Amendment 0001

View the file

Other files for this federal contract opportunity

Other files attached to CONSTRUCT PUMPHOUSE AND FUEL STORAGE, CANNON AIR FORCE BASE, newest first.
File Type Posted
W912PP-16-R-0005_Amendment_0006.pdf PDF
W912PP-16-R-0005_Amendment_0005.pdf PDF
W912PP-16-R-0005_Amendment_0004.pdf PDF
W912PP-16-R-0005-Amendment_0003.pdf PDF
Site_Visit_Attendance_Sheet.pdf PDF
W912PP-16-R-0005_Amendment_0002.pdf PDF
W912PP-16-R-0005-Drawings-Shts-92-264_10-Feb-16.pdf PDF
W912PP-16-R-0005-Drawings-Shts-1-91_10-Feb-16.pdf PDF
W912PP-16-R-0005-Specs-Vol-1of2.pdf PDF
W912PP-16-R-0005-Specs-Vol-2of2.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

PROJECT: CONSTRUCT PUMPHOUSE AND FUEL STORAGE, CANNON AIR FORCE BASE, CURRY

1. This is Amendment No. 0001 to Solicitation No. W912PP-16-R-0005. The follow ing revisions shall be incorporated into the specif ications.

All other provisions shall remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912PP-16-R-0005

X 9B. DATED (SEE ITEM 11)

09-Feb-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

17-Feb-2017

CODE

US ARMY ENGINEER DISTRICT, ALBUQUERQUE

4101 JEFFERSON PLAZA NE

ALBUQUERQUE NM 87109-3435

W912PP 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

COUNTY, NEW MEXICO

W912PP-16-R-0005

Amendment 0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

2. SPECIFICATIONS: DELETE THE FOLLOWING LISTED PAGES AND SUBSTITUTE THE PAGES

ATTACHED HERETO. ON THE REVISED PAGES, FOR CONVENIENCE, CHANGES ARE

EMPHASIZED BY STRIKETHROUGH FOR DELETIONS AND UNDERLINE FOR ADDITIONS FROM

THE PREVIOUS ISSUE. ALL PORTIONS OF THE REVISED (OR NEW) PAGES SHALL APPLY

WHETHER OR NOT CHANGES HAVE BEEN INDICATED.

Delete Page Insert Page

Section 00010, Page 3a of 97 Section 00010, Page 3a of 97

Section 00100, Page 9 of 97 Section 00100, Page 9 of 97

N/A New Clause in Section 00700

////////LAST ITEM////////

Page 3a of 97

W912PP-16-R-0005

Construct Pumphouse and Fuel Storage

DESC 1702

Cannon AFB, NM

CONTRACT LINE ITEM PRICING SCHEDULE

Item No.

Description of Item Estimated Quantity

Unit Unit Price

Estimated Amount

BASE BID ITEMS

0001 All work complete for New Pumphouse and associated appurtenances, excluding Basic Items and Options Item 0008 and 0014 listed below.

1 JOB XXX $_________

0002 All work complete for four Truck Fill stands and associated piping and appurtenances excluding Basic Items and Option Item 0009 listed below.

1 JOB XXX $_________

0003 All work complete for four twoTruck Offloads and associated piping and appurtenances, excluding Basic Items and Option Item 0010 listed below.

1 JOB XXX $_________

0004 All work complete for Two Above Ground Storage Tanks and associated piping and appurtenances, excluding Basic Items and Option Item 0013 listed below.

1 JOB XXX $_________

0005 All work complete for New POL Building and associated appurtenances including Basic Items and Options Items listed below.

1 JOB XXX $_________

0006 All work complete for remaining work, excluding Basic Items 0001, 0002, 0003, 0004 and 0005 and Option Items 0007, 0011 and 0012 listed below.

1 JOB XXX $_________

TOTAL BASIC (ITEM 0001-0006) $_________

Estimated Quantity

Unit Unit Price

Estimated Amount

OPTION ITEMS

0007 Decorative Aggregate Surfacing Around

Facility

1 JOB XXX $_________

0008 Emergency Lighting and Power - Generator 1 JOB XXX $_________ 0009 Canopies for Fill Stand Stations 1 JOB XXX $_________ 0010 Canopies for Offload Stations 1 JOB XXX $_________ 0011 Disposal of Petroleum Contaminated Soils.

Includes Stockpiling, Sampling, Transportation and Disposal to an Off-Site Facility

150 C.Y. $_____ $_________

0012 Disposal of Petroleum Contaminated Water.

Includes Storage, Sampling, Transportation and Disposal to an Off-Site Facility

50 GAL $_____ $_________

l4ctemlk Cross-Out

49.0% 11% 6.9%

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract

Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from

Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract

Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Cannon Air

Force Base, Curry County, New Mexico.

(End of provision)

52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.

The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-

(c) The amount of the bid guarantee shall be twenty (20) percent of the bid price or $3,000,000.00, whichever is less.-

Amendment 0001 l4ctemlk Cross-Out

SECTION 00700 - CONTRACT CLAUSES

The following have been added by full text:

52.222-60 PAYCHECK TRANSPARENCY (EXECUTIVE ORDER 13673) (OCT 2016)

(a) Wage statement. In each pay period, the Contractor shall provide a wage statement document (e.g. a pay stub) to all individuals performing work under the contract subject to the wage records requirements of any of the following statutes:

(1) The Fair Labor Standards Act.

(2) 40 U.S.C. chapter 31, subchapter IV, Wage Rate Requirements (Construction) (formerly known as the Davis

Bacon Act).

(3) 41 U.S.C. chapter 67, Service Contract Labor Standards (formerly known as the Service Contract Act of 1965).

(b) Content of wage statement. (1) The wage statement shall be issued every pay period and contain--

(i) The total number of hours worked in the pay period;

(ii) The number of those hours that were overtime hours;

(iii) The rate of pay (e.g., hourly rate, piece rate);

(iv) The gross pay; and

(v) Any additions made to or deductions taken from gross pay. These shall be itemized. The itemization shall identify and list each one separately, as well as the specific amount added or deducted for each.

(2) If the wage statement is not provided weekly and is instead provided bi-weekly or semi-monthly (because the pay period is bi-weekly or semi-monthly), the hours worked and overtime hours contained in the wage statement shall be broken down to correspond to the period (which will almost always be weekly) for which overtime is calculated and paid.

(3) The wage statement provided to an individual exempt from the overtime compensation requirements of the Fair

Labor Standards Act (FLSA) need nota record of hours worked, if the Contractor informs the individual in writing of his or her overtime exempt status. The notice may not indicate or suggest that DOL or the courts agree with the

Contractor's determination that the individual is exempt. The notice must be given either before the individual begins work on the contract, or in the first wage statement under the contract. Notice given before the work begins can be a stand-alone document, or can be in an offer letter, employment contract, or position description. If during performance of the contract, the Contractor determines that the individual's status has changed from non-exempt to exempt from overtime, it must provide the notice to the individual before providing a wage statement without hours worked information or in the first wage statement after the change.

(c) Substantially similar laws. A Contractor satisfies this wage statement requirement by complying with the wage statement requirement of any State or locality (in which the Contractor has employees) that has been determined by the United States Secretary of Labor to be substantially similar to the wage statement requirement in this clause.

The determination of substantially similar wage payment states may be found at www.dol.gov/fairpayandsafeworkplaces.

(d) Independent contractor.

http://www.dol.gov/fairpayandsafeworkplaces

(1) If the Contractor is treating an individual performing work under the contract as an independent contractor (e.g., an individual who is in business for him or herself or is self-employed) and not as an employee, the Contractor shall provide a written document to the individual informing the individual of this status. The document may not ndicate or suggest that the enforcement agencies or the courts agree with the Contractor's determination that the worker is an independent contractor. The Contractor shall provide the document to the individual either at the time an independent contractor relationship is established with the individual or prior to the time the individual begins to perform work on the contract. The document must be provided for this contract, even if the worker was notified of independent contractor status on other contracts. The document must be separate from any independent ontractor agreement between the Contractor and the individual. If the Contractor determines that a worker's status while performing work on the contract changes from employee to independent contractor, then the Contractor shall provide the worker with notice of independent contractor status before the worker performs any work under the contract as an independent contractor.

(2) The fact that the Contractor does not make social security, Medicare, or income tax withholding deductions from the individual's pay and that an individual receives at year end an IRS Form 1099-Misc is not evidence that the

Contractor has correctly classified the individual as an independent contractor under the labor laws.

(e) Notices--(1) Language. Where a significant portion of the workforce is not fluent in English, the Contractor shall provide the wage statement required in paragraph (a) of this clause, the overtime exempt status notice described in paragraph (b)(3) of this clause, and the independent contractor notification required in paragraph (d) of this clause in English and the language(s) with which the significant portion(s) of the workforce is fluent.

(2) Electronic notice. If the Contractor regularly provides documents to its workers by electronic means, the

Contractor may provide to workers electronically the written documents and notices required by this clause.

Workers must be able to access the document through a computer, device, system or network provided or made available by the Contractor.

(f) Subcontracts. The Contractor shall insert the substance of this clause, including this paragraph (f), in all subcontracts that exceed $500,000, at all tiers, for other than commercially available off-the-shelf items.

(End of clause)

File details come from the government source that posted it. Updated .