This solicitation document requests proposals for the construction of an Army Reserve Center and Area Maintenance Support Activity at Wright-Patterson Air Force Base in Ohio. The solicitation includes specifications for products and services required such as site work, concrete, masonry, metals, woodwork, doors and windows, finishes, equipment, special construction, utilities, and electrical work. It details performance periods, submittal requirements, and quality standards that must be met. The Army Corps of Engineers Engineering District Louisville is the contracting agency managing this project.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation For Area Maintenance Support Activity (AMSA)/Army Reserve Center (ARC) Wright-Patterson Air Force Base, OH
P2: 478327/418158
Design-Bid-Build
Specifications Vol. 2 of 4 Certified Final Design
15 November 2023
W912QR24R0006
ARIMS: 200A Disposition: Maintain for 15yrs after construction.
W912QR24R0006_Specs_Vol2-0000
P2# 478327 AMSA / P2# 481858 ARC
Wright Patterson Air Force Base, OH
PROJECT TABLE OF CONTENTS
VOLUME ONE:
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 80 00.00 06 SPECIAL PROVISIONS
APPENDIX A - CONSTRUCTION PROJECT SIGN
APPENDIX B - SUBMITTAL REGISTER
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 32 01.00 06 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 33 29.00 06 SUSTAINABILITY REPORTING
APPENDIX A - HIGH PERFORMANCE AND SUSTAINABLE BUILDING
CHECKLISTS
APPENDIX B - LEED SCORECARDS
01 35 26.00 06 GOVERNMENT SAFETY REQUIREMENTS
01 35 43 GENERAL ENVIRONMENTAL PROTECTION REQUIREMENTS (WPAFB)
APPENDIX A - STORM WATER POLLUTION PREVENTION PLAN (SWP3)
APPENDIX B - HUFFMAN RETARDING BASIN PERMIT
APPENDIX C - ENVIRONMENTAL BASELINE SURVEY
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 04.10 06 CONTRACTOR QUALITY CONTROL
01 45 35 SPECIAL INSPECTIONS
APPENDIX A - STATEMENT OF SPECIAL INSPECTIONS
APPENDIX B - SCHEDULE OF SPECIAL INSPECTIONS
01 46 00.00 06 TOTAL BUILDING COMMISSIONING
APPENDIX A - (AMSA) OWNER'S PROJECT REQUIREMENTS (OPR)
APPENDIX B - (AMSA) BASIS OF DESIGN (BOD)
APPENDIX C - (AMSA) DEMAND RESPONSE ACTION PLAN
APPENDIX D - (ARC) OWNER'S PROJECT REQUIREMENTS (OPR)
APPENDIX E - (ARC) BASIS OF DESIGN (BOD)
APPENDIX F - (ARC) DEMAND RESPONSE ACTION PLAN
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
APPENDIX A - FIELD OFFICE TRAILER FOR REFERENCE ONLYH
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 23 OPERATION AND MAINTENANCE DATA
VOLUME TWO:
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
DIVISION 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
03 45 00 PRECAST ARCHITECTURAL CONCRETE
DIVISION 04 - MASONRY
04 20 00 UNIT MASONRY
DIVISION 05 - METALS
PROJECT TABLE OF CONTENTS Page 1
CERTIFIED FINAL
05 12 00 STRUCTURAL STEEL
05 21 00 STEEL JOIST FRAMING
05 30 00 STEEL DECKS
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 51 33 METAL LADDERS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS
06 61 16 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS
07 22 00 ROOF AND DECK INSULATION
07 27 10.00 10 BUILDING AIR BARRIER SYSTEM
07 27 19.01 SELF-ADHERING AIR BARRIERS
07 42 13 METAL WALL PANELS
07 54 19 POLYVINYL-CHLORIDE (PVC) ROOFING
07 60 00 FLASHING AND SHEET METAL
07 61 14.00 20 STEEL STANDING SEAM ROOFING
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 11 16 ALUMINUM DOORS AND FRAMES
08 14 00 WOOD DOORS
08 31 00 ACCESS DOORS AND PANELS
08 33 23 OVERHEAD COILING DOORS
08 34 59 VAULT DOORS AND DAY GATES
08 34 73 SOUND CONTROL DOOR ASSEMBLIES
08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS
08 44 00 CURTAIN WALL AND GLAZED ASSEMBLIES
08 51 13 ALUMINUM WINDOWS
08 60 45 INSULATED TRANSLUCENT FIBERGLASS SKYLIGHTS AND INSULATED
TRANSLUCENT FIBERGLASS WALL PANELS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
08 91 00 METAL WALL LOUVERS
DIVISION 09 - FINISHES
09 22 00 SUPPORTS FOR GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 30 10 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 ACOUSTICAL CEILINGS
09 62 38 STATIC-CONTROL FLOORING
09 65 00 RESILIENT FLOORING
09 67 23.13 STANDARD RESINOUS FLOORING & ESD RESINOUS FLOORING
09 67 23.15 FUEL RESISTIVE RESINOUS FLOORING, 3-COAT SYSTEM
09 68 00 CARPETING
09 90 00 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 11 00 VISUAL DISPLAY UNITS
PROJECT TABLE OF CONTENTS Page 2
10 12 01.00 48 RECESSED DISPLAY CASES
10 14 00.10 EXTERIOR SIGNAGE
10 14 00.20 INTERIOR SIGNAGE
10 21 13 TOILET COMPARTMENTS
10 22 13.00 48 WIRE MESH PARTITIONS
10 22 39 FOLDING PANEL PARTITIONS
10 26 00 WALL AND DOOR PROTECTION
10 28 00.00 48 TOILET AND SHOWER ACCESSORIES AND COAT RACKS
10 44 13.00 48 FIRE EXTINGUISHERS, CABINETS AND WALL BRACKETS
10 51 52.00 48 METAL WARDROBE LOCKERS
10 56 13.00 48 METAL STORAGE SHELVING
10 90 00.00 48 MISCELLANEOUS SPECIALTIES (PARTIAL OMAR FUNDED)
VOLUME THREE:
DIVISION 11 - EQUIPMENT
11 46 01.00 48 KITCHEN
11 46 01.01 48 APPENDIX TO FOOD SERVICE EQUIPMENT
APPENDIX A - ARMY RESERVE KITCHEN STANDARD PRODUCT DATA
DIVISION 12 - FURNISHINGS
12 24 13 ROLLER WINDOW SHADES
12 48 13 ENTRANCE FLOOR MATS AND FRAMES
DIVISION 13 - SPECIAL CONSTRUCTION
13 34 19.01 METAL BUILDING SYSTEMS (UNHEATED STORAGE BUILDING)
13 34 19.02 METAL BUILDING SYSTEMS (AMSA WASH RACK)
DIVISION 21 - FIRE SUPPRESSION
21 13 13 WET PIPE SPRINKLER SYSTEMS, FIRE PROTECTION
21 21 03.00 10 WET CHEMICAL FIRE EXTINGUISHING SYSTEM
21 30 00 FIRE PUMPS WITH FIRE PUMP ENCLOSURE
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
22 31 00 WATER SOFTENERS, CATION-EXCHANGE (SODIUM CYCLE)
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 93.00 06 TESTING, ADJUSTING, AND BALANCING (TAB) OF HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC
23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING
CONTROL SYSTEMS
23 11 20 FACILITY GAS PIPING
23 23 00 REFRIGERANT PIPING
23 30 00 HVAC AIR DISTRIBUTION
23 35 16.17 10 MECHANICAL ENGINE AND WELDING FUME EXHAUST SYSTEMS
23 52 00 HEATING BOILERS
23 64 10 WATER CHILLERS, VAPOR COMPRESSION TYPE
23 64 26 CHILLED, CHILLED-HOT, AND CONDENSER WATER PIPING SYSTEMS
23 80 20.00 10 GAS-FIRED HEATING EQUIPMENT
PROJECT TABLE OF CONTENTS Page 3
23 81 00 DECENTRALIZED UNITARY HVAC EQUIPMENT
23 82 00.00 20 TERMINAL HEATING UNITS
23 82 46.00 40 ELECTRIC UNIT HEATERS
VOLUME FOUR:
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.01 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS - DDC
25 05 11.02 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS -
FA/MNS SYSTEM
25 05 11.03 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS - IDS
25 05 11.04 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS - AMRS
SYSTEM
25 10 10 CONTROL SYSTEM (UMCS) FRONT END INTEGRATION
DIVISION 26 - ELECTRICAL
26 08 00 APPARATUS INSPECTION AND TESTING
26 12 19.10 THREE-PHASE, LIQUID-FILLED PAD-MOUNTED TRANSFORMERS
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 24 13 SWITCHBOARDS
26 27 13.10 30 ELECTRIC METERS
26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION
26 41 00 LIGHTNING PROTECTION SYSTEM
26 51 00 INTERIOR LIGHTING
26 56 00 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 05 28.36 48 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
27 51 16 PUBLIC ADDRESS SYSTEMS
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 08 10 ELECTRONIC SECURITY SYSTEM ACCEPTANCE TESTING
28 10 05 ELECTRONIC SECURITY SYSTEMS (ESS)
28 31 70 FIRE PUMP HOUSE FIRE ALARM SYSTEM, ADDRESSABLE
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM,
ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00.00 06 EARTHWORK
31 05 22.00 06 GEOTEXTILES USED AS FILTERS
31 11 00 CLEARING AND GRUBBING
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19.61 SEALING OF JOINTS IN RIGID PAVEMENT
32 05 33 LANDSCAPE ESTABLISHMENT
32 11 23 AGGREGATE BASE COURSE
32 11 23.23 BASE COURSE DRAINAGE LAYERS
32 12 13 BITUMINOUS TACK AND PRIME COATS
32 12 16.16 ROAD-MIX ASPHALT PAVING
32 13 13.06 06 PORTLAND CEMENT CONCRETE PAVEMENT FOR LIGHT DUTY CONCRETE
PAVEMENTS FACILITIES
32 13 14.13 CONCRETE PAVING FOR HEAVY DUTY PAVEMENTS
PROJECT TABLE OF CONTENTS Page 4
32 15 00 AGGREGATE SURFACING
32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 PAVEMENT MARKINGS
32 31 13 CHAIN LINK FENCES AND GATES
32 92 19 SEEDING
32 92 23 SODDING
32 93 00 EXTERIOR PLANTS
APPENDIX A - WPAFB APPROVED PLANTING LIST
DIVISION 33 - UTILITIES
33 30 00 SANITARY SEWERAGE
33 40 00 STORMWATER UTILITIES
33 46 11.53 06 BIORETENTION AREAS
33 46 16 SUBDRAINAGE PIPING
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT
41 22 13.14 BRIDGE CRANES, OVERHEAD ELECTRIC, TOP RUNNING
DIVISION 48 - ELECTRICAL POWER GENERATION
48 14 00 SOLAR PHOTOVOLTAIC SYSTEMS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 5
SECTION TABLE OF CONTENTS
DIVISION 02 - EXISTING CONDITIONS
SECTION 02 41 00
DEMOLITION
08/22
PART 1 GENERAL
1.1 REFERENCES
1.2 PROJECT DESCRIPTION
1.2.1 Definitions
1.2.1.1 Demolition
1.2.1.2 Demolition Plan
1.2.2 Demolition Plan
1.2.3 General Requirements
1.3 ITEMS TO REMAIN IN PLACE
1.3.1 Existing Construction Limits and Protection
1.3.2 Trees
1.3.3 Utility Service
1.4 BURNING
1.5 AVAILABILITY OF WORK AREAS
1.6 SUBMITTALS
1.7 QUALITY ASSURANCE
1.7.1 Dust and Debris Control
1.8 PROTECTION
1.8.1 Traffic Control Signs
1.9 RELOCATIONS
1.10 EXISTING CONDITIONS
PART 2 PRODUCTS
2.1 FILL MATERIAL
PART 3 EXECUTION
3.1 EXISTING FACILITIES TO BE REMOVED
3.1.1 Structures
3.1.2 Utilities and Related Equipment
3.1.2.1 General Requirements
3.1.2.2 Disconnecting Existing Utilities
3.1.3 Chain Link Fencing
3.1.4 Paving and Slabs
3.1.5 Air Conditioning Equipment
3.1.6 Cylinders and Canisters
3.1.7 Electrical Equipment and Fixtures
3.1.7.1 Fixtures
3.1.7.2 Electrical Devices
3.1.7.3 Wiring Ducts or Troughs
3.1.7.4 Conduit and Miscellaneous Items
3.2 CONCURRENT EARTH-MOVING OPERATIONS
3.3 DISPOSITION OF MATERIAL
3.3.1 Title to Materials
SECTION 02 41 00 Page 1
3.3.2 Reuse of Materials and Equipment
3.3.3 Unsalvageable and Non-Recyclable Material
3.4 CLEANUP
3.5 DISPOSAL OF REMOVED MATERIALS
3.5.1 Regulation of Removed Materials
3.5.2 Burning on Government Property
3.5.3 Removal to Spoil Areas on Government Property
3.5.4 Removal from Government Property
3.6 REUSE OF SALVAGED ITEMS
-- End of Section Table of Contents --
SECTION 02 41 00 Page 2
SECTION 02 41 00
DEMOLITION
08/22
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF SAFETY PROFESSIONALS (ASSP)
ASSP A10.6 (2006) Safety & Health Program Requirements for Demolition Operations - American National Standard for Construction and Demolition Operations
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety -- Safety and Health Requirements Manual
U.S. FEDERAL AVIATION ADMINISTRATION (FAA)
FAA AC 70/7460-1 (2016; Rev L; Change 2) Obstruction Marking and Lighting
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
40 CFR 61 National Emission Standards for Hazardous Air Pollutants
1.2 PROJECT DESCRIPTION
1.2.1 Definitions
1.2.1.1 Demolition
Demolition is the process of tearing apart and removing any feature of a facility together with any related handling and disposal operations.
1.2.1.2 Demolition Plan
Demolition Plan is the planned steps and processes for managing demolition activities and identifying the required sequencing activities and disposal mechanisms.
1.2.2 Demolition Plan
Prepare a Demolition Plan and submit proposed demolition and removal procedures for approval before work is started. Include in the plan procedures for careful removal and disposition of materials specified to be salvaged, coordination with other work in progress, a disconnection schedule of utility services, and a detailed description of methods and
SECTION 02 41 00 Page 3 equipment to be used for each operation and of the sequence of operations.
Coordinate with Waste Management Plan in accordance with Section 01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL. Provide procedures for safe conduct of the work in accordance with EM 385-1-1 . Plan must be approved by Contracting Officer prior to work beginning.
1.2.3 General Requirements
Do not begin demolition until authorization is received from the Contracting Officer. The work includes demolition , salvage of identified items and materials, and removal of resulting rubbish and debris. Remove rubbish and debris from Government property daily, unless otherwise directed. Store materials that cannot be removed daily in areas specified by the Contracting Officer. In the interest of occupational safety and health, perform the work in accordance with EM 385-1-1 , Section 23, Demolition, and other applicable Sections.
1.3 ITEMS TO REMAIN IN PLACE
Comply with FAR 52.236-9 to protect existing vegetation, structures, equipment, utilities, and improvements. Coordinate the work of this section with all other work indicated. Do not overload pavements to remain.
Provide new supports and reinforcement for existing construction weakened by demolition or removal work. Repairs, reinforcement, or structural replacement require approval by the Contracting Officer prior to performing such work.
1.3.1 Existing Construction Limits and Protection
Do not disturb existing construction beyond the extent indicated or necessary for installation of new construction. Provide protective measures to control accumulation and migration of dust and dirt in all work areas. Remove dust, dirt, and debris from work areas daily.
1.3.2 Trees
Protect trees within the project site which might be damaged during demolition, and which are indicated to be left in place, by a 6 foot high fence. Erect and secure fence a minimum of 5 feet from the trunk of individual trees or follow the outer perimeter of branches or clumps of trees. Replace any tree designated to remain that is damaged during the work under this contract with like-kind or as approved by the Contracting Officer.
1.3.3 Utility Service
Maintain existing utilities indicated to stay in service and protect against damage during demolition operations. Prior to start of work, the utility provider will disconnect and seal utilities serving each area of alteration or removal upon written request from the Contractor.
1.4 BURNING
The use of burning at the project site for the disposal of refuse and debris will not be permitted . Where burning is permitted, adhere to federal, state, and local regulations.
SECTION 02 41 00 Page 4
1.5 AVAILABILITY OF WORK AREAS
Areas in which the work is to be accomplished will be available at contract award.
1.6 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Demolition Plan; G , RO
Existing Conditions
SD-07 Certificates
Notification; G , RO
SD-11 Closeout Submittals
Receipts
1.7 QUALITY ASSURANCE
Submit timely notification of demolition projects to Federal, State, regional, and local authorities in accordance with 40 CFR 61 , Subpart M.
Notify the State's environmental protection agency and the Contracting Officer in writing 10 working days prior to the commencement of work in accordance with 40 CFR 61 , Subpart M. Comply with federal, state, and local hauling and disposal regulations. In addition to the requirements of the "Contract Clauses," conform to the safety requirements contained in ASSP A10.6 . Comply with the Environmental Protection Agency requirements specified. Use of explosives will not be permitted.
1.7.1 Dust and Debris Control
Prevent the spread of dust and debris and avoid the creation of a nuisance or hazard in the surrounding area. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, or pollution. Sweep pavements as often as necessary to control the spread of debris.
1.8 PROTECTION
1.8.1 Traffic Control Signs
a. Where pedestrian and driver safety is endangered in the area of removal work, use traffic barricades with flashing lights. Notify the Contracting Officer prior to beginning such work.
Provide a minimum of 2 FAA type L-810 steady burning red obstruction lights on temporary structures (including cranes) over 100 feet, but
SECTION 02 41 00 Page 5 less than 200 ft, above ground level. The use of LED based obstruction lights are not permitted. For temporary structures (including cranes) over 200 ft above ground level provide obstruction lighting in accordance with FAA AC 70/7460-1 . Perform light construction and installation in compliance with FAA AC 70/7460-1 .
Lights must be operational during periods of reduced visibility, darkness, and as directed by the Contracting Officer. Maintain the temporary services during the period of construction and remove only after permanent services have been installed and tested and are in operation.
1.9 RELOCATIONS
Perform the removal and reinstallation of relocated items as indicated with workmen skilled in the trades involved. Repair or replace items to be relocated which are damaged by the Contractor with new undamaged items as approved by the Contracting Officer.
1.10 EXISTING CONDITIONS
Before beginning any demolition work, survey the site and examine the drawings and specifications to determine the extent of the work. Record existing conditions in the presence of the Contracting Officer or the Contracting Officer's Representative showing the condition of structures and other facilities adjacent to areas of alteration or removal.
Photographs or electronic images with a minimum resolution of 3072 x 2304 pixels, capable of a print resolution of 300 dpi, will be acceptable as a record of existing conditions. Include in the record the elevation of the top of foundation walls, finish floor elevations, possible conflicting electrical conduits, plumbing lines, alarms systems, the location and extent of existing cracks and other damage and description of surface conditions that exist prior to starting work. It is the Contractor's responsibility to verify and document all required outages which will be required during the course of work, and to note these outages on the record document. Submit survey results to the Contracting Officer or the Contracting Officer's Representative.
PART 2 PRODUCTS
2.1 FILL MATERIAL
a. Comply with specification 31 00 00.00 06 EARTHWORK forexcavating, backfilling, and compacting procedures for soils used as backfill material to fill basements, voids, depressions or excavations resulting from demolition of structures.
PART 3 EXECUTION
3.1 EXISTING FACILITIES TO BE REMOVED
Inspect and evaluate existing structures onsite for reuse. Disassemble existing construction scheduled to be removed for reuse. Dismantled and removed materials are to be separated, set aside, and prepared as specified, and stored or delivered to a collection point for reuse, remanufacture, recycling, or other disposal, as specified. Designate materials for reuse onsite whenever possible.
SECTION 02 41 00 Page 6
3.1.1 Structures
a. Remove existing structures indicated to be removed to 2 feet below grade. Remove sidewalks, curbs, gutters and street light bases as indicated.
d. Building, or the remaining portions thereof, not exceeding 80 feet in height may be demolished by the mechanical method of demolition.
3.1.2 Utilities and Related Equipment
3.1.2.1 General Requirements
Do not interrupt existing utilities serving occupied or used facilities, except when authorized in writing by the Contracting Officer. Do not interrupt existing utilities serving facilities occupied and used by the Government except when approved in writing and then only after temporary utility services have been approved and provided. Do not begin demolition work until all utility disconnections have been made. Shut off and cap utilities for future use, as indicated.
Complete utility demolition in accordance with American Water Specifications 33 31 00.13-5 and 33 11 00.19. Specifications located at:
https://www.amwater.com/corp/products-services/military-services/wright-patterson-air-force-base
3.1.2.2 Disconnecting Existing Utilities
Remove existing utilities , as indicated and terminate in a manner conforming to the nationally recognized code covering the specific utility and approved by the Contracting Officer. When utility lines are encountered but are not indicated on the drawings, notify the Contracting Officer prior to further work in that area. Remove meters and related equipment and deliver to a location in accordance with instructions of the Contracting Officer.
3.1.3 Chain Link Fencing
Remove chain link fencing, gates and other related salvaged items scheduled for removal and transport to designated areas. Cut chain link fabric to 25 foot lengths and store in rolls off the ground.
3.1.4 Paving and Slabs
Remove sawcut concrete and asphaltic concrete paving and slabs as indicated to the depth shown on the plans. Provide neat sawcuts at limits of pavement removal as indicated. Move, grind and store pavement and slabs designated to be recycled and utilized in this project as directed by the Contracting Officer. Remove pavement and slabs not to be used in this project from the installation at Contractor's expense.
3.1.5 Air Conditioning Equipment
Remove air conditioning, refrigeration, and other equipment containing refrigerants without releasing chlorofluorocarbon refrigerants to the atmosphere in accordance with the Clean Air Act Amendment of 1990.
3.1.6 Cylinders and Canisters
Remove all fire suppression system cylinders and canisters and dispose of
SECTION 02 41 00 Page 7 in accordance with the paragraph entitled "Disposal of Ozone Depleting Substance (ODS)."
3.1.7 Electrical Equipment and Fixtures
Salvage motors, motor controllers, and operating and control equipment that are attached to the driven equipment. Salvage wiring systems and components. Box loose items and tag for identification. Disconnect primary, secondary, control, communication, and signal circuits at the point of attachment to their distribution system.
3.1.7.1 Fixtures
Remove and salvage electrical fixtures. Salvage unprotected glassware from the fixture and salvage separately. Salvage incandescent, mercury-vapor, and fluorescent lamps and fluorescent ballasts manufactured prior to 1978, boxed and tagged for identification, and protected from breakage.
3.1.7.2 Electrical Devices
Remove and salvage switches, switchgear, transformers, conductors including wire and nonmetallic sheathed and flexible armored cable, regulators, meters, instruments, plates, circuit breakers, panelboards, outlet boxes, and similar items. Box and tag these items for identification according to type and size.
3.1.7.3 Wiring Ducts or Troughs
Remove and salvage wiring ducts or troughs. Dismantle plug-in ducts and wiring troughs into unit lengths. Remove plug-in or disconnecting devices from the busway and store separately.
3.1.7.4 Conduit and Miscellaneous Items
Salvage conduit except where embedded in concrete or masonry. Consider corroded, bent, or damaged conduit as scrap metal. Sort straight and undamaged lengths of conduit according to size and type. Classify supports, knobs, tubes, cleats, and straps as debris to be removed and disposed.
3.2 CONCURRENT EARTH-MOVING OPERATIONS
Do not begin excavation, filling, and other earth-moving operations that are sequential to demolition work in areas occupied by structures to be demolished until all demolition in the area has been completed and debris removed. Fill holes, open basements and other hazardous openings.
3.3 DISPOSITION OF MATERIAL
3.3.1 Title to Materials
All materials and equipment removed and not reused or salvaged, become the property of the Contractor and must be removed from Government property. Materials approved for storage by the Contracting Officer must be removed before completion of the contract. Title to materials resulting from demolition, and materials and equipment to be removed, is vested in the Contractor upon approval by the Contracting Officer. The Government will not be responsible for the condition or loss of, or damage
SECTION 02 41 00 Page 8 to, such property after contract award. Showing for sale or selling materials and equipment on site is prohibited.
3.3.2 Reuse of Materials and Equipment
Remove and store materials and equipment indicated on the plans to be reused or relocated to prevent damage, and reinstall as the work progresses. Coordinate the re-use of materials and equipment with the re-use requirements in accordance with Section 01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL. Capture re-use of materials in the diversion calculations for the project.
3.3.3 Unsalvageable and Non-Recyclable Material
Dispose of unsalvageable and non-recyclable noncombustible material in an approved landfill.
3.4 CLEANUP
Remove debris and rubbish from project site and similar excavations.
Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply local regulations regarding hauling and disposal.
3.5 DISPOSAL OF REMOVED MATERIALS
3.5.1 Regulation of Removed Materials
Dispose of debris, rubbish, scrap, and other nonsalvageable materials resulting from removal operations with all applicable federal, state and local regulations as contractually specified in the Waste Management Plan .
Storage of removed materials on the project site is prohibited.
3.5.2 Burning on Government Property
Burning of materials removed from demolished and deconstructed structures will not be permitted on Government property .
3.5.3 Removal to Spoil Areas on Government Property
Transport noncombustible materials removed from demolition structures to state certified landfill.
3.5.4 Removal from Government Property
Transport waste materials removed from demolished and deconstructed structures, except waste soil, from Government property for legal disposal. Surplus soil must be handled according to Specification 01 57
19.00 06.
3.6 REUSE OF SALVAGED ITEMS
Recondition salvaged materials and equipment designated for reuse before installation. Replace items damaged during removal and salvage operations or restore them as necessary to usable condition.
-- End of Section --
SECTION 02 41 00 Page 9
SECTION TABLE OF CONTENTS
DIVISION 03 - CONCRETE
SECTION 03 30 00
CAST-IN-PLACE CONCRETE
02/19
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.3 SUBMITTALS
1.4 MODIFICATION OF REFERENCES
1.5 DELIVERY, STORAGE, AND HANDLING
1.5.1 Reinforcement
1.6 QUALITY ASSURANCE
1.6.1 Design Data
1.6.1.1 Concrete Mix Design
1.6.2 Shop Drawings
1.6.2.1 Reinforcing Steel
1.6.3 Control Submittals
1.6.3.1 Pumping Concrete
1.6.3.2 Safety Data Sheets
1.6.4 Test Reports
1.6.4.1 Fly Ash and Pozzolan
1.6.4.2 Slag Cement
1.6.4.3 Aggregates
1.6.5 Quality Control Plan
1.6.6 Quality Control Personnel Certifications
1.6.6.1 Quality Manager Qualifications
1.6.6.2 Field Testing Technician and Testing Agency
1.6.7 Laboratory Qualifications for Concrete Qualification Testing
1.6.8 Laboratory Accreditation
1.7 ENVIRONMENTAL REQUIREMENTS
1.7.1 Submittals for Environmental Performance
1.8 SUSTAINABLE DESIGN REQUIREMENTS
1.8.1 Local/Regional Materials
PART 2 PRODUCTS
2.1 FORMWORK MATERIALS
2.1.1 Wood Forms
2.1.1.1 Concrete Form Plywood (Standard Rough)
2.1.1.2 Overlaid Concrete Form Plywood (Standard Smooth)
2.1.2 Plastic Forms
2.1.3 Carton Forms
2.1.4 Steel Forms
2.2 FORMWORK ACCESSORIES
2.2.1 Form Ties
2.2.2 Waterstops
2.2.2.1 PVC Waterstop
2.2.2.2 Rubber Waterstop
2.2.2.3 Thermoplastic Elastomeric Rubber Waterstop
SECTION 03 30 00 Page 1
2.2.2.4 Hydrophilic Waterstop
2.2.3 Biodegradable Form Release Agent
2.2.4 Chamfer Materials
2.2.5 Construction and movement joints
2.2.6 Perimeter Insulation
2.2.7 Other Embedded items
2.3 CONCRETE MATERIALS
2.3.1 Cementitious Materials
2.3.1.1 Portland Cement
2.3.1.2 Blended Cements
2.3.1.3 Fly Ash
2.3.1.4 Slag cement
2.3.1.5 Silica Fume
2.3.1.6 Other Supplementary Cementitious Materials
2.3.2 Water
2.3.3 Aggregate
2.3.3.1 Normal-Weight Aggregate
2.3.3.2 Recycled Aggregate Materials
2.3.4 Admixtures
2.4 MISCELLANEOUS MATERIALS
2.4.1 Concrete Curing Materials
2.4.2 Nonshrink Grout
2.4.3 Floor Finish Materials
2.4.3.1 Liquid Chemical Floor Hardeners and Sealers
2.4.4 Expansion/Contraction Joint Filler
2.4.5 Joint Sealants
2.4.5.1 Horizontal Surfaces, 3 Percent Slope, Maximum
2.4.5.2 Vertical Surfaces Greater Than 3 Percent Slope
2.4.5.3 Preformed Polychloroprene Elastomeric Type
2.4.5.4 Lubricant for Preformed Compression Seals
2.4.6 Vapor Barrier
2.5 CONCRETE MIX DESIGN
2.5.1 Properties and Requirements
2.5.2 Durability
2.5.2.1 Alkali-Aggregate Reaction
2.5.2.2 Freezing and Thawing Resistance
2.5.2.3 Corrosion and Chloride Content
2.5.2.4 Sulfate Resistance
2.5.2.5 Concrete Temperature
2.5.2.6 Concrete permeability
2.5.3 Trial Mixtures
2.5.4 Ready-Mix Concrete
2.6 REINFORCEMENT
2.6.1 Reinforcing Bars
2.6.1.1 Headed Reinforcing Bars
2.6.1.2 Bar Mats
2.6.1.3 Headed Shear Stud Reinforcement
2.6.2 Mechanical Reinforcing Bar Connectors
2.6.3 Reinforcing Bar Supports
2.6.4 Dowels for Load Transfer in Floors
PART 3 EXECUTION
3.1 EXAMINATION
3.2 PREPARATION
3.2.1 General
3.2.2 Subgrade Under Foundations and Footings
3.2.3 Subgrade Under Slabs on Ground
3.2.4 Edge Forms and Screed Strips for Slabs
SECTION 03 30 00 Page 2
3.2.5 Reinforcement and Other Embedded Items
3.3 FORMS
3.3.1 Coating
3.3.2 Reshoring
3.3.3 Reuse
3.3.4 Forms for Standard Rough Form Finish
3.3.5 Tolerances for Form Construction
3.3.6 Removal of Forms and Supports
3.3.7 Strength of Concrete Required for Removal of Formwork
3.4 WATERSTOP INSTALLATION AND SPLICES
3.4.1 PVC Waterstop
3.4.2 Rubber Waterstop
3.4.3 Thermoplastic Elastomeric Rubber Waterstop
3.4.4 Hydrophilic Waterstop
3.5 PLACING REINFORCEMENT AND MISCELLANEOUS MATERIALS
3.5.1 General
3.5.2 Vapor Barrier
3.5.3 Perimeter Insulation
3.5.4 Reinforcement Supports
3.5.5 Splicing
3.5.6 Future Bonding
3.5.7 Setting Miscellaneous Material
3.5.8 Fabrication
3.5.9 Placing Reinforcement
3.5.10 Spacing of Reinforcing Bars
3.5.11 Concrete Protection for Reinforcement
3.5.12 Welding
3.6 BATCHING, MEASURING, MIXING, AND TRANSPORTING CONCRETE
3.6.1 Measuring
3.6.2 Mixing
3.6.3 Transporting
3.7 PLACING CONCRETE
3.7.1 Footing Placement
3.7.2 Pumping
3.7.3 Cold Weather
3.7.4 Hot Weather
3.7.5 Bonding
3.8 WASTE MANAGEMENT
3.8.1 Mixing Equipment
3.8.2 Reinforcing Steel
3.8.3 Other Waste
3.9 SURFACE FINISHES EXCEPT FLOOR, SLAB, AND PAVEMENT FINISHES
3.9.1 Defects
3.9.2 Not Against Forms (Top of Walls)
3.9.3 Formed Surfaces
3.9.3.1 Tolerances
3.9.3.2 As-Cast Rough Form
3.9.3.3 Standard Smooth Finish
3.10 FLOOR, SLAB, AND PAVEMENT FINISHES AND MISCELLANEOUS CONSTRUCTION
3.10.1 Finish
3.10.1.1 Scratched
3.10.1.2 Floated
3.10.1.3 Steel Troweled
3.10.1.4 Nonslip Finish
3.10.1.5 Broomed
3.10.1.6 Pavement
3.10.1.7 Concrete Toppings Placement
3.10.2 Flat Floor Finishes
3.10.2.1 Measurement of Floor Tolerances
SECTION 03 30 00 Page 3
3.10.2.2 Remedies for Out of Tolerance Work
3.10.3 Concrete Walks
3.10.4 Pits and Trenches
3.10.5 Curbs
3.10.6 Splash Blocks
3.11 JOINTS
3.11.1 Construction Joints
3.11.1.1 Maximum Allowable Construction Joint Spacing
3.11.1.2 Construction Joints for Constructability Purposes
3.11.2 Isolation Joints in Slabs on Ground
3.11.3 Contraction Joints in Slabs on Ground
3.11.4 Sealing Joints in Slabs on Ground
3.12 CONCRETE FLOOR TOPPING
3.12.1 Standard Floor Topping
3.12.1.1 Preparations Prior to Placing
3.12.1.2 Placing
3.12.1.3 Finishing
3.13 CURING AND PROTECTION
3.13.1 Requirements for Type III, High-Early-Strength Portland Cement
3.13.2 Curing Periods
3.13.3 Curing Formed Surfaces
3.13.4 Curing Unformed Surfaces
3.13.5 Temperature of Concrete During Curing
3.13.6 Protection from Mechanical Injury
3.13.7 Protection After Curing
3.14 FIELD QUALITY CONTROL
3.14.1 Sampling
3.14.2 Testing
3.14.2.1 Slump Tests
3.14.2.2 Temperature Tests
3.14.2.3 Compressive Strength Tests
3.14.2.4 Air Content
3.14.2.5 Unit Weight of Structural Concrete
3.14.2.6 Chloride Ion Concentration
3.14.2.7 Strength of Concrete Structure
3.14.2.8 Non-Conforming Materials
3.14.2.9 Testing Concrete Structure for Strength
3.15 REPAIR, REHABILITATION AND REMOVAL
3.15.1 Repair of Weak Surfaces
3.15.2 Failure of Quality Assurance Test Results
-- End of Section Table of Contents --
SECTION 03 30 00 Page 4
SECTION 03 30 00
CAST-IN-PLACE CONCRETE
02/19
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN CONCRETE INSTITUTE (ACI)
ACI 117 (2010; Errata 2011) Specifications for Tolerances for Concrete Construction and Materials and Commentary
ACI 121R (2008) Guide for Concrete Construction Quality Systems in Conformance with ISO
ACI 301 (2016) Specifications for Structural Concrete
ACI 302.1R (2015) Guide for Concrete Floor and Slab Construction
ACI 304.2R (2017) Guide to Placing Concrete by Pumping Methods
ACI 304R (2000; R 2009) Guide for Measuring, Mixing, Transporting, and Placing Concrete
ACI 305R (2010) Guide to Hot Weather Concreting
ACI 306R (2016) Guide to Cold Weather Concreting
ACI 308.1 (2011) Specification for Curing Concrete
ACI SP-2 (2007; Abstract: 10th Edition) ACI Manual of Concrete Inspection
ACI SP-15 (2011) Field Reference Manual: Standard Specifications for Structural Concrete ACI 301-05 with Selected ACI References
AMERICAN HARDBOARD ASSOCIATION (AHA)
AHA A135.4 (1995; R 2004) Basic Hardboard
AMERICAN WELDING SOCIETY (AWS)
AWS D1.4/D1.4M (2011) Structural Welding Code - Reinforcing Steel
SECTION 03 30 00 Page 5
ASTM INTERNATIONAL (ASTM)
ASTM A53/A53M (2018) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless
ASTM A184/A184M (2019) Standard Specification for Welded Deformed Steel Bar Mats for Concrete Reinforcement
ASTM A615/A615M (2020) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement
ASTM A934/A934M (2016) Standard Specification for Epoxy-Coated Prefabricated Steel Reinforcing Bars
ASTM A970/A970M (2018) Standard Specification for Headed Steel Bars for Concrete Reinforcement
ASTM A996/A996M (2016) Standard Specification for Rail-Steel and Axle-Steel Deformed Bars for Concrete Reinforcement
ASTM A1044/A1044M (2016a) Standard Specification for Steel Stud Assemblies for Shear Reinforcement of Concrete
ASTM A1064/A1064M (2017) Standard Specification for Carbon-Steel Wire and Welded Wire Reinforcement, Plain and Deformed, for Concrete
ASTM C31/C31M (2019a) Standard Practice for Making and Curing Concrete Test Specimens in the Field
ASTM C33/C33M (2018) Standard Specification for Concrete Aggregates
ASTM C39/C39M (2020) Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens
ASTM C42/C42M (2020) Standard Test Method for Obtaining and Testing Drilled Cores and Sawed Beams of Concrete
ASTM C78/C78M (2018) Standard Test Method for Flexural Strength of Concrete (Using Simple Beam with Third-Point Loading)
ASTM C94/C94M (2020) Standard Specification for Ready-Mixed Concrete
ASTM C138/C138M (2017a) Standard Test Method for Density (Unit Weight), Yield, and Air Content (Gravimetric) of Concrete
SECTION 03 30 00 Page 6
ASTM C143/C143M (2015) Standard Test Method for Slump of Hydraulic-Cement Concrete
ASTM C150/C150M (2020) Standard Specification for Portland Cement
ASTM C172/C172M (2017) Standard Practice for Sampling Freshly Mixed Concrete
ASTM C173/C173M (2016) Standard Test Method for Air Content of Freshly Mixed Concrete by the Volumetric Method
ASTM C231/C231M (2017a) Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method
ASTM C260/C260M (2010a; R 2016) Standard Specification for Air-Entraining Admixtures for Concrete
ASTM C311/C311M (2018) Standard Test Methods for Sampling and Testing Fly Ash or Natural Pozzolans for Use in Portland-Cement Concrete
ASTM C330/C330M (2017a) Standard Specification for Lightweight Aggregates for Structural Concrete
ASTM C494/C494M (2019) Standard Specification for Chemical Admixtures for Concrete
ASTM C552 (2017; E 2018) Standard Specification for Cellular Glass Thermal Insulation
ASTM C567/C567M (2019) Determining Density of Structural Lightweight Concrete
ASTM C578 (2019) Standard Specification for Rigid, Cellular Polystyrene Thermal Insulation
ASTM C591 (2019a) Standard Specification for Unfaced Preformed Rigid Cellular Polyisocyanurate Thermal Insulation
ASTM C595/C595M (2020) Standard Specification for Blended Hydraulic Cements
ASTM C618 (2019) Standard Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete
ASTM C803/C803M (2018) Standard Test Method for Penetration Resistance of Hardened Concrete
ASTM C845/C845M (2018) Standard Specification for Expansive Hydraulic Cement
ASTM C873/C873M (2015) Standard Test Method for Compressive Strength of Concrete Cylinders
SECTION 03 30 00 Page 7
Cast in Place in Cylindrical Molds
ASTM C900 (2015) Standard Test Method for Pullout Strength of Hardened Concrete
ASTM C920 (2018) Standard Specification for Elastomeric Joint Sealants
ASTM C989/C989M (2018a) Standard Specification for Slag Cement for Use in Concrete and Mortars
ASTM C1012/C1012M (2018b) Standard Test Method for Length Change of Hydraulic-Cement Mortars Exposed to a Sulfate Solution
ASTM C1017/C1017M (2013; E 2015) Standard Specification for Chemical Admixtures for Use in Producing Flowing Concrete
ASTM C1074 (2011) Standard Practice for Estimating Concrete Strength by the Maturity Method
ASTM C1077 (2017) Standard Practice for Agencies Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Testing Agency Evaluation
ASTM C1107/C1107M (2020) Standard Specification for Packaged Dry, Hydraulic-Cement Grout (Nonshrink)
ASTM C1157/C1157M (2020) Standard Performance Specification for Hydraulic Cement
ASTM C1218/C1218M (2017) Standard Test Method for Water-Soluble Chloride in Mortar and Concrete
ASTM C1240 (2020) Standard Specification for Silica Fume Used in Cementitious Mixtures
ASTM C1260 (2014) Standard Test Method for Potential Alkali Reactivity of Aggregates (Mortar-Bar Method)
ASTM C1293 (2008; R 2015) Standard Test Method for Determination of Length Change of Concrete Due to Alkali-Silica Reaction
ASTM C1567 (2013) Standard Test Method for Potential Alkali-Silica Reactivity of Combinations of Cementitious Materials and Aggregate (Accelerated Mortar-Bar Method)
ASTM C1602/C1602M (2018) Standard Specification for Mixing Water Used in Production of Hydraulic Cement Concrete
ASTM C1778 (2016) Standard Guide for Reducing the Risk of Deleterious Alkali-Aggregate
SECTION 03 30 00 Page 8
Reaction in Concrete
ASTM D412 (2016) Standard Test Methods for Vulcanized Rubber and Thermoplastic Elastomers - Tension
ASTM D471 (2016a) Standard Test Method for Rubber Property - Effect of Liquids
ASTM D1751 (2004; E 2013; R 2013) Standard Specification for Preformed Expansion Joint Filler for Concrete Paving and Structural Construction (Nonextruding and Resilient Bituminous Types)
ASTM D1752 (2018) Standard Specification for Preformed Sponge Rubber, Cork and Recycled PVC Expansion Joint Fillers for Concrete Paving and Structural Construction
ASTM D2628 (1991; R 2016) Standard Specification for Preformed Polychloroprene Elastomeric Joint Seals for Concrete Pavements
ASTM D2835 (1989; R 2017) Standard Specification for Lubricant for Installation of Preformed Compression Seals in Concrete Pavements
ASTM D3042 (2017) Standard Test Method for Insoluble Residue in Carbonate Aggregates
ASTM D5759 (2012; R 2020) Characterization of Coal Fly Ash and Clean Coal Combustion Fly Ash for Potential Uses
ASTM D6690 (2015) Standard Specification for Joint and Crack Sealants, Hot Applied, for Concrete and Asphalt Pavements
ASTM E96/E96M (2016) Standard Test Methods for Water Vapor Transmission of Materials
ASTM E329 (2020) Standard Specification for Agencies Engaged in Construction Inspection, Testing, or Special Inspection
ASTM E1155 (2014) Standard Test Method for Determining Floor Flatness and Floor Levelness Numbers
ASTM E1643 (2018a) Standard Practice for Selection, Design, Installation, and Inspection of Water Vapor Retarders Used in Contact with Earth or Granular Fill Under Concrete Slabs
ASTM E1745 (2017) Standard Specification for Water Vapor Retarders Used in Contact with Soil or Granular Fill under Concrete Slabs
SECTION 03 30 00 Page 9
ASTM E1993/E1993M (1998; R 2020) Standard Specification for Bituminous Water Vapor Retarders Used in Contact with Soil or Granular Fill Under Concrete Slabs
CONCRETE REINFORCING STEEL INSTITUTE (CRSI)
CRSI 10MSP (2018) Manual of Standard Practice
CRSI RB4.1 (2016) Supports for Reinforcement Used in Concrete
NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY (NIST)
NIST PS 1 (2009) DOC Voluntary Product Standard PS 1-07, Structural Plywood
U.S. ARMY CORPS OF ENGINEERS (USACE)
COE CRD-C 513 (1974) Corps of Engineers Specifications for Rubber Waterstops
COE CRD-C 572 (1974) Corps of Engineers Specifications for Polyvinylchloride Waterstops
U.S. GREEN BUILDING COUNCIL (USGBC)
LEED NC (2009) Leadership in Energy and Environmental Design(tm) New Construction Rating System
1.2 DEFINITIONS
a. "Cementitious material" as used herein must include all portland cement, pozzolan, fly ash, slag cement.
b. "Exposed to public view" means situated so that it can be seen from eye level from a public location after completion of the building. A public location is accessible to persons not responsible for operation or maintenance of the building.
c. "Chemical admixtures" are materials in the form of powder or fluids that are added to the concrete to give it certain characteristics not obtainable with plain concrete mixes.
d. "Supplementary cementing materials" (SCM) include coal fly ash, slag cement, natural or calcined pozzolans, and ultra-fine coal ash when used in such proportions to replace the portland cement that result in improvement to sustainability and durability and reduced cost.
e. "Design strength" (f'c) is the specified compressive strength of concrete at time(s) specified in this section to meet structural design criteria.
f. "Mass Concrete" is any concrete system that approaches a maximum temperature of 158 degrees F within the first 72 hours of placement.
In addition, it includes all concrete elements with a section thickness of 3 feet or more regardless of temperature.
SECTION 03 30 00 Page 10
g. "Mixture proportioning" is the process of designing concrete mixture proportions to enable it to meet the strength, service life and constructability requirements of the project while minimizing the initial and life-cycle cost.
h. "Mixture proportions" are the masses or volumes of individual ingredients used to make a unit measure (cubic meter or cubic yard) of concrete.
i. "Pozzolan" is a siliceous or siliceous and aluminous material, which in itself possesses little or no cementitious value but will, in finely divided form and in the presence of moisture, chemically react with calcium hydroxide at ordinary temperatures to form compounds possessing cementitious properties.
j. "Workability (or consistence)" is the ability of a fresh (plastic) concrete mix to fill the form/mould properly with the desired work (vibration) and without reducing the concrete's quality. Workability depends on water content, chemical admixtures, aggregate (shape and size distribution), cementitious content and age (level of hydration).
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Quality Control Plan; G
Quality Control Personnel Certifications
Quality Control Organizational Chart
Laboratory Accreditation
Maturity Method Data
SD-02 Shop Drawings
Reinforcing Steel; G , AE
SD-03 Product Data
Joint Sealants; ( LEED NC)
Joint Filler; ( LEED NC)
Formwork Materials
Recycled Aggregate Materials; ( LEED NC)
Cementitious Materials; ( LEED NC)
SECTION 03 30 00 Page 11
Vapor Barrier
Concrete Curing Materials
Reinforcement; ( LEED NC)
Liquid Chemical Floor Hardeners and Sealers
Admixtures
Waterstops
Local/Regional Materials; ( LEED NC)
Biodegradable Form Release Agent
Pumping Concrete Nonshrink Grout
SD-05 Design Data
Concrete Mix Design; G , RO
SD-06 Test Reports
Concrete Mix Design; G , RO
Testing and Inspection for CQC;,G RO
Fly Ash
Pozzolan
Slag Cement
Aggregates
Tolerance Report Compressive Strength Tests Unit Weight of Structural Concrete Chloride Ion Concentration Air Content Slump Tests
Water
SD-07 Certificates
Reinforcing Bars
Safety Data Sheets
Forest Stewardship Council (FSC) Certification
Field Testing Technician and Testing Agency
SD-08 Manufacturer's Instructions
SECTION 03 30 00 Page 12
Liquid Chemical Floor Hardeners and Sealers
Joint Sealants; ( LEED NC)
Curing Compound
1.4 MODIFICATION OF REFERENCES
Accomplish work in accordance with ACI publications except as modified herein. Consider the advisory or recommended provisions to be mandatory.
Interpret reference to the "Building Official," the "Structural Engineer," and the "Architect/Engineer" to mean the Contracting Officer.
1.5 DELIVERY, STORAGE, AND HANDLING
Follow ACI 301 , ACI 304R and ASTM A934/A934M requirements and recommendations. Do not deliver concrete until vapor retarder, vapor barrier, forms, reinforcement, embedded items, and chamfer strips are in place and ready for concrete placement. Do not store concrete curing compounds or sealers with materials that have a high capacity to adsorb volatile organic compound (VOC) emissions. Do not store concrete curing compounds or sealers in occupied spaces.
1.5.1 Reinforcement
Store reinforcement of different sizes and shapes in separate piles or racks raised above the ground to avoid excessive rusting. Protect from contaminants such as grease, oil, and dirt. Ensure bar sizes can be accurately identified after bundles are broken and tags removed.
1.6 QUALITY ASSURANCE
1.6.1 Design Data
1.6.1.1 Concrete Mix Design
Sixty days minimum prior to concrete placement, submit a mix design for each strength and type of concrete. Submit a complete list of materials including type; brand; source and amount of cement, supplementary cementitious materials, and admixtures; and applicable reference specifications. Submit mill test and all other test for cement, supplementary cementitious materials, aggregates, and admixtures. Provide documentation of maximum nominal aggregate size, gradation analysis, percentage retained and passing sieve, and a graph of percentage retained verses sieve size. Provide mix proportion data using at least three different water-cementitious material ratios for each type of mixture, which produce a range of strength encompassing those required for each type of concrete required. If source material changes, resubmit mix proportion data using revised source material. Provide only materials that have been proven by trial mix studies to meet the requirements of this specification, unless otherwise approved in writing by the Contracting Officer. Indicate clearly in the submittal where each mix design is used when more than one mix design is submitted. Resubmit data on concrete components if the qualities or source of components changes.
For previously approved concrete mix designs used within the past twelve months, the previous mix design may be re-submitted without further trial batch testing if accompanied by material test data conducted within the last six months. Obtain mix design approval from the contracting officer
SECTION 03 30 00 Page 13 prior to concrete placement.
1.6.2 Shop Drawings
1.6.2.1 Reinforcing Steel
Indicate bending diagrams, assembly diagrams, splicing and laps of bars, shapes, dimensions, and details of bar reinforcing, accessories, and concrete cover. Do not scale dimensions from structural drawings to determine lengths of reinforcing bars. Reproductions of contract drawings are unacceptable.
1.6.3 Control Submittals
1.6.3.1 Pumping Concrete
Submit proposed materials and methods for pumping concrete. Submittal must include mix designs, pumping equipment including type of pump and size and material for pipe, and maximum length and height concrete is to be pumped.
1.6.3.2 Safety Data Sheets
Submit Safety Data Sheets (SDS) for all materials that are regulated for hazardous health effects. SDS must be readily accessible during each work shift to employees when they are at the construction site.
1.6.4 Test Reports
1.6.4.1 Fly Ash and Pozzolan
Submit test results in accordance with ASTM C618 for fly ash and pozzolan. Submit test results performed within 6 months of submittal date.
1.6.4.2 Slag Cement
Submit test results in accordance with ASTM C989/C989M for slag cement.
Submit test results performed within 6 months of submittal date.
1.6.4.3 Aggregates
Submit test results in accordance with ASTM C33/C33M, or ASTM C330/C330M for lightweight aggregate, and ASTM C1293 or ASTM C1567 as required in the paragraph titled ALKALI-AGGREGATE REACTION.
1.6.5 Quality Control Plan
Develop and submit for approval a concrete quality control program in accordance with the guidelines of ACI 121R and as specified herein. The plan must include approved laboratories. Provide direct oversight for the concrete qualification program inclusive of associated sampling and testing. All quality control reports must be provided to the Contracting Officer, Quality Manager and Concrete Supplier. Maintain a copy of ACI SP-15 and CRSI 10MSP at project site.
1.6.6 Quality Control Personnel Certifications
The Contractor must submit for approval the responsibilities of the various quality control personnel, including the names and qualifications
SECTION 03 30 00 Page 14 of the individuals in those positions and a quality control organizational chart defining the quality control hierarchy and the responsibility of the various positions. Quality control personnel must be employed by the Contractor.
Submit American Concrete Institute certification for the following:
a. CQC personnel responsible for inspection of concrete operations.
b. Lead Foreman or Journeyman of the Concrete Placing, Finishing, and Curing Crews.
c. Field Testing Technicians: ACI Concrete Field Testing Technician, Grade I.
1.6.6.1 Quality…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .