SOW_Tech_Exhibit_3_Deliverables_Schedule.pdf
PDF 139 KB Posted
- Attached to
- Exterior Concrete Minor Construction
- Solicitation number
- W912QM-19-R-0006
About this file
Deliverables
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOW_Tech_Exhibit_2_Pricing_Format.pdf | ||
| W912QM-19-R-0006.pdf | ||
| SOW_Tech_Exhibit_1_Drawings.pdf | ||
| SOW_Tech_Exhibit_1_Drawings.pdf | ||
| SOW_Tech_Exhibit_2_Pricing_Format.pdf | ||
| SOW.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Technical Exhibit 3 – DELIVERABLES SCHEDULE
Deliverable Frequency # of Copies Medium/Format Submit To
1. Contractor shall provide a copy of the QC plan.
Deliverable with proposal and after
Contract Award
One copy, with proposal and
30 days after contract award
Electronic copy, MS Word, Excel, or pdf.
COR and KO
2. Contractor shall provide background checks for employees. See 1.11 for more details.
Upon request by COR
1 copy Electronic copy, MS Word, Excel, or pdf.
COR and KO
3. Contractor shall provide
Key Personnel listing. IAW
1.25
Within 10 days after contract award
1 copy Electronic copy, MS Word, Excel, or pdf.
COR and KO
4. Personnel Listing.
Contractor shall have five days to submit to the KO a list of workers and Project
Managers assigned to work.
See paragraph 1.27 for additional information.
Deliverable 2 days after
Contract Award
1 copy Electronic copy, MS Word, Excel, or pdf.
COR and KO
5. Contractor shall provide license and permit documentation. See paragraph 1.34
Prior start construction
1 copy Electronic copy, MS Word, Excel, or pdf.
COR and KO
6. The Contractor shall provide licenses and permits 1.34
Upon request by the KO or
COR
1 copy Electronic copy, MS Word, Excel, or pdf.
COR and KO
7. The Contractor shall provide personnel licensed for Accident Protection and Emergency Medical Treatment IAW 1.36.1
5 days prior start of work
1 copy Electronic copy, MS Word, Excel, or pdf.
COR and KO
8.. Contractor shall provide a list of all vehicles. See paragraph 1.39 for additional information.
Within 5 days of contract award
1 copy Electronic copy, MS Word, Excel, or pdf.
COR and KO
W912QM-19-R-0006
W912QM-19-R-0006
Deliverable Frequency # of Copies Medium/Format Submit To
9. Contractor shall certify all completed work on weekly basis and provide weekly progress report. See paragraph 4.6 for additional information.
Due every
Tuesday, no later than 1300 hrs (1:00 p.m.
CST).
1 copy Electronic copy, MS Word, Excel, or pdf.
COR and KO
10. Prohibition on Asbestos and Lead Based Paints. See paragraph 4.9.4 for additional information.
Deliverable after Contract completion
2 copies after contract completion
Certified letter, hard copy of
PDF file
COR and KO
13. Reserved
14. The contractor shall notify in writing Final
Inspection Date
5 days in advance of final inspection date
1 copy Electronic copy, MS Word, Excel, or pdf.
COR and KO
12. Reserved
11. Reserved