SOW_Tech_Exhibit_2_Pricing_Format.pdf

PDF 128 KB Posted

Attached to
Exterior Concrete Minor Construction
Solicitation number
W912QM-19-R-0006
Issued by

About this file

Pricing Format

View the file

Other files

File Type Posted
W912QM-19-R-0006.pdf PDF
SOW_Tech_Exhibit_1_Drawings.pdf PDF
SOW_Tech_Exhibit_3_Deliverables_Schedule.pdf PDF
SOW_Tech_Exhibit_1_Drawings.pdf PDF
SOW_Tech_Exhibit_2_Pricing_Format.pdf PDF
SOW.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CLIN SUPPLIES/SERVICES QTY UNIT ISSUE UNIT PRICE TOTALS COMMENTS

The Contractor shall layout the proposed slab and walkways using spray paint or other markers for approval by the COR prior to commencing construction 1 JOB

The contractor shall prep the area for concrete (level ground, remove grass and other unwanted ground cover, build forms, and supports) 1 JOB

The contractor shall poor 4” mesh rebar, reinforced slab concrete and walkways with anti-slip and crack mitigation for the areas roughly shown in figure 1-2. The large circular areas will have a stamped paver appearance.

1 JOB

Mesh rebar Unk EACH Concrete (4" depth) Unk EACH The Contractor shall install two access boxes for the existing water shutoffs near the fountain. 1 JOB

In Ground Access Box 2 EACH The Contractor shall remove 2 sections of fence to allow the walk way to tie into the road. 1 JOB The Contractor tie the new walkway into the existing street, temporarily move the barriers and replace them after the concrete is cured, place an appropriately sized draining pipe under the walkway next to the road to allow water to flow in the draining ditch.

1 JOB

Drainage Pipe 1 EACH

The contractor shall construct two seating benches made finished with smooth cement.

Construction can be cinder block or solid concrete. 1 JOB

Cinder Blocks Seating 2 EACH

The Contractor shall create a cement flag stand like the one outside BLDG M-05 capable of holding 4 flags 1 JOB

The Contractor shall build a Stone Fire pit with gas burner 1 JOB

Gas Burner 1 EACH Stone Façade 1 EACH Trench and bury ~3M of Propane gas line 1 JOB ~3M of Propane gas line 1 EACH The Contractor shall procure, deliver, and install a remote propane tank storage box with a removable and refillable Liquid Propane tank similar to the following (https://www.ashleyfurniture.com/p/hatchlands-tank-storage-box/P015-907.html):

1 EACH

The Contractor shall procure, deliver, and install 6 wooden chairs 6 EACH

The contractor shall remove and replant the tree at the specified location to the location requested in the diagram 1 JOB

SOW Tech Exhibit 2_Pricing Format

Fire Pit - CLIN 0004

New Cement Work - CLIN 0001

Permanent Cement Seating - CLIN 0002

Permanent Flag Stand - CLIN 0003

Move Tree - CLIN 0005

CLIN SUPPLIES/SERVICES QTY UNIT ISSUE UNIT PRICE TOTALS COMMENTS

The contractor shall move existing logs to create four new parking spots. 1 JOB Add three new divider logs and 3 EACH Paint all new and existing logs yellow 1 JOB The contractor shall add weed and grass prevention measures and then add 3” of gravel for new spots 1 JOB

Weed and grass prevention material 1 EACH Gravel 1 EACH

The Contractor shall install 8 new parking signs and poles as depicted in figure 6-2: 1 JOB

Parking Signs 8 EACH Parking Sign Posts 8 EACH

Contractor shall procure, deliver and install 6 sets of café style tables with 4 chairs per set 6 EACH

The Contractor shall place 3” of gravel the length of the walkway between the R-31 fence and the existing jersey barriers as specified in the diagram 1 JOB

The contractor shall install border guards to prevent gravel spill over into the fenced grass area surrounding Bldg. R-31 1 EACH

The contractor shall add weed and grass prevention measures 1 JOB Weed and grass prevention material 1 EACH Gravel 1 EACH

The Contractor shall do a final cleaning to include disposal of debris resulting from construction as well as dispose of containers for the materials used during construction.

All debris and garbage, demolition materials, debris from the construction, as well as the garbage created by the containers for the materials, such as boxes and bags shall be removed. All the grass that grows in the construction lot during construction shall be cut and clippings moved to the municipal dumps by Contractor.

1 JOB

The Contractor shall repair all trenched areas (repair any damaged concrete) and backfill and resod as appropriate. 1 JOB

Concrete Unknown EACH Sod Unknown EACH

Contractor shall warrant its work against faulty workmanship for a period of not less than one year from the date of Government acceptance of the work provided under this contract. Under this warranty, Contractor shall be prepared to return to the work site within one working day after notification without charge to make any necessary repairs as a result of faulty workmanship. Refer to FAR Clause 52.236-5, Warranty of Construction.

1 EACH

Clean up and Finishing - CLIN 0009

Warranty - CLIN 0010

Enlarge Gravel Parking Area - CLIN 0006

Café Style Seating - CLIN 0007

Gravel Walkway - CLIN 0008 not used

File details come from the government source that posted it.