W912QR24R0008_Specs-0004.pdf

PDF 1 MB Posted

Attached to
Ground Transport Equipment Building (GTEB) at Detroit Arsenal, MI
Solicitation number
W912QR24R0008
Issued by

About this file

This document is an amendment to Solicitation W912QR24R0008 for the construction of a new Ground Transport Equipment Building (GTEB) for the Ground Vehicle Systems Center at the Detroit Arsenal (DTA) in Warren, MI. The solicitation is a single-phase, Design/Bid/Build, 100% Full and Open (Unrestricted) procurement with an estimated construction cost between $25,000,000 and $100,000,000. The amendment includes the following key details:

The solicitation is modified to add several new specification sections, replace existing sections, and revise multiple drawings. The submission date for proposals is extended from April 5, 2024 to April 10, 2024 at 2:00 pm ET. The amendment provides a list of the specification sections and drawings that have been added, replaced, or revised. This includes sections related to bituminous dampproofing, exterior signage, cybersecurity for fire and mass notification control systems, and bridge cranes among others. The project is targeting a LEED Silver certification, and the amendment provides additional details on the LEED and sustainability requirements for the project.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Solicitation W912QR24R0008 for the Construction of a new Ground Transport Equipment Building (GTEB) for the Ground Vehicle Systems Center at Detroit Arsenal (DTA), located in Warren, MI is hereby modif ied as follows:

SEE CONTINUATION PAGE

1. CONTRACT ID CODE PAGE OF PAGES

1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912QR24R0008

X 9B. DATED (SEE ITEM 11)

11-Jan-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

29-Mar-2024

CODE

U. S. ARMY ENGINEER DISTRICT, LOUISVILLE

600 DR. MARTIN LUTHER KING, JR. PLACE

ROOM 821

LOUISVILLE KY 40202-2239

W912QR 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912QR24R0008_Specs-0004

W912QR24R0008

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0004

Solicitation W912QR24R0008 for the Construction of a new Ground Transport Equipment Building (GTEB) for the Ground Vehicle Systems Center at Detroit Arsenal (DTA), located in Warren, MI is hereby modified as follows:

a. The following Specification sections have been ADDED to the package:

07 11 13 BITUMINOUS DAMPPROOFING

10 14 00.10 EXTERIOR SIGNAGE

b. The following Specification sections have been replaced in their entirety:

01 33 29.00 06 SUSTAINABILITY REPORTING

25 05 11.02 CYBERSECURITY FOR FIRE & MASS NOTIFICATION CONTROL SYSTEMS

27 11 16 COMMUNICATIONS RACKS, FRAMES AND ENCLOSURES

28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM, ADDRESSABLE

41 22 13.14 BRIDGE CRANES, OVERHEAD ELECTRIC, TOP RUNNING

c. The following Drawings have been replaced in their entirety:

Drawing No. Drawing Name

C-002 GENERAL NOTES AND ABBREVIATIONS

C-109 HAUL ROUTE

G-002 SHEET INDEX

G-003 SHEET INDEX

S-001 GENERAL STRUCTURAL NOTES

S-005 GENERAL STRUCTURAL NOTES

S-400 TEST PIT FOUNDATION PLAN AND SECTIONS

A-401 ENLARGED PLANS AND ELEVATIONS

A-402 ENLARGED PLANS AND ELEVATIONS

A-403 ENLARGED PLANS AND ELEVATIONS

I-111 FIRST FLOOR FINISH PLAN - SECTOR 1

I-112 FIRST FLOOR FINISH PLAN - SECTOR 2

I-113 FIRST FLOOR FINISH PLAN - SECTOR 3

I-403 INTERIOR ELEVATIONS

FA111 FIRE ALARM PLAN – SECTOR 1

FA601 FIRE ALARM AND MNS RISER DIAGRAM

M-601 MECHANICAL SCHEDULES

E-602 MSWBDA AND MSWBDB ELECTRICAL ONE-LINE

E-610 PANEL SCHEDULES

W912QR24R0008

T-100 TELECOMMUNICATIONS SITE PLAN

T-101 TELECOMMUNICATIONS ENLARGED SITE PLAN

d. The submission date is hereby extended to 10 April 2024 at 2:00 pm ET. Acknowledgment of receipt of this amendment and proposals are due at that time.

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 05-Apr-2024 02:00 PM to 10-Apr-2024 02:00 PM.

(End of Summary of Changes)

P2#: 500060 - Ground Transportation Equipment Building Detroit Arsenal, MI

PROJECT TABLE OF CONTENTS

Amendment 0004 22 March 2024

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 80 00.00 06 04/21 SPECIAL PROVISIONS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 08/15, CHG 2: 08/21 SUMMARY OF WORK

01 32 01.00 06 07/18 PROJECT SCHEDULE

01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES

01 33 29.00 06 11/17 SUSTAINABILITY REPORTING

01 35 26.00 06 GOVERNMENT SAFETY REQUIREMENTS

01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.15 10 11/16, CHG 2: 08/19 RESIDENT MANAGEMENT SYSTEM CONTRACTOR

MODE (RMS CM)

01 45 04.10 06 CONTRACTOR QUALITY CONTROL

01 45 35 11/20 SPECIAL INSPECTIONS

01 46 00.00 06 04/20 TOTAL BUILDING COMMISSIONING

01 50 00 11/20, CHG 1: 08/21 TEMPORARY CONSTRUCTION FACILITIES AND

CONTROLS

01 57 19.00 06 04/20 TEMPORARY ENVIRONMENTAL CONTROLS AND

PERMITS

01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND

DISPOSAL

01 78 23 08/15, CHG 2: 08/21 OPERATION AND MAINTENANCE DATA

DIVISION 02 - EXISTING CONDITIONS

02 41 00 05/10, CHG 2: 02/19 DEMOLITION

DIVISION 03 - CONCRETE

03 30 00 02/19, CHG 3: 11/21 CAST-IN-PLACE CONCRETE

03 45 00 05/16, CHG 2: 11/21 PRECAST ARCHITECTURAL CONCRETE

DIVISION 04 - MASONRY

04 20 00 11/15, CHG 2: 05/19 UNIT MASONRY

DIVISION 05 - METALS

05 05 20.00 27 02/21 POST-INSTALLED CONCRETE AND MASONRY

ANCHORS

05 05 23.13 10 08/18 ULTRASONIC INSPECTION OF WELDMENTS

05 05 23.16 08/18 STRUCTURAL WELDING

05 12 00 08/18, CHG 2: 05/21 STRUCTURAL STEEL

05 30 00 05/15, CHG 2: 08/18 STEEL DECKS

05 40 00 05/15, CHG 1: 08/18 COLD-FORMED METAL FRAMING

05 50 13 05/17, CHG 1: 08/18 MISCELLANEOUS METAL FABRICATIONS

05 51 33 02/16, CHG 2: 02/18 METAL LADDERS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 08/16, CHG 2: 11/18 ROUGH CARPENTRY

06 41 16.00 10 08/10, CHG 1: 11/18 PLASTIC-LAMINATE-CLAD ARCHITECTURAL

CABINETS

06 61 16 08/20 SOLID SURFACING FABRICATIONS

PROJECT TABLE OF CONTENTS Page 1 Certified Final Submittal-Addendum 0004

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 05 23 08/19 PRESSURE TESTING AN AIR BARRIER SYSTEM

FOR AIR TIGHTNESS

07 11 13 08/11, CHG 1: 05/17 BITUMINOUS DAMPPROOFING

07 13 53 02/16, CHG 1: 08/17 ELASTOMERIC SHEET WATERPROOFING

07 21 13 02/16, CHG 2: 08/20 BOARD AND BLOCK INSULATION

07 22 00 02/16, CHG 3: 11/18 ROOF AND DECK INSULATION

07 27 10.00 10 08/19, CHG 1: 02/20 BUILDING AIR BARRIER SYSTEM

07 42 13 05/11, CHG 2: 02/18 METAL WALL PANELS

07 54 19 THERMOPLASTIC POLYOLEFIN (TPO) ROOFING

07 60 00 05/17, CHG 2: 11/18 FLASHING AND SHEET METAL

07 81 00 02/11 SPRAY-APPLIED FIREPROOFING

07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING

07 92 00 08/16, CHG 3: 11/18 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 08/20 STEEL DOORS AND FRAMES

08 14 00 08/16, CHG 1: 08/18 WOOD DOORS

08 31 00 05/17, CHG 1: 08/18 ACCESS DOORS AND PANELS

08 33 23 08/20 OVERHEAD COILING DOORS

08 34 73 11/19, CHG 1: 02/21 SOUND CONTROL DOOR ASSEMBLIES

08 41 13 08/18, CHG 1: 08/18 ALUMINUM-FRAMED ENTRANCES AND

STOREFRONTS

08 60 45 08/20 TRANSLUCENT PANELS

08 71 00 02/16, CHG 3: 08/20 DOOR HARDWARE

08 81 00 05/19 GLAZING

08 91 00 08/20 METAL WALL LOUVERS

DIVISION 09 - FINISHES

09 22 00 02/10, CHG 2: 08/18 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 29 00 08/16, CHG 4: 02/20 GYPSUM BOARD

09 30 10 08/20 CERAMIC, QUARRY, AND GLASS TILING

09 51 00 08/20 ACOUSTICAL CEILINGS

09 65 00 08/10, CHG 3: 08/18 RESILIENT FLOORING

09 67 23.15 02/21 FUEL RESISTIVE RESINOUS FLOORING,

3-COAT SYSTEM

09 68 00 11/17, CHG 2: 08/20 CARPETING

09 84 20 08/16, CHG 1: 08/18 ACOUSTICAL WALL PANELS

09 90 00 02/21 PAINTS AND COATINGS

DIVISION 10 - SPECIALTIES

10 11 00 08/20 VISUAL DISPLAY UNITS

10 14 00.10 08/17, CHG 1: 11/18 EXTERIOR SIGNAGE

10 14 00.20 08/20 INTERIOR SIGNAGE

10 21 13 08/20 TOILET COMPARTMENTS

10 26 00 08/20 WALL AND DOOR PROTECTION

10 28 13 08/20 TOILET ACCESSORIES

10 44 16 11/19 FIRE EXTINGUISHERS

10 51 13 05/11 METAL LOCKERS

DIVISION 12 - FURNISHINGS

12 24 13 08/20 ROLLER WINDOW SHADES

12 50 00.13 10 08/17, CHG 1: 11/18 FURNITURE AND FURNITURE INSTALLATION

12 59 00 08/17, CHG 1: 08/18 SYSTEMS FURNITURE

PROJECT TABLE OF CONTENTS Page 2 Certified Final Submittal-Addendum 0004

*********************************************************************************Amdt. #0004

Amdt. #0004*********************************************************************************

Amdt. #0004*******************************************************************************

*******************************************************************************Amdt. #0004

DIVISION 21 - FIRE SUPPRESSION

21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE

PROTECTION

21 30 00 04/08, CHG 1: 08/13 FIRE PUMPS

DIVISION 22 - PLUMBING

22 00 00 11/15, CHG 4: 05/21 PLUMBING, GENERAL PURPOSE

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 05 15 02/14 COMMON PIPING FOR HVAC

23 05 93.00 06 08/16 TESTING, ADJUSTING, AND BALANCING

(TAB) OF HVAC

23 07 00 02/13, CHG 7: 05/20 THERMAL INSULATION FOR MECHANICAL

SYSTEMS

23 08 00.00 20 02/21, CHG 1: 05/21 COMMISSIONING OF MECHANICAL AND

PLUMBING SYSTEMS

23 09 00 02/19, CHG 3: 05/21 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 11/15, CHG 2: 05/21 INSTRUMENTATION AND CONTROL DEVICES

FOR HVAC

23 09 23.02 02/19, CHG 1: 02/20 BACNET DIRECT DIGITAL CONTROL FOR HVAC

AND OTHER BUILDING CONTROL SYSTEMS

23 11 20 05/20 FACILITY GAS PIPING

23 21 23 08/17 HYDRONIC PUMPS

23 23 00 08/21 REFRIGERANT PIPING

23 30 00 05/20 HVAC AIR DISTRIBUTION

23 52 00 04/08, CHG 5: 11/19 HEATING BOILERS

23 64 10 11/16, CHG 2: 08/18 WATER CHILLERS, VAPOR COMPRESSION TYPE

23 64 26 08/09, CHG 5: 11/19 CHILLED AND CONDENSER WATER PIPING

SYSTEMS

23 65 00 11/16, CHG 2: 08/18 COOLING TOWERS

23 81 00 05/18, CHG 1: 02/21 DECENTRALIZED UNITARY HVAC EQUIPMENT

23 81 23 11/20 COMPUTER ROOM AIR CONDITIONING UNITS

DIVISION 25 - INTEGRATED AUTOMATION

25 05 11.01 05/21 CYBERSECURITY FOR FACILITY-RELATED

CONTROL SYSTEMS

25 05 11.02 05/21 CYBERSECURITY FOR FIRE & MASS

NOTIFICATION CONTROL SYSTEMS

25 05 11.03 05/21 CYBERSECURITY FOR FACILITY-RELATED

CONTROL SYSTEMS

25 08 10 05/21 UTILITY MONITORING AND CONTROL SYSTEM

TESTING

25 10 10 02/19, CHG 1: 05/21 UTILITY MONITORING AND CONTROL SYSTEM

(UMCS) FRONT END AND INTEGRATION

DIVISION 26 - ELECTRICAL

26 08 00 11/21 APPARATUS INSPECTION AND TESTING

26 12 19.10 05/19, CHG 1: 11/19 THREE-PHASE, LIQUID-FILLED PAD-MOUNTED

TRANSFORMERS

26 13 00 05/21 SF6/HIGH-FIREPOINT FLUIDS INSULATED

PAD-MOUNTED SWITCHGEAR

26 20 00 08/19, CHG 3: 11/21 INTERIOR DISTRIBUTION SYSTEM

26 24 13 08/21 SWITCHBOARDS

PROJECT TABLE OF CONTENTS Page 3

26 28 01.00 10 08/21 COORDINATED POWER SYSTEM PROTECTION

26 29 23 02/20, CHG 1: 05/21 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS

UNDER 600 VOLTS

26 41 00 11/13 LIGHTNING PROTECTION SYSTEM

26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING

26 56 00 08/21 EXTERIOR LIGHTING

DIVISION 27 - COMMUNICATIONS

27 05 28.36 40 05/17 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING

SYSTEM

27 11 16 11/14 COMMUNICATIONS RACKS, FRAMES AND

ENCLOSURES

27 13 13 11/14 COMMUNICATIONS COPPER BACKBONE CABLING

27 13 23.00 40 11/14 COMMUNICATIONS OPTICAL BACKBONE CABLING

27 15 13 11/14 COMMUNICATIONS COPPER HORIZONTAL

CABLING

27 41 00 11/21 AUDIO-VISUAL SYSTEMS

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 31 76 08/20 INTERIOR FIRE ALARM AND MASS

NOTIFICATION SYSTEM, ADDRESSABLE

DIVISION 31 - EARTHWORK

31 00 00.00 06 07/18 EARTHWORK

31 05 19.13 02/21 GEOTEXTILES FOR EARTHWORK

31 11 00 11/18 CLEARING AND GRUBBING

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 01 19.61 11/19 SEALING OF JOINTS IN RIGID PAVEMENT

32 05 33 08/17 LANDSCAPE ESTABLISHMENT

32 11 20 08/17 BASE COURSE FOR RIGID AND SUBBASES FOR

FLEXIBLE PAVING

32 12 13 05/17 BITUMINOUS TACK AND PRIME COATS

32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING

32 13 13.06 05/20 PORTLAND CEMENT CONCRETE PAVEMENT FOR

ROADS AND SITE FACILITIES

32 15 00 05/17 AGGREGATE SURFACING

32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS

32 17 23 08/16, CHG 5: 11/18 PAVEMENT MARKINGS

32 92 19 08/17, CHG 1: 08/21 SEEDING

DIVISION 33 - UTILITIES

33 11 00 02/18 WATER UTILITY DISTRIBUTION PIPING

33 30 00 05/18 SANITARY SEWERAGE

33 40 00 11/21 STORMWATER UTILITIES

33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION

33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT

41 22 13.14 11/19, CHG 1: 02/21 BRIDGE CRANES, OVERHEAD ELECTRIC, TOP

RUNNING

41 24 26 05/20, CHG 1: 11/20 HYDRAULIC POWER SYSTEMS

PROJECT TABLE OF CONTENTS Page 4

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 5

SECTION 01 33 29.00 06

SUSTAINABILITY REPORTING

11/17

Amendment 0004 22 March 2024

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING

ENGINEERS (ASHRAE)

ASHRAE 189.1 (2014; ERTA 1 2017) Standard for the Design of High-Performance Green Buildings Except Low-Rise Residential Buildings

SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION

(SMACNA)

ANSI/SMACNA 008 (2007) IAQ Guidelines for Occupied Buildings Under Construction, 2nd Edition

U.S. DEPARTMENT OF AGRICULTURE (USDA)

FSRIA 9002 Farm Security and Rural Investment Act Section 9002 (USDA Biopreferred Program)

U.S. DEPARTMENT OF ENERGY (DOE)

Energy Star (1992; R 2006) Energy Star Energy Efficiency Labeling System (FEMP)

U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)

SNAP (2016) EPA's Significant New Alternatives Policy Program

U.S. GREEN BUILDING COUNCIL (USGBC)

LEED v4 BDC Ref Guide (2013; R 2020) USGBC LEED Reference Guide for Building Design and Construction, v4

LEED v4.1 BDC Ref Guide (2023) LEED v4.1 Building Design and Construction Reference Guide

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

40 CFR 247 Comprehensive Procurement Guideline for Products Containing Recovered Materials

SECTION 01 33 29.00 06 Page 1 Certified Final Submittal-Amendment 0004

1.2 SUMMARY

This specification includes general requirements and procedures for this project to be constructed and documented per the federally mandated High Performance and Sustainable Building Guiding Principles (GP), LEED certification requirements, and other requirements identified in this specification.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following that "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with LRL Section 01 33 00 Submittal Procedures:

SD-01 Preconstruction Submittals

Sustainability Action Plan; G, AE

LEED Implementation Plan; G, AE

Indoor Air Quality Plan; G, AE

LEED AP BD+C; G, AE

SD-09 Manufacturer's Field Reports

Sustainability Progress Report; G, AE

SD-11 Closeout Submittals

Final Sustainability eNotebook; G, AE

Amended Final Sustainability eNotebook; G, AE

Final High Performance and Sustainable Building Checklist; G, AE

LEED Plaque and Certificate; G, AE

1.4 LEED Accredited Professional (LEED AP BD+C)

A LEED Accredited Professional with specialty in Building Design + Construction (LEED AP BD+C), accredited by the Green Building Certification Institute, on the Contractor's Quality Control Staff must assemble documentation and ensure that Guiding Principles Compliance documentation is prepared in accordance with this specification section and ensure that Third Party Certification requirements are achieved .

Identify the LEED AP BD+C on the Contractor's Quality Control Staff in accordance with specification LRL Section 01 45 04.10 06 CONTRACTOR QUALITY CONTROL. Provide a statement of qualifications of the LEED AP BD+C submitted to the Government with the QC Plan. Includes name and date of expiration of the current credential.

The LEED AP BD+C must review all requests for information, Contractor proposals, contract modifications, deviations from the design documents, or any other items that could potentially impact the compliance and Third Party Certification and rating of the project. Bring any actions that

SECTION 01 33 29.00 06 Page 2 could negatively impact the Third Party Certification rating or ability to comply with Guiding Principles to the attention of the Contracting Officer.

1.5 Guiding Principles Compliance

Provide construction related sustainability documentation to verify compliance with Federal High Performance and Sustainable Building requirements. Refer to paragraph Guiding Principle Requirements for requirements and associated documentation to include in the Sustainability eNotebook.

1.5.1 Construction Phase

1.5.1.1 Sustainability Action Plan

Provide a Sustainability Action Plan to demonstrate planned methods to comply with the Guiding Principles requirements and comply with Third Party Certification requirements identified herein. Submit the LEED Implementation Plan as a part of the Sustainability Action Plan. Provide 3 copies submitted to the Government on compact disk with the QC Plan . The Government will consider an interim Sustainability Action Plan and LEED Implementation Plan for the first 60 calendar days of the Contractor's operation. Construction will be permitted to begin only after acceptance of the plans or acceptance of an interim plan applicable to the work to be started related to the Guiding Principles requirements identified in the interim plan. Include a detailed description of all activities that relate to accomplishing each project Guiding Principle requirement, including construction practices and procurement practices. Include any plans required by the Guiding Principle Requirements including the Indoor Air Quality Plan and Waste Management Plan. Include a schedule for completion and documentation of each requirement. Include the template to be used for Sustainability Progress Reports, a plan for indoctrinating employees to sustainable goals and responsibilities, a team structure identifying responsibility for documentation, and a process for reviewing sustainability related submittals and documentation.

1.5.1.2 Sustainability eNotebook

Provide and maintain a comprehensive Sustainability eNotebook to document compliance with the Guiding Principles requirements identified herein.

All materials requirements must be updated each month. The Sustainability eNotebook must contain all required data to support compliance with the Guiding Principles requirements. The Sustainability eNotebook must be in the form of an Adobe PDF file; bookmarked at each requirement, and sub-bookmarked at each document. Include the Final High performance and Sustainable Building Checklist. Include all "S" submittals through the specification sections of this contract.

Provide 3 copies of the Final Sustainability eNotebook and Final High Performance and Sustainable Building Checklist to the Government on DVD 30 calendar days prior to the Contract Required Completion Date. Include a separate section in the Final Sustainability eNotebook with a copy of all Third Party Certification documentation, bookmarked at each separate requirement. Final progress payment retainage may be held by the Contracting Officer until the documentation is complete. Provide an Amended Final Sustainability eNotebook including any updates to documentation based on post-occupancy corrections or based on Third Party Certification requirements .

SECTION 01 33 29.00 06 Page 3

1.5.1.3 High Performance and Sustainable Building Checklist

Complete the Army Energy & Sustainability Record Card shown in Attachment A as required in paragraph Sustainability eNotebook. Obtain the electronic copy of the Army Energy & Sustainability Record Card from the Contracting Officer's Representative. Only the RECYCLED MATERIALS section of the Building Data Worksheet is required. If any deviations from contract result in a change in status to compliance with a listed requirement in the checklist, update the status of that item in the checklist.

1.5.1.4 Progress Report

Submit a monthly Sustainability Progress Report, on the same day each month, that identifies the Guiding Principles requirements completed and documented to date. The Sustainability Progress Report must also include the Third Party Certification requirements and documentation completed to date. The Government will compare the Sustainability Progress Report and the available data in the current Sustainability eNotebook and Third Party Certification documentation to the schedule in the Sustainability Action Plan and LEED Implementation Plan . Failure to adhere to the schedule for completion of requirements, including the associated documentation, in the Sustainability Action Plan and LEED Implementation Plan will be cause for withholding the monthly progress payment until the information is updated and in accordance with the Sustainability Action Plan.

1.6 Guiding Principles Requirements

Incorporate each of the following Guiding Principles requirements into the project construction, and provide documentation that proves compliance with each listed requirement. For each of the following paragraphs that require the use of products listed on Government-required websites, provide documentation of the process used to select products, or process used to determine why listed products do not meet project performance requirements.

1.6.1 Commissioning

Comply with the requirements of LRL section 01 46 00.00 06 TOTAL BUILDING

COMMISSIONING.

1.6.2 Energy Efficient Products

Provide only energy-using products that are Energy Star rated, or have the Federal Energy Management Program (FEMP) recommended efficiency for products with established Energy Star or FEMP requirements. Provide only energy using products that meet FEMP requirements for low standby power consumption. Energy efficient products can be found at:

https://energy.gov/eere/femp/federal-energy-management-program and https://www.energystar.gov/ . Provide the following documentation:

Proof that products are labeled energy efficient and comply with the cited requirements.

1.6.3 Indoor Water Use

Provide only water-consuming products that are EPA WaterSense labeled, or water fixtures available that meet the requirements of ASHRAE 189.1 Section 6.3.2, whichever is most water-efficient. Provide the following

SECTION 01 33 29.00 06 Page 4 documentation:

For products available with EPA WaterSense labeling, proof that fixtures are labeled EPA WaterSense or Energy Star ; for all other fixtures, proof they comply with the cited efficiency requirements.

1.6.4 Reduce Volatile Organic Compound (VOC) (Low Emitting Materials)

Meet the requirements of Table 3-1 at the end of this specification.

Provide the following documentation:

Provide certifications or labels that demonstrate compliance with cited requirements.

1.6.5 Indoor Air Quality During Construction

Prior to construction, create indoor air quality plan. Implement IAQ plan during construction and flush building air before occupancy.

For new construction and for renovation of unoccupied existing buildings, indoor air quality plan must meet the requirements of ANSI/SMACNA 008 , Chapter 3 and ASHRAE 189.1 Section 10.3.1.4, (Indoor Air Quality (IAQ) Construction Management), with maximum outdoor air consistent with achieving relative humidity no greater than 60 percent.

Provide documentation showing that after construction ends and prior to occupancy, HVAC filters were replaced and building air was flushed out in accordance with the cited standard.

1.6.6 Regional Materials

Comply with ASHRAE 189.1 paragraph 9.4.1.2 Regional Materials. Provide documentation demonstrating that 15% of the cost of building materials or products used were extracted, harvested, recovered or manufactured within 500 miles of the project site.

1.6.7 Recycled Content

Comply with 40 CFR 247 . Refer to https://www.epa.gov/smm/comprehensive-procurement-guidelines-construction-products for assistance identifying products cited in 40 CFR 247 . Selected products must comply with non-proprietary requirements of the Federal Acquisition Regulation, and must meet performance requirements. Provide the following documentation:

a. Manufacturers’ documents stating the recycled content by material, or written justification for claiming one of the exceptions allowed on the cited website.

b. Substitutions: Submit for Government approval, proposed alternative products or systems that provide equivalent performance and appearance and have greater contribution to project recycled content requirements. For all such proposed substitutions, submit with the Sustainability Action Plan accompanied by product data demonstrating equivalence.

1.6.8 Bio-Based Products

Provide products and material composed of the highest percentage of

SECTION 01 33 29.00 06 Page 5 biobased materials (including rapidly renewable resources and certified sustainably harvested products), consistent with FSRIA 9002 USDA Biopreferred Program, to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the end user. Use only supplies and materials of a type and quality that conform to applicable specifications and standards.

Comply with FSRIA 9002 USDA BioPreferred Program. Refer to https://www.biopreferred.gov/BioPreferred/ for the product categories and BioPreferred Catalog. Selected products must comply with non-proprietary requirements of the Federal Acquisition Regulation, and must meet performance requirements. Provide the following documentation:

USDA Biopreferred label for each product; for bio-based products used on project but not listed with Biopreferred program, provide bio-based content and percentage.

1.6.9 Ozone Depleting Substances

Meet the requirements of ASHRAE 189.1 Section 9.3.3 Refrigerants for no CFC-based refrigerants in heating ventilation, air conditioning and refrigeration systems. Where feasible, use products from U.S. EPA Significant New Alternatives Policy (SNAP) ( https://www.epa.gov/snap ) or meet the criteria of SNAP. Provide the following documentation:

a. MSDS sheets for all refrigerants.

b. Provide label for each product meeting the cited standards.

1.6.10 Waste Material Management (Recycling – Construction)

A minimum of 75% of nonhazardous construction and demolition waste material generated prior to the issuance of the final certificate of occupancy shall be diverted from disposal in landfills and incinerators by recycling or reuse. Reuse includes donation of materials to charitable organization, salvage of existing materials onsite, and packaging materials returned to the manufacturer, shipper, or other source that will reuse the packaging in future shipments. Excavated soil and land clearing debris shall not be included in the calculation. Calculations are allowed to be done by either weight or volume, but shall be consistent throughout. Specific areas on the construction site shall be designated for collection of recyclable and reusable materials. Off-site storage and sorting of materials shall be allowed. Diversion efforts shall be tracked by the contractor throughout the construction process and documentation provided to the Government prior to contract closeout. Refer to LEED v4 MR Construction and Demolition Waste Management Planning prerequisite and MR Construction and Demolition Waste Management credit for addiitonal requirments.

1.7 Third Party Certification

Comply with all requirements and provide all required documentation for the project to achieve certification in the Third Party Certification system identified herein. The Contractor must bear all costs and perform all administrative actions necessary to complete Third Party Certification.

1.7.1 LEED

This project has been designed for a rating of Silver in the Leadership in

SECTION 01 33 29.00 06 Page 6

Energy and Environmental Design (LEED) version 4 certification system.

Certify the project at the designed LEED rating through the Green Building Certification Institute. The project has been registered with the Green Building Certification Institute. The Final Design Review of the Split Design & Construction Review path has been completed. Complete all remaining activities necessary for LEED certification.

Some LEED prerequisites and credits are similar to Guiding Principle Requirements. Some LEED credits are are substituted with LEED v4.1 requirements in lieu of LEED v4 requirements. Comply with both the LEED and Guiding Principle Requirements. Refer to LEED v4 BDC Ref Guide and LEED v4.1 BDC Ref Guide for additional information regarding LEED and LEED certification processes.

1.7.2 LEED Documentation

LEED documentation requires the following:

a. Refer to Attachment B, LEED Checklist at the end of this specification section.

b. Obtain approval of the LEED Checklist from the Contracting Officer at the Sustainability Implementation Meeting.

No variations or substitutions to the approved LEED Checklist are allowed without written consent from the Contracting Officer.

Immediately bring to the attention of the Contracting Officer any project changes that impact meeting the approved LEED Requirements for this project. Demonstrate that change will not: incur additional construction cost; increase the life cycle cost; impact previous LEED Design Review; or impact required LEED certification level.

c. Complete all work required to incorporate the applicable LEED Requirements.

d. Maintain the construction related information, and provide replacement pages, in the Sustainability eNotebook pertaining to additions and changes to the approved sustainability requirements. The Sustainability eNotebook is in electronic format and is explained in the paragraph entitled "SUSTAINABILITY eNOTEBOOK". The Sustainability eNotebook contains the following components in addition to the GPV components above:

(1) LEED Checklist

(2) Completed LEED Online forms for each identified prerequisite and credit

(3) Copy of all correspondence with the LEED organization.

(4) Documentation illustrating compliance with LEED requirements.

(5) LEED Award Certificate and Plaque.

e. LEED Implementation Plan: Include the following information in the Sustainability Action Plan. Provide this LEED information in addition to the GPV Action Plan items above:

(1) Contractor's planned method to achieve each LEED requirement.

SECTION 01 33 29.00 06 Page 7

(2) For each required LEED credit that is attempted but not achieved, provide narrative explaining how mission or activity precludes achieving specific sustainability requirement or goal. Provide analysis of particular requirement and level to which project is able to comply.

(3) Name and contact information for: Contractor's Sustainability POC and other names of sustainability professionals on the Contractor's Staff responsible for ensuring LEED sustainability goals are accomplished and documentation is assembled and who requires access to the LEED online website.

(4) Provide the plan and schedule for performance testing, data collection, and commissioning to take place during first year of facility usage.

(5) Prepare and submit detailed work plans directly related to achieving LEED construction phase prerequisites and credits. Note that some of the following plans must be uploaded to LEED Online as supporting documents to specific credits, and others are intended to demonstrate the Contractor's understanding of LEED data collection, early planning and communication with relevant parties. Such planning and execution is required for LEED credit achievement. The list of work plans shall include the following:

f. Contractor is responsible for all costs associated with constructing and demonstrating that project complies with approved LEED requirements, including but not limited to:

(1) Final LEED review, certification and plaque fees

(2) Online LEED management and documentation.

(3) Obtaining LEED certification based on Government-approved sustainability goals.

(4) Construction work required to incorporate LEED prerequisites and credits.

(5) Submittals required to demonstrate compliance with Government approved LEED checklists.

g. Provide all calculations, product data, and certifications required in this specification to demonstrate compliance with the LEED Requirements.

h. Provide all online LEED management and documentation.

i. Contractor is responsible for all required responses to USGBC/GBCI.

j. Provide LEED Plaque and Certificates. Use format below to create the Plaque, Certificate and Letter of Congratulations. Forward to parties designated by Contracting Officer:

(1) Plaque:

Name: Final Building Name. If unknown, provide Form DD1391 Project Name.

SECTION 01 33 29.00 06 Page 8

(2) Certificate:

Project Title, first line: P-(X); Form DD1391 Project Name).

Project Title, second line: UIC (Installation code)

(3) Letter Congratulations:

Address letter to Facility's Installation commander Name. Address the letter to an individual person.

1.7.3 LEED Documentation Requirements

LEED v4 and v4.1 credits as identified in Attachment B shall be incorporated and documented as required by the Contract documents and in full compliance with the LEED v4 BDC Ref Guide or the LEED v4.1 BDC Ref Guide . LEED v4 and LEED v4.1 credits not identified elsewhere in the Contract documents and those requiring further instruction are specified below. Refer to the LEED v4 BDC Ref Guide and the LEED v4.1 BDC Ref Guide for further definitions and requirements.

1.7.3.1 MR Construction and Demolition Waste Management

Contractor shall employ construction waste management practices as required in the LEED v4 BDC Ref Guide Option 1 - Diversion,Path 2 - Divert 75% and Four Material Streams, and in 01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT to achieve the threshold stated therein.

1.7.3.1.1 Calculations for MR Construction Waste Management

Contractor shall track all construction and demolition waste and diverted waste using the LEED Online Construction and Demoltion Waste Calculator.

1.7.3.2 MR Building Product Disclosure and Optimization - Environmental Product Declarations

1.7.3.2.1 Option 1 Environmental Product Declaration

Contractor shall select materials so that the sum of installed products with Environmental Product Declarations (EPD) is at least 20 different products from at least five different manufacturers. EPDs shall comply with the requirements in the LEED v4.1 BDC Ref Guide.

1.7.3.2.2 Option 2 Embodied Carbon/LCA Optimization

Contractor shall select at least 5 permanently installed products sourced from at least three different manufacturers that have an embodied carbon optimization report or action plan in compliance with the LEED v4.1 BDC Ref Guide .

1.7.3.3 MR Building Product Disclosure and Optimization - Sourcing of Raw Materials

Amdt. #0004******************************************************************

Contractor shall select materials so that the sum of the following constitutes at least one of the responsible sourcing and extraction criteria for at least 30 percent by cost, of the total value of permanently installed building prodducts in compliance with the

SECTION 01 33 29.00 06 Page 9

LEED v4.1 BDC Ref Guide .

a. Extended producer responsibility: Products meeting extended producer responsibility criteria are valued at 50 percent of their cost for purposes of credit achievement calculation.

b. Bio-based materials: Products that meet bio-based product criteria are valued at 50 percnet of the cost multiplied by the biobased content of the product for purposes of credit achievement calculation.

c. Certified wood products: Products that meet certified wood products criteria are valued at 100 percent of their cost for purposes of the credit achievment calculation.

d. Materials reuse: Products meeting materials reuse criteria are valued at 200 percent of their cost for the purposes of credit achievement calculation.

e. Recycled content: Products that meet recycled content criteria are valued at 100 percent of their cost for purposes of credit achievement calculation.

f. For credit achievement, products meeting any of the above criteria that are sourced (extracted, manufactured and purchased)within 100 miles of the project site are valued at twice their base contributing cost, up to a maximum of 200 percent of cost.

1.7.3.4 MR Building Product Disclosure and Optimization - Material Ingredients

1.7.3.4.1 Option 1 Material Ingredient Reporting

Contractor shall select materials so that the sum of installed products demonstrating a chemical inventory of the product to at least 0.1 percent is at least 20 different products from at least five different manufacturers. Material Ingredient Reporting programs shall comply with the requirements in the LEED v4.1 BDC Ref Guide .

a. ANSI/BIFMA e3 Furniture Sustainability Standard

b. Cradle to Cradle

c. Declare

d. Facts – NSF/ANSI 336

e. Global Green TAG

f. Health Product Declaration

g. Living Product Challenge

h. Manufacturer Inventory

i. Product Lens Certification

j. Any compliant reports above with third-party verification that includes the verification of content inventory are worth 1.5 products for credit achievement calculations.

1.7.3.4.2 Option 2 Material Ingredient Optimization

Contractor shall select products that have a compliant material ingredient optimization report or action plan. Use at least 5 permanently installed products sourced from at least three different manufacturers. Products are valued according to the Option 2 Material Ingredient Optimization table in the LEED v4.1 BDC Ref Guide .

For credit achievement calculation, products sourced (extracted,manufactured, purchased) within 100 miles of the project site are valued at twice their base contributing number of products, up to a maximum of 2 products.

SECTION 01 33 29.00 06 Page 10

1.7.3.5 Low-Emitting Materials

Contractor shall select materials used on the interior of the building that comply with the low-emitting requirements in the LEED v4.1 BDC Ref Guide for the following categories:

a. Paints and coatings: At least 75 percent of all paints and coatings, by volume or surface area, meet the VOC emissions evaluation and 100 percent meet the VOC content evaluation.

b. Adhesives and sealants: At least 75 percent of all adhesives and sealants, by volume or surface area, meet the VOC emissions evaluation and 100 percent meet the VOC content evaluation.

c. Flooring: At least 90 percent of all flooring, by cost or surface area, meets the VOC emissions evaluation or inherently nonemitting sources criteria, or salvaged and reused materials criteria.

d. Wall panels: At least 75 percent of all wall panels, by cost or surface area, meet the VOC emissions evaluation, or inherently nonemitting sources criteria, OR salvaged and reused materials criteria.

e. Ceilings: At least 90 percent of all ceilings, by cost or surface area, meet the VOC emissions evaluation, or inherently nonemitting sources criteria, or salvaged and reused materials criteria.

f. Insulation: At least 75 percent of all insulation, by cost or surface area, meets the VOC emissions evaluation.

g. Furniture: At least 75 percent of all furniture in the project scope of work, by cost, meets the furniture emissions evaluation, or inherently nonemitting sources criteria, OR salvaged and reused materials criteria.

h. Composite wood: At least 75 percent of all composite wood, by cost or surface area, meets the Formaldehyde emissions evaluation OR salvaged and reused materials criteria.

1.7.3.6 Construction Indoor Air Quality Management Plan

Comply with the requirements of sub-section 1.6.5 Indoor Air Quality During Construction for indoor air quality plan requirements.

Additionally, indoor air quality plan shall address the following:

a. Protect all absorptive materials that are stored onsite and installed from moisture damage.

b. Install minimum efficiency MERV 8 filters at each return air grille and return or transfer duct inlet opening prior to operating permanently installed air-handling equipment during construction and replace filtration media with specified filtration media prior to occupancy.

c. Prohibit smoking inside the building and within 50 feet of all building openings during construction.

d. Conduct building flush-out or baseline air testing per sub-section

1.7.3.7 Indoor Air Quality Assessment.

1.7.3.7 Indoor Air Quality Assessment

1.7.3.7.1 Option 2 Air Testing

After substantial completion and prior to occupancy, conduct baseline indoor air quality testing in occupied spaces using protocols consistent with the methods listed in Table 1 of the LEED v4 BDC Ref Guide .

******************************************************************Amdt. #0004

SECTION 01 33 29.00 06 Page 11

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

SECTION 01 33 29.00 06 Page 12

3.1 SUSTAINABILITY IMPLEMENTATION MEETING

The LEED AP BD+C , QC System Manager, and Contracting Officer's Representative must meet within 60 calendar days after notice to proceed to review project sustainability goals with respect to the Sustainability Action Plan and LEED Implementation Plan , identify potential difficulties related to meeting the Guiding Principle Requirements, and discuss mitigation strategies.

3.2 Sustainability Pre-Closeout Meeting

The LEED AP BD+C , QC System Manager, and Contracting Officer's Representative must meet 60 calendars days prior to Contract Required Completion Date to review completion status of sustainability requirements including level of completion of Third Party Certification, Guiding Principles Requirements documentation and the High Performance and Sustainable Building Checklist. Discuss any potential difficulties in completing Third Party Certification, outstanding requirements and documentation. Provide a copy of the Sustainability eNotebook with up-to-date documentation.

LEED Plaque and Certificate

Finalize the process requirements and obtain the LEED Plaque and Certificate, and compliance report, indicating completion of the project's sustainability goals. Include LEED compliance report with final LEED scoresheet as applicable.

Provide one original framed copy of the certificate, assessment, or validation, mounted in 1 inch deep metal frames, with double matt, and wire hangers, in location approved by Contracting Officer. Deliver one original certificate and compliance report to Contractor Officer, unless otherwise instructed. Provide and hang Plaque in a prominent interior location approved by the Contracting Officer.

3.3 TABLE 3-1 VOLATILE ORGANIC COMPOUNDS (VOC) (LOW EMITTING MATERIALS)

REQUIREMENTS

Refer to following table, based on ASHRAE 189.1 section 8.4.2 (Materials), for compliance criteria.

SECTION 01 33 29.00 06 Page 13

TABLE 3-1 Volatile Organic Compounds (VOC) (Low Emitting Materials) Requirements

MATERIAL CATEGORY EMISSIONS

REQUIREMENT

MATERIALS WITH

ADDED VOC

REQUIREMENT

MATERIAL CATEGORY

Adhesives and Sealants

CDPH/EHLB/Standard method V1.1 (California Section 01350) (Use "office" or "classroom" space limits for all applications) or Adhesives (carpet, resilient, wood flooring; panel;

primers) Sealants (acoustical;

firestop; HVAC Air duct; primers) Caulks

SCAQMD Rule 1168 (Use "other" category for HVAC duct sealant) (for firestop adhesive, UFC 3-600-01 overrides conflicting requirements)

Aerosol adhesives Section 3 of Green Seal Standard

GS-36

(except:

cleaners, solvent cements, and primers used with plastic piping and conduit in plumbing, fire suppression, and electrical systems; HVAC air duct sealants when the application space air temp is less than 40 F (4.5 C).

Paints and Coatings CDPH/EHLB/Standard method V1.1 (Ca lifornia Section 01350) (Use "office" or "classroom" space limits for all applications) or Flat and nonflat topcoats, primers, undercoaters, and anti-corrosive coatings

Green Seal Standard GS-11

SECTION 01 33 29.00 06 Page 14

TABLE 3-1 Volatile Organic Compounds (VOC) (Low Emitting Materials) Requirements

MATERIAL CATEGORY EMISSIONS

REQUIREMENT

MATERIALS WITH

ADDED VOC

REQUIREMENT

MATERIAL CATEGORY

Paints and Coatings CDPH/EHLB/Standard method V1.1 (California Section 01350) (Use "office" or "classroom" space limits for all applications) or Concrete/masonry sealers (waterproofing concrete/masonry sealers), concrete curing compounds, dry fog coatings, faux finishing coatings, fire resistive coatings, floor coatings, graphic arts (sign) coatings, industrial maintenance coatings, mastic texture coatings, metallic pigmented coatings, multicolor coatings, pretreatment wash primers, reactive penetrating sealers, recycled coatings, shellacs (clear and opaque), specialty primers, stains, wood coatings (clear wood finishes), wood preservatives, and zinc primers

California Air Resources Board (CARB) Suggested Control Measure for Architectural Coatings or SCAQMD Rule 1113

SECTION 01 33 29.00 06 Page 15

TABLE 3-1 Volatile Organic Compounds (VOC) (Low Emitting Materials) Requirements

MATERIAL CATEGORY EMISSIONS

REQUIREMENT

MATERIALS WITH

ADDED VOC

REQUIREMENT

MATERIAL CATEGORY

Paints and Coatings CDPH/EHLB/Standard method V1.1 (California Section 01350) (Use "office" or "classroom" space limits for all applications) or Basement specialty coatings, high-temperature coatings, low solids coatings, stone consolidants, swimming-pool coatings, tub- and tile-refining coatings, and waterproofing membranes

California Air Resources Board (CARB) Suggested Control Measure for Architectural Coatings

Floor Covering Materials

For carpet, all locations:

CDPH/EHLB/Standard Method V1.1 ( California Section 01350) or label for Section 9 of CDPH/EHLB/Standard Method V1.1 (Cali fornia Section 01350) none none

SECTION 01 33 29.00 06 Page 16

TABLE 3-1 Volatile Organic Compounds (VOC) (Low Emitting Materials) Requirements

MATERIAL CATEGORY EMISSIONS

REQUIREMENT

MATERIALS WITH

ADDED VOC

REQUIREMENT

MATERIAL CATEGORY

Composite Wood, Wood Structural Panel, and Agrifib er Products particleboard medium density fiberboard (MDF) wheatboard strawboard panel substrates door cores no added urea-formaldehyde resins including laminating adhesives for composite wood and agrifiber assemblies

Third-party certification (approved by CARB) of California Air Resource Board's (CARB) regulation , Airborne Toxic Control Measure to Reduce Formaldehyde Emissions from Composite Wood Products none none

CDPH/EHLB/Standard method V1.1 (Ca lifornia Section 01350) (Use "office" or "classroom" space limits for all applications) (except: Structural panel components such as plywood, particle board, wafer board, and oriented strand board identified as

"EXPOSURE 1,"

"EXTERIOR," or "HUD-APPROVED" are considered acceptable for interior use.)

SECTION 01 33 29.00 06 Page 17

TABLE 3-1 Volatile Organic Compounds (VOC) (Low Emitting Materials) Requirements

MATERIAL CATEGORY EMISSIONS

REQUIREMENT

MATERIALS WITH

ADDED VOC

REQUIREMENT

MATERIAL CATEGORY

Office Furniture Systems and Seating installed prior to occupancy

ANSI/BIFMA X7.1

ANSI/BIFMA X7.1:

(95 percent of installed office furniture system workstations and seating units)

Section 7.6.2 of ANSI/BIFMA e3 (50 percent of office furniture system workstations and seating units) none none

Ceiling and Wall Systems ceiling and wall insulation acoustical ceiling panels tackable wall panels gypsum wall board and panels wall coverings

CDPH/EHLB/Standard method V1.1 (Ca lifornia Section 01350) (Use "office" or "classroom" space limits for all applications) none none

SECTION 01 33 29.00 06 Page 18

SECTION 01 33 29.00 06 Page 19

Attachment A

HIGH PERFORMANCE AND SUSTAINABLE BUILDING CHECKLIST

SECTION 01 33 29.00 06 Page 20

Attachment B

LEED PROJECT CHECKLIST

-- End of Section --

SECTION 01 33 29.00 06 Page 21

SECTION 07 11 13

BITUMINOUS DAMPPROOFING

08/11, CHG 1: 05/17

Amendment 0004 22 March 2024

Amdt. #0004******************************************************************

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM C208 (2012; R 2017; E 2017; E 2019) Standard Specification for Cellulosic Fiber Insulating Board

ASTM C728 (2017; R 2022) Standard Specification for Perlite Thermal Insulation Board

ASTM D1187/D1187M (1997; E 2011; R 2011) Asphalt-Base Emulsions for Use as Protective Coatings for Metal

ASTM D1227 (2013) Emulsified Asphalt Used as a Protective Coating for Roofing

ASTM D4263 (1983; R 2018) Standard Test Method for Indicating Moisture in Concrete by the Plastic Sheet Method

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-07 Certificates

Materials

1.3 DELIVERY AND STORAGE

Deliver materials in sealed containers bearing…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .