W912QR21R0015_Specs-0003.pdf
PDF 3 MB Posted
- Attached to
- Ft. Campbell Vehicle Maintenance Shop
- Solicitation number
- W912QR21R0015
About this file
This document is a draft solicitation for the construction of a Vehicle Maintenance Shop at Fort Campbell, Kentucky. The project involves constructing a maintenance shop with an estimated cost between $25-100 million. Responses are due within 30 days of the formal solicitation release on April 16, 2021. This is a full and open competition with no set-asides. Offerors must comply with CCR/ORCA requirements through the System for Award Management. A 10% price evaluation adjustment applies for HUBZone small businesses. The scope includes building a shop, parking areas, and associated site work. The selected contractor must meet all federal contracting requirements for certified payrolls, bonding, and reporting.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CIVIL/OPS/ENVIRONMENTAL BR
ATTN: MARCEL D HULL
600 DR M L KING JR PL RM 821
LOUISVILL KY 40202-2236
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Solicitation W912QR21R0015 for the Construction of a Vehicle Maintenance Shop at Ft. Campbell, KY is hereby amended as follow s:
Please see attached Summary of Changes AMDT 0003.
1. CONTRACT ID CODE PAGE OF PAGES
1 5
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912QR21R0015
X 9B. DATED (SEE ITEM 11)
16-Apr-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
20-May-2021
CODE
U. S. ARMY ENGINEER DISTRICT, LOUISVILLE
600 DR. MARTIN LUTHER KING, JR. PLACE
ROOM 821
LOUISVILLE KY 40202-2239
W912QR 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE 964860
FACILITY CODECODE
EMAIL:TEL:
W912QR21R0015-0003
W912QR21R0015
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
SUMMARY OF CHANGES AMDT 0003
Solicitation W912QR21R0015 for the Construction of a Vehicle Maintenance Shop at Ft. Campbell, KY is hereby amended as follows:
A. Section 00 10 00, Price Breakout Schedule, is hereby revised and replaced in its entirety.
B. The following SPECIFICATION SECTIONS are hereby revised and replaced in their entirety:
01 33 29 03 30 00 05 51 00 08 60 45 09 06 00 09 65 00 09 90 00 10 22 3 32 01 19 32 13 14.13 Table of Contents
C. The following APPENDIX is hereby added in its entirety:
Appendix G
D. The following APPENDIX is hereby deleted in its entirety:
Appendix B
E. The following DRAWINGS are hereby revised and replaced in their entirety:
GC104
CS103
CG101
CG105
CG106
CP103
CU101
CU102A
SB105
SF301
SF501
A-101 A-102 A-103
A-104 A-405 A-506 A-510
SF101
A-310 A-312 A-313 A-601 A-607 A-702 I-501 I-600
EP601
A-102X A-201X
F. All other terms and conditions remain unchanged.
SECTION 00 10 00 - SOLICITATION
The following have been modified:
PRICE BREAKOUT SCHEDULE
SECTION 00 10 00
PRICE BREAKOUT SCHEDULE
OFFEROR’S NAME: _______________________________________
CONTRACT LINE ITEM SCHEDULE
CLIN Description Unit Unit Amount Amount
BASE PROPOSAL
0001 All work, labor, materials, and equipment required to construct the Vehicle Maintenance Shop (TEMF) as shown, including delegated design of utilities as shown. JB ___________ ___________
0002 All work, labor, materials, and equipment required to construct South Site Organizational Vehicle Parking as shown. JB ___________ ___________
0003 All work, labor, materials, and equipment required to construct South Site Development Outside Five (5) Foot Line as shown. JB ___________ ___________
0004 All work, labor, materials, and equipment required to construct (3) Organizational Storage Buildings including associated building systems and delegated design of utilities as shown. JB ___________ ___________
0005 All work required for coordination with the Electrical utility service provider, City Light & Power (CLP) for review of Design After Award (DAA) review submittals. Est.
Quantity 50 hours. See note no. 3. $70.35/HR $3,517.50
0006 All work required for coordination with the Electrical utility service provider, City Light & Power (CLP) for Quality Assurance (QA) Inspections. Est. Quantity 100 hours.
See note no. 3. $70.35/HR $7,035.00
0007 All work required for coordination with the Electrical utility service provider, City Light & Power (CLP) for the final connection fee. JB $1,500.00 $1,500.00
SUBTOTAL (BASE-MILCON) _________________
OPTION 1
0008 All work, labor, materials, and equipment required to construct (1) Organizational Storage Building including associated building systems and delegated utility design as shown. JB ___________ ___________
************************************AMDT003*****************************************
OPTION 2
0009 All work, labor, materials, and equipment required to construct North Site Development as shown. JB ___________ ___________
OPTION 3
0010 All work, labor, materials, and equipment required to construct North Site Organizational Vehicle Parking as shown. Can only be executed if Option 2 is executed first. JB ___________ ___________
************************************AMDT003*****************************************
OPTION 4
0011 All work, labor, materials, and equipment required to construct Petroleum Oil Storage Building including associated Building systems and delegated utility design as shown. JB ___________ ___________
OPTION 5
0012 All work, labor, materials, and equipment required to construct Hazardous Waste Storage Building including associated building systems and delegated utility design as shown. JB ___________ ___________
TOTAL (BASE PLUS OPTIONS) _________________
NOTES FOR CONTRACT LINE ITEM (CLIN) SCHEDULE
NOTE NO. 1. To better facilitate the receipt and proposal process, all modifications to proposals are to be submitted on copies of the latest Contract Line Item (CLIN) schedules as published in the solicitation or the latest amendment thereto. In lieu of indicating additions/deductions to line items, all Offerors should state their revised prices for each item.
NOTE NO. 2. Offerors must insert a price on all numbered items including unit prices and options of the CLIN Schedule. Failure to do so may result in the offer being unacceptable.
NOTE NO. 3. CLIN Items as noted are estimates and are subject to the requirements of FAR 52.211-18 Variation in Estimated Quantity. Variations in the actual quantities encountered will be the subject of a contract modification as provided in Clause 52.211-18 Variation in Estimated Quantities.
NOTE NO. 4. The Offeror’s Base Proposal and all Options will be evaluated. In accordance with 52.217-5, Evaluation of Options, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
NOTE NO. 5. The Contracting Officer may exercise any option by written notice to the Contractor within 60 calendar days of notice to proceed.
(End of Summary of Changes)
Vehicle Maintenance Shop W912QR21R0015 Ft. Campbell, KY
PROJECT TABLE OF CONTENTS
Amendment 0003
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 80 00 SPECIAL PROVISIONS
DIVISION 01 - GENERAL REQUIREMENTS
01 32 01 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 33 29 SUSTAINABILITY REPORTING
01 35 26 GOVERNMENT SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.15 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 04.10 CONTRACTOR QUALITY CONTROL
01 45 35 SPECIAL INSPECTIONS
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS AND PERMITS
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 23 OPERATION AND MAINTENANCE DATA
01 91 00 TOTAL BUILDING COMMISSIONING
DIVISION 03 - CONCRETE
03 11 13 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING
03 15 00 CONCRETE ACCESSORIES
03 20 00 CONCRETE REINFORCING
03 30 00 CAST-IN-PLACE CONCRETE
03 30 53 MISCELLANEOUS CAST-IN-PLACE CONCRETE
03 39 00 CONCRETE CURING
03 42 13 PLANT-PRECAST CONCRETE PRODUCTS FOR BELOW GRADE
CONSTRUCTION
DIVISION 04 - MASONRY
04 20 00 MASONRY
DIVISION 05 - METALS
05 05 23.16 STRUCTURAL WELDING
05 12 00 STRUCTURAL STEEL
05 30 00 STEEL DECKS
05 40 00 COLD-FORMED METAL FRAMING
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 51 00 METAL STAIRS
05 51 33 METAL LADDERS
05 52 00 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
06 41 16 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS
06 61 16 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS
07 11 13 BITUMINOUS DAMPPROOFING
PROJECT TABLE OF CONTENTS Page 1 Amendment 0003
07 13 53 ELASTOMERIC SHEET WATERPROOFING
07 21 13 BOARD AND BLOCK INSULATION
07 21 16 MINERAL FIBER BLANKET INSULATION
07 27 10 BUILDING AIR BARRIER SYSTEM
07 27 19.01 SELF-ADHERING AIR BARRIERS
07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS
07 60 00 FLASHING AND SHEET METAL
07 61 14 STEEL STANDING SEAM ROOFING
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 11 16 ALUMINUM DOORS AND FRAMES
08 33 13 COILING COUNTER DOORS
08 33 23 OVERHEAD COILING DOORS
08 34 59 VAULT DOORS AND DAY GATES
08 44 00 CURTAIN WALL AND GLAZED ASSEMBLIES
08 51 13 ALUMINUM WINDOWS
08 60 45 SKYLIGHTS AND TRANSLUCENT PANELS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
08 91 00 METAL WALL AND DOOR LOUVERS
DIVISION 09 - FINISHES
09 06 00 SCHEDULES FOR FINISHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 30 10 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 ACOUSTICAL CEILINGS
09 65 00 RESILIENT FLOORING
09 90 00 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 10 00 VISUAL COMMUNICATIONS SPECIALTIES
10 14 01 EXTERIOR SIGNAGE
10 14 02 INTERIOR SIGNAGE
10 14 53 TRAFFIC SIGNAGE
10 21 13 TOILET COMPARTMENTS
10 22 13 WIRE MESH PARTITIONS
10 22 39 FOLDING PANEL PARTITIONS
10 26 13 WALL AND CORNER GUARDS
10 28 13 TOILET ACCESSORIES
10 44 16 FIRE EXTINGUISHERS
10 51 13 METAL LOCKERS
DIVISION 12 - FURNISHINGS
12 24 13 ROLLER WINDOW SHADES
12 48 00.13 WALK-OFF MAT
12 93 00 SITE FURNISHINGS
DIVISION 13 - SPECIAL CONSTRUCTION
13 12 80 RELOCATABLE HAZARDOUS MATERIAL AND HAZARDOUS WASTE
STORAGE BUILDINGS
PROJECT TABLE OF CONTENTS Page 2
13 34 19 METAL BUILDING SYSTEMS (OSB)
13 34 20 METAL BUILDING SYSTEMS (TEMF)
13 48 00 SEISMIC PROTECTION FOR MISCELLANEOUS EQUIPMENT
DIVISION 14 - CONVEYING EQUIPMENT
14 24 23 HYDRAULIC PASSENGER ELEVATORS
DIVISION 21 - FIRE SUPPRESSION
21 13 13 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION
21 30 00 FIRE PUMPS
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
22 05 48 MECHANICAL SOUND, VIBRATION, AND SEISMIC CONTROL
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 05 15 COMMON PIPING FOR HVAC
23 05 48 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND
EQUIPMENT
23 05 48.19 SEISMIC BRACING FOR HVAC
23 05 93 TESTING, ADJUSTING, AND BALANCING (TAB) OF HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC
23 09 23.01 LONWORKS DIRECT DIGITAL CONTROL FOR HVAC AND OTHER
BUILDING CONTROL SYSTEMS
23 09 93 SEQUENCES OF OPERATION FOR HVAC CONTROL
23 11 25 FACILITY GAS PIPING
23 23 00 REFRIGERANT PIPING
23 35 00 OVERHEAD VEHICLE TAILPIPE AND WELDING FUME EXHAUST
REMOVAL SYSTEM(S)
23 52 00 HEATING BOILERS
23 54 16 HEATING SYSTEM - GAS-FIRED HEATERS
23 81 00 DECENTRALIZED UNITARY HVAC EQUIPMENT
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS
25 05 13 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS
(FA/MNS)
DIVISION 26 - ELECTRICAL
26 00 00 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 48 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT
26 08 00 APPARATUS INSPECTION AND TESTING
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 23 00 SWITCHBOARDS
26 28 01 COORDINATED POWER SYSTEM PROTECTION
26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS
26 41 00 LIGHTNING PROTECTION SYSTEM
26 42 14 CATHODIC PROTECTION SYSTEM (SACRIFICIAL ANODE)
26 51 09.23 INTERIOR LIGHTING AND LIGHTING CONTROL DEVICES
26 56 00 EXTERIOR LIGHTING
PROJECT TABLE OF CONTENTS Page 3
DIVISION 27 - COMMUNICATIONS
27 05 14 CABLE TELEVISION PREMISES DISTRIBUTION SYSTEM
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 05 19 GEOTEXTILE
31 05 22 GEOTEXTILES USED AS FILTERS
31 11 00 CLEARING AND GRUBBING
31 31 16.13 CHEMICAL TERMITE CONTROL
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID
PAVEMENTS
32 05 33 LANDSCAPE ESTABLISHMENT
32 11 23 AGGREGATE BASE COURSES
32 11 23.23 BASE COURSE DRAINAGE LAYERS
32 12 13 BITUMINOUS TACK COATS
32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS
32 13 14.13 CONCRETE PAVING FOR AIRFIELDS AND OTHER HEAVY DUTY
PAVEMENTS
32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 PAVEMENT MARKINGS
32 31 13.53 HIGH-SECURITY CHAIN LINK FENCES AND GATES
32 92 19 SEEDING
32 93 00 EXTERIOR PLANTS
DIVISION 33 - UTILITIES
33 11 00 WATER UTILITY DISTRIBUTION PIPING
33 30 00 SANITARY SEWERAGE
33 40 00 STORM DRAINAGE UTILITIES
33 46 13 FOUNDATION DRAINAGE SYSTEM
33 46 16 SUBDRAINAGE PIPING
33 48 00 BIORETENTION AREAS
33 71 00 ELECTRICAL UTILITY
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT
41 22 13 BRIDGE CRANES
APPENDICES
APPENDIX A ELECTRICAL SERVICE APPLICATION AND MANUAL
Amendment 0003*******************************************
APPENDIX B WATER, WASTEWATER AND RECYCLED WATER DESIGN, STANDARDS,
AND DETAILS <DELETED>
*******************************************Amendment 0003
APPENDIX C FORT CAMPBELL INSTALLATION ACCESS
PROJECT TABLE OF CONTENTS Page 4
APPENDIX D COMMISSIONING APPENDICES A - E
APPENDIX E EXTERIOR SIGNAGE AND MARKINGS
APPENDIX F FORT CAMPBELL TECHNICAL DESIGN GUIDE
Amendment 0003*******************************************
APPENDIX G GEOTECHNICAL REPORTS
*******************************************Amendment 0003
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 5
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 29
SUSTAINABILITY REPORTING
11/17
PART 1 GENERAL
1.1 REFERENCES
1.2 SUMMARY
1.3 SUBMITTALS
1.4 LEED ACCREDITED PROFESSIONAL (LEED AP BD+C)GBI GUIDING PRINCIPLES
COMPLIANCE PROFESSIONAL (GBI GPCP)
1.5 GUIDING PRINCIPLES COMPLIANCE
1.5.1 Construction Phase
1.5.1.1 Sustainability Action Plan
1.5.1.2 Sustainability eNotebook
1.5.1.3 High Performance and Sustainable Building Checklist
1.5.1.4 Progress Report
1.6 GUIDING PRINCIPLES REQUIREMENTS
1.6.1 Commissioning
1.6.2 Energy Efficient Products
1.6.3 Indoor Water Use
1.6.4 Reduce Volatile Organic Compound (VOC) (Low Emitting Materials)
1.6.5 Indoor Air Quality During Construction
1.6.6 Regional Materials
1.6.7 Recycled Content
1.6.8 Bio-Based Products
1.6.9 Ozone Depleting Substances
1.6.10 Waste Material Management (Recycling – Construction)
1.7 THIRD PARTY CERTIFICATION
1.7.1 LEED
1.7.1.1 Registration
1.7.1.2 LEED Project Checklist
1.7.1.3 LEED Correction Plan
1.7.1.4 LEED Interpretations
1.7.1.5 LEED Implementation Plan
1.7.1.6 LEED Documentation
1.7.1.7 LEED Plaque and Certificate
1.7.2 USGBC Guiding Principles Assessment
1.7.2.1 Documentation
1.7.2.2 USGBC GPA Certificates
1.7.3 GBI Guiding Principles Certification
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 SUSTAINABILITY IMPLEMENTATION MEETING
3.2 SUSTAINABILITY PRE-CLOSEOUT MEETING
3.3 TABLE 3-1 VOLATILE ORGANIC COMPOUNDS (VOC) (LOW EMITTING
SECTION 01 33 29 Page 1
MATERIALS) REQUIREMENTS
-- End of Section Table of Contents --
SECTION 01 33 29 Page 2
SECTION 01 33 29
SUSTAINABILITY REPORTING
11/17
Amendment 0003
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING
ENGINEERS (ASHRAE)
ASHRAE 189.1 (2014; ERTA 1 2017) Standard for the Design of High-Performance Green Buildings Except Low-Rise Residential Buildings
GREEN BUILDING INITIATIVE (GBI)
GBI GP Compliance (2016) GBI Guiding Principles Compliance Program for New Construction (DOD Version)
U.S. DEPARTMENT OF AGRICULTURE (USDA)
FSRIA 9002 Farm Security and Rural Investment Act Section 9002 (USDA Biopreferred Program)
U.S. DEPARTMENT OF ENERGY (DOE)
Energy Star (1992; R 2006) Energy Star Energy Efficiency Labeling System (FEMP)
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
SNAP (2016) EPA's Significant New Alternatives Policy Program
U.S. GREEN BUILDING COUNCIL (USGBC)
LEED BDC Ref Guide (2013) USGBC LEED Reference Guide for Building Design and Construction, v4
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
40 CFR 247 Comprehensive Procurement Guideline for Products Containing Recovered Materials
1.2 SUMMARY
This specification includes general requirements and procedures for this project to be constructed and documented per the federally mandated High Performance and Sustainable Building Guiding Principles (GP), LEED certification requirements, USGBC Guiding Principles Assessment, GBI Guiding Principles Compliance Program for New Construction (DoD version), SECTION 01 33 29 Page 3 and other requirements identified in this specification.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following that "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 Submittal Procedures:
SD-01 Preconstruction Submittals
Sustainability Action Plan ; G, RO,S
LEED Implementation Plan ; G, RO,S
LEED AP BD+C; G, RO,S
GBI GPCP; G, RO,S
Sustainability Progress Report ; G, RO,S
SD-05 Design Data
LEED Correction Plan ; G, RO,S
SD-11 Closeout Submittals
Final Sustainability eNotebook ; G, RO,S
Amended Final Sustainability eNotebook ; G, RO,S
Final High Performance and Sustainable Building Checklist ; G, RO,S
LEED Plaque and Certificate ; G, RO
USGBC GPA Certificates ; G, RO,S
1.4 LEED ACCREDITED PROFESSIONAL (LEED AP BD+C) GBI GUIDING PRINCIPLES
COMPLIANCE PROFESSIONAL (GBI GPCP)
A LEED Accredited Professional with specialty in Building Design + Construction (LEED AP BD+C), accredited by the Green Building Certification Institute, GBI Green Building Compliance Professional (GBI GPCP), certified by the Green Building Institute, on the Contractor's Quality Control Staff must assemble documentation and ensure that Guiding Principles Compliance documentation is prepared in accordance with this specification section and ensure that Third Party Certification requirements are achieved . Identify the LEED AP BD+C GBI GPCP on the Contractor's Quality Control Staff in accordance with specification LRL Section 01 45 04.10 CONTRACTOR QUALITY CONTROL. Provide a statement of qualifications of the LEED AP BD+C GBI GPCP submitted to the Government with the QC Plan. Includes name and date of expiration of the current credential.
The LEED AP BD+C GBI GPCP must review all requests for information, Contractor proposals, contract modifications, deviations from the design documents, or any other items that could potentially impact the compliance and Third Party Certification and rating of the project. Bring any
SECTION 01 33 29 Page 4 actions that could negatively impact the Third Party Certification rating or ability to comply with Guiding Principles to the attention of the Contracting Officer.
1.5 GUIDING PRINCIPLES COMPLIANCE
Provide construction related sustainability documentation to verify compliance with Federal High Performance and Sustainable Building requirements. Refer to paragraph Guiding Principle Requirements for requirements and associated documentation to include in the Sustainability eNotebook.
1.5.1 Construction Phase
1.5.1.1 Sustainability Action Plan
Provide a Sustainability Action Plan to demonstrate planned methods to comply with the Guiding Principles requirements and comply with Third Party Certification requirements identified herein. Submit the LEED Implementation Plan as a part of the Sustainability Action Plan. Provide three (3) copies submitted to the Government on compact disk with the QC Plan . The Government will consider an interim Sustainability Action Plan and LEED Implementation Plan for the first 60 calendar days of the Contractor's operation. Construction will be permitted to begin only after acceptance of the plans or acceptance of an interim plan applicable to the work to be started related to the Guiding Principles requirements identified in the interim plan. Include a detailed description of all activities that relate to accomplishing each project Guiding Principle requirement, including construction practices and procurement practices.
Include any plans required by the Guiding Principle Requirements including the Indoor Air Quality Plan and Waste Management Plan. Include a schedule for completion and documentation of each requirement. Include the template to be used for Sustainability Progress Reports, a plan for indoctrinating employees to sustainable goals and responsibilities, a team structure identifying responsibility for documentation, and a process for reviewing sustainability related submittals and documentation.
1.5.1.2 Sustainability eNotebook
Provide and maintain a comprehensive Sustainability eNotebook to document compliance with the Guiding Principles requirements identified herein.
All materials requirements must be updated each month. The Sustainability eNotebook must contain all required data to support compliance with the Guiding Principles requirements. The Sustainability eNotebook must be in the form of an Adobe PDF file; bookmarked at each requirement, and sub-bookmarked at each document. Include the Final High performance and Sustainable Building Checklist. Include all "S" submittals through the specification sections of this contract.
Provide three copies of the Final Sustainability eNotebook and Final High Performance and Sustainable Building Checklist to the Government on DVD 30 calendar days prior to the Contract Required Completion Date. Include a separate section in the Final Sustainability eNotebook with a copy of all Third Party Certification documentation, bookmarked at each separate requirement. Final progress payment retainage may be held by the Contracting Officer until the documentation is complete. Provide an Amended Final Sustainability eNotebook including any updates to documentation based on post-occupancy corrections or based on Third Party Certification requirements .
SECTION 01 33 29 Page 5
1.5.1.3 High Performance and Sustainable Building Checklist
Complete the Army Energy & Sustainability Record Card as required in paragraph Sustainability eNotebook. Obtain the electronic copy of the Army Energy & Sustainability Record Card from the Contracting Officer's Representative. Only the RECYCLED MATERIALS section of the Building Data Worksheet is required. If any deviations from contract result in a change in status to compliance with a listed requirement in the checklist, update the status of that item in the checklist. The LEED worksheet of the Army Energy & Sustainability Record Card is not required.
1.5.1.4 Progress Report
Submit a monthly Sustainability Progress Report , on the same day each month, that identifies the Guiding Principles requirements completed and documented to date. The Sustainability Progress Report must also include the Third Party Certification requirements and documentation completed to date. The Government will compare the Sustainability Progress Report and the available data in the current Sustainability eNotebook and Third Party Certification documentation to the schedule in the Sustainability Action Plan and LEED Implementation Plan . Failure to adhere to the schedule for completion of requirements, including the associated documentation, in the Sustainability Action Plan and LEED Implementation Plan will be cause for withholding the monthly progress payment until the information is updated and in accordance with the Sustainability Action Plan.
1.6 GUIDING PRINCIPLES REQUIREMENTS
Incorporate each of the following Guiding Principles requirements into the project construction, and provide documentation that proves compliance with each listed requirement. For each of the following paragraphs that require the use of products listed on Government-required websites, provide documentation of the process used to select products, or process used to determine why listed products do not meet project performance requirements.
1.6.1 Commissioning
Comply with the requirements of LRL section 01 91 00 TOTAL BUILDING
COMMISSIONING.
1.6.2 Energy Efficient Products
Provide only energy-using products that are Energy Star rated, or have the Federal Energy Management Program (FEMP) recommended efficiency for products with established Energy Star or FEMP requirements. Provide only energy using products that meet FEMP requirements for low standby power consumption. Energy efficient products can be found at:
https://energy.gov/eere/femp/federal-energy-management-program and https://www.energystar.gov/ . Provide the following documentation:
Proof that products are labeled energy efficient and comply with the cited requirements.
1.6.3 Indoor Water Use
Provide only water-consuming products that are EPA WaterSense labeled, or water fixtures available that meet the requirements of ASHRAE 189.1
SECTION 01 33 29 Page 6
Section 6.3.2, whichever is most water-efficient. Provide the following documentation:
For products available with EPA WaterSense labeling, proof that fixtures are labeled EPA WaterSense or Energy Star ; for all other fixtures, proof they comply with the cited efficiency requirements.
1.6.4 Reduce Volatile Organic Compound (VOC) (Low Emitting Materials)
Meet the requirements of Table 3-1 at the end of this specification.
Provide the following documentation:
Provide certifications or labels that demonstrate compliance with cited requirements.
1.6.5 Indoor Air Quality During Construction
Prior to construction, create indoor air quality plan. Implement IAQ plan during construction and flush building air before occupancy.
For new construction and for renovation of unoccupied existing buildings, indoor air quality plan must meet the requirements of ASHRAE 189.1 Section
10.3.1.4. (Indoor Air Quality (IAQ) Construction Management), with maximum outdoor air consistent with achieving relative humidity no greater than 60 percent.
Provide documentation showing that after construction ends and prior to occupancy, HVAC filters were replaced and building air was flushed out in accordance with the cited standard.
1.6.6 Regional Materials
Comply with ASHRAE 189.1 paragraph 9.4.1.2 Regional Materials. Provide documentation demonstrating that 15% of the cost of building materials or products used were extracted, harvested, recovered or manufactured within 500 miles of the project site.
1.6.7 Recycled Content
Comply with 40 CFR 247 . Refer to https://www.epa.gov/smm/comprehensive-procurement-guidelines-construction-products for assistance identifying products cited in 40 CFR 247 . Selected products must comply with non-proprietary requirements of the Federal Acquisition Regulation, and must meet performance requirements. Provide the following documentation:
a. Manufacturers’ documents stating the recycled content by material, or written justification for claiming one of the exceptions allowed on the cited website.
b. Substitutions: Submit for Government approval, proposed alternative products or systems that provide equivalent performance and appearance and have greater contribution to project recycled content requirements. For all such proposed substitutions, submit with the Sustainability Action Plan accompanied by product data demonstrating equivalence.
SECTION 01 33 29 Page 7
1.6.8 Bio-Based Products
Provide products and material composed of the highest percentage of biobased materials (including rapidly renewable resources and certified sustainably harvested products), consistent with FSRIA 9002 USDA Biopreferred Program, to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the end user. Use only supplies and materials of a type and quality that conform to applicable specifications and standards.
Comply with FSRIA 9002 USDA BioPreferred Program. Refer to https://www.biopreferred.gov/BioPreferred/ for the product categories and BioPreferred Catalog. Selected products must comply with non-proprietary requirements of the Federal Acquisition Regulation, and must meet performance requirements. Provide the following documentation:
USDA Biopreferred label for each product; for bio-based products used on project but not listed with Biopreferred program, provide bio-based content and percentage.
1.6.9 Ozone Depleting Substances
Meet the requirements of ASHRAE 189.1 Section 9.3.3 Refrigerants for no CFC-based refrigerants in heating ventilation, air conditioning and refrigeration systems. Where feasible, use products from U.S. EPA Significant New Alternatives Policy (SNAP) ( https://www.epa.gov/snap ) or meet the criteria of SNAP. Provide the following documentation:
a. MSDS sheets for all refrigerants.
b. Provide label for each product meeting the cited standards.
1.6.10 Waste Material Management (Recycling – Construction)
Divert construction debris from landfill disposal where markets or on-site recycling exists, and provide documentation in accordance with UFGS Section 01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT.
A minimum of 60% of nonhazardous construction and demolition waste material generated prior to the issuance of the final certificate of occupancy shall be diverted from disposal in landfills and incinerators by recycling or reuse. Reuse includes donation of materials to charitable organization, salvage of existing materials onsite, and packaging materials returned to the manufacturer, shipper, or other source that will reuse the packaging in future shipments. Excavated soil and land clearing debris shall not be included in the calculation. Calculations are allowed to be done by either weight or volume, but shall be consistent throughout. Specific areas on the construction site shall be designated for collection of recyclable and reusable materials. Off-site storage and sorting of materials shall be allowed. Diversion efforts shall be tracked by the contractor throughout the construction process and documentation provided to the Government prior to contract closeout.
1.7 THIRD PARTY CERTIFICATION
Comply with all requirements and provide all required documentation for the project to achieve certification in the Third Party Certification system identified herein. The Contractor must bear all costs and perform all administrative actions necessary to complete Third Party Certification.
SECTION 01 33 29 Page 8
1.7.1 LEED
Amendment 0003***************************************************************
This project has been designed for a rating of Certified Silver in the Leadership in Energy and Environmental Design (LEED) version 4 certification system. Certify the project at the designed LEED rating through the Green Building Certification Institute. The project has been registered with the Green Building Certification Institute. The Project has not been registered with USGBC (TPC. The Contractor must register the project and pay the associated registration fees . Complete all remaining activities necessary for LEED certification.
**************************************************************Amendment Some LEED prerequisites and credits are similar to Guiding Principle Requirements. Comply with both the LEED and Guiding Principle Requirements. Refer to LEED BDC Ref Guide for additional information regarding LEED and LEED certification processes.
1.7.1.1 Registration
Complete the project information section in LEED Online in accordance with the following:
Project Name: Contact the Contracting Officer for the correct Project Name. For information only, the Project Name will begin with the using agency (Army, AF, DLA, etc.), followed by the project number (PNXXXXX), project name, and building.
Project Address: Contact the Contracting Officer for the correct Project Address. For information only, the first line includes the facility number, street address, block number, etc. The second line includes the base identification code, category code, and real property unique identification code (RPUID). Project Real Property Unique Identification Code (RPUID) may not be available until near the end of construction. Coordinate with the Contracting Officer to obtain the RPUID as soon as possible.
Project City: Include the name of the installation. Example:
Fort Campbell or Scott Air Force Base. If the project is not on an installation, include the nearest town or city.
Project Confidential: Contact the Contracting Officer for the correct designation. Generally, the project is not confidential unless the project has security sensitivity.
Notification of Local Chapter: Indicate NO.
Project Owner: Contact the Contracting Officer for the correct Project Owner. Generally, the project owner will be the USACE Project Manager through project construction. Immediately prior to occupancy and prior to acceptance of the LEED certification from GBCI, the owner must change to the Department of Public Works or Base Civil Engineer. Contact the Contracting Officer prior to final submission to GBCI for the correct Project Owner information.
Owner Organization: U.S. Army Corps of Engineers, Louisville District
May we publish Owner information: Indicate NO.
SECTION 01 33 29 Page 9
Owner Type: Federal Government
The remaining fields are self-explanatory. Contact the Contracting Officer for correct information as necessary.
Coordinate with the Government to identify and grant access to representatives of the Government that will monitor documentation in LEED Online.
Coordinate with the Government to obtain a Project Manager role for the project in LEED Online. The Government will retain the Project Administrator role.
1.7.1.2 LEED Project Checklist
Amendment 0003***************************************************************
Attachment A "LEED Score Card", Attachment B, "LEED Project Credit Guidance Checklist", and Attachment C "HPSB Checklist" identify the LEED credits, High Performance Sustainable Building Checklist, and prerequisites that are designed into or required for this project and identifies which are Construction Phase credits. Comply with the requirements of the Construction Phase credits and prerequisites identified in the LEED Project Checklist including providing all associated documentation required by the Green Building Certification Institute for LEED certification.
**************************************************************Amendment 0003
1.7.1.3 LEED Correction Plan
No variation or substitutions to the LEED credits and prerequisites identified for this contract are permitted without written consent from the Contracting Officer. Should there be a case where there is any current or projected problem meeting the full requirements of a LEED credit or prerequisite identified for this project, notify the Contracting Officer in writing immediately. Submit a LEED Correction Plan to the Government for acceptance detailing the method by which the LEED rating for the project will be preserved. Include the LEED credit or prerequisite impacted, the reason for non-compliance, the proposed correction or solution, an alternate credit, and a schedule for completion of the correction, solution, or alternate credit. If an alternate credit is proposed, submit, with the LEED Correction Plan, an explanation of associated documentation required by LEED certification requirements.
1.7.1.4 LEED Interpretations
Apply existing US Green Building Council or Green Building Certification Institute LEED Interpretations when pursuing credits using non-standard compliance paths or when there are special circumstances making compliance difficult. Applicable LEED Interpretations are those that apply to the LEED version under which the project has been registered. The Contractor may apply for a LEED Interpretation from the Green Building Certification Institute or US Green Building Council for any new proposed strategy, non-standard compliance path, or special circumstances. If a LEED Interpretation is to be used to substantiate compliance with attempted credits and prerequisites, a copy of the request and ruling, including the dates, must be included in the documentation on LEED Online for the associated credit or prerequisite. Compliance methods that are not addressed by existing or new LEED Interpretations may be submitted for LEED certification but are not permitted to be necessary to achieve the required LEED rating.
SECTION 01 33 29 Page 10
1.7.1.5 LEED Implementation Plan
Submit the LEED Implementation Plan as a part of the Sustainability Action Plan. Include a detailed description of all activities that relate to accomplishing project LEED requirements, including construction practices and procurement practices. Also include:
a. The name of the LEED Accredited Professional Building Design + Construction (LEED AP BD+C).
b. Copies of the LEED calculators or forms to be used for tracking and documenting LEED credits and prerequisites. Provide a list of proposed materials, estimated material costs, purchasing plans for materials and resources credits, and other calculation details to demonstrate that the requirements of the specified LEED credits and prerequisites can be attained.
c. The schedule for completion of the requirements and documentation for each credit and prerequisite.
d. List all plans required by the attempted LEED credits and prerequisites and the proposed completion date of each plan. Add the plans to the LEED Implementation Plan and LEED Online as they are completed. Include the Indoor Air Quality Management Plan and the Construction and Demolition Waste Management Plan, coordinated with the Guiding Principle Requirements, in the LEED Implementation Plan.
e. List all applicable LEED Interpretations that will be used to substantiate compliance with credits and prerequisites. Include the complete text of each LEED Interpretation and the date of each.
1.7.1.6 LEED Documentation
Maintain LEED documentation using LEED Online. Complete the documentation in LEED Online in accordance with the schedule in the LEED Implementation Plan. Update the LEED calculators or forms used for tracking and documenting LEED Materials and Resources credits in LEED Online monthly with the information available at that time.
Within the Sustainability eNotebook, include a copy of all completed documentation in LEED Online including both Design Phase and Construction Phase documentation. Include correspondence occurring during construction with the Green Building Certification Institute. Include a copy of each LEED Correction Plan.
1.7.1.7 LEED Plaque and Certificate
Provide and install a LEED Plaque. The LEED Plaque must be 16 inches in diameter by 3/4-inch brushed aluminum with clear coat and must be machined from solid aluminum sheet. Provide brushed aluminum mounting brackets and concealed mounting screws. Mount the LEED Plaque to wall at a location directed by the Contracting Officer's Representative. Provide the LEED Certificate, framed in 1 inch deep metal frames, with double matt, and wire hangars, concurrent with the LEED Plaque. The name of the project and installation on the plaque and certificate must be the final building name provide by the Contracting Officer's Representative.
SECTION 01 33 29 Page 11
1.7.2 USGBC Guiding Principles Assessment
Amendment 0003**************************************************************
This project has been designed to comply with the High Performance and Sustainable Building Guiding Principles and to achieve certification through the USGBC Guiding Principles Assessment. Certify the project through the Green Building Certification Institute. The project has been registered with the Green Building Certification Institute. The Project has not been registered with USGBC (TPC. The Contractor must register the project and pay the associated registration fees. Complete all remaining activities necessary for certification.
**************************************************************Amendment 0003
1.7.2.1 Documentation
Maintain documentation using GBCI's online tool. Complete the documentation in online in accordance with the schedule in the Sustainability Action Plan. Update the calculators or forms used for tracking and documenting Materials and Resources requirements monthly with the information available at that time.
Within the Sustainability eNotebook, include a copy of all completed documentation online including both Design Phase and Construction Phase documentation. Include correspondence occurring during construction with the Green Building Certification Institute.
1.7.2.2 USGBC GPA Certificates
Provide the a USGBC Guiding Principles Assessment Certificate, framed in 1 inch deep metal frames, with double matt, and wire hangers. The name of the project and installation on the certificate must be the final building name provide by the Contracting Officer's Representative.
1.7.3 GBI Guiding Principles Certification
Refer to GBI GP Compliance (DoD version) document for additional information regarding GBI Guiding Principles Certification processes.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
3.1 SUSTAINABILITY IMPLEMENTATION MEETING
The LEED AP BD+C GBI GPCP, QC System Manager, and Contracting Officer's Representative must meet within 60 calendar days after notice to proceed to review project sustainability goals with respect to the Sustainability Action Plan and LEED Implementation Plan , identify potential difficulties related to meeting the Guiding Principle Requirements, and discuss mitigation strategies.
3.2 SUSTAINABILITY PRE-CLOSEOUT MEETING
The LEED AP BD+C GBI GPCP, QC System Manager, and Contracting Officer's Representative must meet 60 calendars days prior to Contract Required Completion Date to review completion status of sustainability requirements including level of completion of Third Party Certification, Guiding Principles Requirements documentation and the High Performance and Sustainable Building Checklist. Discuss any potential difficulties in
SECTION 01 33 29 Page 12 completing Third Party Certification, outstanding requirements and documentation. Provide a copy of the Sustainability eNotebook with up-to-date documentation.
3.3 TABLE 3-1 VOLATILE ORGANIC COMPOUNDS (VOC) (LOW EMITTING MATERIALS)
REQUIREMENTS
Refer to following table, based on ASHRAE 189.1 section 8.4.2 (Materials), for compliance criteria.
TABLE 3-1 Volatile Organic Compounds (VOC) (Low Emitting Materials) Requirements
MATERIAL CATEGORY EMISSIONS
REQUIREMENT
MATERIALS WITH
ADDED VOC
REQUIREMENT
MATERIAL CATEGORY
Adhesives and Sealants
CDPH/EHLB/Standard method V1.1 (California Section 01350) (Use "office" or "classroom" space limits for all applications) or Adhesives (carpet, resilient, wood flooring; panel;
primers) Sealants (acoustical;
firestop; HVAC Air duct; primers) Caulks
SCAQMD Rule 1168 (Use "other" category for HVAC duct sealant) (for firestop adhesive, UFC 3-600-01 overrides conflicting requirements)
Aerosol adhesives Section 3 of Green Seal Standard
GS-36
(except:
cleaners, solvent cements, and primers used with plastic piping and conduit in plumbing, fire suppression, and electrical systems; HVAC air duct sealants when the application space air temp is less than 40 F (4.5 C).
SECTION 01 33 29 Page 13
TABLE 3-1 Volatile Organic Compounds (VOC) (Low Emitting Materials) Requirements
MATERIAL CATEGORY EMISSIONS
REQUIREMENT
MATERIALS WITH
ADDED VOC
REQUIREMENT
MATERIAL CATEGORY
Paints and Coatings CDPH/EHLB/Standard method V1.1 (California Section 01350) (Use "office" or "classroom" space limits for all applications) or Flat and nonflat topcoats, primers, undercoaters, and anti-corrosive coatings
Green Seal Standard GS-11
SECTION 01 33 29 Page 14
TABLE 3-1 Volatile Organic Compounds (VOC) (Low Emitting Materials) Requirements
MATERIAL CATEGORY EMISSIONS
REQUIREMENT
MATERIALS WITH
ADDED VOC
REQUIREMENT
MATERIAL CATEGORY
Paints and Coatings CDPH/EHLB/Standard method V1.1 (California Section 01350) (Use "office" or "classroom" space limits for all applications) or Concrete/masonry sealers (waterproofing concrete/masonry sealers), concrete curing compounds, dry fog coatings, faux finishing coatings, fire resistive coatings, floor coatings, graphic arts (sign) coatings, industrial maintenance coatings, mastic texture coatings, metallic pigmented coatings, multicolor coatings, pretreatment wash primers, reactive penetrating sealers, recycled coatings, shellacs (clear and opaque), specialty primers, stains, wood coatings (clear wood finishes), wood preservatives, and zinc primers
California Air Resources Board (CARB) Suggested Control Measure for Architectural Coatings or SCAQMD Rule 1113
SECTION 01 33 29 Page 15
TABLE 3-1 Volatile Organic Compounds (VOC) (Low Emitting Materials) Requirements
MATERIAL CATEGORY EMISSIONS
REQUIREMENT
MATERIALS WITH
ADDED VOC
REQUIREMENT
MATERIAL CATEGORY
Paints and Coatings CDPH/EHLB/Standard method V1.1 (California Section 01350) (Use "office" or "classroom" space limits for all applications) or Basement specialty coatings, high-temperature coatings, low solids coatings, stone consolidants, swimming-pool coatings, tub- and tile-refining coatings, and waterproofing membranes
California Air Resources Board (CARB) Suggested Control Measure for Architectural Coatings
Floor Covering Materials
For carpet, all locations:
CDPH/EHLB/Standard Method V1.1 ( California Section 01350) or label for Section 9 of CDPH/EHLB/Standard Method V1.1 (Cali fornia Section 01350) none none
SECTION 01 33 29 Page 16
TABLE 3-1 Volatile Organic Compounds (VOC) (Low Emitting Materials) Requirements
MATERIAL CATEGORY EMISSIONS
REQUIREMENT
MATERIALS WITH
ADDED VOC
REQUIREMENT
MATERIAL CATEGORY
Composite Wood, Wood Structural Panel, and Agrifib er Products particleboard medium density fiberboard (MDF) wheatboard strawboard panel substrates door cores no added urea-formaldehyde resins including laminating adhesives for composite wood and agrifiber assemblies
Third-party certification (approved by CARB) of California Air Resource Board's (CARB) regulation , Airborne Toxic Control Measure to Reduce Formaldehyde Emissions from Composite Wood Products none none
CDPH/EHLB/Standard method V1.1 (Ca lifornia Section 01350) (Use "office" or "classroom" space limits for all applications) (except: Structural panel components such as plywood, particle board, wafer board, and oriented strand board identified as
"EXPOSURE 1,"
"EXTERIOR," or "HUD-APPROVED" are considered acceptable for interior use.)
SECTION 01 33 29 Page 17
TABLE 3-1 Volatile Organic Compounds (VOC) (Low Emitting Materials) Requirements
MATERIAL CATEGORY EMISSIONS
REQUIREMENT
MATERIALS WITH
ADDED VOC
REQUIREMENT
MATERIAL CATEGORY
Office Furniture Systems and Seating installed prior to occupancy
ANSI/BIFMA X7.1
ANSI/BIFMA X7.1:
(95 percent of installed office furniture system workstations and seating units)
Section 7.6.2 of ANSI/BIFMA e3 (50 percent of office furniture system workstations and seating units) none none
Ceiling and Wall Systems ceiling and wall insulation acoustical ceiling panels tackable wall panels gypsum wall board and panels wall coverings
CDPH/EHLB/Standard method V1.1 (Ca lifornia Section 01350) (Use "office" or "classroom" space limits for all applications) none none
-- End of Section --
SECTION 01 33 29 Page 18
SECTION TABLE OF CONTENTS
DIVISION 03 - CONCRETE
SECTION 03 30 00
CAST-IN-PLACE CONCRETE
05/14
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.2.1 Cementitious Material
1.2.2 Complementary Cementing Materials (CCM)
1.2.3 Design Strength (f'c)
1.2.4 Mass Concrete
1.2.5 Mixture Proportioning
1.2.6 Mixture Proportions
1.2.7 Pozzolan
1.2.8 Workability or Consistency
1.3 SUBMITTALS
1.4 QUALITY ASSURANCE
1.4.1 Laboratory Accreditation
1.4.1.1 Aggregate Testing and Mix Proportioning
1.4.1.2 Acceptance Testing
1.4.1.3 Contractor Quality Control
1.4.2 Quality Control Plan
1.4.3 Special Properties and Products
1…