must submit its own Unique Entity Identifier (formally DUNS number) with the proposal. A copy of the offeror's signed joint venture agreement shall be submitted with the proposal.
Small business offerors (e.g., 8(a), HUBZone, SDVOSB) submitting a proposal as a JV or Mentor-Protégé shall submit evidence from the offeror's SBA Servicing Agency that the offeror has notified and discussed the proposed joint venture for this specific project with the appropriate SBA Representative or Business Opportunity Specialist. Joint Venture agreements and approved 8(a) Mentor-Protégé agreements must be submitted with the proposal.
8.2.2 Evaluation Criteria:
This information will be used for the purpose of completing the Pre-Award Survey and will not be rated.
Joint Venture Agreements and Mentor-Protégé agreements must comply with the relevant regulations in Title 13 of the Code of Federal Regulations in order for an offeror to be eligible for any small business-related price preference.
8.3 Tab C – Evidence of Ability to Obtain Bonding and Proof of Financial Ability
8.3.1 Submission Requirements:
A. Financial Capability. Submit Proof of Financial Ability (Most recent financial statement covering assets and liabilities). Include the name, address, and telephone number of offeror's banking institution. If the offeror is a joint venture, submit this information for all joint venture members.
B. Bonding Capability. Submit information showing offeror's ability to be bonded for this project. Include the name, address, and telephone number of the offeror's bonding company.
8.3.2 Evaluation Criteria:
This information will be used for the purpose of completing the Pre-Award Survey and will not be rated.
See FAR Part 28 for information related to bonds.
8.4 Tab D – Pre-Award Information
8.4.1 Submission Requirements:
A. The offeror shall submit one completed copy of Section 00 45 00, Representations and Certification.
B. The offeror shall submit the following information:
a) Number of years the firm has been in business
b) Name, address, and telephone numbers of two credit/trade references
c) A list of present commitments, including the dollar value
If the offeror is a joint venture, submit this information for all joint venture members.
8.4.2 Evaluation Criteria:
This information will be used for the purpose of completing the Pre-Award Survey and will not be rated.
8.5 Tab E - Subcontracting Plan
8.5.1 Submission Requirements:
Large business offerors shall submit a Subcontracting Plan in accordance with FAR Clauses 52.219-8 and 52.219-9 Alt II. To be acceptable, plans must adequately address the required statutory elements and provide sufficient information to enable the Contracting Officer to answer affirmatively questions 1 through 13 of Appendix DD, Part 2, AFARS 5119.705-4. The offeror may use the attached sample sub-contracting plan as a starting point. Percentage goals apply to the total amount being subcontracted.
8.5.2 Evaluation Criteria:
Submitted information will be evaluated for acceptability in accordance with AFARS 5119.705. To be acceptable, subcontracting plans must:
(a) Adequately address the required statutory elements.
(b) Provide sufficient information to enable the Contracting Officer to answer affirmatively questions 1 through 13 of Appendix DD, Part 2, AFARS 5119.705-4, a copy of which is attached.
(c) To be acceptable, subcontracting plans must meet all of the requirements outlined in Appendix DD, Part 3, AFARS 5119.705. If discussions with offerors are necessary, those areas where the plan is deficient will be reviewed with each offeror with the goal of correcting deficiencies.
NAVFAC/USACE PAST PERFORMANCE QUESTIONNAIRE (Form PPQ-0)
CONTRACT INFORMATION (Contractor to complete Blocks 1-4)
1. Contractor Information Firm Name: CAGE Code:
Address: DUNs Number:
Phone Number:
Email Address:
Point of Contact: Contact Phone Number:
2. Work Performed as: Prime Contractor Sub Contractor Joint Venture Other (Explain) Percent of project work performed:
If subcontractor, who was the prime (Name/Phone #):
3. Contract Information Contract Number:
Delivery/Task Order Number (if applicable):
Contract Type: Firm Fixed Price Cost Reimbursement Other (Please specify):
Contract Title:
Contract Location:
Award Date (mm/dd/yy):
Contract Completion Date (mm/dd/yy):
Actual Completion Date (mm/dd/yy):
Explain Differences:
Original Contract Price (Award Amount):
Final Contract Price (to include all modifications, if applicable):
Explain Differences:
4. Project Description:
Complexity of Work High Med Routine How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)
CLIENT INFORMATION (Client to complete Blocks 5-8)