W912QR20R0045Plans-0003.pdf
PDF 10 MB Posted
- Attached to
- Consolidated Mission Complex (CMC), Phase 3 at Warner Robins Air Force Base (AFB), Georgia
- Solicitation number
- W912QR20R0045
About this file
This document provides details on a federal contract solicitation for construction services. The solicitation is for construction of a Consolidated Mission Complex (CMC), Phase 3 located at Warner Robins Air Force Base in Georgia, with an estimated cost between $25-100 million. The NAICS code is 236220 and size determination is $39.5 million. This is a Full-and-Open procurement that requires the HUBZone 10% price evaluation. The solicitation was issued by the Department of the Army Corps of Engineers Engineering District Louisville. Technical inquiries must be submitted through the Bidder Inquiry system at ProjNet by the specified deadline. The funds are not presently available and no award will be made until appropriated funds are received.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
L
A
K
E
S
I
D
E
C
I
R
C
L
E
EXISTING
PHASE 2
AREA 1
A R
AREA 2
AREA 1
AREA 2
AREA 1
A R
R
R
S
S
S
S
S
S
S
PHASE 3
OPTION 1
OPTION 2
N: 948672.06
E:2476066.12
N: 948672.59
E:2475718.69
N: 948714.55
E:2475603.42
N: 948751.09
E:2475608.18
N: 948740.35
E:2476090.98
N: 948653.26
E:2476060.35
N: 948653.26
E:2476086.58
N: 948704.45
E:2476087.14
N: 948766.62
E:2476097.20
N: 948805.89
E:2476103.20
N: 948799.56
E:2476097.20
13.33'
8'
T
Y P
N: 948810.52
E:2476090.50
N: 948885.47
E:2476017.61
N: 948903.68
E:2476023.70
N: 948907.05
E:2476018.55
N: 948905.07
E:2476017.82
R
17.33'
N: 948749.81
E:2476103.65
N: 948640.08
E:2476055.55
23.8'
N: 948635.31
E:2476086.58
6'
GENERAL NOTES
A REFER TO V-106 FOR SURVEY CONTROL PLAN.
B ALL DIMENSIONS ARE TO BACK OF CURB UNLESS
OTHERWISE NOTED.
C ALL RADII ARE 2.5' UNLESS OTHERWISE NOTED
LEGEND
EXISTING ASPHALT PAVEMENT
EXISTING CONCRETE SIDEWALK
BID 33' UNOBSTRUCTED SPACE
EXISTING CONCRETE PAVEMENT
BASE BID CONCRETE SIDEWALK
BUILDING OUTLINE
EXISTING GRASS PAVERS
OPTION CONCRETE SIDEWALK
BID 50' CLEAR ZONE
KEYNOTES
201 SIDEWALK; RE: A1/CS500
205 ABA PARKING SIGN (TYP.); RE: D9/CS503
ABA PARKING STRIPING (TYP.); RE: E2/CS503206
217 TYPE A ABA RAMP; RE: C1/CS502
OPTION ASPHALT PAVEMENT RE:
F1/CS500
204 WHEEL STOP (TYP.); RE: E4/CS502
BASE BID ASPHALT PAVEMENT
218 TYPE B ABA RAMP; RE: C1/CS502
BASE BID CONCRETE PAVEMENT
D REFER TO SHEET GI002 AND GI003 FOR LIST OF
ABBREVIATIONS USED IN DRAWINGS.
LIMITS OF CONSTRUCTION
229 CROSSWALK STRIPING; RE: D6/CS500
238 HANDRAIL; RE: SHEET A-541
240 WHITE EDGE STRIPING; RE: F5/CS503
241 RETAINING WALL; RE: STRUCTURAL PLANS
XXX
S I T
E
P
L A
N
A
R E
O
P T
I O
N
U B
L D
G U
S A o u i s v i l l e
D i s t r i c t D
A
F R
C
C
M
P h
W o r k i n g
D o c u m e n t s
S h e e t s
C i v i l U
H H
Z C
S d w g
P
M
T h o m a s
S a m u e l
C
B
L
E
V
HOV
HOV
HOV
L
E
V
L
E
V
L
E
V
HOV
L
E
V
L
E
V
H
O
V
L
E
V
H
O
V
H
O
V
HOV
HOV
LEV
LEV
LEV
LEV
LEV
HOV
HOV
HOV
HOV
LEV
H
O
V
H
O
V
H
O
V
L
E
V
L
E
V
LEV
LEV
LEV
H
O
V
H
O
V
H
O
V
D
I
D
I
D I
DI
D
CO
D
D
D
D
I
D
I
D
I
D
S
V
V
C.O
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
SHEET ID
G
2 3 4 5 6 7 8 9 10
F
E
D
C
B
A
US Army Corps of Engineers
Louisville District ®
D A
T E
M A
R K
D E
S C
R I P
T I O
N
R M
Y
C
O R
F
E
N G
I N
E E
R S
D R
A W
N
B
Y
D E
S I G
N E
D
B
Y
S U
B M
I T
T E
D
B
Y
S I Z
E
C H
E C
K E
D
B
Y
A N
S x
I S
S U
E
D
A T
E
C O
N T
R A
T
S O
L I C
I T
A T
I O
N
N
O
D A
T E
M A
R K
D E
S C
R I P
T I O
N
D R
A W
I N
G
C
O D
E
T B
D
T B
D
V
S A
R O
N I
F I
M
E
L O
U I S
V I L
S
T R
I C
T
L O
U I S
V I L
L E
K
E N
T U
C K
Y
J A
C O
B
G
I N
E E
R I N
G
G
R O
C
M a i n t r e e t
F o r t
W o r t h
T
X
J A
C O
D
TEXAS REGISTERED
ENGINEERING FIRM F-2966
S
T H
O M
A S
U H
H Z
30' 60'0
SCALE: 1"=30'
15'
TRUE NORTH
KEY PLAN
K
K E
N N
E D
Y
KATHYRIYA H. KENNEDY
98244
F Y
A
F R
C
C
O N
S O
L I D
A T
S
S I O
N
C
O M
P L
X
H A
O
B I N
S
A
R
S
E
G
E O
R G
I A
P R
O J E
M
B E
R
U
H H
Z
P
AREA 1
T B
D
J H
A Y
N E
S
O
CERTIFIED FINAL DESIGN
CS111
SCALE 1" = 30'
SITE PLAN - AREA 1 - OPTIONS 1 & 2
A1
C S
A M
E N
D M
E N
T
10/27/2020
W
2Q R
R
-0
PHASE 3
S X
S
SX
S
SX
S
SX
S
S
X
S
S
X
S
S
X
S S
X
S S
X
S S
X
S
S
X
S
S
X
S
S
X
S
S
X
S
D
X
S
D
X
S
D
X
E x
W x
W x
W x
W x
U
K X
G
X
U
K
X
U
K X
U
K
X
W x
W x
W x
W
W x
U
K
X
U
K
X
U
K X
U
K
X
W x
W x
W x
W x
W x
W x
W x
C x
U
K
X
S S
X
S
S
X
S S
X
S S
X
S
S
X
S
S
S
S X
S
D
X
S
D
C x
C x
E x
D
L
A
K
E
S
I
R
C
L
E
C x
EXISTING
PHASE 2
S
S
S
S
S
S
C
B
D
C
B
D
C
B
D
C
B
C
B
C
B
C
B
C
O
C
O
AREA 1
A R
AREA 1
AREA 2
AREA 1
A R
R
S
S
S
S
S
S
S S
S S
S S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S
S S
S S
S
S
D
CB
D
C
B
S
D
S
D
S
D
CB
C B
S
D
CB
DD
D D
D
SD
D
D
C
B
D
D
2+003+004+00
S S
SS SS
S
S
S
S
G
2+003+004+005+00
S
S S
S S
1+00
2+00
FF
SS SS
W W W W W
S
S
W
F F
D
STA 1+00.00, FL-01
INSTALL:
8" X 6" TEE
N:948644.61
E:2476106.57
STA 1+05.98, FL-01
INSTALL:
1 - 11.25° BEND
N:948646.13
E:2476100.79
STA 1+17.94, FL-01
INSTALL:
PIV
RE: E5/CU502
N:948650.22
E:2476089.55
8" PVC FL-01
STA 2+43.90, FL-02
INSTALL:
1 - 45° BEND
N:948654.72
E:2476091.81
STA 2+62.17, FL-02
INSTALL FDC
N:948638.17
E:2476099.52
STA 1+00.00, FL-02
CONNECT TO BUILDING
RE: FIRE PROTECTION
N:948699.49
E:2475956.77
STA 2+59.56, FL-01
CONNECT TO BUILDING
RE: FIRE PROTECTION
N:948698.66
E:2475956.47
STA 1+60.40, SSWR-01
INSTALL 4'
DROP MANHOLE
RE: A6/CU502
N:948901.75
E:2475867.62
P
V
W
R
P
V
W
R
STA 2+73.39, SSWR-01
INSTALL 4' SSMH
RE: A6/CU502
N:948940.39
E:2475761.45
STA 1+56.70, SSWR-02
CONNECT TO BUILDING
N:948852.32
E:2475839.85
STA 1+56.12, SSWR-03
CONNECT TO BUILDING
N:948889.40
E:2475738.01
STA 1+00.00, WL-01
INSTALL:
6X8 TAPPING SLEEVE AND
VALVE, RE:A4/CU500
N:948901.19
E:2476059.22
STA 1+22.67, WL-01
INSTALL:
1 - 22.5° BEND
N:948885.34
E:2476043.01
STA 1+38.19, WL-01
INSTALL:
8" X 6" TEE
N:948880.20
E:2476028.37
STA 1+10.71, WL-02
INSTALL:
1 - F.H. ASSEMBLY
RE: D5/CU501
N:948890.31
E:2476024.82
STA 1+70.28, WL-01
INSTALL:
1 - 45° BEND
N:948869.57
E:2475998.09
STA 3+67.80, WL-01
INSTALL:
8" X 6" TEE
N:948937.13
E:2475812.49
STA 1+29.44, WL-03
INSTALL:
1 - F.H. ASSEMBLY
RE: D5/CU501
N:948964.80
E:2475822.56
6" PVC WL-03
STA 5+02.55, WL-01
INSTALL:
8" X 3" TEE
N:948983.21
E:2475685.86
STA 5+20.88, WL-01
INSTALL:
1 - 45° BEND
N:948989.48
E:2475668.64
STA 1+84.49, WL-04
CONNECT TO
BUILDING
N:948903.81
E:2475656.96
STA 5+61.73, WL-01
INSTALL:
8" X 6" TEE
N:949026.50
E:2475651.37
6" PVC WL-02
STA 1+00.00, SSWR-01
EXISTING SSMH
N:948911.31
E:2475927.26
6" PVC SSWR-01
2" HDPE - SDR 11
FFE 290.07'
N:948722.10
E:2476127.01
N:948681.64
E:2476116.34
STA 1+18.40, FL-02
INSTALL:
1 - 45° BEND
N:948693.20
E:2475974.06
STA 1+24.22, FL-02
INSTALL:
1 - 45° BEND
N:948695.66
E:2475979.34
6" PVC FL-02
GENERAL NOTES
A
B
REFER TO V-106 FOR CONTROL MONUMENT.
UNDERGROUND UTILITY LOCATIONS ARE BASED UPON
PHYSICAL AND GEOPHYSICAL SURVEY DATA. ACTUAL
LOCATIONS SHOULD BE VERIFIED WITH THE APPROPRIATE
UTILITY COMPANY AND/OR ROBINS AFB PRIOR TO
CONSTRUCTION.
C
REFER TO ELECTRICAL PLANS FOR ADDITIONAL
INFORMATION ON CATV CONDUITS AND
ELECTRICAL/COMMUNICATION DUCTBANKS/MANHOLES.
D
E
EXISTING WATER PIPE IS ASSUMED TO BE ASBESTOS
CONTAINING MATERIAL.
REFER TO ELECTRICAL PLANS FOR ADDITIONAL
LIGHTING REQUIRED FOR OPTIONS.
KEYNOTES
LEGEND
SANITARY SEWER LINE
SS
WATER LINE
W
EXISTING FIRE HYDRANT
COMMUNICATIONS DUCTBANK
C
ELECTRICAL DUCTBANK
E
EXISTING EXTERIOR LIGHT
EXISTING EXTERIOR BOLLARD LIGHT
EXISTING SANITARY SEWER LINE
SS
x
EXISTING GAS LINE
G x
EXISTING WATER LINE
W x
EXISTING COMMUNICATIONS DUCTBANK
C x
EXISTING CATV CONDUIT
EXISTING ELECTRICAL DUCTBANK
E x
SANITARY SEWER MANHOLE, RE: A1, D1/CU500
FIRE HYDRANT, RE: D5/CU501
CATV
S
EXISTING UNKNOWN UTILITY LINE
UK
X
EXTERIOR BOLLARD LIGHT
EXTERIOR LIGHT
PIV, RE: E5/CU502
FIRE LINE
F
FREESTANDING FDC
F REFER TO SHEETS CU201-CU205 FOR UTILITY PROFILES.
G REFER TO SHEET GI002 AND GI003 FOR LIST OF
ABBREVIATIONS USED IN DRAWINGS.
501 CONNECT TO BUILDING, RE: PLUMBING
LIMITS OF CONSTRUCTION
509 EXISTING WATERLINE TO BE LOWERED TO INSTALL STORM
DRAIN, RE: D1/CU500
511 FIRE HYDRANT BOLLARD, RE: D8/CU501
512 GREASE WASTE LINE, RE: PLUMBING
XXX
CB
L
E
V
HOV
HOV
HOV
L
E
V
L
E
V
L
E
V
HOV
L
E
V
L
E
V
H
O
V
L
E
V
H
O
V
H
O
V
HOV
HOV
LEV
LEV
LEV
LEV
LEV
HOV
HOV
HOV
HOV
LEV
H
O
V
H
O
V
H
O
V
L
E
V
L
E
V
LEV
LEV
LEV
H
O
V
H
O
V
H
O
V
D
I
D
I
D
I
DI
D
C
O
D
D
D
D
I
D
I
D
I
D
S
V
V
C
.O
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
SHEET ID
G
2 3 4 5 6 7 8 9 10
F
E
D
C
B
A
US Army Corps of Engineers
Louisville District ®
D A
T E
M A
R K
D E
S C
R I P
T I O
N
M
Y
C
O R
E
N G
I N
E E
R S
D R
A W
N
B
Y
D E
S I G
N E
D
B
Y
S U
B M
I T
T E
D
B
Y
S I Z
E
C H
E C
K E
D
B
Y
A N
S x
I S
S U
E
D
A T
E
C O
N T
R A
S O
L I C
I T
A T
I O
N
N
O
D A
T E
M A
R K
D E
S C
R I P
T I O
N
D R
A W
I N
G
C
O D
E
T B
D
T B
D
V
S
A R
O N
I
F I
M
E
L O
U I S
V I L
S
T R
I C
T
L O
U I S
V I L
L E
K
E N
T U
C K
Y
J A
C O
G
I N
E E
R I N
G
G
R O
C
M a r e e t
F o r t
W o r t h
T
X
J A
C O
D
TEXAS REGISTERED
ENGINEERING FIRM F-2966
S
T
H O
M A
S
U H
H Z
30' 60'0
SCALE: 1"=30'
15'
TRUE NORTH
KEY PLAN
K
K
E N
N E
D Y
KATHYRIYA H. KENNEDY
98244
F Y
A
F R
C
C
O N
S O
L I D
A T
S
S I O
N
C
O M
P L
H A
O
B I N
S
A
R
S
E
G
E O
R G
I A
P R
O J E
M
B E
R
U
H H
Z
P
AREA 1
T B
D
J
H
A Y
N E
S
O
CERTIFIED FINAL DESIGN
CU101
U B
L D
G U
S A u i s v i l l e
D i s t r i c t D
A
F R
C
C
W o r k i n g
D o c u m e n t s
S h e e t s
C i v i l U
H H
Z C
U d w g
P
M
T h o m a s
S a m u e l
U T
I L
I T
Y
P
L A
N
A
R E
A
SCALE 1" = 30'
UTILITY PLAN - AREA 1
A1
C U
A M
E N
D M
E N
T
10/27/2020
W
2Q R
R
-0
DUCK LAKE
S
X
S
S
X
S
S
X
S
S
X
S
S
X
S
S X
S
S X
S
S X
S
SX
S
SX
S
SX
S
S
X
S
S
X
S
S X
S
S
X
S
S
X
S
D
X
S
D
X
S
D
X
S
D
X
C x C x C x
C x
C x
C x
C x
C x
C x
E x E x E x
E x
E x
E x
E x
E x
E x x
W x
W x
W x W x
W x
W x
W x
W x
W x
U
K
X
U
K
X
U
K
X
U
K
X
W x
W x
W x
W x
W x
W x
W x
W x
W x
G
X
G
X
G
X
G
X
G
X
G
X
G
X
G
X
G
X
G
X
G
X
G
X
G
X
U K
X
U K
X
U K
X
U K
X
U K
X
U K
X
UK
X
UK
X
UK
X U K
X
U K
X
U
K
X
U
K
X
S
S
S S
X
A R
AREA 1
AREA 2
AREA 1
S
C B
D
C B
S D
S
D
S
D
C
B
D
S
D
S
D
S
D
C
B
S
D
S
D
C
B
C
B
S
D
D
W
W
W
W
STA 1+00.00, WL-01
INSTALL:
6X8 TAPPING SLEEVE AND
VALVE, RE:A4/CU500
N:948901.19
E:2476059.22
8" PVC WL-01
N:949071.17
E:2475854.27
N:949085.77
E:2475827.96
EXISTING 6" WATERLINE
GENERAL NOTES
A
B
REFER TO V-106 FOR CONTROL MONUMENT.
UNDERGROUND UTILITY LOCATIONS ARE BASED UPON
PHYSICAL AND GEOPHYSICAL SURVEY DATA. ACTUAL
LOCATIONS SHOULD BE VERIFIED WITH THE APPROPRIATE
UTILITY COMPANY AND/OR ROBINS AFB PRIOR TO
CONSTRUCTION.
C
REFER TO ELECTRICAL PLANS FOR ADDITIONAL
INFORMATION ON CATV CONDUITS AND
ELECTRICAL/COMMUNICATION DUCTBANKS/MANHOLES.
LEGEND
WATER LINE
W
EXISTING SANITARY SEWER LINE
SS
x
EXISTING GAS LINE
G x
EXISTING WATER LINE
W x
EXISTING COMMUNICATIONS DUCTBANK
C x
EXISTING ELECTRICAL DUCTBANK
E x
EXISTING UNKNOWN UTILITY LINE
UK
X
D
E
EXISTING WATER PIPE IS ASSUMED TO BE ASBESTOS
CONTAINING MATERIAL (ACM). CONTRACTOR SHALL USE
CAUTION WHEN TYING IN TO EXISTING PIPE AND
SHOULD FIELD VERIFY PIPE MATERIAL. IF ACM IS
ENCOUNTERED AT TIE IN LOCATION, CONTRACTOR
SHALL REPLACE WITH PVC ON BOTH SIDES OF THE TIE
IN LOCATION FOR A MINIMUM OF 10 LINEAR FEET.
REFER TO ELECTRICAL PLANS FOR ADDITIONAL
LIGHTING REQUIRED FOR OPTIONS.
F REFER TO SHEETS CU201-CU205 FOR UTILITY PROFILES.
G
REFER TO SHEET GI002 AND GI003 FOR LIST OF
ABBREVIATIONS USED IN DRAWINGS.
KEYNOTES
LIMITS OF CONSTRUCTION
510 REPLACE 20' OF EXISTING TRANSITE WATERLINE WITH PVC
WATERLINE. CONNECT TO EXISTING WATERLINE WITH AN
EXTENDED RANGE PIPE COUPLING.
XXX
514 EXISTING WATERLINE TO BE LOWERED AND REPLACED
WITH PVC C-900 TO INSTALL STORM DRAIN, RE: D1/CU500
CB
L
E
V
HOV
HOV
HOV
L
E
V
L
E
V
L
E
V
HOV
L
E
V
L
E
V
H
O
V
L
E
V
H
O
V
H
O
V
HOV
HOV
LEV
LEV
LEV
LEV
LEV
HOV
HOV
HOV
HOV
LEV
H
O
V
H
O
V
H
O
V
L
E
V
L
E
V
LEV
LEV
LEV
H
O
V
H
O
V
H
O
V
D
I
D
I
D
I
DI
D
C
O
D
D
D
D
I
D
I
D
I
D
S
V
V
C
.O
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
SHEET ID
G
2 3 4 5 6 7 8 9 10
F
E
D
C
B
A
US Army Corps of Engineers
Louisville District ®
D A
T E
M A
R K
D E
S C
R I P
T I O
N
M
Y
C
O R
E
N G
I N
E E
R S
D R
A W
N
B
Y
D E
S I G
N E
D
B
Y
S U
B M
I T
T E
D
B
Y
S I Z
E
C H
E C
K E
D
B
Y
A N
S x
I S
S U
E
D
A T
E
C O
N T
R A
S O
L I C
I T
A T
I O
N
N
O
D A
T E
M A
R K
D E
S C
R I P
T I O
N
D R
A W
I N
G
C
O D
E
T B
D
T B
D
V
S
A R
O N
I
F I
M
E
L O
U I S
V I L
S
T R
I C
T
L O
U I S
V I L
L E
K
E N
T U
C K
Y
J A
C O
G
I N
E E
R I N
G
G
R O
C
M a r e e t
F o r t
W o r t h
T
X
J A
C O
D
TEXAS REGISTERED
ENGINEERING FIRM F-2966
S
T
H O
M A
S
U H
H Z
30' 60'0
SCALE: 1"=30'
15'
TRUE NORTH
KEY PLAN
K
K
E N
N E
D Y
KATHYRIYA H. KENNEDY
98244
F Y
A
F R
C
C
O N
S O
L I D
A T
S
S I O
N
C
O M
P L
H A
O
B I N
S
A
R
S
E
G
E O
R G
I A
P R
O J E
M
B E
R
U
H H
Z
P
AREA 2
T B
D
J
H
A Y
N E
S
O
CERTIFIED FINAL DESIGN
CU102
U B
L D
G U
S A u i s v i l l e
D i s t r i c t D
A
F R
C
C
W o r k i n g
D o c u m e n t s
S h e e t s
C i v i l U
H H
Z C
U d w g
P
M
T h o m a s
S a m u e l
U T
I L
I T
Y
P
L A
N
A
R E
A
SCALE 1" = 30'
UTILITY PLAN - AREA 2
A1
C U
A M
E N
D M
E N
T
10/27/2020
W
2Q R
R
-0
SHEET ID
G
2 3 4 5 6 7 8 9 10
F
E
D
C
B
A
US Army Corps of Engineers
Louisville District ®
D A
T E
M A
R K
D E
S C
R I P
T I O
N
M
Y
C
O R
E
N G
I N
E E
R S
D R
A W
N
B
Y
D E
S I G
N E
D
B
Y
S U
B M
I T
T E
D
B
Y
S I Z
E
C H
E C
K E
D
B
Y
A N
S x
I S
S U
E
D
A T
E
C O
N T
R A
S O
L I C
I T
A T
I O
N
N
O
D A
T E
M A
R K
D E
S C
R I P
T I O
N
D R
A W
I N
G
C
O D
E
T B
D
T B
D
V
S
A R
O N
I
F I
M
E
L O
U I S
V I L
S
T R
I C
T
L O
U I S
V I L
L E
K
E N
T U
C K
Y
J A
C O
G
I N
E E
R I N
G
G
R O
C
M a r e e t
F o r t
W o r t h
T
X
J A
C O
D
TEXAS REGISTERED
ENGINEERING FIRM F-2966
S
T
H O
M A
S
U H
H Z
K
K
E N
N E
D Y
KATHYRIYA H. KENNEDY
98244
F Y
A
F R
C
C
O N
S O
L I D
A T
S
S I O
N
C
O M
P L
H A
O
B I N
S
A
R
S
E
G
E O
R G
I A
P R
O J E
M
B E
R
U
H H
Z
P
T B
D
J
H
A Y
N E
S
O
CERTIFIED FINAL DESIGN
U T
I L
I T
Y
D
E T
A I L
S
CU500
C U
PLAN VIEW
SECTIONAL VIEW
1'-0"
LIMIT OF EXCAVATION
AS REQUIRED FOR
TAPPING MACHINE
EXISTING PIPE
NEW PIPE
NEW TAPPING SLEEVE
LIMIT OF EXCAVATION
NEW VALVE
NEW PIPE
CONCRETE
SUPPORT1
CONCRETE
BLOCKING
1/2"3/4"
2"
B
B
3"
CAST IRON
1/4"
3/4"
HOLE
1" DIAMETER
24" DIAMETER
23 1/2"
1 1/2"=10 1/2"
3"
7 AT
E
N
A
S
S
E
W
I T
R
A
Y
R
3"
CAST IRON
WEIGHT=156 LBS.
APPROXIMATE
8-RIBS, SPACED
EQUALLY
PLAN OF SANITARY SEWER MANHOLE
APPROX. WEIGHT 158 POUNDS
SECTION A SECTION B-B
BOTTOM VIEW OF COVER
22"
30 3/4"
1/4"
1"
24 1/4"
1"
PLAN
SECTION A
3/4"
SCALE N.T.S.
MANHOLE COVER
SCALE N.T.S.
MANHOLE FRAME
4 3/4"
10"
4 1/2"
10"
3/4" POLYPROPYLENE COATED
60 STEEL ROD SHAPED AS SHOWN
7 1/2"
4 1/2" 3"
PLAN
SECTION A
SCALE N.T.S.
MANHOLE RUNG
TYPE SC
TYPE SA
SCALE N.T.S.
TAPPING SLEEVE AND VALVE INSTALLATION
7"
30" DIA.
S E
E
P
R O
F I L
E
TYP.
6"
48" DIA.
MANHOLE COVER
AND FRAME
GALVANIZED STEEL
SIDE RAIL LADDER
A8/CU500
A
MANHOLE COVER
AND FRAME
COVER AND FRAME
SECURELY SEATED IN
A 1:2 GROUT MIXTURE
GRADE RINGS
AS NEEDED
ECCENTRIC
CONE
PRECAST
CONCRETE
RISER
PRECAST OR CAST IN
PLACE CONCRETE
BASE
#4 @ 12" EACH WAY
TOP FACE - 2" CLEAR
CAST-IN-PLACE
CONCRETE
BENCH
RIM OR TOP
ELEVATION
GROUT
SCALE N.T.S.
PRECAST STORM DRAIN MANHOLE
3/4" POLYPROPYLENE COATED
60 STEEL ROD SHAPED AS SHOWN
A4
A8
D5
E7
E9
D5/CU500
A
E7/CU500
A
E
C
U
A
CAST IRON
1" DIAMETER
I
S
D
R
A
T
O M
R
N
PLAN OF STORM DRAIN MANHOLE
D5/CU500
A
MANHOLE RUNGS TYPE
"SC", RE: E9/CU500
SCALE N.T.S.
PRECAST SANITARY SEWER MANHOLE
FOR MANHOLES LESS THAN 12' DEEP
6" MIN.
5'-10" MIN.
REQUIRED
ADJUSTED AS
SECTION TO BE
HEIGHT OF THIS
O.C., BOTH WAYS
#5 BARS 12"
D
D
MANHOLE RISER
2'-0"
4'-0"
OF BENCH
FROM TOP
2'-0" MAX
SEE DETAIL E9/CU500
TYPE "SA" RUNG
TYPE "SC" RUNGS
SEE DETAIL E9/CU500
8"
PRECAST
MORTAR
M
I N
V A
R I E
S
8"
S E
C T
I O
N
C
O N
E
5'-10" MIN.
#5 BARS
FRAME AND COVER
SEWER MANHOLE
SECTION "A"
SEE D5\CU500 AND E7/CU500
CONCRETE
FOOTING
NOTE: CONTRACTOR TO ADD BITUMASTIC
COATING TO THE EXTERIOR OF MANHOLES.
or 5'-0"
A1
A1/CU500
A
8" CONCRETE
WALLS
HOLE
PLAN
SECTION A
SCALE N.T.S.
WATERLINE OBSTRUCTION CROSSING
D1
NOTES
1. ALL VERTICAL ADJUSTMENTS TO THE EXISTING WATER MAINS SHALL BE DONE IN THIS MANNER.
USING PVC PIPE AND FITTINGS, HAVE THE SAME INSIDE DIAMETER AS THE EXISTING MAIN.
2. ALL MATERIALS AND COATING TO BE IN ACCORDANCE WITH THE SPECIFICATIONS.
3. METAL PIPING OR FITTINGS TO BE WRAPPED PER THE SPECIFICATIONS.
A M
E N
D M
E N
T
EXISTING
WATER LINE
M
I N
OBSTRUCTION
V
A
R
I
E
S
W
O
F
F
S
E
T
45° RESTRAINED JOINT
FITTINGS (TYP)
PVC PIPE (TYP)
VARIES
FLANGE CONN.
(TYP. TRANSITION BOTH ENDS)
4. FOR TRANSITIONS FROM TRANSITE TO PVC, USE FLEXIBLE COUPLING PVC 60 DURO SHORE A.
10/27/2020
W
2Q R
R
-0
T/SLAB
EL= 96'-8"
T/SLAB
EL= 100'-0" ±
T/FOOTING
EL= 95'-0"
SLAB ON GRADE, RE:
PLAN FOR REINF
GRANULAR SUBBASE,
PER SPECS
SLAB ON GRADE,
RE: PLAN FOR REINF
CONT #5 @ 18" O.C.
MAX
1/2" JOINT WITH
FILLER & SEALANT
#5 CORNER DOWEL TO MATCH
SLAB REINF SPACING
BARS TO MATCH SIZE
AND SPACING OF
SLAB REINF
(2) #5 CONT
(4) #5 CONT #5 @ 12" O.C.
#5 DOWELS @ 18" O.C.
VAPOR BARRIER
NOTES:
2. ROUGHEN SURFACES BETWEEN HORIZONTAL CONCRETE INTERFACES.
1. SAWCUT CONTROL JOINT PER C1/S-503. DO NOT DISCONTINUE SLAB AND TURNDOWN
REINFORCING AT JOINT.
CONTROL JOINT,
NOTE 1
1.5
R E
P
L A
N
R E
P
L A
N
7'-1 3/8"8" CONC
WALL
EQ EQ
3'-6"
4'-0"
T/SLAB EL
RE: PLAN
T/SLAB EL
VARIES
RE: PLAN
T/GRADE BEAM EL
RE: PLAN
SLAB ON GRADE, RE:
PLAN FOR REINF
BARS TO MATCH SIZE
AND SPACING OF
SLAB REINF
(2) #5 CONT
GRANULAR SUBBASE,
PER SPECS
SLAB ON GRADE, RE:
PLAN FOR REINF
CONT #5 @
12" O.C. MAX
GRADE BEAM,
RE: A4/S-302
1/2" JOINT WITH
FILLER & SEALANT
CONTROL JOINT,
NOTE 1
DOWELS TO MATCH
SIZE AND SPACING
OF SLAB REINF
2'-0"
2'-0"
#5 CORNER DOWEL TO
MATCH SPACING OF
SLAB REINF
#5 @ 18" O.C.
VAPOR BARRIER
NOTES:
2. ROUGHEN SURFACES BETWEEN
HORIZONTAL CONCRETE INTERFACES.
1. SAWCUT CONTROL JOINT PER C1/S-503.
DO NOT DISCONTINUE SLAB AND
TURNDOWN REINFORCING AT JOINT.
D
R E
P
L A
N
1'-4"
R E
P
L A
N
8"
C L R
T Y
P 2" CLR
TYP
8" CONC
WALL
EQ EQ
2'-6"
T/SLAB
EL= 96'-8"
T/SLAB EL
VARIES
RE: PLAN
T/FOOTING
EL= 95'-0"
GRANULAR SUBBASE,
PER SPECS
SLAB ON GRADE, RE:
PLAN FOR REINF
SLAB ON GRADE, RE:
PLAN FOR REINF
BARS TO MATCH SIZE AND
SPACING OF SLAB REINF
CONT #5 @ 12" O.C.
MAX
(2) #5 CONT
1/2" JOINT WITH
FILLER & SEALANT
#5 @ 12" O.C.
(4) #5 CONT
#5 CORNER DOWELS TO MATCH
SLAB REINF SPACING
#5 DOWELS @ 18" O.C.
NOTES:
2. ROUGHEN SURFACES BETWEEN HORIZONTAL CONCRETE INTERFACES.
1. SAWCUT CONTROL JOINT PER C1/S-503. DO NOT DISCONTINUE SLAB AND TURNDOWN REINFORCING AT JOINT.
VAPOR BARRIER
CONTROL JOINT,
NOTE 1
D
R E
P
L A
N
" R
E
P L A
N
8" CONC
WALL
8"
3'-6"
4'-0"
T/SLAB
EL= 100'-0" ±
T/SLAB EL
VARIES
RE: PLAN
T/FTG EL
RE: PLAN
GRANULAR SUBBASE,
PER SPECS
SLAB ON GRADE, RE:
PLAN FOR REINF
CONT #5 @ 18"
O.C. MAX
CORNER DOWELS TO
MATCH SIZE AND
SPACING OF SLAB REINF
SLAB ON GRADE, RE:
PLAN FOR REINF
#5 DOWELS @ 18" O.C.
(4) #5 CONT
#5 @ 12" O.C.
NOTES:
ROUGHEN SURFACES BETWEEN HORIZONTAL CONCRETE INTERFACES.1.
VAPOR BARRIER
D
R E
P
L A
N
8"
R E
P
L A
N
8"
4'-0"
CL
(2) #8 TOP,(3) #8
BOTTOM
(2) #5 CONT
BRICK VENEER
RE: ARCH
CONTROL JOINT,
NOTE 1
T/SLAB EL
RE: PLAN
T/GRADE BEAM
EL = 96'-0"
PAVING OR FINISHED
GRADE, RE: CIVIL
#3 @ 10" OC
SLAB ON GRADE
RE: PLAN FOR REINF
VAPOR BARRIER
MATCH SIZE AND
SPACING OF
SLAB REINF
#5 DOWELS @ 12"
OC AT MID-HEIGHT
GRANULAR SUBBASE
PER SPECIFICATIONS
1'-0"
2'-0"
F
RE: PLAN
1'-0"
7 1/2"
C L R
R E
P
L A
N
GROUT SOLID BETWEEN
SLAB AND BRICK W/
MASONRY GROUT
BRICK SUPPORT POST
PREPARED SUBGRADE
RE: SPECIFICATIONS
REINFORCING
RE: FOOTING
SCHEDULE ON
S-603
ADDITIONAL #8 BAR,
8'-0" LONG, CENTERED
ON POST
NOTES:
2. ROUGHEN SURFACES BETWEEN HORIZONTAL CONCRETE INTERFACES.
1. SAWCUT CONTROL JOINT PER C1/S-503. DO NOT DISCONTINUE SLAB AND TURNDOWN
REINFORCING AT JOINT.
RE: SCHEDULE
2"
CLR
2"
CLR
C L R
2'-6"
1'-3"
T/ SLAB EL
RE: PLAN
T/ FOOTING EL
RE: PLAN
T/ SLAB EL
RE: PLAN
SLAB ON GRADE
RE: PLAN FOR REINF
1/2" JOINT WITH FILLER
& SEALANT, TYP
VAPOR BARRIER
GRANULAR SUBBASE
PER SPECIFICATIONS
BARS TO MATCH SIZE
AND SPACING OF SLAB
REINF
NOTES: SEE A4/S-305 FOR INFORMATION NOT SHOWN.
#5 DOWELS
@ 16" O.C.
WALL BEYOND
4'-0"
T/ SLAB EL
RE: PLAN
SLAB ON GRADE
RE: PLAN FOR REINF
1/2" JOINT WITH FILLER
& SEALANT, TYP
VAPOR BARRIER
GRANULAR SUBBASE
PER SPECIFICATIONS
#5 DOWELS
@ 16" O.C.
WALL BEYOND
TYP
2" CLR
RE: SCHEDULE PREPARED SUBGRADE
RE: SPECIFICATIONS
REINFORCING
RE: SCHEDULE
C L R
(6) #5 CONT, REINFORCING
TO CONTINUE THROUGH
PIER
T/CONC
EL = 92-8"
T/FTG
EL = 90'-8"
BRICK VENEER RE: ARCH
SLAB-ON-GRADE
OR PAVING, RE:
CIVIL
#5 DOWELS @ 12" O.C.
#3 TIES @ 10" O.C.
GROUT SOLID BETWEEN
BRICK W/ MASONRY GROUT
NOTES:
1. ROUGHEN SURFACE BETWEEN HORIZONTAL CONCRETE INTERFACES.
SHEET ID
G
2 3 4 5 6 7 8 9 10
F
E
D
C
B
A
US Army Corps of Engineers
F Y
A
F R
C C
O N
S O
L
ID
A T
E D
M
IS
S
IO
N C
O M
P L
E X
P
H A
S E
R O
B
IN
S A
IR
F
O R
C E
B A
S E
G
E O
R G
IA
Louisville District ®
M A
R K
D E
S C
R
IP
T
IO
N
U S
A R
M Y
C O
R P
S O
F E
N G
IN
E
E R
S
D R
A W
N B
Y
D E
S
IG
N E
D B
Y
S U
B M
IT
T
E D
B Y
S
IZ
E
C H
E C
K E
D B
Y
A N
S I D x
IS
S
U E
D A
T E
C O
N T
R A
C T
N O
S O
L
IC
IT
A
T
IO
N N
O
D A
T E
M A
R K
D E
S C
R
IP
T
IO
N
D R
A W
IN
G
C O
D E
T B
D
T B
D
O
C T
V S
A R
O N
I F
IL
E
N A
M E
L O
U
IS
V
IL
L E
D
IS
T R
IC
U
IS
V
IL
L E
K
E N
T U
C K
Y
J A
C O
B S
E N
G
IN
E E
R
IN
G G
R O
U P
I N
C
M a in
S tr e e t, F o rt
W o rt h
T X
J A
C O
B S
N o
D
AMENDMENT 0003
P R
O J E
C T
N U
M B
E R
U
H H
Z P
T B
D
S-304
C O
N C
R E
T E
S E
C T
IO
N
S
D W
IS
N
IE
W
S K
I
M M
IL
L E
R
C S
A U
E R
U H
H Z
S
-3
SCALE 3/4" = 1'-0"
E1 SECTION AT SLAB STEP
SCALE 3/4" = 1'-0"
C1 SECTION AT RAMP SLAB AT GRADE BEAM
SCALE 3/4" = 1'-0"
A1 SECTION AT RAMP SLAB 0
SCALE: 3/4"=1'-0"
12 2
SCALE 3/4" = 1'-0"
E5 SECTION AT RAMP SLAB
SCALE 3/4" = 1'-0"
A5 SECTION AT BRICK SUPPORT POST
SCALE 3/4" = 1'-0"
D5 SECTION AT BRICK WALL SUPPORT - OPTION 2
SCALE 3/4" = 1'-0"
A8 SECTION AT WALL OPENING - OPTION 2
SCALE 3/4" = 1'-0"
D8 SECTION AT WALL OPENING - OPTION 2
A
M E
N D
M E
N T
O C
T
10/27/2020
W
2Q R
R
-0
G
14.5 15 16 17
H
G.6
F.9
D.8
37' - 0"27' - 8"7' - 5"
T/SLAB
EGDE OF SLAB-
ON-GRADE, TYP
EL = 96' - 8"
1:12
1:12
1:12
EL = 96' - 4"
T/SLAB
EL = 94' - 4"
T/SLAB
EL = 93' - 4"
EL = 96' - 0"
T/SLAB
EL = 95' - 8"
T/SLAB
EL = 95' - 4"
T/SLAB
EL = 95' - 0"
T/SLAB
EL = 94' - 8"
EL = 93' - 4"
T/SLAB
CMU WALL,
PER STRUCT
EL = 91' - 4"
T/SLAB
T/SLAB
T/SLAB
2' - 8"
R= 115' - 0"
45' - 4 3/8"92' - 0"
WORKING POINT
FOR CENTER OF
RADIUS OF
CURVED SLABS
R= 127' - 0"
T/FTG
T/FTG
T/FTG
F1 / 96' - 0"
F1 / 92' - 8"
F2 / 92' - 8"
F.S.
F.S.
F .S
F .S
F1 / 90' - 8"
F.S.
EL = 92' - 8"
EL = 94' - 8"
EL = 96' - 0"
EL = 92' - 0"
T/FTG
T/FTG
EL = 90' - 8"
T/FTG
EL = 92' - 0"
T/FTG
EL = 94' - 8"
T/FTG
EL = 92' - 8"
T/FTG
EL = 92' - 0"
T/FTG
EL = 96' - 0"
T/FTG
F .S
/8
9"
P1
P1
EL = 92' - 8"
F .S
F .S
EL = 90' - 8"
T/FTG
EL = 93' - 4"
T/SLAB
EL = 92' - 10"
T/SLAB
R= 106' - 1"
11' - 2 1/4"
C5 S-306
E1 S-306
A7 S-305
A7 S-305
E8 S-306
E8 S-306
C1 S-306
C8 S-306
A7 S-306
A4 S-306
A1 S-306
A4 S-306
A4 S-306
A1 S-306
A1 S-306
A1 S-306
A1 S-306
D5 S-306
A1 S-305
E1 S-305
E1 S-305
E1 S-305
EL = 96' - 8"
T/SLAB
E4 S-305
A8 S-304
E1 S-30518' - 0"
18' - 0"
A
F1 / 92' - 8"
D8 S-304
E7 S-305
E4 S-305
F1 / 94' - 0"
5' - 6"
/8
F
D8 S-304
D8 S-304
E7 S-305
A8 S-304
A4 S-305
TRUE NORTH
SCALE: 3/16"=1'-0"
48 8
THE RECORD
COPY OF THIS DRAWING
IS ON FILE AT THE OFFICES
IS RELEASED FOR THE PURPOSES OF
MANAGEMENT UNDER THE AUTHORITY OF
COORDINATION, AND/OR FACILITY
ARCHITECT/ENGINEER OF RECORD
76102. THIS ELECTRONIC DOCUMENT
NOT BE MODIFIED BY ANY PERSON
IT IS RELEASED.
UNDER WHOSE AUTHORITY
OTHER THAN THE PROFESSIONAL
THIS ELECTRONIC DOCUMENT MAY
OF JACOBS ENGINEERING GROUP
INC. 777 MAIN ST., FORT WORTH TX,
SHEET ID
G
2 3 4 5 6 7 8 9 10
F
E
D
C
B
A
US Army Corps of Engineers
F Y
A
F R
C C
O N
S O
L
ID
A T
E D
M
IS
S
IO
N C
O M
P L
E X
P
H A
S E
R O
B
IN
S A
IR
F
O R
C E
B A
S E
G
E O
R G
IA
Louisville District ®
M A
R K
D E
S C
R
IP
T
IO
N
U S
A R
M Y
C O
R P
S O
F E
N G
IN
E
E R
S
D R
A W
N B
Y
D E
S
IG
N E
D B
Y
S U
B M
IT
T
E D
B Y
S
IZ
E
C H
E C
K E
D B
Y
A N
S I D x
IS
S
U E
D A
T E
C O
N T
R A
C T
N O
S O
L
IC
IT
A
T
IO
N N
O
D A
T E
M A
R K
D E
S C
R
IP
T
IO
N
D R
A W
IN
G
C O
D E
T B
D
T B
D
O
C T
V S
A R
O N
I F
IL
E
N A
M E
L O
U
IS
V
IL
L E
D
IS
T R
U
IS
V
IL
L E
K
E N
T U
C K
Y
J A
C O
B S
E N
G
IN
E E
R
IN
G G
R O
U P
I N
C
M a in
S tr e e t, F o rt
W o rt h
T X
J A
C O
B S
N o
D
AMENDMENT 0003
KEY PLAN
P R
O J E
C T
N U
M B
E R
U
H H
Z P
T B
D
S-404
E N
L A
R G
E D
P L A
N S
D W
IS
N
IE
W
S K
I
M M
IL
L E
R
C S
A U
E R
U H
H Z
S
-4
OPT
SCALE 3/16" = 1'-0"
A1 ENLARGED PLAN - OPTION 2 - AUDITORIUM SLAB-ON-GRADE PLAN
NOTES:
1. SEE SHEET SB108 FOR GENERAL FOUNDATION NOTES.
2. F.S. - INDICATES WALL FOOTING STEP, RE: E3/S-504.
3. SEE SF101 FOR ELEVATED SLABS NOT SHOWN.
A
M E
N D
M E
N T
O C
T
10/27/2020
W
2Q R
R
-0
G
F
E
C.5
C
B
G.5
ELEC
CONTROL
AUDITORIUM
MECH
CORR
ACT-1
PT-1
CTB-1
CT-1
ACT-1/GYP-1/OTS-1
WP-1,3 / AWC-1,2,3
/PT-2,PT-3
RB-1
CPT-2/SC-2
OTS-1
PT-1
RB-1
SC-1
GREEN RM
ACT-1
PT-1 / PT-3
RB-1
CPT-2
OTS-1
PT-1 / AFP-1
RB-1
SC-1
ACT-1
PT-1
RB-1
CPT-2
114114
114114
OTS-1
PT-3
RB-1
CPT-2
OTS-1
PT-1
RB-1
CPT-2
ACT-1
PT-1/WP-1
CTB-1
CT-1
J
D
D.2
12.6 13.1 14 14.5 16 17
H
G.6
D.8
D.1
MECH YARD
100C
MENS
WOMENS
STG
130B
STG
130A
I-203A1
I-203
E1
C1
I-204E1 C1
120120
153153
153153
120120
I-201
A1 Sim
S226
S157
S158
175147
CORR
I-401
A8
I-402
A8
S255
I-204 A1
114114114114
S149
114114
114114
GYP-1
PT-1
RB-1
RF-1
STAIR 4
FINISH KEY LEGEND
CEILING FINISHES
ACT ACOUSTICAL CEILING TILE
EVC ELEVATOR CEILING
GYP PAINTED GYPSUM BOARD
OTS OPEN TO STRUCTURE
WALL FINISHES
AWC ACOUSTICAL WALL COVERING
EWP ELEVATOR WALL PANEL
FRP FIBER REINFORCED PANEL
PT PAINT
WP WALL PANEL
WT WALL TILE
BASE FINISHES
CTB PORCELAIN TILE BASE
CB METAL COVE TRANSITION
QTB QUARRY TILE BASE
RB RESILIENT BASE
FLOOR FINISHES
CPT CARPET TILE
CT PORCELAIN FLOOR TILE
QT QUARRY TILE
RF RESILIENT FLOORING
SC SEALED CONCRETE
SD STATIC DISSAPATIVE TILE
SDC STATIC DISSAPATIVE CARPET
WC WALK OFF CARPET TILE
CEILING FINISH
WALL FINISH
BASE FINISH
FLOOR FINISH
(ORIENTATION
OF FINISHES
IN FINISH
SYMBOL BOX)
BID OPTION LEGEND
HATCHED AREA INDICATES BASE
BID; REFER TO BASE BID DRAWINGS
TRUE NORTH
IGST
E S
R
NE
S A
ET
S T
A
I
RE
G
OF ET
X
E
ID
RE
IONTER R D
J E R I
L.
CHAM
PIN
E
164 8268
SCALE: 1/8"=1'-0"
SHEET ID
G
2 3 4 5 6 7 8 9 10
F
E
D
C
B
A
US Army Corps of Engineers
F Y
A
F R
C C
O N
S O
L
ID
A T
E D
M
IS
S
IO
N C
O M
P L
E X
P
H A
S E
R O
B
IN
S A
IR
F
O R
C E
B A
S E
G
E O
R G
IA
Louisville District ®
M A
R K
D E
S C
R
IP
T
IO
N
U S
A R
M Y
C O
R P
S O
F E
N G
IN
E
E R
S
D R
A W
N B
Y
D E
S
IG
N E
D B
Y
S U
B M
IT
T
E D
B Y
S
IZ
E
C H
E C
K E
D B
Y
A N
S I D x
IS
S
U E
D A
T E
C O
N T
R A
C T
N O
S O
L
IC
IT
A
T
IO
N N
O
D A
T E
M A
R K
D E
S C
R
IP
T
IO
N
D R
A W
IN
G
C O
D E
T B
D
T B
D
O
C T
V S
A R
O N
I F
IL
E
N A
M E
L O
U
IS
V
IL
L E
D
IS
T R
U
IS
V
IL
L E
K
E N
T U
C K
Y
J A
C O
B S
E N
G
IN
E E
R
IN
G G
R O
U P
I N
C
M a in
S tr e e t, F o rt
W o rt h
T X
J A
C O
B S
N o
D
CERTIFIED FINAL DESIGN
KEY PLAN
OPT
OPTION 2
P R
O J E
C T
N U
M B
E R
U
H H
Z P
B
A
C
ED
T B
D
IN108
P A
R T
IA
L F
IN
IS
H A
N D
S
IG
N A
G E
P L A
N
L E
V E
L
O
P T
IO
N
J C
H A
M P
IN
E
H M
C E
L R
O Y
S L E
B E
A U
U H
H Z
IN
SCALE 1/8" = 1'-0"
A1
PARTIAL FINISH AND SIGNAGE PLAN - LEVEL 1 - OPTION 2
GENERAL NOTES - FINISH PLANS
A FIELD VERIFY ALL DIMENSIONS PRIOR TO ORDERING
MATERIALS/FINISHES.
B REFER TO I-603 FOR FINISH LEGEND.
C ALL TRANSITIONS ARE TO OCCUR AT THE CENTERLINE
OF THE DOOR, DOORWAY OR CEILING LINE, UNLESS
OTHERWISE NOTED.
D REFER TO REFLECTED CEILING PLANS FOR ADDITIONAL
INFORMATION.
E APPLY BASE AS SPECIFIED ON GYPSUM BOARD. DO NOT
APPLY BASE TO CMU WALLS.
F DEMOUNTABLE PARTITIONS ARE PROVIDED AS PART OF
THE FURNITURE, FIXTURES, AND EQUIPMENT PACKAGE,
FUNDED SEPERATELY FROM THE CONSTRUCTION
CONTRACT. DEMOUNTABLE PARTITIONS ARE SHOWN
HALF-TONE SCREENED FOR COORDINATION ONLY.
FLOORING AND WALL BASE TO BE INSTALLED PRIOR TO
DEMOUNTABLE PARTIITON INSTALLATION.
KEYNOTES
114 CORNER GUARD CG-2. REFER TO FINISH LEGEND
120 PAINT PT-3.
147 AFS-1; FIXED AUDITORIUM SEATING, CFCI. REFER TO
FINISH SCHEDULE I-603
151 MOTORIZED CURTAIN AND TRACK-ASC-1; VERIFY VIDEO
SCREEN WITH CONTRACTING OFFICER TO ENSURE
ADEQUATE CLEARANCE BETWEEN SCREEN AND
CURTAIN. REFER TO F1/A-314 FOR DETAIL.
153 STAIR NOSING TO MATCH WALL BASE AS SCHEDULED; 2"
LEGS WITH SQUARE NOSE AND TAPERED EDGE; TYP ALL
RISERS IN AUDITORIUM.
174 STAGE CURTAIN DRAW MACHINE - HERCULES MODEL
6505 - COORDINATE WITH MECHANICAL
175 AFS-2; FIXED AUDITORIUM SEATING W / TABLET ARM,
CFCI. REFER TO FINISH SCHEDULE I-603
179 VIDEO MONITOR SCREEN 264"W X 148"H; REFER TO A.V.
DRAWINGS
182 FLOORING UNDER FIXED SEATING TO BE SEALED
CONCRETE SC-2; REFER TO FINISH SCHEDULE I-603
196 ROOM TO RECEIVE AFP-1 ON WALLS; COORDINATE WITH
MECHANICAL EQUIPMENT
A
M E
N D
M E
N T
O
C T
W
2Q R
R
-0
8 9 9.5 10 11 11.5 12 12.5 13
E
C.5
C
B
A
114114114
TYP. ALL
COLUMNS
AT EXTERIOR
WALL
111111
114114
114114114114
109105
132132
132 132 132 132 132 132 132 132 132 132 132 123123 123 123123123
ELEV
202A
STG
A1 STG
203E
STAIR 3
CORR
JAM
232P
JA CONF
232D
COURT
REPORTER
230C
CONF
FILING
232C
VISIT ATTY
230E
VISIT ATTY
230D
DELIBERATION
ROOM
230ACORR
BOARD
ROOM
230B
STAIR 4
MECH
ELEC
TR
BREAK
IG SIPR
CAFE
215H
JAN
TR
STG
215A
WOMENS
MENS
JA
JA
EVC-1
EWP-1
NO BASE
CT-1
ACT-1
PT-1
RB-1
CPT-1
ACT-1
FRP-1/PT-1
RB-1
CPT-1 ACT-1
PT-1
RB-1
CPT-1
OTS-1
FRP-1/PT-1
RB-1
SC-1
OTS-1
PT-1
RB-1
SD-1
ACT-1
PT-1
RB-1
CPT-1
ACT-1
PT-1
RB-1
RF-1
OTS-1
PT-1
RB-1
SC-1
OTS-1
PT-1
RB-1
SC-1
OTS-1
PT-1
RB-1
SD-1
ACT-1
PT-1
RB-1
CPT-1
ACT-1
PT-1
RB-1
CPT-1
ACT-1
PT-1
RB-1
CPT-1
OTS-1
PT-1
RB-1
SC-1
S161
S159
S164
S165
S166
S167
S168
S169
S170
S171S173S174S175S176S177S178S179S180S181S182S183S184S185
S186
S187 S188
S189
S190 S191
S193
S205
ACT-1
PT-1
RB-1
CPT-1
ACT-1
PT-2,3
RB-1
CPT-1
ACT-1
PT-1
RB-1
CPT-1
ACT-1
PT-1
RB-1
CPT-1
ACT-1
PT-1
RB-1
CPT-1
ACT-1
PT-1
RB-1
CPT-1
ACT-1
PT-1
RB-1
CPT-1
ACT-1
PT-2,3 / WP-1
RB-1
CPT-1
ACT-1
PT-1
RB-1
CPT-1
ACT-1
PT-2,3
RB-1
CPT-1
ACT-1
PT-1
RB-1
CPT-1
ACT-1
PT-1
RB-1
CPT-1
ACT-1
PT-1
RB-1
CPT-1
ACT-1
PT-1
RB-1
CPT-1
ACT-1
PT-1
RB-1
CPT-1
123123132132132132 132 132 132 132 132 132 132 132
ACT-1
PT-1
RB-1
CPT-1
ACT-1
PT-1
RB-1
CPT-1
ACT-1
PT-1
RB-1
CPT-1
ACT-1
PT-1
RB-1
CPT-1
ACT-1
PT-1
RB-1
CPT-1
ACT-1
PT-1
RB-1
CPT-1
ACT-1
PT-1
RB-1
CPT-1
ACT-1
PT-1
RB-1
CPT-1
ACT-1
PT-1
RB-1
CPT-1
ACT-1
PT-1
RB-1
CPT-1
ELECTRICAL
ACT-1
PT-1
RB-1
RF-1
IG
111111111
MATCHLINE
B1 IN110
D
D.2
12.6 13.1 14
D.8
D.1
0.A
I-401
A3
I-201
A1 Sim
I-202 C4
C1
A1
E1120120
120120
CT-1
CPT-1
CPT-1
CT-1
JA
120120
M A
T C
H L
IN
E
B
IN
M A
T C
H L
IN
E
C
IN
111111
106 106 106
S194
S195
S231
S232
S240
CORR
S241 S243
S244
S245 S246
S247
S248
S249 S250
S251
S145
S253
ACT-1
PT-1
RB-1
CPT-1
JA DIR
233E
JAZ
232F
JAO
232G
JAA
232H
JAA
232J
JAA
232M JAA
232K
JAA
232LVISIT ATTY
232N
JAM
232P
SUPER
233C
JA DEP DIR
233D
CC
233B VISIT ATTY
272D
VISIT ATTY
272C
S258
S259 276276276
I-202 E5
S im
(3)
/4
114114 114114
S272
FINISH KEY LEGEND
CEILING FINISHES
ACT ACOUSTICAL CEILING TILE
EVC ELEVATOR CEILING
GYP PAINTED GYPSUM BOARD
OTS OPEN TO STRUCTURE
WALL FINISHES
AWC ACOUSTICAL WALL COVERING
EWP ELEVATOR WALL PANEL
FRP FIBER REINFORCED PANEL
PT PAINT
WP WALL PANEL
WT WALL TILE
BASE FINISHES
CTB PORCELAIN TILE BASE
CB METAL COVE TRANSITION
QTB QUARRY TILE BASE
RB RESILIENT BASE
FLOOR FINISHES
CPT CARPET TILE
CT PORCELAIN FLOOR TILE
QT QUARRY TILE
RF RESILIENT FLOORING
SC SEALED CONCRETE
SD STATIC DISSAPATIVE TILE
SDC STATIC DISSAPATIVE CARPET
WC WALK OFF CARPET TILE
CEILING FINISH
WALL FINISH
BASE FINISH
FLOOR FINISH
(ORIENTATION
OF FINISHES
IN FINISH
SYMBOL BOX)
TRUE NORTH
IGST
E S
R
NE
S A
ET
S T
A
I
RE
G
OF ET
X
E
ID
RE
IONTER R D
J E R I
L.
CHAM
PIN
E
164 8268
SCALE: 1/8"=1'-0"
SHEET ID
G
2 3 4 5 6 7 8 9 10
F
E
D
C
B
A
US Army Corps of Engineers
F Y
A
F R
C C
O N
S O
L
ID
A T
E D
M
IS
S
IO
N C
O M
P L
E X
P
H A
S E
R O
B
IN
S A
IR
F
O R
C E
B A
S E
G
E O
R G
IA
Louisville District ®
M A
R K
D E
S C
R
IP
T
IO
N
U S
A R
M Y
C O
R P
S O
F E
N G
IN
E
E R
S
D R
A W
N B
Y
D E
S
IG
N E
D B
Y
S U
B M
IT
T
E D
B Y
S
IZ
E
C H
E C
K E
D B
Y
A N
S I D x
IS
S
U E
D A
T E
C O
N T
R A
C T
N O
S O
L
IC
IT
A
T
IO
N N
O
D A
T E
M A
R K
D E
S C
R
IP
T
IO
N
D R
A W
IN
G
C O
D E
T B
D
T B
D
O
C T
V S
A R
O N
I F
IL
E
N A
M E
L O
U
IS
V
IL
L E
D
IS
T R
U
IS
V
IL
L E
K
E N
T U
C K
Y
J A
C O
B S
E N
G
IN
E E
R
IN
G G
R O
U P
I N
C
M a in
S tr e e t, F o rt
W o rt h
T X
J A
C O
B S
N o
D
CERTIFIED FINAL DESIGN
KEY PLAN
E
AREA E
P R
O J E
C T
N U
M B
E R
U
H H
Z P
CB
D A
T B
D
IN113
P A
R T
IA
L F
IN
IS
H A
N D
S
IG
N A
G E
P L A
N
L E
V E
L
A
R E
A E
J C
H A
M P
IN
E
H M
C E
L R
O Y
S L E
B E
A U
U H
H Z
IN
1/8" = 1'-0"B1
PARTIAL FINISH AND SIGNAGE PLAN - LEVEL 2 - AREA E
GENERAL NOTES - FINISH PLANS
A FIELD VERIFY ALL DIMENSIONS PRIOR TO ORDERING
MATERIALS/FINISHES.
B REFER TO I-603 FOR FINISH LEGEND.
C ALL TRANSITIONS ARE TO OCCUR AT THE CENTERLINE
OF THE DOOR, DOORWAY OR CEILING LINE, UNLESS
OTHERWISE NOTED.
D REFER TO REFLECTED CEILING PLANS FOR ADDITIONAL
INFORMATION.
E APPLY BASE AS SPECIFIED ON GYPSUM BOARD. DO NOT
APPLY BASE TO CMU WALLS.
F DEMOUNTABLE PARTITIONS ARE PROVIDED AS PART OF
THE FURNITURE, FIXTURES, AND EQUIPMENT PACKAGE,
FUNDED SEPERATELY FROM THE CONSTRUCTION
CONTRACT. DEMOUNTABLE PARTITIONS ARE SHOWN
HALF-TONE SCREENED FOR COORDINATION ONLY.
FLOORING AND WALL BASE TO BE INSTALLED PRIOR TO
DEMOUNTABLE PARTIITON INSTALLATION.
KEYNOTES
105 PAINT STRINGER AND HANDRAIL PT-4.
106 PAINT COLUMN WRAPS PT-1.
109 STAIR TREADS/RISERS AND LANDINGS RF-1.
111 CORNER GUARD CG-1. REFER TO FINISH LEGEND.
114 CORNER GUARD CG-2. REFER TO FINISH LEGEND
120 PAINT PT-3.
123 INSTALL WS-2 WINDOW SHADE AT CONFERENCE
PERIMETER WINDOWS. REFER TO ARCHITECTURE AND
INTERIOR FINISH LEGEND FOR DETAILS.
132 INSTALL WS-1 WINDOW SHADE AT EXTERIOR WINDOWS,
UON. REFER TO FINISH LEGEND ON SHEET I-603.
276 RECESSED, PREFABRICATED CELL PHONE LOCKERS.
ALUMINIUM FINISH. CFCI.
OMITTED
OMITTED
A
M E
N D
M E
N T
O
C T
A
M E
N D
M E
N T
O
C T
W
2Q R
R
-0
| CIVIL |
| CS111 - SITE PLAN - AREA 1 - OPTIONS 1 & 2 |
| CU101 - UTILITY PLAN - AREA 1 |
| CU102 - UTILITY PLAN - AREA 2 |
| CU500 - UTILITY DETAILS |
| STRUCTURAL |
| S-304 - CONCRETE SECTIONS |
| S-404 - ENLARGED PLANS |
| INTERIORS |
| IN108 - PARTIAL FINISH AND SIGNAGE PLAN -LEVEL 1 -OPTION 2 |
| IN113 - PARTIAL FINISH AND SIGNAGE PLAN -LEVEL 2 -AREA E |
File details come from the government source that posted it. Updated .