W912QR-52803153_Specs-0000.pdf

PDF 31 MB Posted

Attached to
FTC CSO DoDEA Roof and RTU Replacement
Solicitation number
W912QR-52803153
Issued by

About this file

This document is a solicitation for a Multiple Award Task Order Contract (MATOC) for the U.S. Army Reserves National Roofing Program, specifically for the DoDEA CSO Roof and RTU Replacement project at Fort Campbell, Kentucky. The solicitation targets existing MATOC contractors with contract numbers W912QR24D0054 through W912QR24D0063, requesting price proposals for design and construction services to repair roofs and replace rooftop units.

The project includes a base bid for removing and replacing 10 existing rooftop units, associated electrical and mechanical infrastructure, and roof curbs, with additional bid options for full roof replacement, installation of a building automation system, exterior awning and door replacement, and a lightning protection system. The cost range is between $1,000,000 and $5,000,000, with proposals due by 1:00 PM ET in 2025. Award will be based on lowest overall price, with the government reviewing past performance through the Contractor Performance Assessment System. Payment and performance bonds will be required, and proposals must incorporate the binding rates from the contractors' existing MATOC contracts.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation For Multiple Award Task Order Contracts Army Reserve National Roofing Program

DoDEA CSO Roof and RTU Replacement, FT Campbell, Ky

P2: 517619

Design-Build Specifications - Vol. 2 Certified Final Design

29 October 2025

W912QR-52803153

MATOC

W912QR24D0054 thru 24D0063 All requirements of the base MATOC Volume 1 of 2 shall apply to this Task Order unless noted otherwise.

RRS-A: 1200A Disposition: Permanent

W912QR-52803153_Specs-0000

REPLY T O

ATTENTION OF

DEPARTMENT OF THE ARMY

LOUISVILLE DISTRICT, CORPS OF ENGINEERS

P.O. BOX 59

LOUISVILLE, KENTUCKY 40201-0059

Contracting Division 29 October 2025

AR6-Cram Company, Inc.

Brazos Roofing International of South Dakota Carmen Roofing Services, LLC Defense Roofing Solutions, LLC Reasor Roofing, LLC South Central Roofing, Inc.

Southwest Construction & Property Management, Inc.

Sustainable Building Solutions, LLC Tabcon, Inc.

Tri-Coast-Pac Tech JV LLLP

Dear MATOC Contractors:

Reference is made to your Indefinite Delivery Contracts, Numbers W912QR24D0054 - W912QR24D0063, Indefinite Delivery Indefinite Quantity (IDIQ), Design-Build Multiple Award Task Order Contract (MATOC) for Building Envelope, Roof Repair and Replacement Construction in Support of the U.S. Army Reserves National Roofing Program (NRP), Army, and Air Force Reserve Sections.

We request you submit a price proposal for design and construction services required to repair roofs at Fort Campbell CSO DoDEA Roof and RTU Replacement as detailed in the scope of work, drawings, and specifications posted at the System for Award Management (www.SAM.gov). The documents are available for download at www.SAM.gov only. All vendors must be registered in the SAM database at SAM.gov. The RFP can be found by logging into the website as a vendor and searching for the solicitation number (W912QR-52803153). The cost range is between $1,000,000 and $5,000,000.

The basis for award of this task order will be made on lowest overall price. The government will review offerors past performance, as found within the Contractor Performance Assessment System (CPARS), in addition to price (base plus all options). Your proposal should include a price breakdown and/or labor category table demonstrating the use of the binding rates included in your MATOC contract.The submitted price breakdown should include sufficient detail to allow the Government to verify that your proposed price incorporates the binding rates from your base contract. Any level of effort shown in the submitted information will not be used for evaluation purposes and will be used only to ensure that the proposal is in compliance with the binding rates from the base contract. Proposals that fail to submit a price breakdown or fail to use the binding rates from your MATOC will not be considered. Proposals submitted in response to this RFP shall be good for no less than 120 calendar days.

Proposals are due no later than 1:00 PM ET on 2025. Submit your proposal by email to Ranzel.L.Merideth@usace.army.mil

Proposals not received by the stated date/time will not be considered. Please acknowledge receipt of this RFP by signing below in the space provided and returning to Ranzel Merideth via email at Ranzel.L.Merideth@usace.army.mil

Payment and Performance Bonds will be required for this project. Performance and Payment Bonds are required within 10 days after the date of award. The Notice to Proceed will be issued after receipt and approval of the bonds.

All questions regarding this Request for Proposal (RFP) must be submitted via ProjNet. The website to access this system is www.projnet.org and the bidder inquiry key for this specific project is:

(IW24YB-HKGXEX). Please see ProjNet instructions included in this RFP.

If you have contractual questions, please contact Ranzel Merideth at Ranzel.L.Merideth@usace.army.mil If an Offeror believes that the requirements in the RFP contain an error, omission, or are otherwise unsound; the offeror shall immediately notify the Contract Specialist in writing with supporting rationale. All Offerors is reminded that the Government reserves the right to award this RFP based on the initial proposals, as received, without discussion.

Sincerely, Joshua K. Westgate, Contracting Officer

(Signature) (Date)

(Printed Name)

(Firm Name)

OFFEROR'S QUESTIONS AND COMMENTS

Technical inquiries and questions relating to proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at http://www.ProjNet.org/ProjNet. As noted below, offerors shall not submit their proposals via ProjNet. Offerors shall submit their proposals in accordance with the provisions stated in the solicitation.

To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into system.

The Solicitation Number is: W912QR-52803153

The Bidder Inquiry Key is: IW24YB-HKGXEX

Specific Instructions for ProjNet Bid Inquiry Access:

1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

2. Identify the Agency. This should be marked as USACE.

3. Key. Enter the Bidder Inquiry Key listed above.

4. Email. Enter the email address you would like to use for communication.

5. Select Continue. A page will then open stating a user account was not found and will ask you to create one using the provided form.

6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.

7. Select Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.

Specific Instructions for Future ProjNet Bid Inquiry Access:

1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.

2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

3. Identify the Agency. This should be marked as USACE.

4. Key. Enter the Bidder Inquiry Key listed above.

5. Email. Enter the email address you used to register previously in ProjNet.

6. Select Continue. A page will then open asking you to enter the answer to your Secret Question.

7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.

From this page you may view all bidder inquiries or add an inquiry.

Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.

Offerors are requested to review the specification in its entirety and to review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

NOTES:

1. Offerors shall not submit their proposals via ProjNet, but in accordance with the provisions stated in the solicitation. Any questions regarding acceptable means of submitting offers shall be made directly to the Contract Specialist identified in the solicitation.

2. Government responses to technical inquiries and questions relating to proposal procedures or bonds that are submitted to ProjNet in accordance with the procedures above are not binding on the Government unless an amendment is issued on Standard Form 30. In the case of any conflicts, the solicitation governs. Any changes or revisions to the solicitation will be made by formal amendment.

3. The ability to enter technical inquiries and questions relating to proposal procedures or bonds will be disabled five (5) calendar days prior to the closing date stated in the solicitation.

No Government responses will be entered into the ProjNet system within two (2) calendar days prior to the closing date stated in the solicitation.

SECTION 00 10 00 SOLICITATION CONTRACT FORM

SECTION 00 10 00 Solicitation Contract Form

T

"General Decision Number: KY20250089 08/22/2025

Superseded General Decision Number: KY20240089

State: Kentucky

Construction Type: Building

County: Christian County in Kentucky.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.

Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).

|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $17.75 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2025. | |If the contract was awarded on |. Executive Order 13658 | |or between January 1, 2015 and | generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $13.30 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours spent performing on |

| | that contract in 2025. |

The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.

Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/03/2025 1 02/07/2025 2 02/28/2025 3 03/14/2025 4 04/04/2025 5 04/11/2025 6 06/06/2025 7 07/18/2025 8 08/08/2025 9 08/22/2025

BOIL0040-001 01/01/2025

Rates Fringes

BOILERMAKER......................$ 43.85 28.44

ENGI0181-053 06/01/2025

Rates Fringes

POWER EQUIPMENT OPERATOR

(Crane)..........................$ 40.65 19.60

CRANES WITH BOOM 150 FEET & OVER, INCLUDING JIB, SHALL

RECEIVE $.75 ABOVE THE WAGE RATE; 250 FEET AND OVER,

INCLUDING JIB, SHALL RECEIVE $1.50 ABOVE THE WAGE RATE.

ALL CRANES WITH PILING LEADS WILL RECEIVE $.50 ABOVE THE

WAGE, REGARDLESS OF BOOM LENGTH.

ENGI0181-054 06/01/2025

Rates Fringes

POWER EQUIPMENT OPERATOR

(Drill)..........................$ 40.65 19.60

ENGI0181-079 06/01/2025

Rates Fringes

POWER EQUIPMENT OPERATOR

(Loader).........................$ 40.65 19.60

ENGI0181-080 06/01/2025

Rates Fringes

POWER EQUIPMENT OPERATOR

(Forklift).......................$ 40.65 19.60

ENGI0181-093 06/01/2025

Rates Fringes

POWER EQUIPMENT OPERATOR

(Oiler)..........................$ 34.99 19.60

IRON0044-017 06/01/2025

Rates Fringes

IRONWORKER, ORNAMENTAL...........$ 37.77 23.90

LABO0561-009 04/01/2025

Rates Fringes

LABORER (Mason Tender - Brick)...$ 28.89 19.20

* LABO1445-002 06/01/2025

Rates Fringes

LABORER (Power Tool Operator)....$ 31.35 23.18

PAIN0156-004 04/01/2024

Rates Fringes

PAINTER: Spray..................$ 30.62 20.30

FOOTNOTE A:

All Structures over 40? $0.75/ hour above base wage All Structures over 75? $1.50/ hour above base wage All Structures over 100? $2.50/ hour above base wage

PLUM0184-006 07/01/2025

Rates Fringes

PLUMBER..........................$ 44.26 20.28

PLUM0633-001 08/01/2024

Rates Fringes

PIPEFITTER.......................$ 38.41 22.26

* ROOF0106-010 07/01/2025

Rates Fringes

ROOFER...........................$ 30.97 13.91

SFKY0669-002 04/01/2025

Rates Fringes

SPRINKLER FITTER.................$ 44.15 26.08

SHEE0020-001 07/01/2014

Rates Fringes

SHEET METAL WORKER (HVAC Duct Installation Only)...............$ 29.45 19.29

* UAVG-KY-0019 01/01/2025

Rates Fringes

ASBESTOS WORKER/HEAT & FROST

INSULATOR........................$ 30.94 21.99

* SUKY2015-028 06/02/2015

Rates Fringes

BRICKLAYER.......................$ 25.09 10.05

CARPENTER (Form Work Only).......$ 25.20 7.12

CARPENTER, Excludes Form Work....$ 21.68 7.20

CEMENT MASON/CONCRETE FINISHER...$ 20.56 9.56

ELECTRICIAN......................$ 30.50 9.21

IRONWORKER, REINFORCING..........$ 27.31 16.86

IRONWORKER, STRUCTURAL...........$ 25.41 7.63

LABORER: Common or General......$ 18.04 0.00

LABORER: Mason Tender - Cement/Concrete..................$ 19.85 9.87

LABORER: Pipelayer..............$ 15.00 ** 4.08

OPERATOR:

Backhoe/Excavator/Trackhoe.......$ 28.01 7.59

OPERATOR: Bulldozer.............$ 24.51 12.72

OPERATOR: Paver (Asphalt, Aggregate, and Concrete).........$ 22.52 4.00

OPERATOR: Roller................$ 23.60 12.65

PAINTER (Brush and Roller).......$ 17.45 ** 0.34

SHEET METAL WORKER, Excludes HVAC Duct Installation...........$ 36.24 6.89

TILE FINISHER....................$ 15.42 ** 7.24

TILE SETTER......................$ 20.96 0.00

TRUCK DRIVER: Dump Truck........$ 23.60 8.03

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

** Workers in this classification may be entitled to a higher minimum wage under Executive Order 14026 ($17.75) or 13658 ($13.30). Please see the Note at the top of the wage determination for more information. Please also note that the minimum wage requirements of Executive Order 14026 are not currently being enforced as to any contract or subcontract to which the states of Texas, Louisiana, or Mississippi, including their agencies, are a party.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)).

The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.

Union Rate Identifiers

A four-letter identifier beginning with characters other than ""SU"", ""UAVG"", ?SA?, or ?SC? denotes that a union rate was prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.

0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.

Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification.

Union Average Rate Identifiers

The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE:

UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio.

The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.

A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.

Survey Rate Identifiers

The ""SU"" identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007 6/27/2024. SU indicates the rate is a single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier.

?SU? wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1).

State Adopted Rate Identifiers

The ""SA"" identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007 01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.

The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the ?SA? identifier took effect under state law in the state from which the rates were adopted.

WAGE DETERMINATION APPEALS PROCESS

1) Has there been an initial decision in the matter? This can be:

a) a survey underlying a wage determination

b) an existing published wage determination

c) an initial WHD letter setting forth a position on a wage determination matter

d) an initial conformance (additional classification and rate) determination

On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of Wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mail to:

Branch of Wage Surveys Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations.

Requests can be submitted via email to BCWD-Office@dol.gov or by mail to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).

Requests for review and reconsideration can be submitted via email to dba.reconsideration@dol.gov or by mail to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210.

END OF GENERAL DECISION"

Section 00 70 00

52.204-27 Prohibition on a ByteDance Covered Application.

As prescribed in 4.2203(c), insert the following clause:

Prohibition on a ByteDance Covered Application (Jun 2023)

(a) Definitions. As used in this clause-

Covered application means the social networking service TikTok or any successor application or service developed or provided by ByteDance Limited or an entity owned by ByteDance Limited.

Information technology, as defined in 40 U.S.C. 11101(6)-

(1) Means any equipment or interconnected system or subsystem of equipment, used in the automatic acquisition, storage, analysis, evaluation, manipulation, management, movement, control, display, switching, interchange, transmission, or reception of data or information by the executive agency, if the equipment is used by the executive agency directly or is used by a contractor under a contract with the executive agency that requires the use-

(i) Of that equipment; or

(ii) Of that equipment to a significant extent in the performance of a service or the furnishing of a product;

(2) Includes computers, ancillary equipment (including imaging peripherals, input, output, and storage devices necessary for security and surveillance), peripheral equipment designed to be controlled by the central processing unit of a computer, software, firmware and similar procedures, services (including support services), and related resources; but

(3) Does not include any equipment acquired by a Federal contractor incidental to a Federal contract.

(b) Prohibition. Section 102 of Division R of the Consolidated Appropriations Act, 2023 (Pub. L. 117-328), the No TikTok on Government Devices Act, and its implementing guidance under Office of Management and Budget (0MB) Memorandum M-23-13, dated February 27, 2023, "No TikTok on Government Devices" Implementation Guidance, collectively prohibit the presence or use of a covered application on executive agency information technology, including certain equipment used by Federal contractors. The Contractor is prohibited from having or using a covered application on any information technology owned or managed by the

Government, or on any information technology used or provided by the Contractor under this contract, including equipment provided by the Contractor's employees;

however, this prohibition does not apply if the Contracting Officer provides written notification to the Contractor that an exception has been granted in accordance with 0MB Memorandum M-23-13.

(c) Subcontracts. The Contractor shall insert the substance of this clause, including this paragraph (c), in all subcontracts, including subcontracts for the acquisition of commercial products or commercial services.

(End of clause)

52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984)

The Contractor shall be required to

(a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed,

(b) prosecute the work diligently, and

(c) complete the entire work ready for use not later than 420 calendar days from Notice to Proceed. The time stated for completion shall include final cleanup of the premises.

(End of Clause)

52.211-12 Liquidated Damages -- Construction (Sept 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $1,010 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

(End of Clause)

52.217-5 -- Evaluation of Options.

As prescribed in 17.208(c), insert a provision substantially the same as the following:

Evaluation of Options (Jul 1990) best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

(End of Provision)

52.217-7 -- Option for Increased Quantity -- Separately Priced Line Item.

The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option Reference Price Breakout Schedule. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.

(End of Clause)

52.236-4 Physical Data (Apr 1984)

Data and information furnished or Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations via surveys.

(b) Weather conditions: The Contractor shall make his own investigations as to weather conditions at the site. Data may be obtained from various National Weather Service offices located generally at airports of principal cities, the nearest to this project being Nashville, TN.

(c) Transportation facilities: Roads and railroads in the general area are shown on the drawings.

Access ways shall be investigated by the Contractor to satisfy himself as to their existence and allowable use.

(d) Historical data for all areas may be obtained from:

US Dept of Commerce National Climatic Center Federal Building Asheville, N.C. 28801

(End of Clause)

52.236-27 Site Visit (Construction) (Feb 1995) Alternate I

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

6 November 2025 at 13:00 CDT (local) POC is Laura Villar Email: Laura.R.Villar@usace.army.mil Phone: (270) 461-4070

252.236-7001 Contract Drawings and Specifications (AUG 2000)

(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.

(b) The Contractor shall

(1) Check all drawings furnished immediately upon receipt;

(2) Compare all drawings and verify the figures before laying out the work;

(3) Promptly notify the Contracting Officer of any discrepancies;

(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and

(5) Reproduce and print contract drawings and specifications as needed.

(c) In general--

(1) Large-scale drawings shall govern small-scale drawings; and

(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.

(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.

(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings: N/A

(End of clause)

P2# 517619 DoDEA CSO ROOF AND RTU REPLACEMENT

FORT CAMPBELL, KY

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 80 50.00 06 05/2023 SPECIAL PROVISIONS

DIVISION 01 - GENERAL REQUIREMENTS

01 03 00.00 06 05/20 DESIGN SUBMISSION REQUIREMENTS AFTER

AWARD

01 11 50.00 06 01/20 SUMMARY OF WORK

01 35 26.00 06 05/24 CHG 1: 10/24 GOVERNMENT SAFETY REQUIREMENTS

01 42 00 05/24 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.15 10 11/23 RESIDENT MANAGEMENT SYSTEM CONTRACTOR

MODE (RMS CM)

PROJECT TABLE OF CONTENTS Page 1 Certified Final

ATTACHMENTS:

ATTACHMENT A: SITE LOCATION

ATTACHMENT B: AS-BUILTS

ATTACHMENT C: CONCEPT DRAWINGS

ATTACHMENT D: SITE PHOTOS

ATTACHMENT E: ASBESTOS REPORT

ATTACHMENT F: EXAMPLE RRO REPORT

ATTACHMENT G: ROOF WARRANTY

ATTACHEMNT H: STANDARD ROOF DETAILS

ATTACHMENT I: AUTHORITY TO CONNECT

ATTACHMENT J: iWATCH DOCUMENTS

ATTACHMENT K: REC REPORT

ATTACHMENT L: PRE-TAB REPORT

-- End of Project Table of Contents --

SECTION 00 80 50.00 06

SPECIAL PROVISIONS

05/2023

PART 1 GENERAL

This section is a supplement to section 00 80 00.00 06 in the base contract. This document will provide additional information or revise base contract requirements for this task order only.

Attachments to this specification are as follows:

Project Submittal Register

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 415-1-15 (1989) Construction Time Extensions for Weather

1.2 SUBMITTALS

Government approval/acceptance is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with LRL Section 01 33 00.00 06

SUBMITTAL PROCEDURES:

SD-02 Shop Drawings

Mechanical/Electrical Room Layout; G

SD-03 Product Data

Warranty Management Plan

SD-07 Certificates

Roof Warranty Identification Placard; G

Equipment Warranty Information; G

SD-10 Operation and Maintenance Data

O&M And Repair Manuals; G

DOCUMENT 00 80 50.00 06 Page 1 Certified Final

1.3 NOT USED

1.4 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the FAR 52.249-10 "Default (Fixed-Price Construction)". Guidance can also be found in ER 415-1-15 , "Construction Time Extensions for Weather". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

b. Indicate the location of the National Weather Service office closest to the site. See: https://www.weather.gov/srh/nwsoffices The Contractor shall make his own investigations and determinations as to weather conditions at the site. Data may be obtained from various National Weather Service offices located generally at airports of principal cities, the nearest to this project being: Nashville, TN.

c. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in weather dependent activities.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY

WORK DAYS BASED ON (5) DAY WORK WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

22 21 21 21 15 5 5 4 3 16 19 20

Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated listed above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the FAR 52.249-10 "Default (Fixed-Price Construction)".

DOCUMENT 00 80 50.00 06 Page 2

1.5 NOT USED

1.6 CONTRACT DRAWINGS AND SPECIFICATIONS

In addition to DFARS 252.236-7001 "Contract Drawings and Specifications" in Section 00 70 00 the following will apply:

a. After Award or no later than Notice to Proceed (NTP), the Government will furnish the Contractor all technical contract documents in electronic media only. This will include a complete set of drawing files and technical specification files which have all amendments included. It will contain drawing files in PDF format along with technical specifications in PDF format. These PDF files are the contract documents that represent the construction requirements of the contract, and are being provided for the Contractor's use in printing paper copies of contract documents.

b. In addition, native CAD files(this includes, but not limited to, all source files, models, custom fonts and linestyles, plot files, and images used to create the contract drawings) are provided in accordance with the "AS-BUILT DOCUMENTS" paragraph for the Contractor's use in maintaining and preparing as-built plans. If another CAD Program is used other than the Using Agency's System, all native CAD files that were generated with that software and all support files will also be included. Only native files are to be used for As-Built preparation and information.

c. Native files are to be used for As-Built preparation only. The PDF files are the contract documents that represent the construction requirements of the contract.

1.7 AT/OPSEC REQUIREMENTS

General security requirements and guidance:

The security requirements described below apply to all contract personnel (including employees of the prime Contractor ("Contractor") and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative.

Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as "RAMs"), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance

DOCUMENT 00 80 50.00 06 Page 3 requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures-this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel.

The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.

Antiterrorism (AT) Level I training: All contract personnel requiring routine access to Army installations, facilities, and controlled access areas, or requiring network access shall complete initial and annual refresher AT Level I awareness training. Online AT Level I awareness training is available at https://jko.jten.mil/ (website subject to change).

Physical security and access control requirements:

All contract personnel requiring physical access to a federal installation or facility shall comply with the access control procedures of that location. Contract personnel requiring unescorted access to meet contract performance requirements on a DoD installation in the US shall be vetted by the installation/facility Provost Marshal/Directorate of Emergency Services/Security Office using the National Crime Information Center-Interstate Identification Index (commonly referred to as "NCIC-III") and Terrorist Screening Database (commonly referred to as "TSDB"). Contract personnel shall comply with all personal identity verification requirements specified in installation/facility policies and procedures. Contract personnel who do not meet requirements for unescorted access to USACE facilities shall coordinate escorted access with the Government representative, as needed. Contract personnel who receive keys, access cards, or lock combinations that provide access to government-owned property shall comply with key and lock control procedures of the RA.

Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See Something, Say Something): All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.

Pre-screen candidates using E-Verify Program:

Contractors shall comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR Subpart 22.18 in using the E-Verify Program at (https://www.e-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements.

Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/eligible candidates shall be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.

DOCUMENT 00 80 50.00 06 Page 4

1.8 NOT USED

1.9 EQUIPMENT DATA, O&M, & REPAIR MANUALS WITH FIELD TRAINING REQUIREMENTS

1.9.1 O&M and Repair Manuals

Withholding & Copies The Contractor shall provide 6 electronic format copies on CD of the Equipment Operating, Maintenance, and Repair Manuals and two complete hardcopies; these requirements shall apply even through the Technical Specification section indicates otherwise. The manuals shall be prepared electronically in PDF format containing bookmarks for each table of contents item. The PDF file shall be referenced in a separate column or linked worksheet in the equipment data excel spreadsheet as described previously. Separate manuals shall be provided for each utility system as defined per the Technical Specification. Operations and Maintenance manuals shall be accepted/approved before field training or 30 calendar days before substantial completion (whichever occurs earlier). An amount of $10,000 shall be withheld until submittal and acceptance/approval of O&M manuals is complete. A draft outline and table of contents shall be submitted for acceptance/approval at 50% contract completion. See paragraph "EQUIPMENT OPERATING, MAINTENANCE,and REPAIR MANUALS" for detail O&M and Repair Manual format.

1.10 AVAILABILITY OF UTILITIES

The contractor will coordinate with City Light & Power (CLP) for electrical utilities during construction. The contractor will be responsible for a connection fee to ensure temporary electrical services are available during construction. CLP will provide a meter and the associated equipment to ensure energy consumption is accurately captured. The contractor is responsible for coordinating with CLP any additional loads that may impact the exterior electrical services. CLP will make all electrical utility connections but not limited to providing overhead or underground extensions, transformers, switchgear, overcurrent protection, anchors, making all connections and disconnections. CLP will be responsible for maintaining all electrical services to the facility once the electrical utility connections have been completed.

1.11 NOT USED

1.12 NOT USED

1.13 NOT USED

1.14 NOT USED

1.15 WARRANTY OF CONSTRUCTION

a. In addition to the requirements found in FAR 52.246-21 "WARRANTY OF CONSTRUCTION" in Section 00 70 00 the following shall be included:

(1) Construction Warranty:

The construction warranty shall continue for a period of 1 year from the date of final acceptance of the work. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 1 year from the date the Government takes possession.

DOCUMENT 00 80 50.00 06 Page 5

(2) Mechanical Equipment Warranty:

The contractor must provide a one year parts and labor warranty on all RTUs and Fans. In addition to the contractors one year warranty the contractor must provide and additional 5 year compressor parts warranty on all RTUs.The construction warranty period must begin on the date of project acceptance and continue for the full product warranty period.

(3) Roof Warranty:

The Installers warranty shall continue for a period of 5 years from the date of final acceptance of the work. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 5 years from the date the Government takes possession.

(a) The contractor must include a nine month warranty inspection. As a part of the nine month warranty inspection,the Contractor shall conduct an infrared roof survey on any project involving a membrane roofing system.

This survey will be conducted in accordance with ASTM C1153, "Standard Practice Infrared Imaging". In accordance with FAR 52.246-21 "WARRANTY OF CONSTRUCTION" in Section 00 70 00, the Contractor shall be required to replace all damaged materials and to locate and repair sources of moisture penetration.

(b) A representative from the manufacturer shall attend the nine month warranty inspection. Any deficiencies noted by the manufacturer that will impact any manufacturer’s warranty will be corrected by the installer.

(4) The roofing system manufacturer’s warranty shall continue for a period of 20 years from the date of final acceptance of the work. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 20 years from the date the Government takes possession.

(a) Warranties shall comply with the requirements of the United Facilities Criteria (UFC) Roofing, UFC 3-110-03 latest version.

(b) Warranty shall include roofing membrane, base flashing, roofing membrane accessories, roof insulation, roof fasteners, roof cover boards, walkway products and other components of the roofing system.

(c) The warranty shall cover the complete roofing system and shall have no financial limitation.

(5) Submit all manufacturer's equipment warranty information to be included in the warranty management plan.

b. Warranty Management

(1) Warranty Management Plan

The Contractor shall develop a warranty management plan which shall contain information relevant to the clause "Warranty of Construction" in FAR 52.246-21. At least thirty (30) calendar days before the planned pre-warranty conference, the Contractor shall submit the warranty management plan for Government approval. The warranty management plan shall include all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan shall be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesmen, or

DOCUMENT 00 80 50.00 06 Page 6 of engineering background, not necessarily familiar with this contract. The term "status" as indicated below shall include due date and whether item has been submitted or was accomplished. Warranty information made available during the construction phase shall be submitted to the Contracting Officer for approval prior to each monthly pay estimate. Approved information shall be assembled in a binder and shall be turned over to the Government upon acceptance of the work. The construction warranty period shall begin on the date of project acceptance and shall continue for the full product warranty period. A joint 4 month and 9 month warranty inspection shall be conducted, measured from time of acceptance, by the Contractor, Contracting Officer and the Customer Representative. Information contained in the warranty management plan shall include, but shall not be limited to, the following:

(a) Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the organizations of the Contractors,subcontractors, manufacturers or suppliers involved.

(b) Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers, and for all commissioned systems such as fire protection and alarm systems, sprinkler systems, lightning protection systems, etc.

(c) A list for each warranted equipment, item, and feature of construction or system indicating:

1. Name of item.

2. Model and serial numbers.

3. Location where installed.

4. Name and phone numbers of manufacturers or suppliers.

5. Names, addresses and telephone numbers of sources of spare parts.

6. Warranties and terms of warranty. This shall include one-year overall warranty of construction. Items which have extended warranties shall be indicated with separate warranty expiration dates.

7. Cross-reference to warranty certificates as applicable.

8. Starting point and duration of warranty period.

9. Summary of maintenance procedures required to continue the warranty in force.

10. Cross-reference to specific pertinent Operation and Maintenance manuals.

11. Organization, names and phone numbers of persons to call for warranty service.

12. Typical response time and repair time expected for various warranted equipment.

(d) The Contractor's plans for attendance at the 9 month post-construction warranty inspections conducted by the Government.

(e) Procedure and status of tagging of all equipment covered by extended warranties.

(f) Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.

DOCUMENT 00 80 50.00 06 Page 7

1.16 NOT USED

1.17 INTERFERENCE WITH TRAFFIC AND PUBLIC AND PRIVATE PROPERTY

a. The Contractor at all times shall dispose his plant and conduct the work in such manner as to cause as little interference as possible with private and public travel. Damage (other than that resulting from normal wear and tear) to roads, shall be repaired to as good a condition as they were prior to the beginning of work and to the satisfaction of the Contracting Officer.

b. It is the Contractor's responsibility to coordinate the submittal of all Notices to Airman (NOTAM) with the installation and airfield managers prior to and during Construction as necessary to not impede current airfield operations.

1.18 NOT USED

1.19 NOT USED

1.20 NOT USED

1.21 GOVERNMENT FIELD OFFICE FACILITIES AND SERVICES

Government field office facilities are not required for this task order.

1.22 COMPLIANCE WITH POST/BASE REGULATIONS

Refer to the base MATOC contract for compliance requirements that apply to all Military projects located on military installations.

Ft Campbell requires the following additional compliance:

Fort Campbell has certain restrictions for…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .