W912QR23R0033_Specs_Vol2-0000.pdf
PDF 4 MB Posted
- Attached to
- SRM WPAFB AFRL Rapid Reaction Lab
- Solicitation number
- W912QR23R0033
About this file
This solicitation is for the renovation of the Rapid Reaction Laboratory at Wright-Patterson Air Force Base in Ohio. The estimated construction cost is between $5 million and $10 million. The project requires compliance with FAR 36.204 and has a NAICS code of 236220 for commercial and institutional building construction with a size standard of $45 million. This is a full and open procurement that requires a 10% price evaluation for HUBZone small businesses in accordance with FAR 19.1307. Technical questions must be submitted through ProjNet by the specified date. Site visits will be conducted in accordance with FAR 52.236-27 ALT 1. The solicitation includes specifications for renovations to the laboratory facility in two volumes, with details on products, services, and construction requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation For B652 Renovation Rapid Reaction Laboratory WPAFB, Dayton, OH
P2: 495449
Design-Bid-Build
Specifications - Vol. 2 of 2 Certified Final Design
03 May 2023
W912QR23R0033
ARIMS: 200A
Disposition: Maintain for 15yrs after construction
W912QR23R0033_Specs_Vol2-0000
CERTIFIED FINAL
P2# 495449 DBB B652 Renovation Rapid Reaction Laboratory
Wright-Patterson AFB, Ohio
PROJECT TABLE OF CONTENTS
Volume 1
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 80 00.00 06 SPECIAL PROVISIONS
00 80 00.00 06-A SUBMITTAL REGISTER
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 32 01.00 06 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26.00 06 GOVERNMENT SAFETY REQUIREMENTS
01 35 43 GENERAL ENVIRONMENTAL PROTECTION REQUIREMENTS (WPAFB)
01 35 43-A HAZARDOUS MATERIALS REPORT Oct 2020
01 35 43-B RAPID REACTION LAB ACM MASTIC REPORT Jun 2023
01 35 43-C HAZARDOUS MATERIALS TESTING April 2023
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 04.10 06 CONTRACTOR QUALITY CONTROL
01 45 35 SPECIAL INSPECTIONS
01 46 00.00 06 TOTAL BUILDING COMMISSIONING
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 23 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
DIVISION 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION 04 - MASONRY
04 20 00 UNIT MASONRY
DIVISION 05 - METALS
05 12 00 STRUCTURAL STEEL
05 30 00 STEEL DECKS
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 51 00 METAL STAIRS
05 52 00 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
06 20 00 FINISH CARPENTRY
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 60 00 FLASHING AND SHEET METAL
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 31 00 ACCESS DOORS AND PANELS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
DIVISION 09 - FINISHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 51 00 ACOUSTICAL CEILINGS
09 65 00 RESILIENT FLOORING
09 67 23.14 CHEMICAL RESISTANT RESINOUS FLOORING
09 90 00 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 14 00.20 INTERIOR SIGNAGE
10 22 26.13 ACCORDION FOLDING PARTITIONS
10 26 00 WALL AND DOOR PROTECTION
10 56 13 STEEL SHELVING
DIVISION 11 - EQUIPMENT
11 11 37 ELECTRIC VEHICLE SUPPLY EQUIPMENT
11 53 00 LABORATORY EQUIPMENT AND FUMEHOODS
11 70 00 GENERAL REQUIREMENTS FOR MEDICAL AND DENTAL EQUIPMENT
11 72 13 MEDICAL EQUIPMENT, MISCELLANEOUS
DIVISION 12 - FURNISHINGS
12 31 00 MANUFACTURED METAL CASEWORK
12 36 00 COUNTERTOPS
Volume 2
DIVISION 21 - FIRE SUPPRESSION
21 13 13 WET PIPE SPRINKLER SYSTEMS, FIRE PROTECTION
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
22 60 70 GAS AND VACUUM SYSTEMS FOR LABORATORY FACILITIES
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 01 30.41 HVAC SYSTEM CLEANING
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 15 COMMON PIPING FOR HVAC
23 05 93.00 06 TESTING, ADJUSTING, AND BALANCING (TAB) OF HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC
23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING CONTROL
SYSTEMS
23 25 00 CHEMICAL TREATMENT OF WATER FOR MECHANICAL SYSTEMS
23 30 00 HVAC AIR DISTRIBUTION
23 51 43.01 20 MECHANICAL CYCLONE DUST COLLECTOR OF FLUE GAS PARTICULATES
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS
25 08 10 UTILITY MONITORING AND CONTROL SYSTEM TESTING
25 10 10 UTILITY MONITORING AND CONTROL SYSTEM (UMCS) FRONT END AND INTEGRATION
DIVISION 26 - ELECTRICAL
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 41 00 LIGHTNING PROTECTION SYSTEM
26 51 00 INTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
DIVISION 31 - EARTHWORK
31 00 00.00 06 EARTHWORK
DIVISION 33 - UTILITIES
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
-- End of Project Table of Contents --
SECTION 21 13 13
WET PIPE SPRINKLER SYSTEMS, FIRE PROTECTION
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)
ASME B16.1 (2020) Gray Iron Pipe Flanges and Flanged Fittings Classes 25, 125, and 250
ASME B16.3 (2021) Malleable Iron Threaded Fittings, Classes 150 and 300
ASME B16.4 (2021) Gray Iron Threaded Fittings;
Classes 125 and 250
ASME B16.21 (2021) Nonmetallic Flat Gaskets for Pipe Flanges
ASTM INTERNATIONAL (ASTM)
ASTM A47/A47M (1999; R 2018; E 2018) Standard Specification for Ferritic Malleable Iron Castings
ASTM A53/A53M (2020) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless
ASTM A135/A135M (2021) Standard Specification for Electric-Resistance-Welded Steel Pipe
ASTM A153/A153M (2016a) Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware
ASTM A183 (2014; R 2020) Standard Specification for Carbon Steel Track Bolts and Nuts
ASTM A536 (1984; R 2019; E 2019) Standard Specification for Ductile Iron Castings
FM GLOBAL (FM)
FM APP GUIDE (updated on-line) Approval Guide http://www.approvalguide.com/
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 13 (2022; ERTA 1 2021) Standard for the
SECTION 21 13 13 Page 1
Installation of Sprinkler Systems
NFPA 291 (2022) Recommended Practice for Fire Flow Testing and Marking of Hydrants
NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES
(NICET)
NICET 1014-7 (2012) Program Detail Manual for Certification in the Field of Fire Protection Engineering Technology (Field Code 003) Subfield of Automatic Sprinkler System Layout
UNDERWRITERS LABORATORIES (UL)
UL 199 (2020) UL Standard for Safety Automatic Sprinklers for Fire-Protection Service
UL Fire Prot Dir Fire Protection Equipment Directory (updated online)
1.2 SYSTEM DESCRIPTION
Provide wet pipe sprinkler system(s) in areas indicated on the drawings.
Except as modified herein, the system must meet the requirements of NFPA 13 .
Pipe sizes which are not indicated on the Contract drawings must be determined by hydraulic calculations.
1.2.1 Hydraulic Design
1.2.1.1 Basis for Calculations
A waterflow test was performed on July 27, 2021 at the hydrant nearest the existing sprinkler tie-in while flowing the hydrant in front of the B20652 parking area. It resulted in a static pressure of 91 psi with a residual pressure of 89 psi while flowing 475 gpm. It is believed that there is an issue with the hydrant used for flow and it has been indicated to the base.
Perform a fire hydrant flow test prior to Hydraulic Calculations submittal, if required, in accordance with NFPA 291 . Results must include hydrant elevations relative to the building and hydrant number/identifiers for the tested hydrants, including which were flowed, which had a gauge.
If the issue with the other hydrant has not been corrected, use different test hydrants. This information must be presented in a tabular form if multiple hydrants were flowed. The results must be included with the hydraulic calculations. Hydraulic calculations must be based on flow test noted in this paragraph, unless approved by Contracting Officer.
Hydraulic calculations must be based upon the Hazen-Williams formula with a "C" value noted in NFPA 13 for piping, and 120 for existing underground piping.
1.2.1.2 Hydraulic Calculations
a. Hydraulic calculations are not required if the number of new sprinklers (not including those swapped out in a ceiling, using the existing outlets) does not exceed 20 sprinklers. If hydraulic calculations are not provided, then pipe sizing is to be consistent with the pipe schedule method.
SECTION 21 13 13 Page 2
b. Water supply curves and system requirements must be plotted on semi-logarithmic graph (N^1.85) paper so as to present a summary of the complete hydraulic calculation.
c. Provide a summary sheet listing sprinklers in the design area and their respective hydraulic reference points, elevations, minimum discharge pressures and minimum flows. Elevations of hydraulic reference points (nodes) must be indicated.
d. Documentation must identify each pipe individually and the nodes connected thereto. Indicate the diameter, length, flow, velocity, friction loss, number and type fittings, total friction loss in the pipe, equivalent pipe length and Hazen-Williams coefficient for each pipe.
e. Where the sprinkler system is supplied by interconnected risers, the sprinkler system must be hydraulically calculated using the hydraulically most demanding single riser. The calculations must not assume the simultaneous use of more than one riser.
f. All calculations must include the backflow preventer manufacturer's stated friction loss at the design flow or 8 psi for double check backflow preventer, whichever is greater.
g. All calculations must be performed back to the actual location of the flow test, taking into account the direction of flow in the service main at the test location.
h. For gridded systems, calculations must show peaking of demand area friction loss to verify that the hydraulically most demanding area is being used. A flow diagram indicating the quantity and direction of flows must be included.
1.2.1.3 Design Criteria
Hydraulically design the system, if hydraulic calculations are required per above, to discharge a minimum density of 0.20 gpm/square foot over the hydraulically most demanding 2,500 square feet of floor area. Hydraulic calculations must be in accordance with the Area/Density Method of NFPA 13 .
Add an allowance for exterior hose streams of 500 gpm to the sprinkler system demand at the point of connection to the existing water system.
1.2.2 Sprinkler Coverage
Sprinklers must be uniformly spaced on branch lines. Provide coverage throughout 100 percent of the area noted on the Contract drawings.
Coverage per sprinkler must be in accordance with NFPA 13 . Provide sprinklers below all obstructions in accordance with NFPA 13 .
1.3 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Partial submittals and submittals not fully complying with NFPA 13 and this specification section must be returned disapproved without review. SD-02, SD-03 and SD-05 must be submitted simultaneously.
SECTION 21 13 13 Page 3
Shop drawings (SD-02), product data (SD-03) and calculations (SD-05) must be prepared by the designer and combined and submitted as one complete package.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Sprinkler System Designer; G
Sprinkler System Installer; G
SD-02 Shop Drawings
Shop Drawing; G
SD-03 Product Data
Pipe; G
Fittings; G
Sprinklers ; G
Pipe Hangers and Supports ; G SD-05 Design Data
Hydraulic Calculations; G
SD-06 Test Reports
Test Procedures; G
SD-07 Certificates
Verification of Compliant Installation; G
Request for Government Final Test; G
SD-11 Closeout Submittals
As-built drawings
1.4 QUALITY ASSURANCE
1.4.1 Preconstruction Submittals
Within 36 days of contract award but no less than 14 days prior to commencing work on site, the prime Contractor must submit the following for review and approval. SD-02, SD-03 and SD-05 submittals received prior to the review and approval of the qualifications will be returned Disapproved Without Review.
1.4.1.1 Shop Drawing
An electronic copy of the shop drawings, no later than 28 days prior to the start of system installation. Working drawings conforming to the requirements prescribed in NFPA 13 and must be no smaller than the
SECTION 21 13 13 Page 4
Contract Drawings. Each set of drawings must include the following:
a. A descriptive index with drawings listed in sequence by number. A legend sheet identifying device symbols, nomenclature, and conventions used in the package.
b. Floor plans drawn to a scale not less than 1/8-inch equals 1-foot clearly showing locations of tie into existing piping, all new piping and sprinklers and existing piping as necessary to verify hydraulic calculations, if required.
c. For new sprinkler locations, actual center-to-center dimensions between sprinklers on branch lines and between branch lines; from end sprinklers to adjacent walls; from walls to branch lines; from sprinkler feed mains, cross mains and branch lines to finished floor and roof or ceiling. A detail must show the dimension from the sprinkler and sprinkler deflector to the ceiling in finished areas.
h. Details of each type of pipe hanger and related components.
1.4.1.2 Product Data
An electronic copy of annotated catalog data to show the specific model, type, and size of each item. Catalog cuts must also indicate the NRTL listing. The data must be highlighted to show model, size, options, and other pertinent information, that are intended for consideration. Data must be adequate to demonstrate compliance with all contract requirements. Product data for all equipment must be combined into a single submittal.
1.4.1.3 Hydraulic Calculations
Where required, calculations must be as outlined in NFPA 13 except that calculations must be performed by computer using software intended specifically for fire protection system design using the design data shown on the drawings.
1.4.2 Qualifications
1.4.2.1 Sprinkler System Designer
The sprinkler system designer must be certified as a Level III Technician by National Institute for Certification in Engineering Technologies (NICET) in the Water-Based Systems Layout subfield of Fire Protection Engineering Technology in accordance with NICET 1014-7 .
1.4.2.2 Sprinkler System Installer
The sprinkler system installer must be regularly engaged in the installation of the type and complexity of system specified in the contract documents, and must have served in a similar capacity for at least three systems that have performed in the manner intended for a period of not less than 6 months.
1.4.3 Regulatory Requirements
Equipment and material must be listed or approved. Listed or approved, as used in this Section, means listed, labeled or approved by a Nationally Recognized Testing Laboratory (NRTL) such as UL Fire Prot Dir or
SECTION 21 13 13 Page 5
FM APP GUIDE. The omission of these terms under the description of an item or equipment described must not be construed as waiving this requirement. All listings or approvals by testing laboratories must be from an existing ANSI or UL published standard. The recommended practices stated in the manufacturer's literature or documentation are mandatory requirements.
1.5 DELIVERY, STORAGE, AND HANDLING
Protect all equipment delivered and placed in storage from the weather, excessive humidity and temperature variations, dirt and dust, or other contaminants. All pipes must be either capped or plugged until installed.
1.6 EXTRA MATERIALS
Spare sprinklers and wrench(es) must be provided as in accordance with
NFPA 13 .
PART 2 PRODUCTS
2.1 MATERIALS AND EQUIPMENT
2.1.1 Standard Products
Provide materials, equipment, and devices listed for fire protection service when so required by NFPA 13 or this specification. Select material from one manufacturer, where possible, and not a combination of manufacturers, for a classification of material. Material and equipment must be standard products of a manufacturer regularly engaged in the manufacture of the products for at least 2 years prior to bid.
2.1.2 Identification and Marking
Pipe and fitting markings must include name or identifying symbol of manufacturer and nominal size. Pipe must be marked with ASTM designation. Valves and equipment markings must have name or identifying symbol of manufacturer, specific model number, nominal size, name of device, arrow indicating direction of flow, and position of installation (horizontal or vertical), except if valve can be installed in either position. Markings must be included on the body casting or on an etched or stamped metal nameplate permanently on the valve or cover plate.
2.1.3 Pressure Ratings
Valves, fittings, couplings, alarm switches, and similar devices must be rated for the maximum working pressures that can be experienced in the system, but in no case less than 175 psi.
2.2 ABOVEGROUND PIPING COMPONENTS
2.2.1 Steel Piping Components
2.2.1.1 Steel Pipe
Except as modified herein, steel pipe must be black as permitted by NFPA 13 and conform to the applicable provisions of ASTM A53/A53M, ASTM A135/A135M or ASTM A153/A153M .
Steel pipe must be minimum Schedule 40 for sizes 2 inches and less; and
SECTION 21 13 13 Page 6 minimum Schedule 10 for sizes larger than 2 inches. Steel piping with wall thickness less than Schedule 40 must not be threaded.
2.2.1.2 Fittings
Fittings must be welded, threaded, or grooved-end type. Threaded fittings must be cast-iron conforming to ASME B16.4 , malleable-iron conforming to ASME B16.3 or ductile-iron conforming to ASTM A536. Plain-end fittings with mechanical couplings, fittings that use steel gripping devices to bite into the pipe, steel press fittings and field welded fittings are not permitted. Fittings, mechanical couplings, and rubber gaskets must be supplied by the same manufacturer. Threaded fittings must use Teflon tape or manufacturer's approved joint compound. Saddle tees using rubber gasketed fittings are permitted only when connecting to existing piping for additions or modifications. Saddle tees must use a connection method that completely wraps around the pipe. Reducing couplings are not permitted except as allowed by NFPA 13 .
2.2.1.3 Grooved Mechanical Joints and Fittings
Joints and fittings must be designed for not less than 175 psi service and the product of the same manufacturer. Field welded fittings must not be used. Fitting and coupling housing must be malleable-iron conforming to ASTM A47/A47M, Grade 32510; ductile-iron conforming to ASTM A536, Grade 65-45-12. Rubber gasketed grooved-end pipe and fittings with mechanical couplings are permitted in pipe sizes 2 inches and larger. Gasket must be the flush type that fills the entire cavity between the fitting and the pipe. Nuts and bolts must be heat-treated steel conforming to ASTM A183 and must be cadmium-plated or zinc-electroplated.
2.2.1.4 Flanges
Flanges must conform to NFPA 13 and ASME B16.1 . Gaskets must be non-asbestos compressed material in accordance with ASME B16.21 , 1/16-inch thick, and full face or self-centering flat ring type.
2.2.2 Flexible Sprinkler Hose
The use of flexible hose is not permitted.
2.2.3 Pipe Hangers and Supports
Provide galvanized pipe hangers and supports in accordance with NFPA 13 .
2.3 SPRINKLERS
Sprinklers must comply with UL 199 and NFPA 13 . Sprinklers with internal O-rings are not acceptable. Sprinklers in high heat areas including attic spaces or in close proximity to unit heaters must have temperature classification in accordance with NFPA 13 . Extended coverage sprinklers are permitted for loading docks, residential occupancies and high-piled storage applications only.
2.3.1 Pendent Sprinkler
Pendent sprinkler must be recessed quick-response type with nominal K-factor of 8.0 for areas with new sprinkler locations, in areas where sprinklers are being swapped at the outlet in a one-for-one arrangement, the sprinkler K-factor must match the existing. Pendent sprinklers must
SECTION 21 13 13 Page 7 have a polished chrome finish. Assembly must include an integral escutcheon.
2.3.2 Upright Sprinkler
Upright sprinkler must be brass quick-response type and have a nominal K-factor of 8.0.
2.4 ACCESSORIES
2.4.1 Sprinkler Cabinet
Provide spare sprinklers in accordance with NFPA 13 and must be placed in a suitable metal or plastic cabinet of sufficient size to accommodate all the spare sprinklers and wrenches in designated locations. Spare sprinklers must be representative of, and in proportion to, the number of each type and temperature rating of the sprinklers installed as required by NFPA 13 . At least one wrench of each type required must be provided.
2.4.2 Pendent Sprinkler Escutcheon
Escutcheon must be one-piece metallic type with a depth of less than 3/4-inch and suitable for installation on pendent sprinklers. The escutcheon must have a factory finish that matches the pendent sprinkler.
2.4.3 Pipe Escutcheon
Provide split hinge metal plates for piping entering walls, floors, and ceilings in exposed spaces. Provide polished stainless steel plates or chromium-plated finish on copper alloy plates in finished spaces. Provide paint finish on metal plates in unfinished spaces.
2.4.4 Sprinkler Guard
Listed guard must be a steel wire cage designed to encase the sprinkler and protect it from mechanical damage. Guards must be provided on sprinklers located within 7 feet of the floor.
2.4.5 Identification Sign
Valve identification sign must be minimum 6 inches wide by 2 inches high with enamel baked finish on minimum 18 gage steel or 0.024-inch aluminum with red letters on a white background or white letters on red background. Wording of sign must include, but not be limited to "main drain", "auxiliary drain", "inspector's test", "alarm test", "alarm line", and similar wording as required to identify operational components. Where there is more than one sprinkler system, signage must include specific details as to the respective system.
PART 3 EXECUTION
3.1 VERIFYING ACTUAL FIELD CONDITIONS
Before commencing work, examine all adjoining work on which the contractor's work that is dependent for perfect workmanship according to the intent of this specification section, and report to the Contracting Officer's Representative a condition that prevents performance of first class work. No "waiver of responsibility" for incomplete, inadequate or defective adjoining work will be considered unless notice has been filed
SECTION 21 13 13 Page 8 before submittal of a proposal.
3.2 INSTALLATION
The installation must be in accordance with the applicable provisions of NFPA 13 and publications referenced therein. Locate sprinklers in a consistent pattern with ceiling grid, lights, and air supply diffusers.
Install sprinkler system over and under ducts, piping and platforms when such equipment can negatively affect or disrupt the sprinkler discharge pattern and coverage.
a. Piping offsets, fittings, and other accessories required must be furnished to provide a complete installation and to eliminate interference with other construction.
b. Wherever the contractor's work interconnects with work of other trades the Contractor must coordinate with other Contractors to insure all Contractors have the information necessary so that they may properly install all necessary connections and equipment. Identify all work items needing access (dampers and similar equipment) that are concealed above hung ceilings by permanent color coded pins/tabs in the ceiling directly below the item.
c. Provide required supports and hangers for piping, conduit, and equipment so that loading will not exceed allowable loadings of structure. Submittal of a bid must be a deemed representation that the contractor submitting such bid has ascertained allowable loadings and has included in his estimates the costs associated in furnishing required supports.
3.2.1 Waste Removal
At the conclusion of each day's work, clean up and stockpile on site all waste, debris, and trash which may have accumulated during the day as a result of work by the contractor and of his presence on the job.
Sidewalks and streets adjoining the property must be kept broom clean and free of waste, debris, trash and obstructions caused by work of the contractor, which will affect the condition and safety of streets, walks, utilities, and property.
3.3 ABOVEGROUND PIPING INSTALLATION
The methods of fabrication and installation of the aboveground piping must fully comply with the requirements and recommended practices of NFPA 13 and this specification section.
3.3.1 Protection of Piping Against Earthquake Damage
Seismic restraint is not required.
3.3.2 Piping in Exposed Areas
Install exposed piping without diminishing exit access widths, corridors or equipment access. Exposed horizontal piping, including drain piping, must be installed to provide maximum headroom.
3.3.3 Piping in Finished Areas
In areas with suspended or dropped ceilings and in areas with concealed
SECTION 21 13 13 Page 9 spaces above the ceiling, piping must be concealed above ceilings. Piping must be inspected, hydrostatically tested and approved before being concealed. Risers and similar vertical runs of piping in finished areas must be concealed.
3.3.4 Pendent Sprinklers
a. Drop nipples to pendent sprinklers must consist of minimum 1-inch pipe with a reducing coupling into which the sprinkler must be threaded.
b. Where sprinklers are installed below suspended or dropped ceilings, drop nipples must be cut such that sprinkler ceiling plates or escutcheons are of a uniform depth throughout the finished space. The outlet of the reducing coupling must not extend below the underside of the ceiling.
c. Recessed pendent sprinklers must be installed such that the distance from the sprinkler deflector to the underside of the ceiling must not exceed the manufacturer's listed range and must be of uniform depth throughout the finished area.
d. Pendent sprinklers in suspended ceilings must be located in the center of the tile (plus or minus 2 inches).
3.3.5 Upright Sprinklers
Riser nipples or "sprigs" to upright sprinklers must contain no fittings between the branch line tee and the reducing coupling at the sprinkler.
3.3.6 Pipe Joints
Pipe joints must conform to NFPA 13 , except as modified herein. Not more than four threads must show after joint is made up. Welded joints will be permitted, only if welding operations are performed as required by NFPA 13 at the Contractor's fabrication shop, not at the project construction site. Flanged joints must be provided where indicated or required by NFPA 13 . Grooved pipe and fittings must be prepared in accordance with the manufacturer's latest published specification according to pipe material, wall thickness and size. Grooved couplings, fittings and grooving tools must be products of the same manufacturer. For copper tubing, pipe and groove dimensions must comply with the tolerances specified by the coupling manufacturer. The diameter of grooves made in the field must be measured using a "go/no-go" gauge, vernier or dial caliper, narrow-land micrometer, or other method specifically approved by the coupling manufacturer for the intended application. Groove width and dimension of groove from end of pipe must be measured and recorded for each change in grooving tool setup to verify compliance with coupling manufacturer's tolerances.
3.3.7 Reducers
Reductions in pipe sizes must be made with one-piece tapered reducing fittings. When standard fittings of the required size are not manufactured, single bushings of the face or hex type will be permitted.
Where used, face bushings must be installed with the outer face flush with the face of the fitting opening being reduced. Bushings cannot be used in elbow fittings, in more than one outlet of a tee, in more than two outlets of a cross, or where the reduction in size is less than 1/2-inch.
SECTION 21 13 13 Page 10
3.3.8 Pipe Penetrations
a. Cutting structural members for passage of pipes or for pipe-hanger fastenings will not be permitted. Pipes that must penetrate concrete or masonry walls or concrete floors must be core-drilled and provided with pipe sleeves. Each sleeve must be Schedule 40 galvanized steel, ductile-iron or cast-iron pipe and extend through its respective wall or floor and be cut flush with each wall surface. Sleeves must provide required clearance between the pipe and the sleeve per NFPA 13 .
The space between the sleeve and the pipe must be firmly packed with mineral wool insulation.
b. Where pipes and sleeves penetrate fire walls, fire partitions, or floors, pipes/sleeves must be firestopped in accordance with Section
07 84 00 FIRESTOPPING.
c. In penetrations that are not fire-rated or not a floor penetration, the space between the sleeve and the pipe must be sealed at both ends with plastic waterproof cement that will dry to a firm but pliable mass or with a mechanically adjustable segmented elastomer seal.
3.3.9 Escutcheons
Escutcheons must be provided for pipe penetration in finished areas of ceilings, floors and walls. Escutcheons must be securely fastened to the pipe at surfaces through which piping passes.
3.3.10 Drains
b. auxiliary drains must be provided as required by NFPA 13 . Auxiliary drains are permitted to discharge to a floor drain if the drain is sized to accommodate full flow (min 40 gpm). Discharge to service sinks or similar plumbing fixtures is not permitted.
3.3.11 Identification Signs
Signs must be affixed to each control valve, inspector test valve, main drain, auxiliary drain, test valve, and similar valves as appropriate or as required by NFPA 13 . Main drain test results must be etched into main drain identification sign. Hydraulic design data must be etched into the nameplates and permanently affixed to each sprinkler riser as specified in NFPA 13 . Provide labeling on the surfaces of all feed and cross mains to show the pipe function (e.g., "Sprinkler System", "Fire Department Connection", "Standpipe") and normal valve position (e.g. "Normally Open", "Normally Closed"). For pipe sizes 4-inch and larger provide white painted stenciled letters and arrows, a minimum of 2 inches in height and visible from at least two sides when viewed from the floor. For pipe sizes less than 4-inch, provide white painted stenciled letters and arrows, a minimum of 0.75-inch in height and visible from the floor.
3.4 PAINTING
Paint piping that is exposed to view red provide stencils or identification labels for new piping that is concealed above ceilings.
SECTION 21 13 13 Page 11
3.5 FIELD QUALITY CONTROL
3.5.1 Test Procedures
Submit detailed test procedures, prepared and signed by the NICET Level III or IV Fire Sprinkler Technician, and the representative of the installing company,30 days prior to performing system tests. Detailed test procedures must list all components of the installed system. Test procedures must include sequence of testing, time estimate for each test, and sample test data forms. The test data forms must be in a check-off format (pass/fail with space to add applicable test data; similar to the forms in NFPA 13 ). The test procedures and accompanying test data forms must be used for the pre-Government testing and the Government final testing.
a. Provide space to identify the date and time of each test. Provide space to identify the names and signatures of the individuals conducting and witnessing each test.
3.5.2 Pre-Government Testing
3.5.2.1 Verification of Compliant Installation
Conduct inspections and tests to ensure that equipment is functioning properly. Tests must meet the requirements of paragraph entitled "Minimum System Tests" and "System Acceptance" as noted in NFPA 13 . The Contractor must be in attendance at the pre-Government testing to make necessary adjustments. After inspection and testing is complete, provide a signed Verification of Compliant Installation letter by the QFPE that the installation is complete, compliant with the specification and fully operable. The letter must include the names and titles of the witnesses to the pre-Government tests. Provide all completion documentation as required by NFPA 13 and the test reports noted below.
a. NFPA 13 Aboveground Material and Test Certificate
3.5.2.2 Request for Government Final Test
When the verification of compliant installation has been completed, submit a formal request for Government final test to the Contracting Officers Designated Representative (COR). Government final testing will not be scheduled until the DFPE has received copies of the request for Government final testing and Verification of Compliant Installation letter with all required reports. Government final testing will not be performed until after the connections to the building fire alarm system have been completed and tested to confirm communications are fully functional.
Submit request for test at least 15 calendar days prior to the requested test date.
3.5.3 Correction of Deficiencies
If equipment was found to be defective or non-compliant with contract requirements, perform corrective actions and repeat the tests. Tests must be conducted and repeated if necessary until the system has been demonstrated to comply with all contract requirements.
3.5.4 Government Final Tests
The tests must be performed in accordance with the approved test
SECTION 21 13 13 Page 12 procedures in the presence of the DFPE. Furnish instruments and personnel required for the tests. The following must be provided at the job site for Government Final Testing:
a. The manufacturer's technical representative.
b. Marked-up red line drawings of the system as actually installed.
Government Final Tests will be witnessed by the Contracting Officer. At this time, all required tests noted in the paragraph "Minimum System Tests" must be repeated at their discretion.
3.6 MINIMUM SYSTEM TESTS
The system, including the underground water mains, and the aboveground piping and system components, must be tested to ensure that equipment and components function as intended. The underground and aboveground interior piping systems and attached appurtenances subjected to system working pressure must be tested in accordance with NFPA 13 .
3.6.1 Aboveground Piping
3.6.1.1 Hydrostatic Test
Aboveground piping must be hydrostatically tested in accordance with NFPA 13 . There must be no drop in gauge pressure or visible leakage when the system is subjected to the hydrostatic test. The test pressure must be read from a gauge located at the low elevation point of the system or portion being tested.
3.6.2 Main Drain Flow Test
Following flushing of the underground piping, a main drain test must be made to verify the adequacy of the water supply. Static and residual pressures must be recorded on the certificate specified in paragraph
SUBMITTALS.
3.7 SYSTEM ACCEPTANCE
Following acceptance of the system, as-built drawings and O&M manuals must be delivered to the Contracting Officer for review and acceptance. Submit six sets of detailed as-built drawings. The drawings must show the system as installed, including deviations from both the project drawings and the approved shop drawings. These drawings must be submitted within two weeks after the final acceptance test of the system. At least one set of as-built (marked-up) drawings must be provided at the time of, or prior to the final acceptance test.
a. Furnish one set of CDs or DVDs containing software back-up and CAD based drawings in latest version of AutoCAD, DXF and portable document formats of as-built drawings and schematics.
-- End of Section --
SECTION 21 13 13 Page 13
SECTION 22 00 00
PLUMBING, GENERAL PURPOSE
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)
ANSI Z21.22/CSA 4.4 (2015; R 2020) Relief Valves for Hot Water Supply Systems
AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)
ASME A112.6.1M (1997; R 2017) Floor Affixed Supports for Off-the-Floor Plumbing Fixtures for Public Use
ASME A112.6.3 (2019) Standard for Floor and Trench Drains
ASME A112.36.2M (1991; R 2017) Cleanouts
ASME B1.20.1 (2013; R 2018) Pipe Threads, General Purpose (Inch)
ASME B16.3 (2021) Malleable Iron Threaded Fittings, Classes 150 and 300
ASME B16.5 (2020) Pipe Flanges and Flanged Fittings NPS 1/2 Through NPS 24 Metric/Inch Standard
ASME B16.15 (2018) Cast Copper Alloy Threaded Fittings Classes 125 and 250
ASME B16.18 (2018) Cast Copper Alloy Solder Joint Pressure Fittings
ASME B16.21 (2016) Nonmetallic Flat Gaskets for Pipe Flanges
ASME B16.22 (2018) Standard for Wrought Copper and Copper Alloy Solder Joint Pressure Fittings
ASME B16.34 (2021) Valves - Flanged, Threaded and Welding End
ASME B16.50 (2013) Wrought Copper and Copper Alloy Braze-Joint Pressure Fittings
ASME B16.51 (2013) Copper and Copper Alloy Press-Connect Pressure Fittings
SECTION 22 00 00 Page 1
ASME B31.1 (2020) Power Piping
ASME B31.5 (2020) Refrigeration Piping and Heat Transfer Components
ASME B40.100 (2013) Pressure Gauges and Gauge Attachments
ASME BPVC SEC IX (2017; Errata 2018) BPVC Section IX-Welding, Brazing and Fusing Qualifications
AMERICAN SOCIETY OF SANITARY ENGINEERING (ASSE)
ASSE 1003 (2020) Performance Requirements for Water Pressure Reducing Valves for Domestic Water Distribution Systems - (ANSI approved 2010)
ASSE 1018 (2001; R 2021) Performance Requirements for Trap Seal Primer Valves - Potable Water Supplied (ANSI Approved 2002
AMERICAN WATER WORKS ASSOCIATION (AWWA)
AWWA B300 (2018) Hypochlorites
AWWA B301 (2018) Liquid Chlorine
AWWA C203 (2020) Coal-Tar Protective Coatings and Linings for Steel Water Pipelines - Enamel and Tape - Hot-Applied
AWWA C606 (2015) Grooved and Shouldered Joints
AWWA C651 (2014) Standard for Disinfecting Water Mains
AWWA C652 (2019) Disinfection of Water-Storage Facilities
AMERICAN WELDING SOCIETY (AWS)
AWS A5.8/A5.8M (2019) Specification for Filler Metals for Brazing and Braze Welding
AWS B2.2/B2.2M (2016) Specification for Brazing Procedure and Performance Qualification
ASTM INTERNATIONAL (ASTM)
ASTM A53/A53M (2020) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless
ASTM A74 (2021) Standard Specification for Cast Iron Soil Pipe and Fittings
ASTM A105/A105M (2021) Standard Specification for Carbon
SECTION 22 00 00 Page 2
Steel Forgings for Piping Applications
ASTM A182/A182M (2020) Standard Specification for Forged or Rolled Alloy and Stainless Steel Pipe Flanges, Forged Fittings, and Valves and Parts for High-Temperature Service
ASTM A183 (2014; R 2020) Standard Specification for Carbon Steel Track Bolts and Nuts
ASTM A193/A193M (2020) Standard Specification for Alloy-Steel and Stainless Steel Bolting Materials for High-Temperature Service and Other Special Purpose Applications
ASTM A269/A269M (2015; R 2019) Standard Specification for Seamless and Welded Austenitic Stainless Steel Tubing for General Service
ASTM A515/A515M (2017) Standard Specification for Pressure Vessel Plates, Carbon Steel, for Intermediate- and Higher-Temperature Service
ASTM A516/A516M (2017) Standard Specification for Pressure Vessel Plates, Carbon Steel, for Moderate-and Lower-Temperature Service
ASTM A536 (1984; R 2019; E 2019) Standard Specification for Ductile Iron Castings
ASTM B32 (2020) Standard Specification for Solder Metal
ASTM B88 (2020) Standard Specification for Seamless Copper Water Tube
ASTM B88M (2020) Standard Specification for Seamless Copper Water Tube (Metric)
ASTM B117 (2019) Standard Practice for Operating Salt Spray (Fog) Apparatus
ASTM B370 (2012; R 2019) Standard Specification for Copper Sheet and Strip for Building Construction
ASTM B813 (2016) Standard Specification for Liquid and Paste Fluxes for Soldering of Copper and Copper Alloy Tube
ASTM B828 (2016) Standard Practice for Making Capillary Joints by Soldering of Copper and Copper Alloy Tube and Fittings
ASTM C564 (2020a) Standard Specification for Rubber Gaskets for Cast Iron Soil Pipe and Fittings
SECTION 22 00 00 Page 3
ASTM C920 (2018) Standard Specification for Elastomeric Joint Sealants
ASTM C1053 (2000; R 2010) Standard Specification for Borosilicate Glass Pipe and Fittings for Drain, Waste, and Vent (DWV) Applications
ASTM D1784 (2020) Standard Specification for Rigid Poly(Vinyl Chloride) (PVC) Compounds and Chlorinated Poly(Vinyl Chloride) (CPVC) Compounds
ASTM D2000 (2018) Standard Classification System for Rubber Products in Automotive Applications
ASTM D2235 (2004; R 2016) Standard Specification for Solvent Cement for Acrylonitrile-Butadiene-Styrene (ABS) Plastic Pipe and Fittings
ASTM D2467 (2015) Standard Specification for Poly(Vinyl Chloride) (PVC) Plastic Pipe Fittings, Schedule 80
ASTM D2564 (2012) Standard Specification for Solvent Cements for Poly(Vinyl Chloride) (PVC) Plastic Piping Systems
ASTM D2683 (2014) Standard Specification for Socket-Type Polyethylene Fittings for Outside Diameter-Controlled Polyethylene Pipe and Tubing
ASTM D2822/D2822M (2005; R 2011; E 2011) Standard Specification for Asphalt Roof Cement, Asbestos-Containing
ASTM D2855 (2015) Standard Practice for Making Solvent-Cemented Joints with Poly(Vinyl Chloride) (PVC) Pipe and Fittings
ASTM D3035 (2015) Polyethylene (PE) Plastic Pipe (DR-PR) Based on Controlled Outside Diameter
ASTM D3122 (1995; R 2009) Solvent Cements for Styrene-Rubber (SR) Plastic Pipe and Fittings
ASTM D3138 (2004; R 2016) Standard Specification for Solvent Cements for Transition Joints Between Acrylonitrile-Butadiene-Styrene (ABS) and Poly(Vinyl Chloride) (PVC) Non-Pressure Piping Components
ASTM D3139 (2019) Joints for Plastic Pressure Pipes Using Flexible Elastomeric Seals
ASTM D3212 (2007; R 2020) Standard Specification for
SECTION 22 00 00 Page 4
Joints for Drain and Sewer Plastic Pipes Using Flexible Elastomeric Seals
ASTM D3261 (2016) Standard Specification for Butt Heat Fusion Polyethylene (PE) Plastic Fittings for Polyethylene (PE) Plastic Pipe and Tubing
ASTM D3311 (2017) Standard Specification for Drain, Waste, and Vent (DWV) Plastic Fittings Patterns
ASTM E1 (2014) Standard Specification for ASTM Liquid-in-Glass Thermometers
ASTM F409 (2017) Standard Specification for Thermoplastic Accessible and Replaceable Plastic Tube and Tubular Fittings
ASTM F477 (2014) Standard Specification for Elastomeric Seals (Gaskets) for Joining Plastic Pipe
ASTM F493 (2020) Standard Specification for Solvent Cements for Chlorinated Poly (Vinyl Chloride) (CPVC) Plastic Pipe and Fittings
ASTM F2389 (2021) Standard Specification for Pressure-rated Polypropylene (PP) Piping Systems
CAST IRON SOIL PIPE INSTITUTE (CISPI)
CISPI 310 (2012) Coupling for Use in Connection with Hubless Cast Iron Soil Pipe and Fittings for Sanitary and Storm Drain, Waste, and Vent Piping Applications
COPPER DEVELOPMENT ASSOCIATION (CDA)
CDA A4015 (2016; 14/17) Copper Tube Handbook
INTERNATIONAL ASSOCIATION OF PLUMBING AND MECHANICAL OFFICIALS
(IAPMO)
IAPMO PS 117 (2005b) Press Type Or Plain End Rub Gasketed W/ Nail CU & CU Alloy Fittings 4 Install On CU Tubing
INTERNATIONAL CODE COUNCIL (ICC)
ICC IPC (2021) International Plumbing Code
INTERNATIONAL SAFETY EQUIPMENT ASSOCIATION (ISEA)
ANSI/ISEA Z358.1 (2014) American National Standard for Emergency Eyewash and Shower Equipment
SECTION 22 00 00 Page 5
MANUFACTURERS STANDARDIZATION SOCIETY OF THE VALVE AND FITTINGS
INDUSTRY (MSS)
MSS SP-25 (2018) Standard Marking System for Valves, Fittings, Flanges and Unions
MSS SP-58 (2018) Pipe Hangers and Supports - Materials, Design and Manufacture, Selection, Application, and Installation
MSS SP-67 (2017; Errata 1 2017) Butterfly Valves
MSS SP-70 (2011) Gray Iron Gate Valves, Flanged and Threaded Ends
MSS SP-71 (2018) Gray Iron Swing Check Valves, Flanged and Threaded Ends
MSS SP-72 (2010a) Ball Valves with Flanged or Butt-Welding Ends for General Service
MSS SP-78 (2011) Cast Iron Plug Valves, Flanged and Threaded Ends
MSS SP-80 (2019) Bronze Gate, Globe, Angle and Check Valves
MSS SP-85 (2011) Gray Iron Globe & Angle Valves Flanged and Threaded Ends
MSS SP-110 (2010) Ball Valves Threaded, Socket-Welding, Solder Joint, Grooved and Flared Ends
NACE INTERNATIONAL (NACE)
NACE SP0169 (2013) Control of External Corrosion on Underground or Submerged Metallic Piping Systems
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 90A (2021) Standard for the Installation of Air Conditioning and Ventilating Systems
NSF INTERNATIONAL (NSF)
NSF 372 (2016) Drinking Water System Components - Lead Content
NSF/ANSI 14 (2020) Plastics Piping System Components and Related Materials
NSF/ANSI 61 (2020) Drinking Water System Components - Health Effects
PLASTIC PIPE AND FITTINGS ASSOCIATION (PPFA)
PPFA Fire Man (2016) Firestopping: Plastic Pipe in Fire
SECTION 22 00 00 Page 6
Resistive Construction
PLUMBING AND DRAINAGE INSTITUTE (PDI)
PDI WH 201 (2010) Water Hammer Arresters Standard
SOCIETY OF AUTOMOTIVE ENGINEERS INTERNATIONAL (SAE)
SAE J1508 (2009) Hose Clamp Specifications
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
EPA SM 9223 (2004) Enzyme Substrate Coliform Test
PL 93-523 (1974; A 1999) Safe Drinking Water Act
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
40 CFR 141.80 National Primary Drinking Water Regulations; Control of Lead and Copper;
General Requirements
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Plumbing System; G
Detail drawings consisting of schedules, performance charts, instructions, diagrams, and other information to illustrate the requirements and operations of systems that are not covered by the Plumbing Code. Detail drawings for the complete plumbing system including piping layouts and locations of connections ; dimensions for roughing-in, foundation, and support points; schematic diagrams and wiring diagrams or connection and interconnection diagrams. Detail drawings shall indicate clearances required for maintenance and operation. Where piping and equipment are to be supported other than as indicated, details shall include loadings and proposed support methods. Mechanical drawing plans, elevations, views, and details, shall be drawn to scale.
SD-03 Product Data
Recycled Content for Steel Pipe; S
Backflow Prevention Assemblies; G
Fixtures
List of installed fixtures with manufacturer, model, and flow
SECTION 22 00 00 Page 7 rate.
Lab Sinks
Emergency Eye and Face Wash
Floor and Shower Drains
Welding
A copy of qualified procedures and a list of names and identification symbols of qualified welders and welding operators.
Plumbing System
Diagrams, instructions, and other sheets proposed for posting.
Manufacturer's recommendations for the installation of bell and spigot and hubless joints for cast iron soil pipe.
SD-06 Test Reports
Tests, Flushing and Disinfection
Test reports in booklet form showing all field tests performed to adjust each component and all field tests performed to prove compliance with the specified performance criteria, completion and testing of the installed system. Each test report shall indicate the final position of controls.
Test of Backflow Prevention Assemblies; G .
Certification of proper operation shall be as accomplished in accordance with state regulations by an individual certified by the state to perform such tests. If no state requirement exists, the Contractor shall have the manufacturer's representative test the device, to ensure the unit is properly installed and performing as intended. The Contractor shall provide written documentation of the tests performed and signed by the individual performing the tests.
SD-07 Certificates
Materials and Equipment
Where equipment is specified to conform to requirements of the ASME Boiler and Pressure Vessel Code, the design, fabrication, and installation shall conform to the code.
Bolts
Written certification by the bolt manufacturer that the bolts furnished comply with the specified requirements.
SD-10 Operation and Maintenance Data
Plumbing System; G
SECTION 22 00 00 Page 8
1.3 STANDARD PRODUCTS
Specified materials and equipment shall be standard products of a manufacturer regularly engaged in the manufacture of such products.
Specified equipment shall essentially duplicate equipment that has performed satisfactorily at least two years prior to bid opening.
Standard products shall have been in satisfactory commercial or industrial use for 2 years prior to bid opening. The 2-year use shall include applications of equipment and materials under similar circumstances and of similar size. The product shall have been for sale on the commercial market through advertisements, manufacturers' catalogs, or brochures during the 2 year period.
1.3.1 Alternative Qualifications
Products having less than a two-year field service record will be acceptable if a certified record of satisfactory field operation for not less than 6000 hours, exclusive of the manufacturer's factory or laboratory tests, can be shown.
1.3.2 Service Support
The equipment items shall be supported by service organizations. Submit a certified list of qualified permanent service organizations for support of the equipment which includes their addresses and qualifications. These service organizations shall be reasonably convenient to the equipment installation and able to render satisfactory service to the equipment on a regular and emergency basis during the warranty period of the contract.
1.3.3 Manufacturer's Nameplate
Each item of equipment shall have a nameplate bearing the manufacturer's name, address, model number, and serial number securely affixed in a conspicuous place; the nameplate of the distributing agent will not be acceptable.
1.3.4 Modification of References
In each of the publications referred to herein, consider the advisory provisions to be mandatory, as though the word, "shall" had been substituted for "should" wherever it appears. Interpret references in these publications to the "authority having jurisdiction", or words of similar meaning, to mean the Contracting Officer.
1.3.4.1 Definitions
For the International Code Council (ICC) Codes referenced in the contract documents, advisory provisions shall be considered mandatory, the word "should" shall be interpreted as "shall." Reference to the "code official" shall be interpreted to mean the "Contracting Officer." For Navy owned property, references to the "owner" shall be interpreted to mean the "Contracting Officer." For leased facilities, references to the "owner" shall be interpreted to mean…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .