This document summarizes an amendment to a solicitation for design and construction services. The U.S. Army Corps of Engineers is seeking proposals to design and construct a high-voltage substation at Detroit Arsenal in Michigan. The amendment extends the response deadline from May 14th to May 21st and replaces the price breakout schedule in its entirety. The new schedule includes pricing requirements for primary facilities, supporting facilities, fire alarm systems, and four options related to additional switches, sheltered switchgear, distribution loop conductors, and telecommunications ductbank. Offerors must provide pricing for all line items. The opportunity is a two-phase design-build procurement that will evaluate technical qualifications, past performance, price, and small business participation to select the winning firm.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MILITARY/RESERVE BRANCH
ATTN: BLAKE GEVEDON
600 DR M L KING JR PL RM 821
LOUISVILLE KY 40202-2236
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Solicitation W912QR20R0008 for the Design and Construction of a high-voltage substation at Detroit Arsenal, MI is hereby modif ied as follow s:
a. Replace the Price Breakout Schedule in section 00 10 00 in its entirety.
b. Extend the solicitation due date from Thursday 14, May 2020 to Thursday 21 May 2020.
c. All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912QR20R0008
X 9B. DATED (SEE ITEM 11)
23-Dec-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
08-May-2020
CODE
U. S. ARMY ENGINEER DISTRICT, LOUISVILLE
600 DR. MARTIN LUTHER KING, JR. PLACE
ROOM 821
LOUISVILLE KY 40202-2239
W912QR 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE 964859
FACILITY CODECODE
EMAIL:TEL:
W912QR20R0008-0004
W912QR20R0008
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 14-May-2020 04:00 PM to 21-May-2020 04:00 PM.
The following have been modified:
PRICE BREAKOUT SCHEDULE
00 10 00
PRICE BREAKOUT SCHEDULE
05/07/2020
PROPOSER’S NAME:
Item Description Unit Amount
BASE PROPOSAL
Primary Facilities – Utility Substation KVA 40,000; Switching Station KVA 40,000; Secondary Substation KVA 10,000;
Underground Distribution Loop; Building Information Systems
Supporting Facilities - Electric Service;
Water, Sewer, Gas; Paving, Walks, Curbs And Gutters; Storm Drainage; Site Improvements; Demo; Information Systems
Job
Job
0003 Simplex Grinnell Fire Alarm System Job $ -
Total Base Proposal $ -
Item Description Unit Unit Price Amount
OPTIONS
0004 Option 1 – Add Sectionalizing Switch
Per switch $ - $ -
0005 Option 2 - Change to Sheltered Aisle Switchgear
NA $ - $ -
Option 3 - Increase 13.2 kV Distribution Loop Conductors
Linear Feet
0007 Option 4 – Install Telecommunications Ductbank for Future Microgrid System
Linear Feet $ - $ -
Total All Options
Total $ -
Total Base Proposal with All Options $ -
NOTES FOR PRICE BREAKOUT SCHEDULE
1. The company name should be indicated on the face of the Price Breakout Schedule to preclude being misplaced.
2. Offerors must insert a price on all numbered items (including options) of the Price Breakout Schedule. Failure to do so may result in the offer being unacceptable.
3. Description of Proposal Items - The general outline of the principal features of each item as listed below does not in any way limit the responsibility of the offeror for making a thorough investigation of the drawings and the specifications to determine the scope of work including each item of the Price Breakout Schedule.
DESCRIPTION OF BASE PROPOSAL ITEMS
a) Item No. 0001 – “Primary Facilities – Construct a high-voltage Substation. Work includes the substation, transformers, primary and secondary-voltage switchgear with associated distribution loop, underground cable vault and cabling and all associated duct banks with cabling. Work also includes a lower-voltage substation, transformers, switchgear, duct banks and cabling. Equipment will be sized and compatible with existing electrical infrastructure.
b) Item No. 0002 – “Supporting facilities” – Work includes reconfiguring existing underground utilities, site development and improvements, paving, parking, walkways, fencing, storm drainage, information systems, and communications. Measures in accordance with the Department of Defense (DoD) Minimum Antiterrorism for Buildings standards will be provided. Access for individuals with disabilities will be provided. Cyber Security Measures will be incorporated into this project. Facilities will be designed to a minimum life of 40 years in accordance with DoD's Unified Facilities Criteria (UFC 1-200-02) including energy efficiencies, building envelope and integrated building systems performance.
c) Item 0003 - “Simplex Grinnell Fire Alarm System”. Fixed price payable by the awarded contractor for the base standardized fire protection/monitoring system.
DESCRIPTION OF OPTION PROPOSAL ITEMS
a) Item No. 0004 – “Option 1 – Add Sectionalizing Switch” includes addition to the distribution to the 13.2kV loop for a future load or building. Providing a unit price for the additional sectionalizing switch as an option gives an upfront cost to an additional switch, versus non-competitive pricing during final design and construction. This option may be exercised up to 365 calendar days after NTP.
b) Item No. 0005 – “Option 2 - Change to Sheltered Aisle Switchgear.” The base proposal includes non-sheltered aisle switchgear. This option would be for a Sheltered Aisle Switchgear that allows for maintenance and operation of the switchgear that is out of weather elements. This option must be awarded at time of award.
c) Item No. 0006 – “Option 3 – Increase 13.2 kV Distribution Loop Conductors” is to provide the remaining
13.2kV feeders for all the circuits in the distribution loop. This option is at the discretion of DTA DPW to include additional 13.2 kV distribution loop; however, per DTA DPW, it is believed the base proposal provides a complete and usable facility. This option may be exercised up to 180 calendar days after NTP.
d) Item No. 0007 – “Option 4 – Install Telecommunications Ductbank for Future Microgrid System” is to provide additional duct bank routing in the same trench as the underground ductbank for the new substation and power distribution circuits. The additional ductbank routing will have a pull wire only, no dark fiber. The dark fiber will be installed during a future project for a microgrid system. This option may be exercised up to 30 calendar days after NTP.
-END OF PRICE BREAKOUT SCHEDULE—
(End of Summary of Changes)
| SF30 |
| SUMMARY OF CHANGES |
| 00 10 00 |
| PRICE BREAKOUT SCHEDULE |
File details come from the government source that posted it. Updated .