This document is a request for proposal for the design and construction of an electrical substation and underground distribution system at the Detroit Arsenal in Warren, Michigan. The project includes construction of high and low voltage substations with associated transformers, switchgears, duct banks and cabling. Supporting facilities such as site development, paving, fencing and utilities are also required. The contract will have a duration of approximately 730 calendar days. This is a two-phase design-build procurement using a best value tradeoff selection process. Phase I will evaluate past performance and management approach, while Phase II will assess design/technical approach, small business participation, and price. The North American Industry Classification System code for this effort is 237130. The magnitude of construction is estimated between $10-25 million.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MILITARY/RESERVE BRANCH
ATTN: BLAKE GEVEDON
600 DR M L KING JR PL RM 821
LOUISVILLE KY 40202-2236
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Solicitation W912QR20R0008 for the Design and Construction of a high-voltage substation at Detroit Arsenal, MI is hereby modif ied as follow s:
SEE THE ATTACHED SUMMARY OF CHANGES
1. CONTRACT ID CODE PAGE OF PAGES
1 42
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912QR20R0008
X 9B. DATED (SEE ITEM 11)
23-Dec-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
15-May-2020
CODE
U. S. ARMY ENGINEER DISTRICT, LOUISVILLE
600 DR. MARTIN LUTHER KING, JR. PLACE
ROOM 821
LOUISVILLE KY 40202-2239
W912QR 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE 964859
FACILITY CODECODE
EMAIL:TEL:
W912QR20R0008-0005
W912QR20R0008
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been modified:
SUMMARY OF CHANGES
Summary of Changes Amendment 0005 DTA Electrical Substation
A. 1. The following SPECIFICATION SECTIONS have been replaced in their entirety:
01 02 10.00 06 General Requirements
2. The following ATTACHMENTS have been replaced in their entirety:
ATTACHMENT 11 – EXCERPTS FROM DETROIT ARSENAL ELECTRICAL MANHOLE
STUDY
B. Wage Decisions MI20200001 and MI20200065 have been revised
C. The proposal due date for receipt of Phase II proposals is changed from Thursday, 21 May 2020 at 4:00 PM Eastern Time to Thursday, 28 May 2020 at 4:00 PM Eastern Time
All other terms and conditions of this solicitation remain unchanged.
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 21-May-2020 04:00 PM to 28-May-2020 04:00 PM.
SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS
The following have been modified:
WAGE RATES
"General Decision Number: MI20200065 05/08/2020
Superseded General Decision Number: MI20190065
State: Michigan
Construction Type: Heavy
County: Macomb County in Michigan.
Heavy, Includes Water and Sewer Lines, Excavation (Excludes Hazardous Waste Removal; Coal, Oil, Gas, Duct and other similar Pipeline Construction)
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.80 for calendar year 2020 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.80 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2020. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/03/2020 1 05/08/2020
BOIL0169-003 03/01/2018
Rates Fringes
BOILERMAKER......................$ 38.65 26.22
CARP0687-008 06/01/2019
Rates Fringes
CARPENTER, Includes Form Work....$ 32.70 28.94
PILEDRIVERMAN....................$ 32.70 28.94
ELEC0017-003 06/03/2019
Rates Fringes
LINE CONSTRUCTION:
Linemen/Cable Splicer............$ 46.40 20.62
* ELEC0058-007 09/01/2019
Rates Fringes
ELECTRICIAN......................$ 42.39 24.85
ENGI0325-019 09/01/2019
POWER EQUIPMENT OPERATORS: Underground Construction (Including Sewer)
POWER EQUIPMENT OPERATOR
GROUP 1.....................$ 34.63 24.35
GROUP 2.....................$ 29.90 24.35
GROUP 3.....................$ 29.17 24.35
GROUP 4.....................$ 28.60 24.35
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: Backhoe/ Excavator, Boring Machine, Bulldozer, Crane, Grader/ Blade, Loader, Roller, Scraper, Trencher (over 8 ft. digging capacity)
GROUP 2: Trencher (8-ft digging capacity and smaller)
GROUP 3: Boom Truck (non-swinging, non- powered type boom)
GROUP 4: Broom/ Sweeper, Fork Truck, Tractor, Bobcat/ Skid Steer /Skid Loader
ENGI0326-008 06/01/2019
EXCLUDES UNDERGROUND CONSTRUCTION
Rates Fringes
OPERATOR: Power Equipment
GROUP 1....................$ 41.89 24.45
GROUP 2....................$ 40.39 24.45
GROUP 3....................$ 38.89 24.45
GROUP 4....................$ 38.59 24.45
GROUP 5....................$ 37.77 24.45
GROUP 6....................$ 36.91 24.45
GROUP 7....................$ 35.94 24.45
GROUP 8....................$ 34.23 24.45
GROUP 9....................$ 25.89 24.45
FOOTNOTES: Tower cranes: to be paid the crane operator rate determined by the combined length of the mast and the boom.
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: Crane with boom & jib or leads 400' or longer
GROUP 2: Crane with boom & jib or leads 300' or longer
GROUP 3: Crane with boom & jib or leads 220' or longer
GROUP 4: Crane with boom & jib or leads 140' or longer
GROUP 5: Crane with boom & jib or leads 120' or longer
GROUP 6: Regular crane operator
GROUP 7: Backhoe/Excavator, Bobcat/Skid Loader, Boring Machine, Broom/Sweeper, Bulldozer, Grader/Blade, Loader, Roller, Scraper, Tractor, Trencher
GROUP 8: Forklift
GROUP 9: Oiler
IRON0025-006 06/01/2019
Rates Fringes
IRONWORKER
Reinforcing.................$ 30.98 27.99 Structural..................$ 36.77 29.03
LABO0334-009 06/01/2019
EXCLUDES OPEN CUT CONSTRUCTION
Rates Fringes
Landscape Laborer
GROUP 1.....................$ 20.75 7.10
GROUP 2.....................$ 18.75 7.10
LANDSCAPE LABORER CLASSIFICATIONS
GROUP 1: Landscape specialist, including air, gas and diesel equipment operator, lawn sprinkler installer and skidsteer (or equivalent)
GROUP 2: Landscape laborer: small power tool operator, material mover, truck driver and lawn sprinkler installer tender
LABO0334-021 09/01/2018
SCOPE OF WORK:
OPEN CUT CONSTRUCTION: Excavation of earth and sewer, utilities, and improvements, including underground piping/conduit (including inspection, cleaning, restoration, and relining)
LABORER
(1) Common or General.......$ 22.42 16.80
(2) Mason Tender- Cement/Concrete.............$ 22.53 16.80
(4) Grade Checker...........$ 22.66 16.80
(5) Pipelayer...............$ 22.72 16.80
(7) Landscape...............$ 16.79 16.80
LABO1191-004 06/01/2019
EXCLUDES OPEN CUT CONSTRUCTION
Rates Fringes
Laborers:
Common or General; Grade Checker; Mason Tender - Cement/Concrete; Pipelayer..$ 28.55 16.85
PAIN0022-005 07/01/2008
Rates Fringes
PAINTER
Brush & Roller..............$ 25.06 14.75 Spray.......................$ 25.86 14.75
PLAS0067-002 04/01/2014
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 30.63 14.07
PLUM0098-005 06/01/2019
PLUMBER..........................$ 35.77 35.13
PLUM0636-002 06/05/2017
Rates Fringes
PIPEFITTER.......................$ 40.41 29.35
TEAM0007-006 06/01/2019
Rates Fringes
TRUCK DRIVER
Dump Truck under 8 cu.
yds.; Tractor Haul Truck....$ 27.15 .50 + a+b Dump Truck, 8 cu. yds. and over........................$ 27.25 .50 + a+b Lowboy/Semi-Trailer Truck...$ 27.40 .50 + a+b
FOOTNOTE:
a. $446.70 per week.
b. $67.00 daily.
SUMI2010-063 11/09/2010
Rates Fringes
TRUCK DRIVER: Off the Road Truck............................$ 20.82 3.69
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator
U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION"
"General Decision Number: MI20200001 05/08/2020
Superseded General Decision Number: MI20190001
State: Michigan
Construction Types: Highway (Highway, Airport & Bridge xxxxx and Sewer/Incid. to Hwy.)
Counties: Michigan Statewide.
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.80 for calendar year 2020 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.80 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2020. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/03/2020 1 01/24/2020 2 02/07/2020 3 05/08/2020
CARP0004-004 06/01/2019
REMAINDER OF STATE
Rates Fringes
CARPENTER ( Piledriver)..........$ 27.62 20.59
CARP0004-005 06/01/2018
LIVINGSTON (Townships of Brighton, Deerfield, Genoa, Hartland, Oceola & Tyrone), MACOMB, MONROE, OAKLAND, SANILAC, ST. CLAIR
AND WAYNE COUNTIES
CARPENTER (Piledriver)...........$ 30.50 27.28
ELEC0017-005 06/03/2019
STATEWIDE
Rates Fringes
Line Construction Groundman/Driver............$ 28.58 15.27 Journeyman Signal Tech, Communications Tech, Tower Tech & Fiber Optic Splicers.$ 40.35 18.80 Journeyman Specialist.......$ 46.40 20.62 Operator A..................$ 34.10 16.93 Operator B..................$ 31.84 16.25
Classifications
Journeyman Specialist: Refers to a crew of only one person working alone.
Operator A: Shall be proficient in operating all power equipment including: Backhoe, Excavator, Directional Bore and Boom/Digger truck.
Operator B: Shall be proficient in operating any 2 of the above mentioned pieces of equipment listed under Operator A.
ENGI0324-003 06/01/2019
ALCONA, ALPENA, ARENAC, BAY, CHEBOYGAN, CLARE, CLINTON,
CRAWFORD, GENESEE, GLADWIN, GRATIOT, HURON, INGHAM, IOSCO,
ISABELLA, JACKSON, LAPEER, LENAWEE, LIVINGSTON, MACOMB,
MIDLAND, MONROE, MONTMORENCY, OAKLAND, OGEMAW, OSCODA, OTSEGO,
PRESQUE ISLE, ROSCOMMON, SAGINAW, ST. CLAIR, SANILAC,
SHIAWASSEE, TUSCOLA, WASHTENAW AND WAYNE COUNTIES:
OPERATOR: Power Equipment (Steel Erection)
GROUP 1....................$ 46.52 24.35
GROUP 2....................$ 47.52 24.35
GROUP 3....................$ 45.02 24.35
GROUP 4....................$ 46.02 24.35
GROUP 5....................$ 43.52 24.35
GROUP 6....................$ 44.52 24.35
GROUP 7....................$ 43.25 24.35
GROUP 8....................$ 44.25 24.35
GROUP 9....................$ 42.80 24.35
GROUP 10....................$ 43.80 24.35
GROUP 11....................$ 42.07 24.35
GROUP 12....................$ 43.07 24.35
GROUP 13....................$ 41.71 24.35
GROUP 14....................$ 42.71 24.35
GROUP 15....................$ 41.07 24.35
GROUP 16....................$ 38.37 24.35
GROUP 17....................$ 23.89 11.50
GROUP 18....................$ 27.38 11.50
FOOTNOTE:
Paid Holidays: New Year's Day, Memorial Day, Fourth of July, Labor Day, Thanksgiving Day and Christmas Day.
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: Engineer when operating combination of boom and jib 400' or longer
GROUP 2: Engineer when operating combination of boom and jib 400' or longer on a crane that requires an oiler
GROUP 3: Engineer when operating combination of boom and jib 300' or longer
GROUP 4: Engineer when operating combination of boom and jib 300' or longer on a crane that requires an oiler
GROUP 5: Engineer when operating combination of boom and jib 220' or longer
GROUP 6: Engineer when operating combination of boom and jib 220' or longer on a crane that requires an oiler
GROUP 7: Engineer when operating combination of boom and jib 140' or longer
GROUP 8: Engineer when operating combination of boom and jib 140' or longer on a crane that requires an oiler
GROUP 9: Tower crane & derrick operator (where operator's work station is 50 ft. or more above first sub-level)
GROUP 10: Tower crane & derrick operator (where operator's work station is 50 ft. or more above first sub-level) on a crane that requires an oiler
GROUP 11: Engineer when operating combination of boom and jib 120' or longer
GROUP 12: Engineer when operating combination of boom and jib
120' or longer on a crane that requires an oiler
GROUP 13: Crane operator; job mechanic and 3 drum hoist and excavator
GROUP 14: Crane operator on a crane that requires an oiler
GROUP 15: Hoisting operator; 2 drum hoist and rubber tired backhoe
GROUP 16: Forklift and 1 drum hoist
GROUP 17: Compressor or welder operator
GROUP 18: Oiler
ENGI0324-004 06/01/2019
AREA 1: ALLEGAN, BARRY, BERRIEN, BRANCH, CALHOUN, CASS, EATON,
HILLSDALE, IONIA, KALAMAZOO, KENT, LAKE, MANISTEE, MASON,
MECOSTA, MONTCALM, MUSKEGON, NEWAYGO, OCEANA, OSCEOLA, OTTAWA,
ST. JOSEPH, VAN BUREN
AREA 2: ANTRIM, BENZIE, CHARLEVOIX, EMMET, GRAND TRAVERSE,
KALKASKA, LEELANAU, MISSAUKEE AND WEXFORD COUNTIES:
(Steel Erection)
AREA 1
GROUP 1....................$ 46.52 24.35
GROUP 2....................$ 43.25 24.35
GROUP 3....................$ 41.71 24.35
GROUP 4....................$ 38.37 24.35
GROUP 5....................$ 23.89 11.50
GROUP 6....................$ 27.38 11.50
AREA 2
GROUP 1....................$ 46.52 24.35
GROUP 2....................$ 43.25 24.35
GROUP 3....................$ 41.71 24.35
GROUP 4....................$ 38.37 24.35
GROUP 5....................$ 23.89 11.50
GROUP 6....................$ 27.38 11.50
FOOTNOTES:
Crane operator with main boom and jib 300' or longer: $1.50 additional to the group 1 rate. Crane operator with main boom and jib 400' or longer: $3.00 additional to the group 1 rate.
PAID HOLIDAYS: New Year's Day, Memorial Day, Fourth of July, Labor Day, Thanksgiving Day and Christmas Day.
POWER EQUIPMENT OPERATOR CLASSIFICATIONS:
GROUP 1: Crane Operator with main boom & jib 400', 300', or 220' or longer.
GROUP 2: Crane Operator with main boom & jib 140' or longer, Tower Crane; Gantry Crane; Whirley Derrick.
GROUP 3: Regular Equipment Operator, Crane, Dozer, Loader, Hoist, Straddle Wagon, Mechanic, Grader and Hydro Excavator.
GROUP 4: Air Tugger (single drum), Material Hoist Pump 6"" or over, Elevators, Brokk Concrete Breaker.
GROUP 5: Air Compressor, Welder, Generators, Conveyors
GROUP 6: Oiler and fire tender
ENGI0324-005 09/01/2019
AREA 1: GENESEE, LAPEER, LIVINGSTON, MACOMB, MONROE, OAKLAND,
ST. CLAIR, WASHTENAW AND WAYNE COUNTIES
AREA 2: ALCONA, ALLEGAN, ALGER, ALPENA, ANTRIM, ARENAC, BARAGA,
BARRY, BAY, BENZIE, BERRIEN, BRANCH, CALHOUN, CASS,
CHARLEVOIX, CHEBOYGAN, CHIPPEWA, CLARE, CLINTON, CRAWFORD,
DELTA, DICKINSON, EATON, EMMET, GLADWIN, GOGEBIC, GRAND
TRAVERSE, GRATIOT, HILLSDALE, HOUGHTON, HURON, INGHAM, IONIA,
IOSCO, IRON, ISABELLA, JACKSON, KALAMAZOO, KALKASKA, KENT,
KWEENAW, LAKE, LEELANAU, LENAWEE, LUCE, MACKINAC, MANISTEE,
MARQUETTE, MASON, MECOSTA, MENOMINEE, MIDLAND, MISSAUKEE,
MONTCALM, MONTMORENCY, MUSKEGON, NEWAYGO, OCEANA, OGEMAW,
ONTONAGON, OSCEOLA, OSCODA, OTSEGO, OTTAWA, PRESQUE ISLE,
ROSCOMMON, SAGINAW, SANILAC, SCHOOLCRAFT, SHIAWASSEE, ST.
JOSEPH, TUSCOLA, VAN BUREN AND WEXFORD COUNTIES
(Underground construction (including sewer))
AREA 1:
GROUP 1....................$ 34.63 24.35
GROUP 2....................$ 29.90 24.35
GROUP 3....................$ 29.17 24.35
GROUP 4....................$ 28.60 24.35
GROUP 5....................$ 21.40 13.48
AREA 2:
GROUP 1....................$ 32.92 24.35
GROUP 2....................$ 28.03 24.35
GROUP 3....................$ 27.53 24.35
GROUP 4....................$ 27.25 24.35
GROUP 5....................$ 21.40 13.48
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: Backfiller tamper; Backhoe; Batch plant operator (concrete); Clamshell; Concrete paver (2 drums or larger);
Conveyor loader (Euclid type); Crane (crawler, truck type or pile driving); Dozer; Dragline; Elevating grader;
Endloader; Gradall (and similar type machine); Grader;
Mechanic; Power shovel; Roller (asphalt); Scraper (self-propelled or tractor drawn); Side boom tractor (type D-4 or equivalent and larger); Slip form paver; Slope paver; Trencher (over 8 ft. digging capacity); Well drilling rig; Concrete pump with boom operator; Hydro Excavator
GROUP 2: Boom truck (power swing type boom); Crusher; Hoist;
Pump (1 or more - 6-in. discharge or larger - gas or diesel- powered or powered by generator of 300 amperes or more - inclusive of generator); Side boom tractor (smaller than type D-4 or equivalent); Tractor (pneu-tired, other than backhoe or front end loader); Trencher (8-ft. digging capacity and smaller);Vac Truck and End dump operator;
GROUP 3: Air compressors (600 cfm or larger); Air compressors (2 or more-less than 600 cfm); Boom truck (non-swinging, non- powered type boom); Concrete breaker (self-propelled or truck mounted - includes compressor); Concrete paver (1 drum-l/2 yd. or larger); Elevator (other than passenger);
Maintenance person; Pump (2 or more-4-in. up to 6-in.
discharge-gas or diesel powered - excluding submersible pumps); Pumpcrete machine (and similar equipment); Wagon drill (multiple); Welding machine or generator (2 or more-300 amp. or larger - gas or diesel powered)
GROUP 4: Boiler; Concrete saw (40 hp or over); Curing machine (self-propelled); Farm tractor (with attachment); Finishing machine (concrete); Hydraulic pipe pushing machine;
Mulching equipment; Pumps (2 or more up to 4-in. discharge, if used 3 hours or more a day, gas or diesel powered -excluding submersible pumps); Roller (other than asphalt);
Stump remover; Trencher (service); Vibrating compaction equipment, self-propelled (6 ft. wide or over); Sweeper (Wayne type); Water wagon and Extend-a boom forklift
Group 5: Fire Person, Oiler
* ENGI0324-006 06/01/2019
GENESEE, MACOMB, MONROE, OAKLAND, WASHTENAW, WAYNE, ALCONA,
ALGER, ALLEGAN, ALPENA, ANTRIM, ARENAC, BARAGA, BARRY, BAY,
BENZIE, BERRIEN, BRANCH, CALHOUN, CASS, CHARLEVOIX, CHEBOYGAN,
CHIPPEWA, CLARE, CLINTON, CRAWFORD, DELTA, DICKINSON, EATON,
EMMET, GLADWIN, GOGEBIC, GRAND TRAVERSE, GRATIOT, HILLSDALE,
HOUGHTON, HURON, INGHAM, IONIA, IOSCO, IRON, ISABELLA, JACKSON,
KALAMAZOO, KALKASKA, KENT, KEWEENAW, LAKE, LAPEER, LEELANAU,
LENAWEE, LIVINGSTON, LUCE, MACKINAC, MANISTEE, MARQUETTE,
MASON, MECOSTA, MENOMINEE, MIDLAND, MISSAUKEE, MONTCALM,
MONTMORENCY, MUSKEGON, NEWAYGO, OCEANA, OGEMAW, ONTONAGON,
OSCEOLA, OSCODA, OTSEGO, OTTAWA, PRESQUE ISLE, ROSCOMMON,
SAGINAW, ST. CLARE, ST. JOSEPH, SANILAC, SCHOOLCRAFT,
SHIAWASSEE, TUSCOLA, VAN BUREN AND WEXFORD COUNTIES
Power equipment operators:
(AIRPORT, BRIDGE & HIGHWAY
CONSTRUCTION)
GROUP 1.....................$ 34.16 24.35
GROUP 2.....................$ 27.43 24.35
GROUP 3.....................$ 26.87 24.35
GROUP 4.....................$ 26.70 24.35
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: Asphalt plant operator; Crane operator (does not include work on bridge construction projects when the crane operator is erecting structural components); Dragline operator; Shovel operator; Locomotive operator; Paver operator (5 bags or more); Elevating grader operator; Pile driving operator; Roller operator (asphalt); Blade grader operator; Trenching machine operator (ladder or wheel type); Auto-grader; Slip form paver; Self-propelled or tractor-drawn scraper; Conveyor loader operator (Euclid type); Endloader operator (1 yd. capacity and over);
Bulldozer; Hoisting engineer; Tractor operator; Finishing machine operator (asphalt); Mechanic; Pump operator (6-in.
discharge or over, gas, diesel powered or generator of 300 amp. or larger); Shouldering or gravel distributing machine operator (self- propelled); Backhoe (with over 3/8 yd.
bucket); Side boom tractor (type D-4 or equivalent or larger); Tube finisher (slip form paving); Gradall (and similar type machine); Asphalt paver (self- propelled);
Asphalt planer (self-propelled); Batch plant (concrete-central mix); Slurry machine (asphalt); Concrete pump (3 in. and over); Roto-mill; Swinging boom truck (over 12 ton capacity); Hydro demolisher (water blaster);
Farm-type tractor with attached pan; Vacuum truck operator;
Batch Plant (concrete dry batch); Concrete Saw Operator (40h.p. or over; Tractor Operator (farm type); Finishing Machine Operator (concrete); Grader Operator (self-propelled fine grade or form (concrete)).
GROUP 2: Screening plant operator; Washing plant operator;
Crusher operator; Backhoe (with 3/8 yd. bucket or less);
Side boom tractor (smaller than D-4 type or equivalent);
Sweeper (Wayne type and similar equipment); Greese Truck;
Air Compressor Operator (600 cu.ft. per min or more); Air
Compressor Operator (two or more, less than 600 cfm);
GROUP 3: Boiler fire tender; Tractor operator (farm type with attachment); Concrete Breaker; Wagon Drill Operator;
GROUP 4: Oiler; Fire tender; Trencher (service); Flexplane operator; Cleftplane operator; Boom or winch hoist truck operator; Endloader operator *under 1 yd. capacity); Roller Operator (other than asphalt); Curing equipment operator (self-propelled); Power bin operator; Plant drier (6 ft.
wide or over); Guard post driver operator (power driven);
All mulching equipment; Stump remover; Concrete pump (under 3-in.); Mesh installer (self-propelled); End dump; Skid Steer.
ENGI0324-007 05/01/2019
ALGER, BARAGA, CHIPPEWA, DELTA, DICKINSON, GOGEBIC, HOUGHTON,
IRON, KEWEENAW, LUCE, MACKINAC MARQUETTE, MENOMINEE, ONTONAGON
AND SCHOOLCRAFT COUNTIES:
(Steel Erection) Compressor, welder and forklift....................$ 33.90 24.10 Crane operator, main boom & jib 120' or longer........$ 39.87 24.10 Crane operator, main boom & jib 140' or longer........$ 40.17 24.10 Crane operator, main boom & jib 220' or longer........$ 40.76 24.10 Mechanic with truck and tools.......................$ 39.00 24.10 Oiler and fireman...........$ 31.86 24.10 Regular operator............$ 37.22 24.10
ENGI0324-008 10/01/2015
ALCONA, ALGER, ALLEGAN, ALPENA, ANTRIM, ARENAC, BARAGA, BARRY,
BAY, BENZIE, BERRIEN, BRANCH, CALHOUN, CASS, CHARLEVOIX,
CHEBOYGAN, CHIPPEWA, CLARE, CLINTON, CRAWFORD, DELTA,
DICKINSON, EATON, EMMET, GENESEE, GLADWIN, GOGEBIC, GRAND
TRAVERSE, GRATIOT, HILLSDALE, HOUGHTON, HURON, INGHAM, IONIA,
IOSCO, IRON, ISABELLA, JACKSON, KALAMAZOO, KALKASKA, KENT,
KEWEENAW, LAKE, LAPEER, LEELANAU, LENAWEE, LIVINGSTON, LUCE,
MACKINAC, MACOMB, MANISTEE, MARQUETTE, MASON, MECOSTA,
MENOMINEE, MIDLAND, MISSAUKEE, MONTCALM, MONTMORENCY, MONROE,
MUSKEGON, NEWAYGO, OAKLAND, OCEANA, OGEMAW, ONTONAGON, OSCEOLA,
OSCODA, OTSEGO, OTTAWA, PRESQUE ISLE, ROSCOMMON, SAGINAW, ST.
CLARE, ST. JOSEPH, SANILAC, SCHOOLCRAFT, SHIAWASSEE, TUSCOLA,
VAN BUREN, WASHTENAW, WAYNE AND WEXFORD COUNTIES
(Sewer Relining)
GROUP 1.....................$ 30.70 12.93
GROUP 2.....................$ 29.17 12.93
SEWER RELINING CLASSIFICATIONS
GROUP 1: Operation of audio-visual closed circuit TV system, including remote in-ground cutter and other equipment used in connection with the CCTV system
GROUP 2: Operation of hot water heaters and circulation systems, water jetters and vacuum and mechanical debris removal systems
* ENGI0325-012 05/01/2020
Rates Fringes
Power equipment operators -gas distribution and duct installation work:
GROUP 1.....................$ 32.18 24.85
GROUP 2.....................$ 32.06 24.85
GROUP 3.....................$ 30.35 24.85
SCOPE OF WORK: The construction, installation, treating and reconditioning of pipelines transporting gas vapors within cities, towns, subdivisions, suburban areas, or within private property boundaries, up to and including private meter settings of private industrial, governmental or other premises, more commonly referred to as ""distribution work,"" starting from the first metering station, connection, similar or related facility, of the main or cross country pipeline and including duct installation.
Group 1: Backhoe, crane, grader, mechanic, dozer (D-6 equivalent or larger), side boom (D-4 equivalent or larger), trencher(except service), endloader (2 yd.
capacity or greater).
GROUP 2: Dozer (less than D-6 equivalent), endloader (under 2 yd. capacity), side boom (under D-4 capacity), backfiller, pumps (1 or 2 of 6-inch discharge or greater), boom truck (with powered boom), tractor (wheel type other than backhoe or front endloader). Tamper (self-propelled), boom truck (with non-powered boom), concrete saw (20 hp or larger), pumps (2 to 4 under 6-inch discharge), compressor (2 or more or when one is used continuously into the second day) and trencher(service).
GROUP 3: Oiler, hydraulic pipe pushing machine, grease person and hydrostatic testing operator.
IRON0008-007 06/01/2019
ALGER, BARAGA, CHIPPEWA, DELTA, DICKINSON, GOGEBIC, HOUGHTON,
IRON, KEWEENAW, LUCE, MACKINAC MARQUETTE, MENOMINEE, ONTONAGON
Ironworker - pre-engineered metal building erector...........$ 23.70 6.95
IRONWORKER
General contracts $10,000,000 or greater......$ 33.00 27.12 General contracts less than $10,000,000............$ 33.00 27.12
Paid Holidays: New Year's Day, Memorial Day, July 4th, Labor Day, Thanksgiving Day & Christmas Day.
IRON0025-002 06/01/2019
ALCONA, ALPENA, ARENAC, BAY, CHEBOYGAN, CLARE, CLINTON,
CRAWFORD, GENESEE, GLADWIN, GRATIOT, HURON, INGHAM, IOSCO,
ISABELLA, JACKSON, LAPEER, LIVINGSTON, MACOMB, MIDLAND,
MONTMORENCY, OAKLAND, OGEMAW, OSCODA, OTSEGO, PRESQUE ISLE,
ROSCOMMON, SAGINAW, SANILAC, SHIAWASSEE, ST. CLAIR, TUSCOLA,
WASHTENAW AND WAYNE COUNTIES:
Ironworker - pre-engineered metal building erector Alcona, Alpena, Arenac, Cheboygan, Clare, Clinton, Crawford, Gladwin, Gratiot, Huron, Ingham, Iosco, Isabella, Jackson, Lapeer, Livingston (west of Burkhardt Road), Montmorency, Ogemaw, Oscoda, Otsego, Presque Isle, Roscommon, Sanilac, Shiawassee, Tuscola & Washtenaw (west of U.S. 23).$ 24.26 22.11 Bay, Genesee, Lapeer, Livingston (east of Burkhardt Road), Macomb, Midland, Oakland, Saginaw, St. Clair, The University of Michigan, Washtenaw (east of U.S. 23) & Wayne...$ 25.48 23.11
IRONWORKER
Ornamental and Structural...$ 36.77 29.03 Reinforcing.................$ 30.98 27.99
IRON0055-005 07/01/2019
LENAWEE AND MONROE COUNTIES:
Rates Fringes
IRONWORKER
Pre-engineered metal buildings...................$ 23.59 19.35 All other work..............$ 30.38 24.40
IRON0292-003 06/01/2019
BERRIEN AND CASS COUNTIES:
Rates Fringes
IRONWORKER (Including pre-engineered metal building erector).........................$ 30.95 22.25
IRON0340-001 06/19/2017
ALLEGAN, ANTRIM, BARRY, BENZIE, BRANCH, CALHOUN, CHARLEVOIX,
EATON, EMMET, GRAND TRAVERSE, HILLSDALE, IONIA, KALAMAZOO,
KALKASKA, KENT, LAKE, LEELANAU, MANISTEE, MASON, MECOSTA,
MISSAUKEE, MONTCALM, MUSKEGON, NEWAYGO, OCEANA, OSCEOLA,
OTTAWA, ST. JOSEPH, VAN BUREN AND WEXFORD COUNTIES:
IRONWORKER (Including pre-engineered metal building erector).........................$ 24.43 24.67
LABO0005-006 10/01/2017
Rates Fringes
Laborers - hazardous waste abatement: (ALCONA, ALPENA, ANTRIM, BENZIE, CHARLEVOIX, CHEBOYGAN, CRAWFORD, EMMET, GRAND TRAVERSE, IOSCO, KALKASKA, LEELANAU, MISSAUKEE, MONTMORENCY, OSCODA, OTSEGO, PRESQUE ISLE
AND WEXFORD COUNTIES - Zone 10) Levels A, B or C............$ 17.45 12.75 class b....................$ 18.00 12.85 Work performed in conjunction with site preparation not requiring the use of personal protective equipment;
Also, Level D...............$ 16.45 12.75 class a....................$ 17.00 12.85 Zone 10 Laborers - hazardous waste abatement: (ALGER, BARAGA, CHIPPEWA, DELTA, DICKINSON, GOGEBIC, HOUGHTON, IRON, KEWEENAW, LUCE, MACKINAC, MARQUETTE, MENOMINEE, ONTONAGON AND SCHOOLCRAFT
COUNTIES - Zone 11) Levels A, B or C............$ 21.63 12.88 Work performed in conjunction with site preparation not requiring the use of personal protective equipment;
Also, Level D...............$ 20.63 12.88 Laborers - hazardous waste abatement: (ALLEGAN, BARRY, BERRIEN, BRANCH, CALHOUN, CASS, IONIA COUNTY (except the city of Portland);
KALAMAZOO, KENT, LAKE,
MANISTEE, MASON, MECOSTA,
MONTCALM, MUSKEGON, NEWAYGO,
OCEANA, OSCEOLA, OTTAWA, ST.
JOSEPH AND VAN BUREN COUNTIES
- Zone 9) Levels A, B or C............$ 20.95 12.85 Work performed in conjunction with site preparation not requiring the use of personal protective equipment;
Also, Level D...............$ 19.95 12.85 Laborers - hazardous waste abatement: (ARENAC, BAY, CLARE, GLADWIN, GRATIOT, HURON, ISABELLA, MIDLAND, OGEMAW, ROSCOMMON, SAGINAW
AND TUSCOLA COUNTIES - Zone 8) Levels A, B or C............$ 20.65 12.85 Work performed in conjunction with site preparation not requiring the use of personal protective equipment;
Also, Level D...............$ 19.65 12.85 Laborers - hazardous waste abatement: (CLINTON, EATON
AND INGHAM COUNTIES; IONIA
COUNTY (City of Portland);
LIVINGSTON COUNTY (west of Oak Grove Rd., including the City of Howell) - Zone 6) Levels A, B or C............$ 24.65 12.85 Work performed in conjunction with site preparation not requiring the use of personal protective equipment;
Also, Level D...............$ 23.65 12.85 Laborers - hazardous waste abatement: (GENESEE, LAPEER
AND SHIAWASSEE COUNTIES -
Zone 7) Levels A, B or C............$ 23.61 13.41 Work performed in conjunction with site preparation not requiring the use of personal protective equipment;
Also, Level D...............$ 22.61 13.41 Laborers - hazardous waste abatement: (HILLSDALE, JACKSON AND LENAWEE COUNTIES
- Zone 4) Levels A, B or C............$ 24.19 12.85 Work performed in conjunction with site preparation not requiring the use of personal protective equipment;
Also, Level D...............$ 23.19 12.85 Laborers - hazardous waste abatement: (LIVINGSTON COUNTY (east of Oak Grove Rd. and south of M-59, excluding the city of Howell); AND WASHTENAW COUNTY - Zone 3) Levels A, B or C............$ 29.70 14.20 Work performed in conjunction with site preparation not requiring the use of personal protective equipment;
Also, Level D...............$ 28.70 14.20 Laborers - hazardous waste abatement: (MACOMB AND WAYNE
COUNTIES - Zone 1) Levels A, B or C............$ 28.35 16.75 Work performed in conjunction with site preparation not requiring the use of personal protective equipment;
Also, Level D...............$ 27.35 16.75 Laborers - hazardous waste abatement: (MONROE COUNTY - Zone 4) Levels A, B or C............$ 30.85 14.45 Work performed in conjunction with site preparation not requiring the use of personal protective equipment;
Also, Level D...............$ 29.84 14.45 Laborers - hazardous waste abatement: (OAKLAND COUNTY and the Northeast portion of LIVINGSTON COUNTY bordered by Oak Grove Road on the West and M-59 on the South - Zone 2) Level A, B, C...............$ 28.85 16.75 Work performed in conjunction with site preparation not requiring the use of personal protective equipment;
Also, Level D...............$ 27.85 16.75 Laborers - hazardous waste abatement: (SANILAC AND ST.
CLAIR COUNTIES - Zone 5) Levels A, B or C............$ 25.19 15.86 Work performed in conjunction with site preparation not requiring the use of personal protective equipment;
Also, Level D...............$ 24.19 15.86
LABO0259-001 09/01/2018
AREA 1: MACOMB, OAKLAND AND WAYNE COUNTIES
AREA 2: ALCONA, ALGER, ALLEGAN, ALPENA, ANTRIM, ARENAC, BARAGA,
BARRY, BAY, BENZIE, BERRIEN, BRANCH, CALHOUN, CASS, CHARLEVOIX,
CHEBOYGAN, CHIPPEWA, CLARE, CLINTON, CRAWFORD, DELTA,
DICKINSON, EATON, EMMET, GENESEE, GLADWIN, GOGEBIC, GRAND
TRAVERSE, GRATIOT, HILLSDALE, HOUGHTON, HURON, INGHAM, IONIA,
IOSCO, IRON, ISABELLA, JACKSON, KALAMAZOO, KALKASKA, KENT,
KEWEENAW, LAKE, LAPEER, LEELANAU, LENAWEE, LIVINGSTON, LUCE,
MACKINAC, MANISTEE, MARQUETTE, MASON, MECOSTA, MENOMINEE,
MIDLAND, MISSAUKEE, MONROE, MONTCALM, MONTMORENCY, MUSKEGON,
NEWAYGO, OCEANA, OGEMAW, ONTONAGON, OSCEOLA, OSCODA, OTSEGO,
OTTAWA, PRESQUE ISLE, ROSCOMMON, SAGINAW, ST. CLARE, ST.
JOSEPH, SANILAC, SCHOOLCRAFT, SHIAWASSEE, TUSCOLA, VAN BUREN,
WASHTENAW AND WEXFORD COUNTIES
Laborers - tunnel, shaft and caisson:
AREA 1
GROUP 1....................$ 22.57 16.80
GROUP 2....................$ 22.68 16.80
GROUP 3....................$ 22.74 16.80
GROUP 4....................$ 22.92 16.80
GROUP 5....................$ 23.17 16.80
GROUP 6....................$ 23.50 16.80
GROUP 7....................$ 16.78 16.80
AREA 2
GROUP 1....................$ 24.10 12.85
GROUP 2....................$ 24.19 12.85
GROUP 3....................$ 24.29 12.85
GROUP 4....................$ 24.45 12.85
GROUP 5....................$ 24.71 12.85
GROUP 6....................$ 25.02 12.85
GROUP 7....................$ 17.29 12.85
SCOPE OF WORK: Tunnel, shaft and caisson work of every type and description and all operations incidental thereto, including, but not limited to, shafts and tunnels for sewers, water, subways, transportation, diversion, sewerage, caverns, shelters, aquafers, reservoirs, missile silos and steel sheeting for underground construction.
TUNNEL LABORER CLASSIFICATIONS
GROUP 1: Tunnel, shaft and caisson laborer, dump, shanty, hog house tender, testing (on gas) and watchman
GROUP 2: Manhole, headwall, catch basin builder, bricklayer tender, mortar machine and material mixer
GROUP 3: Air tool operator (jackhammer, bush hammer and grinder), first bottom, second bottom, cage tender, car pusher, carrier, concrete, concrete form, concrete repair, cement invert laborer, cement finisher, concrete shoveler, conveyor, floor, gasoline and electric tool operator, gunite, grout operator, welder, heading dinky person, inside lock tender, pea gravel operator, pump, outside lock tender, scaffold, top signal person, switch person, track, tugger, utility person, vibrator, winch operator, pipe jacking, wagon drill and air track operator and concrete saw operator (under 40 h.p.)
GROUP 4: Tunnel, shaft and caisson mucker, bracer, liner plate, long haul dinky driver and well point
GROUP 5: Tunnel, shaft and caisson miner, drill runner, key board operator, power knife operator, reinforced steel or mesh (e.g. wire mesh, steel mats, dowel bars, etc.)
GROUP 6: Dynamite and powder
GROUP 7: Restoration laborer, seeding, sodding, planting, cutting, mulching and top soil grading; and the restoration of property such as replacing mailboxes, wood chips, planter boxes, flagstones, etc.
LABO0334-001 09/01/2018
Rates Fringes
Laborers - open cut:
ZONE 1 - MACOMB, OAKLAND
AND WAYNE COUNTIES:
GROUP 1....................$ 22.42 16.80
GROUP 2....................$ 22.53 16.80
GROUP 3....................$ 22.58 16.80
GROUP 4....................$ 22.66 16.80
GROUP 5....................$ 22.72 16.80
GROUP 6....................$ 20.17 16.80
GROUP 7....................$ 16.79 16.80
ZONE 2 - LIVINGSTON COUNTY
(east of M-151 (Oak Grove Rd.)); MONROE AND
WASHTENAW COUNTIES:
GROUP 1....................$ 23.75 12.85
GROUP 2....................$ 23.86 12.85
GROUP 3....................$ 23.98 12.85
GROUP 4....................$ 24.05 12.85
GROUP 5....................$ 24.20 12.85
GROUP 6....................$ 21.50 12.85
GROUP 7....................$ 18.14 12.85
ZONE 3 - CLINTON, EATON,
GENESEE, HILLSDALE AND
INGHAM COUNTIES; IONIA
COUNTY (City of Portland);
JACKSON, LAPEER AND
LENAWEE COUNTIES;
LIVINGSTON COUNTY (west of M-151 Oak Grove Rd.);
SANILAC, ST. CLAIR AND
SHIAWASSEE COUNTIES:
GROUP 1....................$ 21.94 12.85
GROUP 2....................$ 22.08 12.85
GROUP 3....................$ 22.20 12.85
GROUP 4....................$ 22.25 12.85
GROUP 5....................$ 22.39 12.85
GROUP 6....................$ 19.69 12.85
GROUP 7....................$ 16.84 12.85
ZONE 4 - ALCONA, ALLEGAN,
ALPENA, ANTRIM, ARENAC,
BARRY, BAY, BENZIE,
BERRIEN, BRANCH,
CALHOUN, CASS, CHARLEVOIX,
CHEBOYGAN, CLARE,
CRAWFORD, EMMET,
GLADWIN, GRAND TRAVERSE,
GRATIOT AND HURON
COUNTIES; IONIA COUNTY
(EXCEPT THE CITY OF
PORTLAND); IOSCO,
ISABELLA, KALAMAZOO,
KALKASKA, KENT,
LAKE,LEELANAU, MANISTEE,
MASON, MECOSTA, MIDLAND,
MISSAUKEE, MONTCALM,
MONTMORENCY, MUSKEGON,
NEWAYGO, OCEANA, OGEMAW,
OSCEOLA, OSCODA, OTSEGO,
OTTAWA, PRESQUE ISLE,
ROSCOMMON, SAGINAW, ST.
JOSEPH, TUSCOLA, VAN BUREN
AND WEXFORD COUNTIES:
GROUP 1....................$ 20.97 12.85
GROUP 2....................$ 21.10 12.85
GROUP 3....................$ 21.21 12.85
GROUP 4....................$ 21.28 12.85
GROUP 5....................$ 21.40 12.85
GROUP 6....................$ 18.62 12.85
GROUP 7....................$ 16.96 12.85
ZONE 5 - ALGER, BARAGA,
CHIPPEWA, DELTA,
DICKINSON, GOGEBIC,
HOUGHTON, IRON,
KEWEENAW, LUCE, MACKINAC,
MARQUETTE, MENOMINEE,
ONTONAGON AND SCHOOLCRAFT
COUNTIES:
GROUP 1....................$ 21.19 12.85
GROUP 2....................$ 21.33 12.85
GROUP 3....................$ 21.46 12.85
GROUP 4....................$ 21.51 12.85
GROUP 5....................$ 21.56 12.85
GROUP 6....................$ 18.94 12.85
GROUP 7....................$ 17.05 12.85
SCOPE OF WORK:
Open cut construction work shall be construed to mean work which requires the excavation of earth including industrial, commercial and residential building site excavation and preparation, land balancing, demolition and removal of concrete and underground appurtenances, grading, paving, sewers, utilities and improvements; retention, oxidation, flocculation and irrigation facilities, and also including but not limited to underground piping, conduits, steel sheeting for underground construction, and all work incidental thereto, and general excavation. For all areas except the Upper Peninsula, open cut construction work shall also be construed to mean waterfront work, piers, docks, seawalls, breakwalls, marinas and all incidental work. Open cut construction work shall not include any structural modifications, alterations, additions and repairs to buildings, or highway work, including roads, streets, bridge construction and parking lots or steel erection work and excavation for the building itself and back filling inside of and within 5 ft. of the building and foundations, footings and piers for the building. Open cut construction work shall not include any work covered under Tunnel, Shaft and Caisson work.
OPEN CUT LABORER CLASSIFICATIONS
GROUP 1: Construction laborer
GROUP 2: Mortar and material mixer, concrete form person, signal person, well point person, manhole, headwall and catch basin builder, headwall, seawall, breakwall and dock builder
GROUP 3: Air, gasoline and electric tool operator, vibrator operator, driller, pump person, tar kettle operator, bracer, rodder, reinforced steel or mesh person (e.g., wire mesh, steel mats, dowel bars, etc.), welder, pipe jacking and boring person, wagon drill and air track operator and concrete saw operator (under 40 h.p.), windlass and tugger person and directional boring person
GROUP 4: Trench or excavating grade person
GROUP 5: Pipe layer (including crock, metal pipe, multi-plate or other conduits)
GROUP 6: Grouting man, audio-visual television operations and all other operations in connection with closed circuit television inspection, pipe cleaning and pipe relining work and the installation and repair of water service pipe and appurtenances
GROUP 7: Restoration laborer, seeding, sodding, planting, cutting, mulching and top soil grading; and the restoration of property such as replacing mailboxes, wood chips, planter boxes, flagstones, etc.
LABO0465-001 06/01/2019
LABORER: Highway, Bridge and Airport Construction
AREA 1: GENESEE, MACOMB, MONROE, OAKLAND, WASHTENAW AND WAYNE
COUNTIES
AREA 2: ALLEGAN, BARRY, BAY, BERRIEN, BRANCH, CALHOUN, CASS,
CLINTON, EATON, GRATIOT, HILLSDALE, HURON, INGHAM, JACKSON,
KALAMAZOO, LAPEER, LENAWEE, LIVINGSTON, MIDLAND, MUSKEGON,
SAGINAW, SANILAC, SHIAWASSEE, ST. CLAIR, ST. JOSEPH, TUSCOLA
AND VAN BUREN COUNTIES
AREA 3: ALCONA, ALPENA, ANTRIM, ARENAC, BENZIE, CHARLEVOIX,
CHEBOYGAN, CLARE, CRAWFORD, EMMET, GLADWIN, GRAND TRAVERSE,
IONIA, IOSCO, ISABELLA, KALKASKA, KENT, LAKE, LEELANAU,
MANISTEE, MASON, MECOSTA, MISSAUKEE, MONTCALM, MONTMORENCY,
NEWAYGO, OCEANA, OGEMAW, OSCEOLA, OSCODA, OTSEGO, OTTAWA,
PRESQUE ISLE, ROSCOMMON AND WEXFORD COUNTIES
AREA 4: ALGER, BARAGA, CHIPPEWA, DELTA, DICKINSON, GOGEBIC,
HOUGHTON, IRON, KEWEENAW, LUCE, MACKINAC, MARQUETTE, MENOMINEE,
ONTONAGON AND SCHOOLCRAFT COUNTIES
LABORER (AREA 1)
GROUP 1.....................$ 27.07 12.90
GROUP 2.....................$ 27.20 12.90
GROUP 3.....................$ 27.38 12.90
GROUP 4.....................$ 27.46 12.90
GROUP 5.....................$ 27.67 12.90
GROUP 6.....................$ 27.97 12.90
LABORER (AREA 2)
GROUP 1.....................$ 24.02 12.85
GROUP 2.....................$ 24.22 12.85
GROUP 3.....................$ 24.46 12.85
GROUP 4.....................$ 24.81 12.85
GROUP 5.....................$ 24.68 12.85
GROUP 6.....................$ 25.02 12.85
LABORER (AREA 3)
GROUP 1.....................$ 23.27 12.85
GROUP 2.....................$ 23.48 12.85
GROUP 3.....................$ 23.77 12.85
GROUP 4.....................$ 24.21 12.85
GROUP 5.....................$ 23.83 12.85
GROUP 6.....................$ 24.26 12.85
LABORER (AREA 4)
GROUP 1.....................$ 23.32 12.85
GROUP…