This document is an amendment to Solicitation W912QR24R0008 for the construction of a new Ground Transport Equipment Building (GTEB) for the Ground Vehicle Systems Center at the Detroit Arsenal (DTA) in Warren, MI. The solicitation is a single-phase, Design/Bid/Build, 100% Full and Open (Unrestricted) procurement with an estimated construction cost between $25,000,000 and $100,000,000. The amendment includes the following key details:
The solicitation is modified to add several new specification sections, replace existing sections, and revise multiple drawings. The submission date for proposals is extended from April 5, 2024 to April 10, 2024 at 2:00 pm ET. The amendment provides a list of the specification sections and drawings that have been added, replaced, or revised. This includes sections related to bituminous dampproofing, exterior signage, cybersecurity for fire and mass notification control systems, and bridge cranes among others. The project is targeting a LEED Silver certification, and the amendment provides additional details on the LEED and sustainability requirements for the project.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Solicitation W912QR24R0008 for the Construction of a new Ground Transport Equipment Building (GTEB) for the Ground Vehicle Systems Center at Detroit Arsenal (DTA), located in Warren, MI is hereby modif ied as follows:
SEE CONTINUATION PAGE
1. CONTRACT ID CODE PAGE OF PAGES
1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912QR24R0008
X 9B. DATED (SEE ITEM 11)
11-Jan-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
29-Mar-2024
CODE
U. S. ARMY ENGINEER DISTRICT, LOUISVILLE
600 DR. MARTIN LUTHER KING, JR. PLACE
ROOM 821
LOUISVILLE KY 40202-2239
W912QR 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912QR24R0008_Specs-0004
W912QR24R0008
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0004
Solicitation W912QR24R0008 for the Construction of a new Ground Transport Equipment Building (GTEB) for the Ground Vehicle Systems Center at Detroit Arsenal (DTA), located in Warren, MI is hereby modified as follows:
a. The following Specification sections have been ADDED to the package:
07 11 13 BITUMINOUS DAMPPROOFING
10 14 00.10 EXTERIOR SIGNAGE
b. The following Specification sections have been replaced in their entirety:
01 33 29.00 06 SUSTAINABILITY REPORTING
25 05 11.02 CYBERSECURITY FOR FIRE & MASS NOTIFICATION CONTROL SYSTEMS
27 11 16 COMMUNICATIONS RACKS, FRAMES AND ENCLOSURES
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM, ADDRESSABLE
41 22 13.14 BRIDGE CRANES, OVERHEAD ELECTRIC, TOP RUNNING
c. The following Drawings have been replaced in their entirety:
Drawing No. Drawing Name
C-002 GENERAL NOTES AND ABBREVIATIONS
C-109 HAUL ROUTE
G-002 SHEET INDEX
G-003 SHEET INDEX
S-001 GENERAL STRUCTURAL NOTES
S-005 GENERAL STRUCTURAL NOTES
S-400 TEST PIT FOUNDATION PLAN AND SECTIONS
A-401 ENLARGED PLANS AND ELEVATIONS
A-402 ENLARGED PLANS AND ELEVATIONS
A-403 ENLARGED PLANS AND ELEVATIONS
I-111 FIRST FLOOR FINISH PLAN - SECTOR 1
I-112 FIRST FLOOR FINISH PLAN - SECTOR 2
I-113 FIRST FLOOR FINISH PLAN - SECTOR 3
I-403 INTERIOR ELEVATIONS
FA111 FIRE ALARM PLAN – SECTOR 1
FA601 FIRE ALARM AND MNS RISER DIAGRAM
M-601 MECHANICAL SCHEDULES
E-602 MSWBDA AND MSWBDB ELECTRICAL ONE-LINE
E-610 PANEL SCHEDULES
W912QR24R0008
T-100 TELECOMMUNICATIONS SITE PLAN
T-101 TELECOMMUNICATIONS ENLARGED SITE PLAN
d. The submission date is hereby extended to 10 April 2024 at 2:00 pm ET. Acknowledgment of receipt of this amendment and proposals are due at that time.
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 05-Apr-2024 02:00 PM to 10-Apr-2024 02:00 PM.
(End of Summary of Changes)
P2#: 500060 - Ground Transportation Equipment Building Detroit Arsenal, MI
PROJECT TABLE OF CONTENTS
Amendment 0004 22 March 2024
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 80 00.00 06 04/21 SPECIAL PROVISIONS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 08/15, CHG 2: 08/21 SUMMARY OF WORK
01 32 01.00 06 07/18 PROJECT SCHEDULE
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 33 29.00 06 11/17 SUSTAINABILITY REPORTING
01 35 26.00 06 GOVERNMENT SAFETY REQUIREMENTS
01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.15 10 11/16, CHG 2: 08/19 RESIDENT MANAGEMENT SYSTEM CONTRACTOR
MODE (RMS CM)
01 45 04.10 06 CONTRACTOR QUALITY CONTROL
01 45 35 11/20 SPECIAL INSPECTIONS
01 46 00.00 06 04/20 TOTAL BUILDING COMMISSIONING
01 50 00 11/20, CHG 1: 08/21 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19.00 06 04/20 TEMPORARY ENVIRONMENTAL CONTROLS AND
PERMITS
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 23 08/15, CHG 2: 08/21 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 41 00 05/10, CHG 2: 02/19 DEMOLITION
DIVISION 03 - CONCRETE
03 30 00 02/19, CHG 3: 11/21 CAST-IN-PLACE CONCRETE
03 45 00 05/16, CHG 2: 11/21 PRECAST ARCHITECTURAL CONCRETE
DIVISION 04 - MASONRY
04 20 00 11/15, CHG 2: 05/19 UNIT MASONRY
DIVISION 05 - METALS
05 05 20.00 27 02/21 POST-INSTALLED CONCRETE AND MASONRY
ANCHORS
05 05 23.13 10 08/18 ULTRASONIC INSPECTION OF WELDMENTS
05 05 23.16 08/18 STRUCTURAL WELDING
05 12 00 08/18, CHG 2: 05/21 STRUCTURAL STEEL
05 30 00 05/15, CHG 2: 08/18 STEEL DECKS
05 40 00 05/15, CHG 1: 08/18 COLD-FORMED METAL FRAMING
05 50 13 05/17, CHG 1: 08/18 MISCELLANEOUS METAL FABRICATIONS
05 51 33 02/16, CHG 2: 02/18 METAL LADDERS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 08/16, CHG 2: 11/18 ROUGH CARPENTRY
06 41 16.00 10 08/10, CHG 1: 11/18 PLASTIC-LAMINATE-CLAD ARCHITECTURAL
CABINETS
06 61 16 08/20 SOLID SURFACING FABRICATIONS
PROJECT TABLE OF CONTENTS Page 1 Certified Final Submittal-Addendum 0004
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 05 23 08/19 PRESSURE TESTING AN AIR BARRIER SYSTEM
FOR AIR TIGHTNESS
07 11 13 08/11, CHG 1: 05/17 BITUMINOUS DAMPPROOFING
07 13 53 02/16, CHG 1: 08/17 ELASTOMERIC SHEET WATERPROOFING
07 21 13 02/16, CHG 2: 08/20 BOARD AND BLOCK INSULATION
07 22 00 02/16, CHG 3: 11/18 ROOF AND DECK INSULATION
07 27 10.00 10 08/19, CHG 1: 02/20 BUILDING AIR BARRIER SYSTEM
07 42 13 05/11, CHG 2: 02/18 METAL WALL PANELS
07 54 19 THERMOPLASTIC POLYOLEFIN (TPO) ROOFING
07 60 00 05/17, CHG 2: 11/18 FLASHING AND SHEET METAL
07 81 00 02/11 SPRAY-APPLIED FIREPROOFING
07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING
07 92 00 08/16, CHG 3: 11/18 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 08/20 STEEL DOORS AND FRAMES
08 14 00 08/16, CHG 1: 08/18 WOOD DOORS
08 31 00 05/17, CHG 1: 08/18 ACCESS DOORS AND PANELS
08 33 23 08/20 OVERHEAD COILING DOORS
08 34 73 11/19, CHG 1: 02/21 SOUND CONTROL DOOR ASSEMBLIES
08 41 13 08/18, CHG 1: 08/18 ALUMINUM-FRAMED ENTRANCES AND
STOREFRONTS
08 60 45 08/20 TRANSLUCENT PANELS
08 71 00 02/16, CHG 3: 08/20 DOOR HARDWARE
08 81 00 05/19 GLAZING
08 91 00 08/20 METAL WALL LOUVERS
DIVISION 09 - FINISHES
09 22 00 02/10, CHG 2: 08/18 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 08/16, CHG 4: 02/20 GYPSUM BOARD
09 30 10 08/20 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 08/20 ACOUSTICAL CEILINGS
09 65 00 08/10, CHG 3: 08/18 RESILIENT FLOORING
09 67 23.15 02/21 FUEL RESISTIVE RESINOUS FLOORING,
3-COAT SYSTEM
09 68 00 11/17, CHG 2: 08/20 CARPETING
09 84 20 08/16, CHG 1: 08/18 ACOUSTICAL WALL PANELS
09 90 00 02/21 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 11 00 08/20 VISUAL DISPLAY UNITS
10 14 00.10 08/17, CHG 1: 11/18 EXTERIOR SIGNAGE
10 14 00.20 08/20 INTERIOR SIGNAGE
10 21 13 08/20 TOILET COMPARTMENTS
10 26 00 08/20 WALL AND DOOR PROTECTION
10 28 13 08/20 TOILET ACCESSORIES
10 44 16 11/19 FIRE EXTINGUISHERS
10 51 13 05/11 METAL LOCKERS
DIVISION 12 - FURNISHINGS
12 24 13 08/20 ROLLER WINDOW SHADES
12 50 00.13 10 08/17, CHG 1: 11/18 FURNITURE AND FURNITURE INSTALLATION
12 59 00 08/17, CHG 1: 08/18 SYSTEMS FURNITURE
PROJECT TABLE OF CONTENTS Page 2 Certified Final Submittal-Addendum 0004
*********************************************************************************Amdt. #0004
Amdt. #0004*********************************************************************************
Amdt. #0004*******************************************************************************
*******************************************************************************Amdt. #0004
DIVISION 21 - FIRE SUPPRESSION
21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE
PROTECTION
21 30 00 04/08, CHG 1: 08/13 FIRE PUMPS
DIVISION 22 - PLUMBING
22 00 00 11/15, CHG 4: 05/21 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 05 15 02/14 COMMON PIPING FOR HVAC
23 05 93.00 06 08/16 TESTING, ADJUSTING, AND BALANCING
(TAB) OF HVAC
23 07 00 02/13, CHG 7: 05/20 THERMAL INSULATION FOR MECHANICAL
SYSTEMS
23 08 00.00 20 02/21, CHG 1: 05/21 COMMISSIONING OF MECHANICAL AND
PLUMBING SYSTEMS
23 09 00 02/19, CHG 3: 05/21 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 11/15, CHG 2: 05/21 INSTRUMENTATION AND CONTROL DEVICES
FOR HVAC
23 09 23.02 02/19, CHG 1: 02/20 BACNET DIRECT DIGITAL CONTROL FOR HVAC
AND OTHER BUILDING CONTROL SYSTEMS
23 11 20 05/20 FACILITY GAS PIPING
23 21 23 08/17 HYDRONIC PUMPS
23 23 00 08/21 REFRIGERANT PIPING
23 30 00 05/20 HVAC AIR DISTRIBUTION
23 52 00 04/08, CHG 5: 11/19 HEATING BOILERS
23 64 10 11/16, CHG 2: 08/18 WATER CHILLERS, VAPOR COMPRESSION TYPE
23 64 26 08/09, CHG 5: 11/19 CHILLED AND CONDENSER WATER PIPING
SYSTEMS
23 65 00 11/16, CHG 2: 08/18 COOLING TOWERS
23 81 00 05/18, CHG 1: 02/21 DECENTRALIZED UNITARY HVAC EQUIPMENT
23 81 23 11/20 COMPUTER ROOM AIR CONDITIONING UNITS
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.01 05/21 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS
25 05 11.02 05/21 CYBERSECURITY FOR FIRE & MASS
NOTIFICATION CONTROL SYSTEMS
25 05 11.03 05/21 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS
25 08 10 05/21 UTILITY MONITORING AND CONTROL SYSTEM
TESTING
25 10 10 02/19, CHG 1: 05/21 UTILITY MONITORING AND CONTROL SYSTEM
(UMCS) FRONT END AND INTEGRATION
DIVISION 26 - ELECTRICAL
26 08 00 11/21 APPARATUS INSPECTION AND TESTING
26 12 19.10 05/19, CHG 1: 11/19 THREE-PHASE, LIQUID-FILLED PAD-MOUNTED
TRANSFORMERS
26 13 00 05/21 SF6/HIGH-FIREPOINT FLUIDS INSULATED
PAD-MOUNTED SWITCHGEAR
26 20 00 08/19, CHG 3: 11/21 INTERIOR DISTRIBUTION SYSTEM
26 24 13 08/21 SWITCHBOARDS
PROJECT TABLE OF CONTENTS Page 3
26 28 01.00 10 08/21 COORDINATED POWER SYSTEM PROTECTION
26 29 23 02/20, CHG 1: 05/21 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS
UNDER 600 VOLTS
26 41 00 11/13 LIGHTNING PROTECTION SYSTEM
26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING
26 56 00 08/21 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 05 28.36 40 05/17 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS
27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING
SYSTEM
27 11 16 11/14 COMMUNICATIONS RACKS, FRAMES AND
ENCLOSURES
27 13 13 11/14 COMMUNICATIONS COPPER BACKBONE CABLING
27 13 23.00 40 11/14 COMMUNICATIONS OPTICAL BACKBONE CABLING
27 15 13 11/14 COMMUNICATIONS COPPER HORIZONTAL
CABLING
27 41 00 11/21 AUDIO-VISUAL SYSTEMS
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 08/20 INTERIOR FIRE ALARM AND MASS
NOTIFICATION SYSTEM, ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00.00 06 07/18 EARTHWORK
31 05 19.13 02/21 GEOTEXTILES FOR EARTHWORK
31 11 00 11/18 CLEARING AND GRUBBING
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19.61 11/19 SEALING OF JOINTS IN RIGID PAVEMENT
32 05 33 08/17 LANDSCAPE ESTABLISHMENT
32 11 20 08/17 BASE COURSE FOR RIGID AND SUBBASES FOR
FLEXIBLE PAVING
32 12 13 05/17 BITUMINOUS TACK AND PRIME COATS
32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING
32 13 13.06 05/20 PORTLAND CEMENT CONCRETE PAVEMENT FOR
ROADS AND SITE FACILITIES
32 15 00 05/17 AGGREGATE SURFACING
32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 08/16, CHG 5: 11/18 PAVEMENT MARKINGS
32 92 19 08/17, CHG 1: 08/21 SEEDING
DIVISION 33 - UTILITIES
33 11 00 02/18 WATER UTILITY DISTRIBUTION PIPING
33 30 00 05/18 SANITARY SEWERAGE
33 40 00 11/21 STORMWATER UTILITIES
33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT
41 22 13.14 11/19, CHG 1: 02/21 BRIDGE CRANES, OVERHEAD ELECTRIC, TOP
RUNNING
41 24 26 05/20, CHG 1: 11/20 HYDRAULIC POWER SYSTEMS
PROJECT TABLE OF CONTENTS Page 4
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 5
SECTION 01 33 29.00 06
SUSTAINABILITY REPORTING
11/17
Amendment 0004 22 March 2024
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING
ENGINEERS (ASHRAE)
ASHRAE 189.1 (2014; ERTA 1 2017) Standard for the Design of High-Performance Green Buildings Except Low-Rise Residential Buildings
SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION
(SMACNA)
ANSI/SMACNA 008 (2007) IAQ Guidelines for Occupied Buildings Under Construction, 2nd Edition
U.S. DEPARTMENT OF AGRICULTURE (USDA)
FSRIA 9002 Farm Security and Rural Investment Act Section 9002 (USDA Biopreferred Program)
U.S. DEPARTMENT OF ENERGY (DOE)
Energy Star (1992; R 2006) Energy Star Energy Efficiency Labeling System (FEMP)
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
SNAP (2016) EPA's Significant New Alternatives Policy Program
U.S. GREEN BUILDING COUNCIL (USGBC)
LEED v4 BDC Ref Guide (2013; R 2020) USGBC LEED Reference Guide for Building Design and Construction, v4
LEED v4.1 BDC Ref Guide (2023) LEED v4.1 Building Design and Construction Reference Guide
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
40 CFR 247 Comprehensive Procurement Guideline for Products Containing Recovered Materials
SECTION 01 33 29.00 06 Page 1 Certified Final Submittal-Amendment 0004
1.2 SUMMARY
This specification includes general requirements and procedures for this project to be constructed and documented per the federally mandated High Performance and Sustainable Building Guiding Principles (GP), LEED certification requirements, and other requirements identified in this specification.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following that "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with LRL Section 01 33 00 Submittal Procedures:
SD-01 Preconstruction Submittals
Sustainability Action Plan; G, AE
LEED Implementation Plan; G, AE
Indoor Air Quality Plan; G, AE
LEED AP BD+C; G, AE
SD-09 Manufacturer's Field Reports
Sustainability Progress Report; G, AE
SD-11 Closeout Submittals
Final Sustainability eNotebook; G, AE
Amended Final Sustainability eNotebook; G, AE
Final High Performance and Sustainable Building Checklist; G, AE
LEED Plaque and Certificate; G, AE
1.4 LEED Accredited Professional (LEED AP BD+C)
A LEED Accredited Professional with specialty in Building Design + Construction (LEED AP BD+C), accredited by the Green Building Certification Institute, on the Contractor's Quality Control Staff must assemble documentation and ensure that Guiding Principles Compliance documentation is prepared in accordance with this specification section and ensure that Third Party Certification requirements are achieved .
Identify the LEED AP BD+C on the Contractor's Quality Control Staff in accordance with specification LRL Section 01 45 04.10 06 CONTRACTOR QUALITY CONTROL. Provide a statement of qualifications of the LEED AP BD+C submitted to the Government with the QC Plan. Includes name and date of expiration of the current credential.
The LEED AP BD+C must review all requests for information, Contractor proposals, contract modifications, deviations from the design documents, or any other items that could potentially impact the compliance and Third Party Certification and rating of the project. Bring any actions that
SECTION 01 33 29.00 06 Page 2 could negatively impact the Third Party Certification rating or ability to comply with Guiding Principles to the attention of the Contracting Officer.
1.5 Guiding Principles Compliance
Provide construction related sustainability documentation to verify compliance with Federal High Performance and Sustainable Building requirements. Refer to paragraph Guiding Principle Requirements for requirements and associated documentation to include in the Sustainability eNotebook.
1.5.1 Construction Phase
1.5.1.1 Sustainability Action Plan
Provide a Sustainability Action Plan to demonstrate planned methods to comply with the Guiding Principles requirements and comply with Third Party Certification requirements identified herein. Submit the LEED Implementation Plan as a part of the Sustainability Action Plan. Provide 3 copies submitted to the Government on compact disk with the QC Plan . The Government will consider an interim Sustainability Action Plan and LEED Implementation Plan for the first 60 calendar days of the Contractor's operation. Construction will be permitted to begin only after acceptance of the plans or acceptance of an interim plan applicable to the work to be started related to the Guiding Principles requirements identified in the interim plan. Include a detailed description of all activities that relate to accomplishing each project Guiding Principle requirement, including construction practices and procurement practices. Include any plans required by the Guiding Principle Requirements including the Indoor Air Quality Plan and Waste Management Plan. Include a schedule for completion and documentation of each requirement. Include the template to be used for Sustainability Progress Reports, a plan for indoctrinating employees to sustainable goals and responsibilities, a team structure identifying responsibility for documentation, and a process for reviewing sustainability related submittals and documentation.
1.5.1.2 Sustainability eNotebook
Provide and maintain a comprehensive Sustainability eNotebook to document compliance with the Guiding Principles requirements identified herein.
All materials requirements must be updated each month. The Sustainability eNotebook must contain all required data to support compliance with the Guiding Principles requirements. The Sustainability eNotebook must be in the form of an Adobe PDF file; bookmarked at each requirement, and sub-bookmarked at each document. Include the Final High performance and Sustainable Building Checklist. Include all "S" submittals through the specification sections of this contract.
Provide 3 copies of the Final Sustainability eNotebook and Final High Performance and Sustainable Building Checklist to the Government on DVD 30 calendar days prior to the Contract Required Completion Date. Include a separate section in the Final Sustainability eNotebook with a copy of all Third Party Certification documentation, bookmarked at each separate requirement. Final progress payment retainage may be held by the Contracting Officer until the documentation is complete. Provide an Amended Final Sustainability eNotebook including any updates to documentation based on post-occupancy corrections or based on Third Party Certification requirements .
SECTION 01 33 29.00 06 Page 3
1.5.1.3 High Performance and Sustainable Building Checklist
Complete the Army Energy & Sustainability Record Card shown in Attachment A as required in paragraph Sustainability eNotebook. Obtain the electronic copy of the Army Energy & Sustainability Record Card from the Contracting Officer's Representative. Only the RECYCLED MATERIALS section of the Building Data Worksheet is required. If any deviations from contract result in a change in status to compliance with a listed requirement in the checklist, update the status of that item in the checklist.
1.5.1.4 Progress Report
Submit a monthly Sustainability Progress Report, on the same day each month, that identifies the Guiding Principles requirements completed and documented to date. The Sustainability Progress Report must also include the Third Party Certification requirements and documentation completed to date. The Government will compare the Sustainability Progress Report and the available data in the current Sustainability eNotebook and Third Party Certification documentation to the schedule in the Sustainability Action Plan and LEED Implementation Plan . Failure to adhere to the schedule for completion of requirements, including the associated documentation, in the Sustainability Action Plan and LEED Implementation Plan will be cause for withholding the monthly progress payment until the information is updated and in accordance with the Sustainability Action Plan.
1.6 Guiding Principles Requirements
Incorporate each of the following Guiding Principles requirements into the project construction, and provide documentation that proves compliance with each listed requirement. For each of the following paragraphs that require the use of products listed on Government-required websites, provide documentation of the process used to select products, or process used to determine why listed products do not meet project performance requirements.
1.6.1 Commissioning
Comply with the requirements of LRL section 01 46 00.00 06 TOTAL BUILDING
COMMISSIONING.
1.6.2 Energy Efficient Products
Provide only energy-using products that are Energy Star rated, or have the Federal Energy Management Program (FEMP) recommended efficiency for products with established Energy Star or FEMP requirements. Provide only energy using products that meet FEMP requirements for low standby power consumption. Energy efficient products can be found at:
https://energy.gov/eere/femp/federal-energy-management-program and https://www.energystar.gov/ . Provide the following documentation:
Proof that products are labeled energy efficient and comply with the cited requirements.
1.6.3 Indoor Water Use
Provide only water-consuming products that are EPA WaterSense labeled, or water fixtures available that meet the requirements of ASHRAE 189.1 Section 6.3.2, whichever is most water-efficient. Provide the following
SECTION 01 33 29.00 06 Page 4 documentation:
For products available with EPA WaterSense labeling, proof that fixtures are labeled EPA WaterSense or Energy Star ; for all other fixtures, proof they comply with the cited efficiency requirements.
1.6.4 Reduce Volatile Organic Compound (VOC) (Low Emitting Materials)
Meet the requirements of Table 3-1 at the end of this specification.
Provide the following documentation:
Provide certifications or labels that demonstrate compliance with cited requirements.
1.6.5 Indoor Air Quality During Construction
Prior to construction, create indoor air quality plan. Implement IAQ plan during construction and flush building air before occupancy.
For new construction and for renovation of unoccupied existing buildings, indoor air quality plan must meet the requirements of ANSI/SMACNA 008 , Chapter 3 and ASHRAE 189.1 Section 10.3.1.4, (Indoor Air Quality (IAQ) Construction Management), with maximum outdoor air consistent with achieving relative humidity no greater than 60 percent.
Provide documentation showing that after construction ends and prior to occupancy, HVAC filters were replaced and building air was flushed out in accordance with the cited standard.
1.6.6 Regional Materials
Comply with ASHRAE 189.1 paragraph 9.4.1.2 Regional Materials. Provide documentation demonstrating that 15% of the cost of building materials or products used were extracted, harvested, recovered or manufactured within 500 miles of the project site.
1.6.7 Recycled Content
Comply with 40 CFR 247 . Refer to https://www.epa.gov/smm/comprehensive-procurement-guidelines-construction-products for assistance identifying products cited in 40 CFR 247 . Selected products must comply with non-proprietary requirements of the Federal Acquisition Regulation, and must meet performance requirements. Provide the following documentation:
a. Manufacturers’ documents stating the recycled content by material, or written justification for claiming one of the exceptions allowed on the cited website.
b. Substitutions: Submit for Government approval, proposed alternative products or systems that provide equivalent performance and appearance and have greater contribution to project recycled content requirements. For all such proposed substitutions, submit with the Sustainability Action Plan accompanied by product data demonstrating equivalence.
1.6.8 Bio-Based Products
Provide products and material composed of the highest percentage of
SECTION 01 33 29.00 06 Page 5 biobased materials (including rapidly renewable resources and certified sustainably harvested products), consistent with FSRIA 9002 USDA Biopreferred Program, to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the end user. Use only supplies and materials of a type and quality that conform to applicable specifications and standards.
Comply with FSRIA 9002 USDA BioPreferred Program. Refer to https://www.biopreferred.gov/BioPreferred/ for the product categories and BioPreferred Catalog. Selected products must comply with non-proprietary requirements of the Federal Acquisition Regulation, and must meet performance requirements. Provide the following documentation:
USDA Biopreferred label for each product; for bio-based products used on project but not listed with Biopreferred program, provide bio-based content and percentage.
1.6.9 Ozone Depleting Substances
Meet the requirements of ASHRAE 189.1 Section 9.3.3 Refrigerants for no CFC-based refrigerants in heating ventilation, air conditioning and refrigeration systems. Where feasible, use products from U.S. EPA Significant New Alternatives Policy (SNAP) ( https://www.epa.gov/snap ) or meet the criteria of SNAP. Provide the following documentation:
a. MSDS sheets for all refrigerants.
b. Provide label for each product meeting the cited standards.
1.6.10 Waste Material Management (Recycling – Construction)
A minimum of 75% of nonhazardous construction and demolition waste material generated prior to the issuance of the final certificate of occupancy shall be diverted from disposal in landfills and incinerators by recycling or reuse. Reuse includes donation of materials to charitable organization, salvage of existing materials onsite, and packaging materials returned to the manufacturer, shipper, or other source that will reuse the packaging in future shipments. Excavated soil and land clearing debris shall not be included in the calculation. Calculations are allowed to be done by either weight or volume, but shall be consistent throughout. Specific areas on the construction site shall be designated for collection of recyclable and reusable materials. Off-site storage and sorting of materials shall be allowed. Diversion efforts shall be tracked by the contractor throughout the construction process and documentation provided to the Government prior to contract closeout. Refer to LEED v4 MR Construction and Demolition Waste Management Planning prerequisite and MR Construction and Demolition Waste Management credit for addiitonal requirments.
1.7 Third Party Certification
Comply with all requirements and provide all required documentation for the project to achieve certification in the Third Party Certification system identified herein. The Contractor must bear all costs and perform all administrative actions necessary to complete Third Party Certification.
1.7.1 LEED
This project has been designed for a rating of Silver in the Leadership in
SECTION 01 33 29.00 06 Page 6
Energy and Environmental Design (LEED) version 4 certification system.
Certify the project at the designed LEED rating through the Green Building Certification Institute. The project has been registered with the Green Building Certification Institute. The Final Design Review of the Split Design & Construction Review path has been completed. Complete all remaining activities necessary for LEED certification.
Some LEED prerequisites and credits are similar to Guiding Principle Requirements. Some LEED credits are are substituted with LEED v4.1 requirements in lieu of LEED v4 requirements. Comply with both the LEED and Guiding Principle Requirements. Refer to LEED v4 BDC Ref Guide and LEED v4.1 BDC Ref Guide for additional information regarding LEED and LEED certification processes.
1.7.2 LEED Documentation
LEED documentation requires the following:
a. Refer to Attachment B, LEED Checklist at the end of this specification section.
b. Obtain approval of the LEED Checklist from the Contracting Officer at the Sustainability Implementation Meeting.
No variations or substitutions to the approved LEED Checklist are allowed without written consent from the Contracting Officer.
Immediately bring to the attention of the Contracting Officer any project changes that impact meeting the approved LEED Requirements for this project. Demonstrate that change will not: incur additional construction cost; increase the life cycle cost; impact previous LEED Design Review; or impact required LEED certification level.
c. Complete all work required to incorporate the applicable LEED Requirements.
d. Maintain the construction related information, and provide replacement pages, in the Sustainability eNotebook pertaining to additions and changes to the approved sustainability requirements. The Sustainability eNotebook is in electronic format and is explained in the paragraph entitled "SUSTAINABILITY eNOTEBOOK". The Sustainability eNotebook contains the following components in addition to the GPV components above:
(1) LEED Checklist
(2) Completed LEED Online forms for each identified prerequisite and credit
(3) Copy of all correspondence with the LEED organization.
(4) Documentation illustrating compliance with LEED requirements.
(5) LEED Award Certificate and Plaque.
e. LEED Implementation Plan: Include the following information in the Sustainability Action Plan. Provide this LEED information in addition to the GPV Action Plan items above:
(1) Contractor's planned method to achieve each LEED requirement.
SECTION 01 33 29.00 06 Page 7
(2) For each required LEED credit that is attempted but not achieved, provide narrative explaining how mission or activity precludes achieving specific sustainability requirement or goal. Provide analysis of particular requirement and level to which project is able to comply.
(3) Name and contact information for: Contractor's Sustainability POC and other names of sustainability professionals on the Contractor's Staff responsible for ensuring LEED sustainability goals are accomplished and documentation is assembled and who requires access to the LEED online website.
(4) Provide the plan and schedule for performance testing, data collection, and commissioning to take place during first year of facility usage.
(5) Prepare and submit detailed work plans directly related to achieving LEED construction phase prerequisites and credits. Note that some of the following plans must be uploaded to LEED Online as supporting documents to specific credits, and others are intended to demonstrate the Contractor's understanding of LEED data collection, early planning and communication with relevant parties. Such planning and execution is required for LEED credit achievement. The list of work plans shall include the following:
f. Contractor is responsible for all costs associated with constructing and demonstrating that project complies with approved LEED requirements, including but not limited to:
(1) Final LEED review, certification and plaque fees
(2) Online LEED management and documentation.
(3) Obtaining LEED certification based on Government-approved sustainability goals.
(4) Construction work required to incorporate LEED prerequisites and credits.
(5) Submittals required to demonstrate compliance with Government approved LEED checklists.
g. Provide all calculations, product data, and certifications required in this specification to demonstrate compliance with the LEED Requirements.
h. Provide all online LEED management and documentation.
i. Contractor is responsible for all required responses to USGBC/GBCI.
j. Provide LEED Plaque and Certificates. Use format below to create the Plaque, Certificate and Letter of Congratulations. Forward to parties designated by Contracting Officer:
(1) Plaque:
Name: Final Building Name. If unknown, provide Form DD1391 Project Name.
SECTION 01 33 29.00 06 Page 8
(2) Certificate:
Project Title, first line: P-(X); Form DD1391 Project Name).
Project Title, second line: UIC (Installation code)
(3) Letter Congratulations:
Address letter to Facility's Installation commander Name. Address the letter to an individual person.
1.7.3 LEED Documentation Requirements
LEED v4 and v4.1 credits as identified in Attachment B shall be incorporated and documented as required by the Contract documents and in full compliance with the LEED v4 BDC Ref Guide or the LEED v4.1 BDC Ref Guide . LEED v4 and LEED v4.1 credits not identified elsewhere in the Contract documents and those requiring further instruction are specified below. Refer to the LEED v4 BDC Ref Guide and the LEED v4.1 BDC Ref Guide for further definitions and requirements.
1.7.3.1 MR Construction and Demolition Waste Management
Contractor shall employ construction waste management practices as required in the LEED v4 BDC Ref Guide Option 1 - Diversion,Path 2 - Divert 75% and Four Material Streams, and in 01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT to achieve the threshold stated therein.
1.7.3.1.1 Calculations for MR Construction Waste Management
Contractor shall track all construction and demolition waste and diverted waste using the LEED Online Construction and Demoltion Waste Calculator.
1.7.3.2 MR Building Product Disclosure and Optimization - Environmental Product Declarations
1.7.3.2.1 Option 1 Environmental Product Declaration
Contractor shall select materials so that the sum of installed products with Environmental Product Declarations (EPD) is at least 20 different products from at least five different manufacturers. EPDs shall comply with the requirements in the LEED v4.1 BDC Ref Guide.
1.7.3.2.2 Option 2 Embodied Carbon/LCA Optimization
Contractor shall select at least 5 permanently installed products sourced from at least three different manufacturers that have an embodied carbon optimization report or action plan in compliance with the LEED v4.1 BDC Ref Guide .
1.7.3.3 MR Building Product Disclosure and Optimization - Sourcing of Raw Materials
Amdt. #0004******************************************************************
Contractor shall select materials so that the sum of the following constitutes at least one of the responsible sourcing and extraction criteria for at least 30 percent by cost, of the total value of permanently installed building prodducts in compliance with the
SECTION 01 33 29.00 06 Page 9
LEED v4.1 BDC Ref Guide .
a. Extended producer responsibility: Products meeting extended producer responsibility criteria are valued at 50 percent of their cost for purposes of credit achievement calculation.
b. Bio-based materials: Products that meet bio-based product criteria are valued at 50 percnet of the cost multiplied by the biobased content of the product for purposes of credit achievement calculation.
c. Certified wood products: Products that meet certified wood products criteria are valued at 100 percent of their cost for purposes of the credit achievment calculation.
d. Materials reuse: Products meeting materials reuse criteria are valued at 200 percent of their cost for the purposes of credit achievement calculation.
e. Recycled content: Products that meet recycled content criteria are valued at 100 percent of their cost for purposes of credit achievement calculation.
f. For credit achievement, products meeting any of the above criteria that are sourced (extracted, manufactured and purchased)within 100 miles of the project site are valued at twice their base contributing cost, up to a maximum of 200 percent of cost.
1.7.3.4 MR Building Product Disclosure and Optimization - Material Ingredients
1.7.3.4.1 Option 1 Material Ingredient Reporting
Contractor shall select materials so that the sum of installed products demonstrating a chemical inventory of the product to at least 0.1 percent is at least 20 different products from at least five different manufacturers. Material Ingredient Reporting programs shall comply with the requirements in the LEED v4.1 BDC Ref Guide .
a. ANSI/BIFMA e3 Furniture Sustainability Standard
b. Cradle to Cradle
c. Declare
d. Facts – NSF/ANSI 336
e. Global Green TAG
f. Health Product Declaration
g. Living Product Challenge
h. Manufacturer Inventory
i. Product Lens Certification
j. Any compliant reports above with third-party verification that includes the verification of content inventory are worth 1.5 products for credit achievement calculations.
1.7.3.4.2 Option 2 Material Ingredient Optimization
Contractor shall select products that have a compliant material ingredient optimization report or action plan. Use at least 5 permanently installed products sourced from at least three different manufacturers. Products are valued according to the Option 2 Material Ingredient Optimization table in the LEED v4.1 BDC Ref Guide .
For credit achievement calculation, products sourced (extracted,manufactured, purchased) within 100 miles of the project site are valued at twice their base contributing number of products, up to a maximum of 2 products.
SECTION 01 33 29.00 06 Page 10
1.7.3.5 Low-Emitting Materials
Contractor shall select materials used on the interior of the building that comply with the low-emitting requirements in the LEED v4.1 BDC Ref Guide for the following categories:
a. Paints and coatings: At least 75 percent of all paints and coatings, by volume or surface area, meet the VOC emissions evaluation and 100 percent meet the VOC content evaluation.
b. Adhesives and sealants: At least 75 percent of all adhesives and sealants, by volume or surface area, meet the VOC emissions evaluation and 100 percent meet the VOC content evaluation.
c. Flooring: At least 90 percent of all flooring, by cost or surface area, meets the VOC emissions evaluation or inherently nonemitting sources criteria, or salvaged and reused materials criteria.
d. Wall panels: At least 75 percent of all wall panels, by cost or surface area, meet the VOC emissions evaluation, or inherently nonemitting sources criteria, OR salvaged and reused materials criteria.
e. Ceilings: At least 90 percent of all ceilings, by cost or surface area, meet the VOC emissions evaluation, or inherently nonemitting sources criteria, or salvaged and reused materials criteria.
f. Insulation: At least 75 percent of all insulation, by cost or surface area, meets the VOC emissions evaluation.
g. Furniture: At least 75 percent of all furniture in the project scope of work, by cost, meets the furniture emissions evaluation, or inherently nonemitting sources criteria, OR salvaged and reused materials criteria.
h. Composite wood: At least 75 percent of all composite wood, by cost or surface area, meets the Formaldehyde emissions evaluation OR salvaged and reused materials criteria.
1.7.3.6 Construction Indoor Air Quality Management Plan
Comply with the requirements of sub-section 1.6.5 Indoor Air Quality During Construction for indoor air quality plan requirements.
Additionally, indoor air quality plan shall address the following:
a. Protect all absorptive materials that are stored onsite and installed from moisture damage.
b. Install minimum efficiency MERV 8 filters at each return air grille and return or transfer duct inlet opening prior to operating permanently installed air-handling equipment during construction and replace filtration media with specified filtration media prior to occupancy.
c. Prohibit smoking inside the building and within 50 feet of all building openings during construction.
d. Conduct building flush-out or baseline air testing per sub-section
1.7.3.7 Indoor Air Quality Assessment.
1.7.3.7 Indoor Air Quality Assessment
1.7.3.7.1 Option 2 Air Testing
After substantial completion and prior to occupancy, conduct baseline indoor air quality testing in occupied spaces using protocols consistent with the methods listed in Table 1 of the LEED v4 BDC Ref Guide .
******************************************************************Amdt. #0004
SECTION 01 33 29.00 06 Page 11
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION
SECTION 01 33 29.00 06 Page 12
3.1 SUSTAINABILITY IMPLEMENTATION MEETING
The LEED AP BD+C , QC System Manager, and Contracting Officer's Representative must meet within 60 calendar days after notice to proceed to review project sustainability goals with respect to the Sustainability Action Plan and LEED Implementation Plan , identify potential difficulties related to meeting the Guiding Principle Requirements, and discuss mitigation strategies.
3.2 Sustainability Pre-Closeout Meeting
The LEED AP BD+C , QC System Manager, and Contracting Officer's Representative must meet 60 calendars days prior to Contract Required Completion Date to review completion status of sustainability requirements including level of completion of Third Party Certification, Guiding Principles Requirements documentation and the High Performance and Sustainable Building Checklist. Discuss any potential difficulties in completing Third Party Certification, outstanding requirements and documentation. Provide a copy of the Sustainability eNotebook with up-to-date documentation.
LEED Plaque and Certificate
Finalize the process requirements and obtain the LEED Plaque and Certificate, and compliance report, indicating completion of the project's sustainability goals. Include LEED compliance report with final LEED scoresheet as applicable.
Provide one original framed copy of the certificate, assessment, or validation, mounted in 1 inch deep metal frames, with double matt, and wire hangers, in location approved by Contracting Officer. Deliver one original certificate and compliance report to Contractor Officer, unless otherwise instructed. Provide and hang Plaque in a prominent interior location approved by the Contracting Officer.
3.3 TABLE 3-1 VOLATILE ORGANIC COMPOUNDS (VOC) (LOW EMITTING MATERIALS)
REQUIREMENTS
Refer to following table, based on ASHRAE 189.1 section 8.4.2 (Materials), for compliance criteria.
SECTION 01 33 29.00 06 Page 13
TABLE 3-1 Volatile Organic Compounds (VOC) (Low Emitting Materials) Requirements
MATERIAL CATEGORY EMISSIONS
REQUIREMENT
MATERIALS WITH
ADDED VOC
REQUIREMENT
MATERIAL CATEGORY
Adhesives and Sealants
CDPH/EHLB/Standard method V1.1 (California Section 01350) (Use "office" or "classroom" space limits for all applications) or Adhesives (carpet, resilient, wood flooring; panel;
primers) Sealants (acoustical;
firestop; HVAC Air duct; primers) Caulks
SCAQMD Rule 1168 (Use "other" category for HVAC duct sealant) (for firestop adhesive, UFC 3-600-01 overrides conflicting requirements)
Aerosol adhesives Section 3 of Green Seal Standard
GS-36
(except:
cleaners, solvent cements, and primers used with plastic piping and conduit in plumbing, fire suppression, and electrical systems; HVAC air duct sealants when the application space air temp is less than 40 F (4.5 C).
Paints and Coatings CDPH/EHLB/Standard method V1.1 (Ca lifornia Section 01350) (Use "office" or "classroom" space limits for all applications) or Flat and nonflat topcoats, primers, undercoaters, and anti-corrosive coatings
Green Seal Standard GS-11
SECTION 01 33 29.00 06 Page 14
TABLE 3-1 Volatile Organic Compounds (VOC) (Low Emitting Materials) Requirements
MATERIAL CATEGORY EMISSIONS
REQUIREMENT
MATERIALS WITH
ADDED VOC
REQUIREMENT
MATERIAL CATEGORY
Paints and Coatings CDPH/EHLB/Standard method V1.1 (California Section 01350) (Use "office" or "classroom" space limits for all applications) or Concrete/masonry sealers (waterproofing concrete/masonry sealers), concrete curing compounds, dry fog coatings, faux finishing coatings, fire resistive coatings, floor coatings, graphic arts (sign) coatings, industrial maintenance coatings, mastic texture coatings, metallic pigmented coatings, multicolor coatings, pretreatment wash primers, reactive penetrating sealers, recycled coatings, shellacs (clear and opaque), specialty primers, stains, wood coatings (clear wood finishes), wood preservatives, and zinc primers
California Air Resources Board (CARB) Suggested Control Measure for Architectural Coatings or SCAQMD Rule 1113
SECTION 01 33 29.00 06 Page 15
TABLE 3-1 Volatile Organic Compounds (VOC) (Low Emitting Materials) Requirements
MATERIAL CATEGORY EMISSIONS
REQUIREMENT
MATERIALS WITH
ADDED VOC
REQUIREMENT
MATERIAL CATEGORY
Paints and Coatings CDPH/EHLB/Standard method V1.1 (California Section 01350) (Use "office" or "classroom" space limits for all applications) or Basement specialty coatings, high-temperature coatings, low solids coatings, stone consolidants, swimming-pool coatings, tub- and tile-refining coatings, and waterproofing membranes
California Air Resources Board (CARB) Suggested Control Measure for Architectural Coatings
Floor Covering Materials
For carpet, all locations:
CDPH/EHLB/Standard Method V1.1 ( California Section 01350) or label for Section 9 of CDPH/EHLB/Standard Method V1.1 (Cali fornia Section 01350) none none
SECTION 01 33 29.00 06 Page 16
TABLE 3-1 Volatile Organic Compounds (VOC) (Low Emitting Materials) Requirements
MATERIAL CATEGORY EMISSIONS
REQUIREMENT
MATERIALS WITH
ADDED VOC
REQUIREMENT
MATERIAL CATEGORY
Composite Wood, Wood Structural Panel, and Agrifib er Products particleboard medium density fiberboard (MDF) wheatboard strawboard panel substrates door cores no added urea-formaldehyde resins including laminating adhesives for composite wood and agrifiber assemblies
Third-party certification (approved by CARB) of California Air Resource Board's (CARB) regulation , Airborne Toxic Control Measure to Reduce Formaldehyde Emissions from Composite Wood Products none none
CDPH/EHLB/Standard method V1.1 (Ca lifornia Section 01350) (Use "office" or "classroom" space limits for all applications) (except: Structural panel components such as plywood, particle board, wafer board, and oriented strand board identified as
"EXPOSURE 1,"
"EXTERIOR," or "HUD-APPROVED" are considered acceptable for interior use.)
SECTION 01 33 29.00 06 Page 17
TABLE 3-1 Volatile Organic Compounds (VOC) (Low Emitting Materials) Requirements
MATERIAL CATEGORY EMISSIONS
REQUIREMENT
MATERIALS WITH
ADDED VOC
REQUIREMENT
MATERIAL CATEGORY
Office Furniture Systems and Seating installed prior to occupancy
ANSI/BIFMA X7.1
ANSI/BIFMA X7.1:
(95 percent of installed office furniture system workstations and seating units)
Section 7.6.2 of ANSI/BIFMA e3 (50 percent of office furniture system workstations and seating units) none none
Ceiling and Wall Systems ceiling and wall insulation acoustical ceiling panels tackable wall panels gypsum wall board and panels wall coverings
CDPH/EHLB/Standard method V1.1 (Ca lifornia Section 01350) (Use "office" or "classroom" space limits for all applications) none none
SECTION 01 33 29.00 06 Page 18
SECTION 01 33 29.00 06 Page 19
Attachment A
HIGH PERFORMANCE AND SUSTAINABLE BUILDING CHECKLIST
SECTION 01 33 29.00 06 Page 20
Attachment B
LEED PROJECT CHECKLIST
-- End of Section --
SECTION 01 33 29.00 06 Page 21
SECTION 07 11 13
BITUMINOUS DAMPPROOFING
08/11, CHG 1: 05/17
Amendment 0004 22 March 2024
Amdt. #0004******************************************************************
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM C208 (2012; R 2017; E 2017; E 2019) Standard Specification for Cellulosic Fiber Insulating Board
ASTM C728 (2017; R 2022) Standard Specification for Perlite Thermal Insulation Board
ASTM D1187/D1187M (1997; E 2011; R 2011) Asphalt-Base Emulsions for Use as Protective Coatings for Metal
ASTM D1227 (2013) Emulsified Asphalt Used as a Protective Coating for Roofing
ASTM D4263 (1983; R 2018) Standard Test Method for Indicating Moisture in Concrete by the Plastic Sheet Method
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-07 Certificates
Materials
1.3 DELIVERY AND STORAGE
Deliver materials in sealed containers bearing…