SOW_Tech_Exhibit_1_Drawings.pdf

PDF 659 KB Posted

Attached to
Exterior Concrete Minor Construction
Solicitation number
W912QM-19-R-0006
Issued by

About this file

DRAFT: Visual depiction of location and minor construction exterior finishing work

View the file

Other files

File Type Posted
SOW_Tech_Exhibit_2_Pricing_Format.pdf PDF
W912QM-19-R-0006.pdf PDF
SOW_Tech_Exhibit_1_Drawings.pdf PDF
SOW_Tech_Exhibit_3_Deliverables_Schedule.pdf PDF
SOW_Tech_Exhibit_2_Pricing_Format.pdf PDF
SOW.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

M‐05 Soto Cano AB 29 Mar 2019

As‐Is

29 Mar 2019

New Cement Work

4” rebar reinforced slab concrete finished with a similar texture as existing walkways including anti‐slip and crack mitigation.

Large circular area finished with a stamped paver appearance

Water valve access boxes installed as required to facilitate access

Cement walkway will tie into the road and require removal of a section of fence, temporary removal of the barriers and addition of a large drainage pipe to allow water to flow under the walkway

Contractor will reposition the existing protective barriers on top of the new cement after work is complete to prevent vehicle travel on the path.

29 Mar 2019

Permanent Cement Seating

Two seating benches made finished with smooth cement. Construction can be cinder block or solid concrete. Finished product should look similar to:

29 Mar 2019

Permanent Flag Stand

Permanent Flag Stand close to the fountain for 4 flags similar to the one outside bldg. M‐05.

29 Mar 2019

Fire Pit Stone Firepit with gas burner similar to below (exterior rock finish should match gazeebo):

attached to a remote gas cylinder storage box similar to (https://www.ashleyfurniture.com/p/hatchlands‐tank‐ storage‐box/P015‐907.html)

6 Wooden chairs similar to below:

29 Mar 2019

Move Tree

Remove tree and replant it in garden location centered between the three large boulders.

Fill hole.

29 Mar 2019

Add 4 Parking Spots

Move existing logs to create four new parking spots. Add three new divider logs and paint all new and existing logs yellow.

Add weed and grass prevention measures and then add 3” of gravel for new spots

29 Mar 2019

Install New Parking Spot Signs for all Spots

Remove old parking signs and install eight new parking signs and poles:

JTF‐B

CDR

JTF‐B

CSM

JTF‐B

DCO

JTF‐B

COS

JTF‐B

J5

JTF‐B

J3

JTF‐B

J2

JTF‐B

J3 SGM

29 Mar 2019

Add Metal Café Style Seating (x6)

6 sets of metal café style tables with 4 chairs each similar to below:

29 Mar 2019

Add Gravel Walkway

Put down weed prevention and then place 3” of gravel along the path

29 Mar 2019

Final Project

7.00M

2.8M

1.85M

1.85M

1.85M

1.85M 1.85M

1.85M

3.5M

37M

7.5M

9.8M

7.00M

Edge of concrete pads will follow the natural boundaries created by the existing landscaping. No landscaping should be moved without prior approval.

Measurements provided are for estimating amount of concrete required only. Exact form layout will be coordinated with the COR and will be laid out using spray paint for final approval prior to construction.