W912QR20R0008-0002.pdf

PDF 1 MB Posted

Attached to
Detroit Arsenal Substation
Solicitation number
W912QR20R0008
Issued by

About this file

This document provides details for a federal contract solicitation for design-build construction services. The U.S. Army Corps of Engineers Louisville District is seeking proposals for a project to construct a high-voltage substation at Detroit Arsenal, Michigan. The project scope includes building a high voltage substation, secondary switchgear, distribution transformers, underground distribution loops, duct banks and cabling. Supporting facilities such as site work, utilities and information systems are also required. The contract type is firm-fixed-price, with a duration of 730 calendar days. The North American Industry Classification System code is 237130. This is a full and open competition with no set-aside designated. The selection process will follow a two-phase design-build approach, evaluating past performance, management, and financial capability in Phase 1, then design/technical, small business participation, and price in Phase 2. Discussions are not planned but may be held if determined to be in the government's best interest. Offerors must register in the System for Award Management database to be eligible for award. The point of contact is the listed contract specialist.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MILITARY/RESERVE BRANCH

ATTN: BLAKE GEVEDON

600 DR M L KING JR PL RM 821

LOUISVILLE KY 40202-2236

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Solicitation number W912QR20R0008 for the Design and Construction of a high-voltage substation at Detroit Arsenal, MI is hereby modif ied as follow s:

SEE THE ATTACHED SUMMARY OF CHANGES

1. CONTRACT ID CODE PAGE OF PAGES

1 57

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912QR20R0008

X 9B. DATED (SEE ITEM 11)

23-Dec-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

14-Apr-2020

CODE

U. S. ARMY ENGINEER DISTRICT, LOUISVILLE

600 DR. MARTIN LUTHER KING, JR. PLACE

ROOM 821

LOUISVILLE KY 40202-2239

W912QR 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE 964859

FACILITY CODECODE

EMAIL:TEL:

W912QR20R0008-0002

W912QR20R0008

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been modified:

SUMMARY OF CHANGES

Summary of Changes Amendment 0002 DTA Electrical Substation

1) This amendment incorporates all of the final Plans and Specifications that were previously issued in draft form during Phase I of the solicitation process. Additional plans and specs have been incorporated in association with CLIN 0007 in the revised Price Breakout Schedule. These additional plans and specs include the following:

Addition of Option 4 for new ductbank in the same trench as the power for the new Substation. New ductbank will have a pull wire but no cables. Dark fiber will be installed as part of a future project for connection to a future microgrid system.

Option 4 package includes:

- Substation Microgrid Schematic Design Narrative US Army Detroit Arsenal

- Appendix A – Drawings - FY20 MCA Electrical Substation Drawings, PN: 62856 / P2# 455784

- Appendix B – Documents - DD1391 Scope of work

2) The Price Breakout Schedule has been revised.

3) Section 00 22 18 has been revised

4) Wage Decisions MI20200001 and MI20200065 have been revised

5) ProjNet Instructions have been revised to incorporate a new ProjNet Key for Phase II of this solicitation

6) The site visit information for this project as been added to 52.236-27 Alt I

7) The proposal due date for receipt of Phase II proposals is Thursday, 14 May 2020 at 4:00 PM Eastern Time.

All other terms and conditions of this solicitation remain unchanged.

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 05-Feb-2020 02:00 PM to 14-May-2020 04:00 PM.

The following have been modified:

PRICE BREAKOUT SCHEDULE

00 10 00

PRICE BREAKOUT SCHEDULE

04/13/2020

PROPOSER’S NAME:

Item Description Unit Amount

BASE PROPOSAL

Primary Facilities – Utility Substation KVA 40,000; Switching Station KVA 40,000; Secondary Substation KVA 10,000;

Underground Distribution Loop; Building Information Systems

Supporting Facilities - Electric Service;

Water, Sewer, Gas; Paving, Walks, Curbs And Gutters; Storm Drainage; Site Improvements; Demo; Information Systems

Job

Job

0003 Simplex Grinnell Fire Alarm System Job $ -

Total Base Proposal $ -

Item Description Unit Unit Price Amount

OPTIONS

0004 Option 1 – Add Sectionalizing Switch

Per switch $ - $ -

Option 2 - Change to Sheltered Aisle Switchgear

Option 3 - Increase 13.2 kV Distribution Loop Conductors

NA

Linear Feet

0007 Option 4 – Install Telecommunications Ductbank for Future Microgrid System

Linear Feet $ - $ -

Total All Options Total $ -

Total Base Proposal with All Options $ -

NOTES FOR PRICE BREAKOUT SCHEDULE

1. The company name should be indicated on the face of the Price Breakout Schedule to preclude being misplaced.

2. Offerors must insert a price on all numbered items (including options) of the Price Breakout Schedule. Failure to do so may result in the offer being unacceptable.

3. Description of Proposal Items - The general outline of the principal features of each item as listed below does not in any way limit the responsibility of the offeror for making a thorough investigation of the drawings and the specifications to determine the scope of work including each item of the Price Breakout Schedule.

DESCRIPTION OF BASE PROPOSAL ITEMS

a) Item No. 0001 – “Primary Facilities – Construct a high-voltage Substation. Work includes the substation, transformers, primary and secondary-voltage switchgear with associated distribution loop, underground cable vault and cabling and all associated duct banks with cabling. Work also includes a lower-voltage substation, transformers, switchgear, duct banks and cabling. Equipment will be sized and compatible with existing electrical infrastructure.

b) Item No. 0002 – “Supporting facilities” – Work includes reconfiguring existing underground utilities, site development and improvements, paving, parking, walkways, fencing, storm drainage, information systems, and communications. Measures in accordance with the Department of Defense (DoD) Minimum Antiterrorism for Buildings standards will be provided. Access for individuals with disabilities will be provided. Cyber Security Measures will be incorporated into this project. Facilities will be designed to a minimum life of 40 years in accordance with DoD's Unified Facilities Criteria (UFC 1-200-02) including energy efficiencies, building envelope and integrated building systems performance.

c) Item 0003 - “Simplex Grinnell Fire Alarm System”. Fixed price payable by the awarded contractor for the base standardized fire protection/monitoring system.

DESCRIPTION OF OPTION PROPOSAL ITEMS

a) Item No. 0004 – “Option 1 – Add Sectionalizing Switch” includes addition to the distribution to the 13.2kV loop for a future load or building. Providing a unit price for the additional sectionalizing switch as an option gives an upfront cost to an additional switch, versus non-competitive pricing during final design and construction. This option may be exercised up to 365 calendar days after NTP.

b) Item No. 0005 – “Option 2 - Change to Sheltered Aisle Switchgear.” The base proposal includes non-sheltered aisle switchgear. This option would be for a Sheltered Aisle Switchgear that allows for maintenance and operation of the switchgear that is out of weather elements. This option must be awarded at time of award.

c) Item No. 0006 – “Option 3 – Increase 13.2 kV Distribution Loop Conductors” is to provide the remaining

13.2kV feeders for all the circuits in the distribution loop. This option is at the discretion of DTA DPW to include additional 13.2 kV distribution loop; however, per DTA DPW, it is believed the base proposal provides a complete and usable facility. This option may be exercised up to 180 calendar days after NTP.

d) Item No. 0007 – “Option 4 – Install Telecommunications Ductbank for Future Microgrid System” is to provide additional duct bank routing in the same trench as the underground ductbank for the new substation and power distribution circuits. The additional ductbank routing will have a pull wire only, no dark fiber. The dark fiber will be installed during a future project for a microgrid system. This option must be awarded at time of award.

-END OF PRICE BREAKOUT SCHEDULE—

PROJNET INSTRUCTIONS

OFFEROR'S QUESTIONS AND COMMENTS

Technical inquiries and questions relating to proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at http://www.ProjNet.org/ProjNet. As noted below, offerors shall not submit their proposals via ProjNet.

Offerors shall submit their proposals in accordance with the provisions stated in the solicitation.

To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into system.

The Solicitation Number is: W912QR20R0008 The Bidder Inquiry Key is: RNMFUV-6MPCQ4 Specific Instructions for ProjNet Bid Inquiry Access:

1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

2. Identify the Agency. This should be marked as USACE.

3. Key. Enter the Bidder Inquiry Key listed above.

4. Email. Enter the email address you would like to use for communication.

5. Select Continue. A page will then open stating a user account was not found and will ask you to create one using the provided form.

6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.

7. Select Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.

Specific Instructions for Future ProjNet Bid Inquiry Access:

1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.

2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

3. Identify the Agency. This should be marked as USACE.

4. Key. Enter the Bidder Inquiry Key listed above.

5. Email. Enter the email address you used to register previously in ProjNet.

6. Select Continue. A page will then open asking you to enter the answer to your Secret Question.

7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.

From this page you may view all bidder inquiries or add an inquiry.

Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.

Offerors are requested to review the specification in its entirety and to review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.

NOTES:

1. Offerors shall not submit their proposals via ProjNet, but in accordance with the provisions stated in the solicitation. Any questions regarding acceptable means of submitting offers shall be made directly to the Contract Specialist identified in the solicitation.

2. Government responses to technical inquiries and questions relating to proposal procedures or bonds that are submitted to ProjNet in accordance with the procedures above are not binding on the Government unless an amendment is issued on Standard Form 30. In the case of any conflicts, the solicitation governs. Any changes or revisions to the solicitation will be made by formal amendment. Government responses will be limited to: (a) Notice that an amendment will be issued; (b) Reference to an existing requirement contained in the solicitation; or (c) Notice that a response is not necessary.

3. The ability to enter technical inquiries and questions relating to proposal procedures or bonds will be disabled five (5) days prior to the closing date stated in the solicitation. No Government responses will be entered into the ProjNet system within two (2) days prior to the closing date stated in the solicitation.

SECTION 00 21 00 - INSTRUCTIONS

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

A Site Visit/Pre-Proposal Meeting is scheduled for April 22, 2020 at 0900 A.M. EST at Detroit Arsenal, Michigan.

No project inquiries will be allowed during the site visit. All inquiries must be submitted via the ProjNet Bidder Inquiry site.

Send RSVP to Carmen Cochrain at Carmen.M.Cochrain@usace.army.mil by 3:00 PM EST on April 17, 2020.

(End of provision)

SECTION 00 22 16 - SUPPLEMENTARY INSTRUCTIONS TO PROPOSERS

SECTION 00 22 18 - PHASE II

SECTION 00 22 18

PROCEDURES FOR SUBMITTAL AND EVALUATION OF OFFERS FOR PHASE TWO

1. Overview.

1.1 The intent of this solicitation is to select one contractor for the Design-Build construction of a substation project located at Detroit Arsenal, MI. The basis of award is the Best Value Trade-Off process. This project is for the Design-Build construction of a high voltage substation and a distribution loop serving Detroit Arsenal. Work includes the construction of a high voltage (15kV) substation with two (2) circuit switchers (120kV), two (2) distribution transformers (40MVA, 120kV/13.2kV, 3 phase), two (2) secondary switchgear line-ups with tie breaker (15kV). Included is an additional medium voltage substation (5kV) to support the existing 5kV infrastructure consisting of two (2) distribution transformers (10MVA, 13.2kV/4.8kV, 3 phase), and switchgear (15kV rated but operated at 4.8kV). Supporting substation work includes fuse/breaker coordination, underground connecting cables in conduits, underground cable vault, grounding, concrete pads, lightning protection, and area lighting. Duct banks and cabling to intercept or reroute the existing 4.8kV distribution system for connection to the new 4.8 kV switchgear is required. The 13.2kV distribution loop includes concrete encased duct banks, cabling, manholes, and sectionalizing switches. Equipment will be sized and compatible with existing electrical infrastructure. Supporting facilities includes reconfiguring existing underground utilities, site development and improvements, paving, parking, walkways, fencing, storm drainage, site improvements, information systems, and communications.

1.2 This is a two-phase procurement and the basis of award is the Best Value Trade-Off Process. Following completion of the evaluation of Phase I, up to a maximum of five (5) most highly qualified offerors will be selected to participate in Phase II. The selected offerors for Phase II will be invited to submit the information described in this Section 00 22 18, Procedures for Submittal and Evaluation of Offers for Phase II, for review and evaluation by the Government. Following completion of the Phase II evaluation, the Contracting Officer will award a firm fixed price contract to the responsible offeror whom the Source Selection Authority determines conforms to the solicitation, is fair and reasonable, and offers the best overall value to the Government, all factors considered. The Government reserves the right to accept other than the lowest priced offer or to reject all offers. For Phase II submittals, requirements stated in this RFP are minimums.

NOTE: The rating information from Phase I will not be considered in Phase II or in the final selection.

1.3 The target ceiling for contract award is $20,600,000.00 based on the funds made available for this project.

The Government cannot guarantee that additional funds will be available for award. Offerors are under no obligation to approach this ceiling.

2. Submittal of Offers.

2.1 Offerors submitting proposals for this project should limit submissions to data essential for evaluation of proposals so that a minimum of time and monies will have been expended in preparing information required herein. However, in order to be effectively and equitably evaluated, the proposals must include information sufficiently detailed to clearly describe the offeror's capability for successfully completing the solicited project. For Phase II, requirements stated in this Request for Proposal (RFP) are minimums.

Innovative, creative, or cost-saving proposals that meet or exceed the requirements are encouraged and will be rated accordingly. Proposals should follow in the order of sequence set forth in the RFP. Information provided out of sequence may not be evaluated and may result in the offeror’s disqualification from award.

2.2 Proposals: ALL SUBMISSIONS TO THIS PROPOSAL ANNOUNCEMENT SHALL BE SUBMITTED ELECTRONICALLY THROUGH DOD SAFE. No paper copies, CD-ROMs or facsimile submissions will be accepted. Electronic Proposal Submission is required through the Army’s Electronic File Sharing Service, DOD SAFE (https://safe.apps.mil). The DOD SAFE Application is used to send large files to individuals that would normally be too large to send via email. There are no user accounts for SAFE. Authentication is handled via email.

Anyone has access to DOD SAFE, and the application is available for use by anyone. The SAFE “Getting Started Guide” has information on how to utilize the system (https://safe.apps.mil/about.php). Instructions for uploading are as follows:

1. Send an email to the Contracting Officer and Contract Specialist to receive the link to drop off your proposal. This will need to be completed five (5) business days prior to proposal due date.

a. Blake Gevedon, Contract Specialist at william.b.gevedon@usace.army.mil

b. Bjorn Hale, Contracting Officer at bjorn.t.hale2@usace.army.mil

2. You will receive an email with the link to submit your drop-off. The link will be provided no later than two (2) business days prior to the proposal due date.

3. Short Note to the Recipients: Click the Add Files or Drag and Drop your files. For file description, enter W912QR20R0008-FIRMNAME.

4. Click Upload button to send documents.

5. Guest users will need to check their email to verify their email address before the recipients will be notified. (Government-issued Common Access Cards (CACs) are not required).

File Size Limitations: Offerors are advised to follow the DOD SAFE instructions for uploading files. DOD SAFE supports delivery up to 8GB. If needed, Offerors are advised to break the files down into smaller sections in order to upload it to the system. In such cases, please divide the sections as logically as possible and be sure to clearly name the files as specified below.

File Naming Convention: To ensure your submission is received and processed appropriately, it is important that interested parties CAREFULLY ensure their electronic files adhere to the following naming convention:

• W912QR20R0008-FIRMNAME-VOLUME I

• W912QR20R0008-FIRMNAME-VOLUME II

Each file name shall begin with the solicitation number followed by the firm’s name and a brief file description. Please see examples above.

File Organization: Although hard copies are not accepted, each file shall be clearly indexed, and logically assembled. Font size shall be 10 or larger. Pages shall be letter sized (larger page sizes (such as 11x17 fold-outs, etc.) will be counted as two pages. Proposals shall be in a narrative format, organized and titled so that each section of the proposal follows the order and format of the factors. Information presented should be organized so as to pertain to only the evaluation factor in the section that the information is presented. Information pertaining to more than one evaluation factor should be repeated in the each section for each factor.

Upload Completion & Deadline: Interested parties shall submit responses no later than the date specified on the solicitation document. The time & date of proposal receipt will be the upload completion

W912QR20R0008-0002

mailto:william.b.gevedon@usace.army.mil mailto:bjorn.t.hale2@usace.army.mil

/ delivery time & date recorded within DOD SAFE site. Do not assume that electronic submission will occur instantaneously. Large files (e.g. 10MB or more) will take some time to upload. Offerors should time their upload effort with prudence by not waiting until the last few minutes—this will allow for unexpected delays in the transmittal process. Offerors are encouraged to keep a copy of the upload confirmation for their record. Submissions after the deadline will be considered late and will be processed in accordance with FAR 15.208.

Electronic Files: Files shall be in their native format (i.e. doc, xls, ppt, etc.), or if in pdf format, shall be in searchable text. Text and graphics portfolios of the electronic copies shall be in a format readable by Microsoft Office or Adobe applications. Data submitted in a spreadsheet format shall be readable by MS Excel (all cells and formulas should be unlocked).

Any information, presented in a proposal that the Offeror wants safeguarded from disclosure to other parties must be identified and labeled in accordance with the requirements of Provision “FAR 52.215-1, Instructions to Offerors – Competitive Acquisition (Jan 2017),” subparagraph (e), which is found in 00 21 00 Instructions of the RFP. The Government will endeavor to honor the restrictions against release requested by Offerors, to the extent permitted under United States law and regulations.

3. Proposal Evaluation Process.

3.1 A Source Selection Evaluation Board (SSEB) comprised of representatives of the Corps of Engineers, User/Customer, and other required personnel will evaluate the proposals. Offerors are advised that the technical evaluation and rating of proposals will be conducted in strict confidence. Technical (Volume I) proposals will be reviewed and rated without knowledge of the price offered. The number and identities of offerors are not revealed to anyone not involved in the evaluation and award process or to other offerors.

Proposals will be evaluated based on the factors described herein, and the basis of award is a Best Value Trade-Off, as stated above.

3.2 The evaluation process for Phase II essentially consists of four parts: proposal compliance/responsibility review, technical evaluation, price evaluation, and price/technical trade-off analysis.

3.2.1 Proposal Compliance / Responsibility Review: This is an initial review to ensure that all required forms and certifications are complete, that both a technical and price proposal were received, and that the offeror is financially capable of sustaining performance under the contract and is able to obtain the required level of performance and payment bonds from an acceptable surety.

3.2.2 Technical Evaluation: The SSEB will evaluate and rate the Phase II Volume I proposals against the RFP requirements. Factor I (Design/Technical) will be rated using Table 1 below. Factor II – Small Business Participation Plan will be rated using Table 2 below.

3.2.3 Price Evaluation: The SSEB and Contracting Officer/SSA will evaluate price proposals independent of the technical evaluation. The SSEB will not have access to price information until completion of the technical evaluation.

3.2.4 Price/Technical Trade-off Analysis: After all above evaluations are complete, the Contracting Officer/SSA will compare the relative advantages and disadvantages of technical proposals and compare prices. The Source Selection Authority (SSA) will then consider all factors to select the proposal offering the best value to the Government.

4. Proposal Information and Related Evaluation Factors.

4.1 Phase II proposals will be evaluated in accordance with the factors below, listed in relative order of importance. All evaluation factors, other than price, when combined are considered approximately equal to price. The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.

4.2 Volume I – Factor I – Design / Technical 1st

4.3 Volume I – Factor II – Small Business Participation Plan 2nd

4.4 Volume II - Price and Pro Forma Information (Sealed Envelope)

Tab A Standard Form 1442 and Price Breakout Schedule Not Rated

Tab B Joint Venture Agreement Not Rated

Tab C Evidence of Ability to Obtain Bonding and Not Rated Proof of Financial Ability

Tab D Pre-Award Information Not Rated

Tab E Subcontracting Plan Acceptable / Unacceptable

4.6 Ratings

Evaluators will apply the rating for the definition that most closely matches the evaluation.

TABLE 1

Technical / Risk Assessment Ratings Adjectival Rating Description

Outstanding Proposal indicates an exceptional approach and understanding of the requirements and contains multiple strengths, and risk of unsuccessful performance is low.

Good Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength, and risk of unsuccessful performance is low to moderate.

Acceptable

Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.

Marginal Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high.

Unacceptable Proposal does not meet the requirements of the solicitation, and thus, contains one or more deficiencies, and/or risk of unsuccessful performance is unacceptable. Proposal is unawardable.

TABLE 2

Small Business Ratings

Rating Description

Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the small business objectives.

Unacceptable Proposal does not meet the small business objectives.

4.7 Definitions

1. Deficiency. A material failure of a proposal to meet a Government requirement or a combination of significant weaknesses in a proposal that increases the risk of unsuccessful contract performance to an unacceptable level. See FAR 15.001.

2. Strength. An aspect of an offeror’s proposal that has merit or exceeds specified performance or capability requirements in a way that will be advantageous to the Government during contract performance.

3. Significant Strength. An aspect of an offeror’s proposal that has appreciable merit or appreciably exceeds specified performance or capability requirements in a way that will be appreciably advantageous to the Government during contract performance.

4. Weakness. A flaw in the proposal that increases the risk of unsuccessful contract performance. See

FAR 15.001.

5. Significant Weakness. A flaw in the proposal that appreciably increases the risk of unsuccessful contract performance. See FAR 15.001.

6. Uncertainty. Any aspect of a non-cost/price factor proposal for which the intent of the offeror is unclear (e.g., more than one way to interpret the offer or inconsistencies in the proposal indicating that there may have been an error, omission, or mistake).

7. Clarification. Limited exchanges between the Government and offerors that may occur when award without discussions is contemplated. See FAR 15.306(a)(1).

8. Adverse Past Performance. Past performance information that supports a less than satisfactory rating on any evaluation. Adverse past performance that must be addressed with Offerors includes unfavorable comments received from sources such as those received from respondents from past performance questionnaires or interviews that have not been finalized within a formal rating system.

5. Volume I – Factor I: Design / Technical

5.1 Submission Requirements:

Provide a clear and concise narrative that describes the project and conveys your understanding of the design requirements. The narrative shall at least address, but is not limited to the following key elements:

• Electrical substation design

• Approach for connection of the high voltage and medium voltage systems

• Coordination with the utility

• Interconnectivity of breakers and coordinating power outages with minimal impact to the installation’s ongoing activities

• Integration and connection of existing 4.8kV distribution loop with new switchgear

• Approach for balancing the loads of the six circuits exiting the 15 kV substation to best meet the

Detroit Arsenal electrical needs

• Approach for reconfiguration of services to Buildings 219 and 233 from 4.8kV to 13.2kV

• Safety approach, for example lock out/tag out, energized equipment protocol, procedures for shutdown and re-energizing of power

• Arc Flash Hazard Analysis

• Site Work Utility Connections & Routing

• Commissioning and testing components for operability

• Structural design

• Cybersecurity

NOTE: There is a limit of ten (10) single sided, 8.5” x 11” pages, using a minimum font size of 11 and a minimum margin of one-half inch on all sides, for the Design/Technical Factor.

5.2 Evaluation Criteria:

5.2.1 Design/Technical:

The Design Narrative will be evaluated for completeness and thoroughness as compared to the Submission

Requirements identified herein and in consideration of the features of work identified in Section 01 02

10.00 06, Statement of Work. Proposals that demonstrate a complete understanding of the project requirements beyond those expressly identified in Section 01 02 10.00 06, Statement of Work, may receive additional consideration.

6. Volume I – Factor II: Small Business Participation Plan

6.1 Submission Requirements:

ALL OFFERORS ARE REQUIRED TO SUBMIT A SMALL BUSINESS PARTICIPATION PLAN. The Small Business Participation Plan shall be based on the offeror’s best effort and is required to address each of the following areas individually:

• The extent to which the small business programs listed in FAR 19 (small business, small disadvantaged business, woman-owned small business, HUBZone, service disabled veteran owned small business, etc.) are specifically identified in the Small Business Participation Plan;

• The extent of participation of such firms in terms of the value of the total acquisition in %’s for the base contract and for each individual option; the extent of commitment to use such firms (for example, enforceable commitments, i.e., teaming agreements signed, are to be considered more heavily than non-enforceable ones);

• The complexity and variety of the work small firms are to perform on this acquisition;

• The practicality of the Small Business Participation Plan, i.e., aggressive goals.

The Small Business Participation Plan shall be organized as follows:

(1) Prime Contractor type of business (check all that apply):

( ) Large ( ) Small (also check type of small business) ( ) Small Non-Disadvantaged Business ( ) Small Disadvantaged Business ( ) Woman-Owned Small Business ( ) HUBZone Small Business ( ) Veteran Owned Small Business ( ) Service Disabled, Veteran Owned Small Business

(2) Percentage of your participation as a prime contractor: __________________ %

NOTE: Small Business primes’ self-performance counts as Small Business Participation, and small business primes may achieve small business participation goals through their own performance/participation as a prime and/or through subcontracting to other small businesses.

(3) Percentage of total contract value of subcontracts planned for:

% of Total

Contract Value Large % Total Small % Small Non-Disadvantaged % Small Disadvantaged % Small Woman Owned % Small HUB Zone % Small Veteran Owned % Small Service Disabled Veteran Owned %

Each percentage above shall be accompanied by detailed supporting documentation regarding individual commitments.

NOTE: The sum of the percentages of Small Non-Disadvantaged and Small Disadvantaged should equal the entries for the Total Small; however, the sum of all of the percentages need not equal 100% since the prime is not included and individual subcontractors may be counted towards more than one category.

(4) List principal supplies/services (be specific) to be subcontracted to:

Name of Company

Type of Service/Supply

Large Small Non-Disadvantaged Small Disadvantaged Small Woman Owned Small HUB Zone Small Veteran Owned Small Service Disabled Veteran Owned

(5) Prior Performance Information: Provide any information substantiating the offeror’s track record of utilizing small business on past contracts.

(6) For Large and Small Businesses provide descriptive information for all small business categories. Any information concerning long-term relationships with Small Business subcontractors, such as mentor-protégé relationships, should be provided.

(7) Extent of Commitment: Provide documentation regarding enforceable commitments to utilize any small business category as defined in FAR Part 19 as subcontractors.

(8) Small Business Subcontracting Plan: Each Large Business Offeror shall provide a Small Business Subcontracting Plan that contains all of the elements required by FAR Clause 52.219-9. This Plan shall be submitted separately from the Small Business Participation information required above, which applies to both Large and Small Businesses. The Subcontracting Plan is not a requirement for evaluation in source selection but rather a requirement for award to a Large Business. The approved Small Business Subcontracting Plan will be incorporated into any resultant contract(s).

6.2 Evaluation Criteria:

ALL OFFERORS ARE REQUIRED TO SUBMIT A SMALL BUSINESS PARTICIPATION PLAN.

The Small Business Participation Plan will be evaluated based on the offeror’s best efforts, the level of small business commitment that is being demonstrated for the proposed acquisition, and the prior level of commitment to utilizing small businesses in performance of prior contracts. The Small Business Participation Plan must meet the minimum Total Small Business Participation goal of 15% of the total contract value (through collective small business participation from any type of small business or sub-category small business).

Pursuant to DFARS PGI 215.304(c), the following elements will be considered in evaluating an offeror’s Participation Plan:

• The extent to which such firms, as defined in FAR Part 19, are specifically identified in plans;

• The extent of commitment to use such firms (enforceable commitments will be weighted more heavily than non-enforceable ones);

• The complexity and variety of the work such firms are to perform;

• The realism of the plans;

• Past performance of offerors in complying with the requirements of the Subcontracting Plan Goals for such firms and monetary targets for participation;

• The extent of participation of such firms in terms of the proposed subcontracted value; and

• The extent to which the offeror provides detailed explanations/documentation supporting the proposed participation percentages, or lack thereof. The Department of Defense (DOD) has established small business goals to help ensure small business receives a fair proportion of DOD awards.

7. Volume II - Price and Pro forma Information

7.1 Tab A - Standard Form 1442 and Proposal Price Breakout Schedule.

7.1.1 Submission Requirements:

The offeror shall complete and submit Standard Form 1442 and Section 00 10 00, Proposal Price Breakout Schedule. Both of these forms are included in Section 00 10 00 of this solicitation.

7.1.2 Evaluation Criteria:

The price will be evaluated on base proposal plus all options (if any). The price will be evaluated for fairness and reasonableness through the use of a price analysis. Price will also be checked for unbalancing of line items. Offerors are cautioned to distribute costs appropriately.

7.2 Tab B – Joint Venture Agreements

7.2.1 Submission Requirements:

If more than one contractor is listed in Block 14, or the offeror listed in Block 14 is a joint venture (JV), then a signed JV agreement must be submitted with the proposal and the offeror shall be registered in the System for Award Management (SAM) as a legal entity separate from the individual joint venture members. However, each member of the JV must submit its own Unique Entity Identifier (formally DUNS number) with the proposal.

Small business offerors (e.g., 8(a), HUBZone, SDVOSB) submitting a proposal as a JV or Mentor-Protégé shall submit evidence from the offeror's SBA Servicing Agency that the offeror has notified and discussed the proposed joint venture for this specific project with the appropriate SBA Representative or Business Opportunity Specialist. Joint Venture agreements and approved 8(a) Mentor-Protégé agreements must be submitted with the proposal.

7.2.2 Evaluation Criteria:

This information will be used for the purpose of completing the Pre-Award Survey and will not be rated.

Joint Venture Agreements and Mentor-Protégé agreements must comply with the relevant regulations in Title 13 of the Code of Federal Regulations in order for an offeror to be eligible for any small business-related price preference.

7.3 Tab C – Evidence of Ability to Obtain Bonding and Proof of Financial Ability

7.3.1 Submission Requirements:

A. Financial Capability. Submit Proof of Financial Ability (Most recent financial statement covering assets and liabilities). Include the name, address, and telephone number of offeror's banking institution. If the offeror is a joint venture, submit this information for all joint venture members.

B. Bonding Capability. Submit information showing offeror's ability to be bonded for this project.

Include the name, address, and telephone number of the offeror's bonding company.

7.3.2 Evaluation Criteria:

This information will be used for the purpose of completing the Pre-Award Survey and will not be rated.

See FAR Part 28 for information related to bonds.

7.4 Tab D – Pre-Award Information

7.4.1 Submission Requirements:

A. The offeror shall submit one completed copy of Section 00 45 00, Representations and Certification.

B. The offeror shall submit the following information:

a) Number of years the firm has been in business;

b) Name, address, and telephone numbers of two credit/trade references;

c) A list of present commitments, including the dollar value.

If the offeror is a joint venture, submit this information for all joint venture members.

7.4.2 Evaluation Criteria:

This information will be used for the purpose of completing the Pre-Award Survey and will not be rated.

7.5 Tab E - Subcontracting Plan

7.5.1 Submission Requirements:

Large business offerors shall submit a Subcontracting Plan in accordance with FAR Clauses 52.219-8 and 52.219-9 DEV. To be acceptable, plans must adequately address the required statutory elements and provide sufficient information to enable the Contracting Officer to answer affirmatively questions A through H of Appendix DD, Part 2, AFARS 5119.705. The offeror may use the attached sample sub-contracting plan as a starting point. Percentage goals apply to the total amount being subcontracted.

7.5.2 Evaluation Criteria:

Submitted information will be evaluated for acceptability in accordance with AFARS 5119.705. To be acceptable, subcontracting plans must:

(a) Adequately address the required statutory elements.

(b) Provide sufficient information to enable the Contracting Officer to answer affirmatively questions A through H of Appendix DD (AFARS 5119.705), a copy of which is attached.

(c) To be acceptable, subcontracting plans must meet all of the requirements outlined in Appendix DD, Part 3, AFARS 5119.705. If discussions with offerors are necessary, those areas where the plan is deficient will be reviewed with each offeror with the goal of correcting deficiencies.

AFARS -- Appendix DD Subcontracting Plan Evaluation Guide Part 1 - Introduction DD-100 Purpose.

The guide provides a methodology for uniform and consistent evaluation of subcontracting plans within the Army. It is designed to facilitate compliance with the mandates of 15 U.S.C. 637(d) to increase opportunities for small and small disadvantaged businesses.

DD-101 Applicability.

In accordance with requirements of FAR 19.705-4, DFARS 219.705-4 and AFARS 5119.705-4, the contracting officer shall use this guide to review all subcontracting plans (except those for commercial items), including those submitted in response to the provisions in FAR 19.705-2(d) and (e). When the contract will require subcontracting plans, use the clauses designated by FAR 19.708(b)(1) and (2) and DFARS 219.708(b)(1)(A) in the solicitation. A copy of the completed evaluation shall be included in the contract file.

DD-102 Goals.

Contracting officers must place special emphasis on negotiating subcontracting goals that are realistic, challenging and attainable. The plan must express goals in terms of percentages of total planned subcontracting dollars and must be comparable to the dollar commitments in the small business participation plan. In accordance with FAR 19.705- 4(d), the contracting officer must review enough evidence to determine that the:

1. Offeror can meet subcontracting plan goals;

2. Offeror s goals are consistent with their cost or pricing data or information other than cost or pricing data;

3. Offeror will honor the terms of subcontract agreements (i.e., timely payments of amounts owed, use of firms cited in proposal, etc.); and

4. Offeror s make or buy policy or program does not conflict with the proposed subcontracting plan and is in the Government s best interest.

5. Plan includes the contractor s commitment to adopt and comply with its requirements and goals for small business utilization.

DD-103 Evaluation Rating.

Either the contracting officer, the small business representative, or both, shall evaluate and rate the subcontracting plan as acceptable or unacceptable, in the context of the particular procurement. For instance, in smaller dollar value contracts, or contracts for uniquely manufactured items, it might be impracticable or not cost effective for offerors to take the type of actions that might be appropriate in contracts for larger dollar values or commercial components. To receive an Acceptable rating, the contractor must satisfy all objectives in Part 2 and meet each statutory subcontracting plan requirement outlined in Part 3. Failure to receive a subcontracting plan rating of acceptable could jeopardize the offeror s selection for contract award. The contracting officer must document the decisions in the contract file.

DD-104 Modification of Guide.

Pursuant to AFARS 5101.403, only senior contracting officials may approve individual deviations to this evaluation guide. This approval authority may not be further delegated.

DD-105 Use of Preaward Surveys.

For contracts administered by the Defense Contract Management Agency, obtain information needed to assess contractor compliance with subcontracting plans in current and previous contracts by requesting a preaward survey in accordance with FAR 9.106, DFARS 209.106 and DFARS PGI 209.106.

Part 2 - Rating System DD-201 Acceptable Plans.

Objective: The subcontracting plan meets all of the requirements outlined in Part 3. The offeror has provided details that demonstrate an acceptable approach to assisting, promoting and utilizing small businesses, small disadvantaged businesses, women-owned small businesses, historically underutilized business zone small businesses, veteran-owned small businesses, service disabled veteran-owned small businesses and, for Defense Research Programs, historically black colleges and universities and minority serving institutions. The offeror has demonstrated an ability to meet prior subcontracting plan goals and honor the terms of subcontract agreements. Offeror has outlined an approach utilizing mentor protege firms, joint venture teams, or other partners. The subcontracting goals are realistic, challenging, and attainable. Clarifications and minor rework of the submission may be required to correct slight omissions that do not prejudice other offers.

DD-202 Unacceptable Plans.

Objective: The subcontracting plan fails to meet a requirement outlined in Part 3. The offeror has not provided an acceptable approach to assisting, promoting, and utilizing small businesses. The offeror has a history of failing to honor subcontract agreements. The offeror did not discuss the establishment of mentor protege relationships, teaming, or joint venture agreements with other firms. Ensure the proposed subcontracting goals are attainable in light of the contractor s past performance in meeting subcontracting goals. Proposed subcontracting goals reflect less than a good faith effort. Substantial rework of the document is required to correct omissions and establish realistic, challenging, and attainable goals. Failure to receive a rating of acceptable may jeopardize offeror s eligibility for contract award. See FAR 19.702(a)(1).

Part 3 - Subcontracting Plan Requirements DD-301 Requirements.

If any of the following are answered NO , the plan is not acceptable, and the offeror must revise it before contract award. Does the plan:

1. Contain a policy statement or evidence of internal guidance to company buyers that commits to complying with the Small Business Act (Public Law 99-661, Section 1207 and Public Law 100-180)?

2. Identify separate percentage goals for utilizing small businesses (including Alaska Native Corporations (ANCs) and Indian tribes), veteran-owned small businesses (VOSB), service-disabled veteran-owned small businesses (SDVOSB), historically underutilized business zone small businesses (HUBZone), small disadvantaged businesses (SDB), women-owned small businesses (WOSB), and, for Defense Research Programs, historically black colleges and universities and minority serving institutions where applicable? Negotiated subcontracting goals must correlate with percentages of small business utilization identified in the contractor s small business participation plan, see FAR 15.304 and DFARS 215-304, and/or minimum targets identified in the solicitation or contract modification. FAR 19.704(a)(1)

3. Project the total dollars planned to be subcontracted and a separate statement of the total dollars planned to be subcontracted to small business (including ANCs and Indian tribes), VOSB, SDVOSB, HUBZone, SDB, and WOSB concerns? FAR 19.704(a)(2)

4. Describe the principal types of supplies and services to be subcontracted and identify the types planned for subcontracting to small business (including ANCs and Indian tribes), VOSB, SDVOSB, HUBZone, SDB and WOSB concerns?

5. Describe the method to be used to develop the subcontracting goals? FAR 19.704(a)(4)

6. Describe the method for identifying potential sources for solicitation purposes? FAR 19.704(a)(5)

7. State if the offeror included indirect costs in establishing subcontracting goals, and a description of the method used to determine the proportionate share of indirect costs to be incurred with small business, VOSB, SDVOSB, HUBZone, SDB (including ANCs and Indian tribes), and WOSB concerns? FAR 19.704(a)(6)

8. Identify the name of the employee who will administer the offeror s subcontracting program and describe that person s duties? FAR 19.704(a)(7)

9. Provide an approach for ensuring that small businesses, VOSB, SDVOSB, HUBZone, SDB, (including ANCs and Indian tribes) and WOSB concerns will have an equitable opportunity to compete for subcontracts?

10. Require the offeror to include the clause at FAR 52.219-8, Utilization of Small Business Concerns in all subcontracts that offer further subcontracting opportunities and require all subcontractors (except small business concerns) that receive subcontracts over $650,000 ($1,500,000 for construction) to adopt a plan that complies with the requirements of the clause at FAR 52.219-9, Small Business Subcontracting Plan?

11. Provide assurances that the offeror will:

a. Cooperate in required studies or surveys;

b. Submit periodic reports so that the Government can determine the extent of offeror s compliance with the subcontracting plan;

c. Submit semi-annual Individual Subcontract Reports…

This is the start of the file's text. The full file is on GovTribe.