AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Solicitation hereby amended to include changes and/or clarifications in response to bidder inquiries.

1. Change subCLIN 0002AE and 0002AP titles to match technical requirements.

2. The hour and date specified for receipt of offers has NOT changed as a result of this amendment.

3. See the Technical Summary of Changes

4. All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 08-Jan-2015

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912PM-15-R-0001

X 9B. DATED (SEE ITEM 11)

04-Dec-2014

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

09-Jan-2015

CODE

U S ARMY CORPS OF ENGINEERS

WILMINGTON DISTRICT

ATTN: BRUCE HELMS

69 DARLINGTON AVE

WILMINGTON NC 28403-1343

W912PM 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912PM-15-R-0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 1449 - CONTINUATION SHEET

SUPPLIES OR SERVICES AND PRICES

SUBCLIN 0002AE

The CLIN extended description has changed from Main Units Surge Protection Cabinets to Main Units High Resistance Grounding Cabinets.

SUBCLIN 0002AP

The CLIN description has changed from Install of line relay enclosure to Install of Line Relay concrete pad.

The CLIN extended description has changed from to and conduit.

Amendment 0004

Technical Summary of Changes

PROJECT TABLE OF CONTENTS

Delete existing SECTION Page 2 in its entirety and replace with revised enclosed Page.

00 01 15 – LIST OF DRAWINGS

Delete existing SECTION Pages 1 thru 6 in their entirety and replace with revised enclosed like-numbered Pages.

01 10 00.10 38 – SUPPLEMENTARY SPECIAL CONTRACT REQUIREMENTS

Delete existing SECTION Pages 1 thru 14 in their entirety and replace with revised enclosed like-numbered Pages.

01 10 10 – CONTRACTOR’S OPERATIONS AND REQUIREMENTS

Delete existing SECTION Pages 1 thru 15 in their entirety and replace with revised enclosed like-numbered Pages.

01 11 00 – SUMMARY OF WORK

Delete existing SECTION Pages 1 thru 7 in their entirety and replace with revised enclosed like-numbered Pages.

01 22 00 – MEASUREMENT AND PAYMENT

Delete existing SECTION Pages 1 thru 8 in their entirety and replace with revised enclosed Pages 1 thru 9.

01 45 00.00 10 – QUALITY CONTROL

Delete existing SECTION Pages 1 thru 10 in their entirety and replace with revised enclosed like-numbered Pages.

09 90 00 – PAINTING: HYDRAULIC STRUCTURES

Delete existing SECTION Pages 1 thru 7 in their entirety and replace with revised enclosed Pages 1 thru 8.

13 48 00.01 26 – SEISMIC RESTRAINT FOR MECHANICAL AND ELECTRICAL

EQUIPMENT

Delete existing SECTION Pages 1 thru 9 in their entirety and replace with revised enclosed like-numbered Pages.

K7EPEOAF

Typewritten Text

K7EPEOAF

Typewritten Text

K7EPEOAF

Typewritten Text

13 48 00 – SEISMIC RESTRAINT FOR MECHANICAL AND ELECTRICAL

EQUIPMENT

Delete existing SECTION Pages 1 thru 9 in their entirety.

26 05 00 – BASIC ELECTRICAL MATERIALS AND METHODS

Delete existing SECTION Pages 1 thru 25 in their entirety and replace with revised enclosed like-numbered Pages.

26 08 01 – SYSTEMS TESTING AND COMMISSIONING

Delete existing SECTION Pages 1 thru 6 in their entirety and replace with revised enclosed like-numbered Pages.

26 13 13 – METAL-CLAD SWITCHGEAR

Delete existing SECTION Pages 1 thru 34 in their entirety and replace with revised enclosed like-numbered Pages.

26 23 10 – 480 VOLT STATION SERVICE SWITCHGEAR

Delete existing SECTION Pages 1 thru 23 in their entirety and replace with revised enclosed like-numbered Pages.

26 23 15 – HIGH RESISTANCE GROUNDING SYSTEM (HRG) LOW-VOLTAGE

Delete existing SECTION Pages 1 thru 7 in their entirety.

32 12 10 – BITUMINOUS TACK AND PRIME COATS

Delete existing SECTION Pages 1 thru 8 in their entirety and replace with revised enclosed like-numbered Pages.

32 12 17 – HOT MIX BITUMINOUS PAVEMENT

Delete existing SECTION Pages 1 thru 20 in their entirety and replace with revised enclosed like-numbered Pages.

48 19 26 – AUTOMATIC VOLTAGE REGULATORS

Delete existing SECTION Pages 1 thru 36 in their entirety and replace with revised enclosed like-numbered Pages.

NOTE:

Text that is added or revised by this amendment is identified with and/or printed in bold AND identified with ***Amendment 0004***(beginning and ending of revision OR addition). Track changes shown as

Strike through (Delete in their entirety).

The text changes may have necessitated reformatting of subsequent text or pages. If this is the case, those pages have also been issued as amended pages but are not underlined or bold text.

DRAWINGS

ADD enclosed Sheet No. C-105 in its entirety.

REFERENCE DRAWINGS

ADD in their entirety: 46308 Gate Ring & Conn. Rod, 46382 Shafts, 46384 Gate Shaft Bearing and Gov. Pump Sump.

-- End of Summary of Changes --

Encls As Stated

Switchgear Relocation, Governor Upgrade & W912PM-15-R-0001 AVR Upgrade, Philpott Reservoir Project

DIVISION 13 - SPECIAL CONSTRUCTION

13 34 19 METAL BUILDING SYSTEMS

13 48 00.01 26 SEISMIC RESTRAINT FOR MECHANICAL AND ELECTRICAL EQUIPMENT

13 48 00 SEISMIC RESTRAINT FOR MECHANICAL AND ELECTRICAL EQUIPMENT

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

DIVISION 26 - ELECTRICAL

26 00 00 EQUIPMENT INSTALLATION AND WIRING

26 05 00 BASIC ELECTRICAL MATERIALS AND METHODS

26 05 19 INSULATED WIRE AND CABLE

26 05 26 GROUNDING

26 05 33 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

26 05 36 CABLE TRAY FOR ELECTRICAL SYSTEMS

26 05 73 OVERCURRENT PROTECTIVE DEVICES AND CONTROLS

26 08 01 SYSTEMS TESTING AND COMMISSIONING

26 11 15 HIGH RESISTANCE GROUNDING SYSTEM (HRG)-MEDIUM VOLTAGE

26 12 16 STATION SERVICE TRANSFORMER, DRY-TYPE

26 13 13 METAL-CLAD SWITCHGEAR

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 23 10 480 VOLT STATION SERVICE SWITCHGEAR

26 23 15 HIGH RESISTANCE GROUNDING SYSTEM (HRG)-LOW VOLTAGE

26 24 19 MOTOR CONTROL CENTERS

26 51 00 INTERIOR LIGHTING

26 56 00 EXTERIOR LIGHTING

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

31 05 19 GEOTEXTILE

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 12 10 BITUMINOUS TACK AND PRIME COATS

32 12 17 HOT MIX BITUMINOUS PAVEMENT

32 31 13 CHAIN LINK FENCES AND GATES

32 92 19 SEEDING

DIVISION 33 - UTILITIES

33 11 00 WATER DISTRIBUTION

33 40 00 STORM DRAINAGE UTILITIES

33 46 13 FOUNDATION DRAINAGE SYSTEM

33 72 33 POWER SYSTEM RELAY PROTECTION

DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT

41 24 26.00 26 MECHANICAL REQUIREMENTS FOR DIGITAL GOVERNOR UPGRADE

DIVISION 48 - ELECTRICAL POWER GENERATION

48 19 00 DIGITAL GOVERNOR UPGRADE

48 19 26 AUTOMATIC VOLTAGE REGULATORS

PROJECT TABLE OF CONTENTS Page 2 (Revised by Amendment 0004)

K7EPEOAF

Cross-Out

Cross-Out

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

DOCUMENT 00 01 15

LIST OF DRAWINGS

PART 1 GENERAL

1.1 SUMMARY

1.2 CONTRACT DRAWINGS

1.3 SUPPLEMENTARY DRAWINGS

1.3.1 Reference Drawings

1.4 BORING LOGS

-- End of Section Table of Contents --

DOCUMENT 00 01 15 Page 1 (Revised by Amendment No. 0004)

DOCUMENT 00 01 15

LIST OF DRAWINGS

PART 1 GENERAL

1.1 SUMMARY

This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings and Specifications."

1.2 CONTRACT DRAWINGS

Contract drawings are as follows:

SHEET PLATE

NO. NO. TITLE

GENERAL

G-001 INDEX OF DRAWINGS SHEET 1 OF 2

G-002 INDEX OF DRAWINGS SHEET 2 OF 2 PROJECT LOCATION AND

VICINITY MAP

G-101 WORK AREA - POWERHOUSE

V-001 EXISTING SITE CONDITIONS SURVEY

***AMENDMENT 0004***

CIVIL

C-101 DEMOLITION PLAN

C-102 EROSION & SEDIMENT CONTROL PLAN

C-103 BUILDING SITE PLAN

C-104 SITE UTILITY PLAN

C-105 SITE PAVING PLAN

C-501 SEDIMENT AND EROSION CONTROL DETAILS

C-502 STORMWATER DRAINAGE DETAILS

C-503 FENCE GATE DETAILS

C-504 FENCE DETAILS

C-505 ELECTRICAL DUCT BANK AND CONDUIT DETAILS

***AMENDMENT 0004***

STRUCTURAL

S-201 RETAINING WALL PLAN AND PROFILE

S-301 RETAINING WALL CROSS SECTION AND DETAILS

S-501 BUILDING FOUNDATION DETAILS

ARCHITECTURAL - NEW BUILDING

A-101 BUILDING PLAN AND ELEVATIONS

A-102 LIGHTING & POWER PLAN

A-103 SCHEDULES, RISERS & DETAILS

A-104 MECHANICAL PLAN

ELECTRICAL - POWERHOUSE

E-001 ELECTRICAL LEGEND SHEET

ED101 EQUIPMENT REMOVAL EL. 823.0 PLAN VIEW

ED102 EQUIPMENT REMOVAL ElEVATION VIEW ED401 CONTROL BOARD AND 13.8kV SWITCHGEAR REMOVAL

ED402 480V SWITCHGEAR REMOVAL

DOCUMENT 00 01 15 Page 2

ED601 ONE LINE DIAGRAM REMOVAL

ED602 480V SWITCHGEAR ONE LINE DIAGRAM REMOVAL

ED603 125 VDC SYSTEM REMOVAL DETAILS

ED604 SECONDARY GENERATOR SCHEMATICS REMOVAL SHEET 1 OF 2

ED605 SECONDARY GENERATOR SCHEMATICS REMOVAL SHEET 2 OF 2

ED606 MAIN GENERATOR SCHEMATICS REMOVAL SHEET 1 OF 3

ED607 MAIN GENERATOR SCHEMATICS REMOVAL SHEET 2 OF 3

ED608 MAIN GENERATOR SCHEMATICS REMOVAL SHEET 3 OF 3

ED609 BREAKERS AND LOAD CONTROLLERS SCHEMATICS REMOVAL

ED701 CONDUIT AND CABLE SCHEDULE INSTALL SHEET 1 OF 2

ED702 CONDUIT AND CABLE SCHEDULE INSTALL SHEET 2 OF 2

E-101 EQUIPMENT INSTALL EL. 823.0 PLAN VIEW

E-102 EQUIPMENT INSTALL EL. 823.0 PLAN VIEW

E-103 POWERHOUSE EQUIPMENT INSTALL ELEVATION VIEW

E-401 TRAY ROUTING, TRAY ROUTING PLAN VIEW

E-402 TRAY ROUTING, TRAY ROUTING ELEVATION VIEW

E-403 AVR REPLACEMENT CONDUIT LAYOUT

E-404 SWITCHGEAR BUILDING CONDUITS AND TRENCH DETAILS

E-601 ONE LINE DIAGRAM INSTALL

E-602 480V SWITCHGEAR ONE LINE DIAGRAM INSTALL

E-603 125 VDC SYSTEM MODIFICATIONS DETAILS INSTALL

E-604 SECONDARY GENERATOR OPERATING SCHEMATICS INSTALL

SHEET 1 OF 2

E-605 SECONDARY GENERATOR SCHEMATICS INSTALL SHEET 2 OF 2

E-606 MAIN GENERATOR SCHEMATICS INSTALL SHEET 1 OF 3

E-607 MAIN GENERATOR SCHEMATICS INSTALL SHEET 2 OF 3

E-608 MAIN GENERATOR SCHEMATICS INSTALL SHEET 3 OF 3

E-609 BREAKERS AND LOAD CONTROLLERS SCHEMATICS INSTALL

E-610 480V CQ1, CQ2, CQ3, PANEL SCHEDULES INSTALL

E-611 480V CQ4, CQ5, PANEL SCHEDULES INSTALL

E-612 15KV SWITCHGEAR ONE LINE LAYOUT, NAMEPLATE AND

LOCAL/REMOTE PANEL INSTALL

E-613 BREAKER 52-M, 52-E AND SQ1 TRANSFER CONTROLS

INSTALL

E-614 BUS DIFFERENTIAL PROTECTION INSTALL

E-615 480V SUBSTATION LAYOUT & NAME PLATE INSTALLATION

E-616 CONTROL BOARD AND 52S(F) BREAKER CONTROL INSTALL

E-617 AVR REPLACEMENT EXCITATION SYSTEM EXTERNAL

CONNECTIONS

E-701 CONDUIT AND CABLE SCHEDULE INSTALL SHEET 1 OF 3

E-701 CONDUIT AND CABLE SCHEDULE INSTALL SHEET 2 OF 3

E-701 CONDUIT AND CABLE SCHEDULE INSTALL SHEET 3 OF 3

MECHANICAL - POWERHOUSE

M-101 GOVERNOR AND PUMP ARRANGEMENT

M-102 GATE RING AND CONNECTING ROD SELF LUBRICATED

BUSHING MODIFICATIONS

M-103 SELF LUBRICATED BUSHING MODIFICATIONS

M-201 GOVERNOR & PUMP SECTIONS AND DETAILS

M-901 GATE SHAFT GOVERNOR MECHANICAL UPGRADE PHOTOS

1.3 SUPPLEMENTARY DRAWINGS

These supplementary drawings may not be a part of the contract but are included with the drawings for information.

DOCUMENT 00 01 15 Page 3

1.3.1 Reference Drawings

The following reference drawings are intended only to show the original construction. Drawings are the property of the Government and shall not be used for any purpose other than that intended by the contract. The drawings are 25x15 sizes. Full-size drawings are not available.

SHEET

IDENTIFICATION

NUMBER TITLE

2FDX030U SH.A BATTERY & TRANSCLOSURE FOUNDATION DETAILS

14656 PHILPOTT SHT. 1 SIMS FOCUS 200 TRUNK

14656 PHILPOTT SHT.2 SIMS FOCUS 200 TRUNK

14656 PHILPOTT SHT.3 SIMS FOCUS 200 TRUNK

14656 PHILPOTT SHT.4 SIMS FOCUS 200 TRUNK

14656 PHILPOTT SHT.5 SIMS FOCUS 200 TRUNK

161103-D-S ASSEMBLY DRAWING OF FLOAT VALVE

161116C PRESSURE TANK OIL LEVEL GAUGE ASSEMBLY

176311 AUTOMATIC CONTROL PANEL. WIRING DIAGRAM - REAR PANEL

176312 AUTOMATIC CONTROL PANEL. WIRING DIAGRAM - FRONT PANEL

194416 PUMP BASE FOR MAIN UNIT NO. 2

195192B P RESURE TANK FOR MAIN UNIT NO. 1

30270-100 KERR PHILPOTT UPGRADE SYSTEM BLOCK DIAGRAM

30270-220 RTU 17 CABINET ASSEMBLY PHILPOTT

30270-221 RTU 17 PANEL PHILPOTT

30270-222 1/0 TERMINATION PANELS - PHILPOTT RTU 1 7

30270-223 GROUND BUS ASSEMBLY PHILPOTT

30270-224 PHILPOTT RTU 17 POWER DISTRIBUTION

30270-225 TERMINATION BLOCK WIRING PHILPOTT

30270-230 RTU 19 CABINET ASSEMBLY PHILPOTT - GEN

30270-231 RTU 19 PANEL LAYOUT PHILPOTT - GEN

30270-232 RTU 19 RELAY PANEL LAYOUT PHILPOTT - GEN

30270-233 GROUND BUS ASSEMBLY PHILPOTT - GEN

30270-234 RTU 19 POWER DISTRIBUTION PHILPOTT - GEN

30270-235 RTU 1/0 POWER DISTRIBUTION

30270-236 AI TERMINATION BLOCK WIRING PHILPOTT - GEN

30270-237 DO TERMINATION BLOCK WIRING PHILPOTT - GEN

30270-238 DIGITAL METER CONNECTIONS (TYPICAL)

30270-242 TYPICAL RELAY WIRING PHILPOTT - GEN RTU

30270-243 TYPICAL WIRING AI POINTS PHILPOTT - GEN RTU

41-A-5086 SCHEMATIC DIAGRAM & ONE LINE DIAGRAM OF STATION BOARD

41-A-5087 DUPLEX STATION SWITCHBOARD PANEL NO. 1F - WIRING DIAGRAM

41-A-5088 DUPLEX STATION SWITCHBOARD PANEL NO. 2F - WIRING DIAGRAM

41-A-5089 DUPLEX STATION SWITCHBOARD. PANEL NO. 3F, CONNECTION DIAGRAM

41-A-5090 DUPLEX STATION SWITCHBOARD PANEL NO. 4F - WIRING DIAGRAM

41-A-5092 DUPLEX STATION SWITCHBOARD PANEL NO. 1R - WIRING DIAGRAM

41-A-5093 DUPLEX STATION SWITCHBOARD PANEL NO. 2R - WIRING DIAGRAM

41-A-5094 DUPLEX STATION SWITCHBOARD PANEL NO. 3R - WIRING DIAGRAM

41-A-5095 DUPLEX STATION SWITCHBOARD PANEL NO. 4R - WIRING DIAGRAM

41-A-5096 DUPLEX STATION SWITCHBOARD PANEL NO. 5R - WIRING DIAGRAM

41-A-6012 UNIT 1 STATION TRANSFORMER

41-A-6013A PANEL 2. SECONDARY GENERATOR

41-A-6013B UNIT 3, FUTURE LINES

41-A-6014 UNITS 2N & 2R, GEN. 2 NEUTRAL ACB INDOOR METAL CLAD SWGR

41-A-6014 PANEL 4, MAIN TRANSFORMER

41-A-6014B UNIT 5, GENERATOR 2, AUX.

41-A-6015 PANEL 6, GENERATOR 2

41-A-6016 UNIT 7, GENERATOR 1 ' AUX. INDOOR METAL CLAD SWGR

DOCUMENT 00 01 15 Page 4

41-A-6016A UNIT 7, GENERATOR 1

41-A-6016B UNIT 8, GENERATOR 1

41-A-6017 UNITS 2N & 2R, GEN. 2 NEUTRAL ACB INDOOR METAL CLAD SWGR

41-A-6017A UNIT 2N & 2R, GEN. 2 NEUTRAL ACB

41-A-6017B UNIT 1N & 1R, GEN. 1 NEUTRAL ACB

46300 ASSEMBLY SECTION 56 3/4

46308 GATE RING & CONN. ROD

46308? GATE RING & CONN. ROD ASSEMBLY

528E706 ASSEMBLY, HYDRAULIC TURBINE-DRIVEN GENERATOR

970673 SHTS. 1-3 WIRING DIAGRAM

970673D SH. 2 WIRING DIAGRAM, MAIN UNITS NO. 1 & NO. 2

970673D SH. 3 WIRING DIAGRAM, MAIN UNITS NO. 1 & NO. 2

970673F SH. 1 WIRING DIAGRAM, MAIN UNITS NO. 1 & NO. 2

982296 SH. 4 GOVERNOR & PUMP ARRANGEMENT, SECONDARY UNIT

982296D SH. 5 GOVERNOR & PUMP ARRANGEMENT, MAIN UNITS

D-400AE ANNUNCIATOR RELAY CONTROL PANEL WIRING

D-408 INTERCONNECTION WIRING, ANNUNCIATORS & RELAY CABINETS

E-06-1.02- EQUIPMENT INSTALL EL. 823.0 PLAN VIEW

102-PHP-C

GG204B PROJECT LOCATION

GG226B WORK AREAS

K-8688602 VOLTAGE REGULATOR

KK-6576634 ELEMANTARY DIAGRAM

M-8654697 VOLTAGE REGULATOR <OUTLINE)

P-9159365 INTER-CONNECTION DIAGRAM

PA401B POWERHOUSE PLAN - EL. 814.0

PA402B POWERHOUSE PLAN - EL. 823.0

PA402B PLAN - EL. 823.0

PA402B-2 POWERHOUSE PLAN - EL 823.0

PA403B POWERHOUSE PLAN - EL. 836.0 AND 837.25

PA407B POWERHOUSE UPSTREAM SECTIONAL ELEVATION

PA409B TRANSVERSE SECTION THROUGH MAIN UNIT

PA410B TRANSVERSE SECTION THROUGH SECONDARY UNIT

PA411B LONGITUDINAL SECTION THRU GENERATOR ROOM

PA809B-0 15 kV CABLE AND RACEWAYS

PE501B WIRING -MAIN SINGLE LINE DIAGRAM

PE502B WIRING - STATION SERVICE 460 VAC. SINGLE LINE DIAGRAM

PE503B WIRING- DC SCHEMATIC & DC SINGLE LINE DIAGRAM

PE505B WIRING-MAIN UNIT CONTROL SCHEMATIC DIAGRAM

PE505C MAIN GENERATOR OPERATING SCHEMATICS

PE505D SECONDARY GENERATOR LOAD CONTROLLER

PE506C SECONDARY GENERATOR OPERATING SCHEMATICS

PE506D STATION A.C.B.'S AND AUXILIARY SCHEMATICS

PE506E MAIN GENERATOR LOAD CONTROLLER

PE507B WIRING -STATION SERVICE AUXILIARIES SCHEMATIC DIAGRAMS - SHT 1

PE508B WIRING -STATION SERVICE AUXILIARIES SCHEMATIC DIAGRAMS - SHT 2

PE510B WIRING - ANNUNCIATOR SYSTEM TROUBLE POINT DIAGRAM

PE511B WIRING - DEVICE SCHEDULE

PE520B WIRING - THREE LINE DIAGRAM MAIN UNITS

PE520B-7 WIRING -THREE LINE DIAGRAM. MAIN UNITS

PE521B WIRING -THREE LINE DIAGRAM SECONDARY UNIT

PE525B AUTOMATIC OPERATION SCHEMATICS

PE600B SWITCHBOARDS 13.8 kV SWITCHGEAR

PE601B SWITCHBOARDS NAME PLATE ENGRAVING

PE602B SWITCHBOARDS STATION BOARD

PE701B SWITCHBOARDS 460 VAC SWITCHGEAR

PE801B CONDUIT AND GROUNDING. PLAN - EL. 823.0

PE804B CONDUIT AND GROUNDING. SECTIONS AND DETAILS

PE805B CONDUIT AND GROUNDING. MAIN TRANSFORMER AREA AND

DOCUMENT 00 01 15 Page 5

MISCELLANEOUS DETAILS

PE807B CONDUIT AND GROUNDING MAIN GROUNDING PLAN

PE808B CONDUIT AND GROUNDING. GROUNDING DETAILS

PE809B 15KV CABLE AND RACEWAYS

PHILPOTT SH. 1 ANNUNCIATOR, PANEL #1

PHILPOTT SH. 2 ANNUNCIATOR, PANEL #4

PHILPOTT SH. 3 ANNUNCIATOR

PHILPOTT SH. 4 ANNUNCIATOR. PANEL #3

PHILPOTT SH. 5 ANNUNCIATOR, PANEL #2

PH-LS-D19794 SH. 1 SEC. GEN. GOVERNOR CONTROLLER ELEMENTARY DIAGRAM

PH-LS-D19794 SH. 2 SEC. GEN. GOVERNOR CONTROLLER ELEMENTARY DIAGRAM

PH-LS-D19794 SH. 3 SEC. GEN. GOVERNOR CONTROLLER ELEMENTARY DIAGRAM

PH-LS-D19794 SH. 4 SEC. GEN. GOVERNOR CONTROLLER ELEMENTARY DIAGRAM

PH-LS-D19794 SH. 5 SEC. GEN. GOVERNOR CONTROLLER ELEMENTARY DIAGRAM

PH-LS-D19794 SH. 6 SEC. GEN. GOVERNOR CONTROLLER ELEMENTARY DIAGRAM

PH-LS-D19796 SH. 1 SEC. GEN. GOVERNOR CONTROLLER INTERNAL WIRING DIAGRAM

PH-LS-D19796 SH. 2 SEC. GEN. GOVERNOR CONTROLLER INTERNAL WIRING DIAGRAM

PH-LS-D19796 SH. 3 SEC. GEN. GOVERNOR CONTROLLER INTERNAL WIRING DIAGRAM

PH-LS-D19796 SH. 4 SEC. GEN. GOVERNOR CONTROLLER INTERNAL WIRING DIAGRAM

PH-LS-D19796 SH. 5 SEC. GEN. GOVERNOR CONTROLLER INTERNAL WIRING DIAGRAM

PH-LS-D19796 SH. 6 SEC. GEN. GOVERNOR CONTROLLER INTERNAL WIRING DIAGRAM

PH-LS-D19796 SH. 7 SEC. GEN. GOVERNOR CONTROLLER INTERNAL WIRING DIAGRAM

PH-LS-D19796 SH. 8 SEC. GEN. GOVERNOR CONTROLLER INTERNAL WIRING DIAGRAM

PH-LS-D19797 SH. 1 SEC. GEN. GOVERNOR CONTROLLER EXTERNAL

CONNECTION DIAGRAM

PH-LS-D19797 SH. 2 SEC. GEN. GOVERNOR CONTROLLER EXTERNAL CONNECTION

DIAGRAM

PH-LS-D19797 SH. 3 SEC. GEN. GOVERNOR CONTROLLER EXTERNAL CONNECTION

DIAGRAM

PH-LS-D19798 SH. 1 SEC. GEN. GOVERNOR CONTROLLER GCC ASSEMBLY

PH-LS-D19798 SH. 2 SEC. GEN. GOVERNOR CONTROLLER GCC ASSEMBLY

PH-LS-D19800 SEC. GEN. GOVERNOR CONTROLLER HYDRAULIC SCHEMATIC DIAGRAM

PP401B COMPRESSED AIR SYSTEM - SHEET 1

PPCAD101 MAIN GENERATOR OPERATING SCHEMATICS

(PE505C)

PPCAD102 SECONDARY GENERATOR OPERATING SCHEMATICS

PPCAD103 STATION A.C.B.'S AND AUXILIARY SCHEMATICS

(PE505D)

PPCAD105 SECONDARY GENERATOR LOAD CONTROLLER

PS811B 13.8 kV SWITCHBOARD AND 460 V SWITCHGEAR - CHANNEL

BASE DETAILS

T-6354654 EXCITATION CUBICLE. CONNECTION DIAGRAM

T-9795124 MAIN & NEUTRAL LEAD ARRANGEMENT

T-9910517 EXCITATION CUBICLES

***AMENDMENT 0004***

Reference Drawings for Bidder Inquiry 5907909:

46308 Gate Ring & Conn. Rod 46382 Shafts 46384 Gate Shaft Bearing Gov. Pump Sump

***AMENDMENT 0004***

1.4 BORING LOGS

The Government does not guarantee that borings indicate actual conditions, except for the exact locations and the time that they were made (Appendix A).

DOCUMENT 00 01 15 Page 6

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 10 00.10 38

SUPPLEMENTARY SPECIAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

1.2 SECURITY REQUIREMENTS

1.2.1 Access and General Protection/Security Policy and Procedures

1.2.2 Suspicious Activity Reporting Training

1.2.3 Pre-screen candidates using E-verify Program

1.3 SUBMITTALS

1.4 WATER CONSERVATION

1.5 BULLETIN BOARD

1.6 RETAINAGE FOR UNTIMELY SUBMISSION OF SUBCONTRACTING REPORTS

1.7 SHOP DRAWINGS AND MATERIALS SUBMITTAL

1.8 SAMPLING, CERTIFICATES, AND TESTING

1.9 CERTIFICATES OF COMPLIANCE

1.10 REQUIRED MEETINGS

1.11 "AS-BUILT" RECORD DRAWINGS

1.12 FINISH MATERIAL SUBMITTALS

1.13 ASBESTOS PERMIT AND NOTIFICATION

1.14 ASBESTOS - (Occupational Health and Environment)

1.15 WORK IN QUARANTINED AREA

1.16 PUBLIC CONVENIENCE AND SAFETY

1.16.1 Roads To Be Closed

1.16.2 Storage of Materials

1.17 MAINTENANCE DURING CONSTRUCTION

1.17.1 Maintenance When Work is Suspended

1.17.2 Final Mowing

1.17.3 Spilled Materials

1.18 PARTNERING

1.19 LOAD RESTRICTIONS

1.20 PROTECTION OF EXISTING FACILITIES

1.21 COORDINATION WITH OTHER CONTRACTORS

1.22 CONTRACT DRAWINGS AND SPECIFICATIONS

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 10 00.10 38 Page 1

SECTION 01 10 00.10 38

SUPPLEMENTARY SPECIAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1110-1-5 Plant Pest Quarantined Area and Foreign Soil Samples

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910.20 Access to Employee Exposure and Medical Records

29 CFR 1910.134 Respiratory Protection

29 CFR 1910.1001 Asbestos

29 CFR 1926.55 Gases, Vapors, Fumes, Dusts, and Mists

40 CFR 61.40 General Provisions

40 CFR 61.140 National Emission Standards for Hazardous Air Pollutants

40 CFR 61.156 National Emission Standard for Asbestos

49 CFR 172 Hazardous Materials Table, Special Provisions, Hazardous Materials Communications, Emergency Response Information, and Training Requirements

49 CFR 173 Shippers - General Requirements for Shipments and Packagings

1.2 SECURITY REQUIREMENTS

The Contractor shall be required to comply with the following security requirements:

1.2.1 Access and General Protection/Security Policy and Procedures

All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks or background investigation and to meet installation/facility access requirements to be accomplished by

SECTION 01 10 00.10 38 Page 2 installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.

1.2.2 Suspicious Activity Reporting Training

The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.

Will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas

All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance or access privileges, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.

1.2.3 Pre-screen candidates using E-verify Program

The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.

(End of Clause)

1.3 SUBMITTALS

Government approval is required for submittals with a "G, A" designation;

submittals not having a "G, A" designation are for information only. When used, a designation following the "G, A" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

List of Subcontractors

Progress Chart; G, A

Quality Control Plan; G, A

Within 24 hours of conclusion of physical tests, 5 copies of test results including calibration curves and results of calibration tests.

SECTION 01 10 00.10 38 Page 3

SD-07 Certificates

Certificate of Insurance

Completion of Corps CQC Course

Qualifications of the commercial testing laboratory or Contractor's testing laboratory/facilities G, A

1.4 WATER CONSERVATION

Water is one of our valuable natural resources. Accordingly, the Contractor shall be judicious in its use in the performance of the work as specified. Water needed for compaction of roadway and/or foundation materials, and dust control shall be obtained from uncontrolled stream flow instead of potable supply sources to the extent available and suitable as determined by the Contracting Officer or his/her designated representative.

(End of Clause)

1.5 BULLETIN BOARD

Within one (1) calendar day after commencement of work under this contract, the Contractor shall provide at the job site a weatherproof, glass-covered bulletin board for displaying the Fair Employment poster, wage rates, posters and safety bulletins as noted in Section 01 35 26, paragraph DISPLAY OF SAFETY INFORMATION. The bulletin board shall be located in a conspicuous place, easily accessible to all employees, and legible copies of the aforementioned data shall be displayed until work under the contract is complete. No direct payment will be made for the bulletin board.

(End of Clause)

1.6 RETAINAGE FOR UNTIMELY SUBMISSION OF SUBCONTRACTING REPORTS

(a) In accordance with Contract Clause 52.219-9, Small Business Subcontracting Plan, and 52.219-16, Liquidated Damages - Subcontracting Plan, retainage will be withheld from progress payments in an amount sufficient to protect the Government's ability to assess liquidated damages in accordance with Clause 52.219-16 for the contractor's failure to timely submit Standard Form 294, Subcontracting Report for Individual Contracts, and Standard Form 295, Summary Subcontract Report, reports.

(b) The retainage will be determined in accordance with the following formula:

Total dollar amount for subcontracting to small business multiplied by percentage of actual progress on the contract shall be withheld from the next progress payment due after the Contractor fails to submit a required report. If one or more reports have been submitted before such failure, formula for determining the amount of retainage will be adjusted by deducting any amounts reported as subcontracted to small business from the total dollar amount proposed to be subcontracted and the difference multiplied by the percentage of actual progress.

(c) Subcontracting plans are not required--

(1) For contracts or contract modifications that will be performed entirely outside of any State, territory, or possession of the

SECTION 01 10 00.10 38 Page 4

United States, the District of Columbia, and the Commonwealth of Puerto Rico; or

(2) For modifications to contracts that do not contain the clause 52.219-8, Utilization of Small Business Concerns (or equivalent prior DAR, FPR, or NASA clauses); e.g., contracts awarded before Pub. L.

95-507 and which are within the scope of the contract.

(End of Clause)

1.7 SHOP DRAWINGS AND MATERIALS SUBMITTAL

(a) Five (5) days prior to the preconstruction conference (see paragraph REQUIRED CONSTRUCTION MEETINGS), the Contractor shall complete and submit to the Contracting Officer or his/her designated representative, in duplicate, Submittal Register, listing all submittals and dates. In addition to those items listed on the Submittal Register, the Contractor will furnish submittals for any deviation from the plans or specifications. The scheduled need dates must be recorded on the document for each item for control purposes. In preparing the document, adequate time (minimum of l5 days) will be allowed for review and approval and possible resubmittal. Scheduling shall be coordinated with the approved progress schedule. The Contractor's Quality Control System Manager shall review the listing at least every 30 days and take appropriate action to maintain an effective system. Copies of updated or corrected listings shall be submitted to the Contracting Officer or his/her designated representative at least every 60 days in the quantity specified. Payment will not be made for any material or equipment which does not comply with contract requirements.

(b) Contractor submittals required by the Technical Provisions are indicated in those provisions and are listed on the Submittal Register furnished in Section 01 33 00 SUBMITTAL PROCEDURES. The list does not relieve the Contractor from furnishing submittals required elsewhere in the specifications, those inadvertently omitted from the listing; or from furnishing other submittals that the Government may deem necessary as the work progresses.

(c) Normal review levels for required approvals are indicated by letter designations as follows:

Contractor Quality Control System Manager --- (CQC) Area or Resident Engineer ------------------- (R) Engineering Branch -------------------------- (E)

The Government reserves the right to vary the review levels for (R) and (E) to its convenience.

(d) The Contractor shall use ENG Form 4025, furnished in Section 01 33 00 SUBMITTAL PROCEDURES, to transmit Shop Drawings, Equipment Data, Material Samples or Manufacturer's Certificate of Compliance to the Government.

(End of Clause)

1.8 SAMPLING, CERTIFICATES, AND TESTING

(a) General. Within 30 days after acknowledgment of Notice to Proceed, the Contractor shall submit to the Contracting Officer or his/her

SECTION 01 10 00.10 38 Page 5 designated representative five (5) copies of a list of the items for which he proposes to furnish manufacturer's certificates and/or samples for inspection and testing. The list shall include, but is not limited to the following information:

(1) Name of item

(2) Specification paragraph covering this item

(3) Date sample will be furnished

(4) Delivery date of product

(5) Items for which a certificate will be furnished

(b) Submittals. Any product or item mentioned in these specifications and required to meet Federal, ASTM, AASHTO, U. S. Army or Navy, AREMA, AWWA, and UL Specifications or Codes, specified herein with certain limiting or qualifying requirements, or any product or item which is required to be similar and equal to a specified product or item may require the submission, before delivery of the product or item to the job site, of one or more of the following:

(1) Certificate by the manufacturer that the item meets the contract requirements.

(2) Samples for inspection, comparison, and testing, including destructive tests.

(c) Sample delivery. Unless otherwise specified or authorized, all samples shall be delivered (without cost to the Government) to:

U.S. Army Corps of Engineers Kerr Resident Office 5460 Buggs Island Road Boydton, Virginia 23917

If required by the Contracting Officer or his/her designated representative, duplicate samples shall be shipped to the Wilmington District Office at no expense to the Government.

(d) Testing. All tests required in the Technical Provisions shall be made by and at the expense of the Contractor except those material tests specifically excluded which will be made by and at the expense of the Government. All instruments and personnel required for the required tests shall be furnished by the Contractor. The Government reserves the right to interrupt the work to make tests on all facets of concreting and other operations. These tests will be made as necessary to insure conformance to applicable specifications and drawings and will be made by and at the expense of the Government except Contractor sampling support as required by the Technical Provisions. In those instances where testing is specified to be made at the Government's expense, the cost of the initial testing will be at the Government's expense; however, any retesting due to failure of the materials to meet the requirements in the initial test shall be performed at the Contractor's expense. The retests shall be made at laboratories approved by the Contracting Officer or his/her designated representative. The costs of retests made at Government laboratories will be deducted from the total amount due the Contractor, at actual cost to the Government, unless otherwise specified.

SECTION 01 10 00.10 38 Page 6

(End of Clause)

1.9 CERTIFICATES OF COMPLIANCE

(l969 MAY OCE)

Any certificates required for demonstrating proof of compliance of materials with specification requirements shall be executed in 3 copies.

Each certificate shall be signed by an official authorized to certify in behalf of the manufacturing company and shall contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates shall contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies. Certification shall not be construed as relieving the Contractor from furnishing satisfactory material, if, after tests are performed on selected samples, the material is found not to meet the specific requirements.

(End of Clause)

1.10 REQUIRED MEETINGS

(a) In addition to meetings required elsewhere in the specifications, the Contractor and any Subcontractors identified by the Contracting Officer's Representative shall be required to attend a preconstruction meeting (after award of the contract but before Commencement of Work) and a post construction meeting (after final acceptance of the work but before final payment is made). The Contractor and identified Subcontractors shall meet with Corps of Engineers personnel at a time and place determined by the Contracting Officer's Representative.

(b) At the preconstruction conference, the Contractor shall be oriented with respect to Government procedures and line of authority in contractual, administrative, and construction matters. Additionally, a schedule of required submittals will be discussed.

(c) Five (5) days prior to the preconstruction conference, the Contractor shall submit the following items:

Certificate of Insurance Quality Control Plan (see Section 01 45 00.00 10 QUALITY CONTROL, for additional information) Certificate of Completion of Corps CQC Course Preliminary Submittal Register (ENG Form 4288 exclusive of Contractor submittal dates) Letter Appointing Superintendent (see Contract Clause entitled Superintendence by the Contractor, 52.236-6) List of Subcontractors

(d) The letter of record will be written documenting all items discussed at the conference and a copy will be furnished by the Contracting Officer's Representative to all in attendance.

(End of Clause)

1.11 "AS-BUILT" RECORD DRAWINGS

(a) The Contractor shall be responsible for maintaining in good

SECTION 01 10 00.10 38 Page 7 condition one set of reproducible as-built drawings and five copy sets, including system layout drawings and field wiring diagrams. Drawings shall be "D" 34 by 22 inches, drawn to the same scale as the contract drawings, with title block similar to the contract drawings. Reproducible drawings shall be on mylar film. The Contractor shall keep a careful and neat record of all deviations, field changes and modifications from the original contract drawings which are made to each phase of construction as the work progresses. The Contractor is responsible for noting all changes and corrections on these prints promptly as in-place construction activities occur, but in no case less often than on a weekly basis. In addition to the above, the following shall be included:

(1) Actual location of all Contractor installed subsurface utility lines. Type of materials actually installed, major sizes of lines, etc. In order that the location of these lines and appurtenances may be determined in the event the surface openings or indicators become covered or obscured, the record drawings shall show, by offset dimensions to two permanently fixed surface features, both ends of each run and each change in direction. Valves, splice boxes and similar appurtenances shall be located by dimensions along the utility run from a reference point. The average depth below the surface of each run shall also be recorded.

(2) Any shop drawings which constitute part of the design shall be included with the record drawings.

(3) The manufacturer and model number of all major items of equipment shall be shown on the record drawings.

(4) Upon completion of all construction, the Contractor will delete by notation all references to features not constructed.

(b) These annotated prints shall be certified as to their correctness by the signature of the Contractor and turned over to the Contracting Officer or his/her designated representative not later than ten

(10) days after final acceptance of the work by the Government. Marked up prints shall be reviewed for approval by the Contracting Officer or his/her designated representative and returned for corrections as necessary.

(End of Clause)

1.12 FINISH MATERIAL SUBMITTALS

All finish items requiring submittal for approval shall be packaged by the Contractor to form one coordinated submittal for interior finishes and one coordinated and separate submittal for exterior finishes. Each submittal shall clearly convey colors, textures and finishes proposed to permit a complete review on how the finishes interact.

(End of Clause)

1.13 ASBESTOS PERMIT AND NOTIFICATION

Prior to beginning any demolition or renovation of existing buildings, the Contractor shall submit notification to the appropriate state agency by completing there "Asbestos Permit Application and Notification for Demolition/Renovation" form. State law requires notification whether or not asbestos is present. A copy of the state response shall be submitted to the Government for information.

SECTION 01 10 00.10 38 Page 8

The following state agencies require notification:

The Virginia Department of Labor and Industry - Headquarters 600 East Main Street, Suite 207 Richmond, Virginia 23219

Phone: (804) 371-2327 Fax: (804) 786-0139 http://www.doli.virginia.gov/leadasbestos

(End of Clause)

1.14 ASBESTOS - (Occupational Health and Environment)

(a) THE CONTRACTOR IS WARNED THAT EXPOSURE TO AIRBORNE ASBESTOS HAS

BEEN ASSOCIATED WITH FOUR DISEASES: LUNG CANCER, CERTAIN GASTROINTESTINAL

CANCERS, PLURAL OR PERITONEAL MESOTHELIOMA AND ASBESTOS. Studies indicate there are significantly increased health dangers to persons exposed to asbestos who smoke and further, to family members and other persons who become indirectly exposed as a result of the exposed worker bringing asbestos-laden work clothing home to be laundered.

***AMENDMENT 0004***

(b) The Contractor is advised that friable and/or nonfriable asbestos containing material has been identified in area(s) where contract work is to be performed. Friable asbestos containing material means any material that contains more than 1 percent asbestos by weight that hand pressure can crumble, pulverize or reduce to powder when dry. Nonfriable asbestos containing materials do not release airborne asbestos fiber during routine handling and end-use. However, excessive fiber concentrations may be produced during uncontrolled abrading, sanding, drilling, cutting, machining, removal, demolition or other similar activities. There is asbestos in the original control wiring which comprises approximately 80 percent of the total control wiring. The cable trays that hold the 15kV cables in the control tunnel going from the original switchgear to the transformer are made of asbestos. The 15kV switchgear also contains asbestos in the arc shoots and control wiring.

***AMENDMENT 0004***

(c) Care must be taken to avoid releasing, or causing to be released, asbestos fibers into the atmosphere where they may be inhaled or ingested. The Occupational Safety and Health Administration (OSHA) has set standards at 29 CFR 1910.1001, for exposure to airborne concentrations of asbestos fibers, methods of compliance, medical surveillance, housekeeping procedures and other measures that must be taken when working with or around asbestos containing materials which release airborne asbestos fibers at concentrations in excess of those established. 29 CFR 1926.58 has been identified as applicable to construction (29 CFR 1926.55 gases, vapors, fumes, dusts and mists). The Environmental Protection Agency (EPA) has established standards at 40 CFR 61.40, 40 CFR 61.156 for the control of asbestos emissions to the environment and the handling and disposal of asbestos wastes.

(d) When contract work activities are carried out in locations where the potential exists for exposure to airborne asbestos fibers as described in (b) or where asbestos waste will be generated, the contractor shall assure that all measures necessary to provide effective protection to persons from exposure to asbestos fibers and prevention of contamination to property, materials, supplies, equipment and the internal and external

SECTION 01 10 00.10 38 Page 9 environment are effectively instituted.

(e) As a minimum, the contractor shall comply with the provisions of 29 CFR 1926.58 and 1926.55; 49 CFR 172.101, 49 CFR 172.200-204, 49 CFR 172.316, 49 CFR 173.1090; 40 CFR 61.40, 40 CFR 61.156; any state implementing hazardous waste regulation that regulates asbestos as a hazardous waste under the Resources Conservation and Recovery Act (RCRA) requirements and any other applicable federal, state or local requirements.

(f) In addition to the information required in Section 01 35 26, the Contractors Accident Prevention Plan must also fully address the following topics, and at the Contractor's option may include additional information as applicable.

(1) Medical Surveillance: (29 CFR 1926.58(m)).

(2) Employee training: Prior to beginning work in asbestos containing material area(s) (29 CFR 1926.58 and 29 CFR 1910.134).

(3) Respiratory protection: (29 CFR 1926.58(h) and

29 CFR 1910.134).

(4) Personal protective clothing and equipment: (29 CFR 1926.58(i)).

The use of compressed air to remove asbestos from workers' clothing is prohibited. The contractor shall specify the type of change room, wash facilities and laundering facilities as applicable.

(5) Airborne asbestos monitoring: (29 CFR 1926.58(f)).

Specify the monitoring and analytical procedures to be used prior to, during, and after completion of contract in areas where asbestos containing materials are located. All asbestos monitoring shall be conducted under the guidance of an industrial hygienist certified by the American board of Industrial Hygiene. Samples shall be analyzed by an American Industrial Hygiene Association (AIHA) accredited laboratory proficient in the analysis of asbestos and asbestos containing materials. Turn around time from end of sampling period to review of results of analyses by Contractor shall be no longer than 72 hours.

(6) Housekeeping: (29 CFR 1926.58(l)). Dry sweeping of contract work areas contaminated with asbestos containing material is prohibited. The Contractor shall specify methods and materials used to package asbestos containing waste and plan to control any accidental airborne release or spill of asbestos containing material.

(7) Methods of Compliance: (29 CFR 1926.58(g)). Contractor shall include procedures relating to engineering controls, local exhaust ventilation, particular tools to be used and work practices (1926.58(g)).

Specify methods, materials and equipment to be used to prevent asbestos contamination to property, materials, supplies, equipment and the internal and external environment during maintenance, renovation or other contract activities. Local exhaust ventilation equipment including power operated tools equipped with local exhaust ventilation shall conform with the Standard Fundamentals Governing the Design and operation of Local Exhaust Systems ANSI Z9.2 latest revised edition. Describe the type of high-efficiency filtered (HEPA) vacuum cleaners that shall be used to vacuum asbestos containing materials. Describe methods and materials to be used to assure all asbestos containing material will be thoroughly wetted

SECTION 01 10 00.10 38 Page 10 by use of a wetting agent and water before removal land that airborne asbestos dust will be kept to a minimum.

(8) Methods and materials to be used to decontaminate any property, materials, supplies, equipment and the environment if asbestos contamination results. (29 CFR 1926.58(g)).

(9) Recordkeeping procedures. (29 CFR 1926.58(n) and

29 CFR 1910.20).

(10) Specific description of type of packaging, marking and shipping conveyances to be used to transport asbestos containing waste from the generation point to a storage or disposal facility in compliance with Department of Transportation requirements. (49 CFR 172.101, 49 CFR

172.200-204, 49 CFR 176.316, 49 CFR 173-1090).

(11) Emergency procedures that would be taken if an accident or spill of asbestos containing materials occurs during the transport of asbestos containing waste. (40 CFR 61.140, 40 CFR 61.156).

(12) Methods and equipment used to off load and bury asbestos containing waste to control airborne emissions at the burial site. (

40 CFR 61.140-40 CFR 61.156).

(g) The Contractor shall complete and return to the Contracting Officer or his/her designated representative within 15 working days after the completion of all airborne asbestos monitoring conducted under this contract, a "Summarization of Airborne Asbestos Sampling Results" form provided by the Government (see Attachment 1).

NOTE: This completed summarization form is to be used by the US Army Corps of Engineers for statistical information purposes and does not relieve the contractor from his recordkeeping requirements as described in 29 CFR 1926.58(n) and 29 CFR 1910.20.

(End of Clause)

1.15 WORK IN QUARANTINED AREA

USACE and the U.S. Department of Agriculture (USDA) have a compliance agreement requiring measures to prevent the spread of certain plant pests that may be present in the soil (USACE ER 1110-1-5). Major portions of all southeastern states are in a quarantine area for such pests, including the imported fire ant. In addition, adjacent states to the north have introduced infestations resulting from movement of soil from infested southeastern states. The Contractor shall thoroughly clean all construction equipment and tools at the previous job site in a manner that ensures that these implements are free from residual soil, egg deposits from plant pests, noxious weeds, and plant seeds. Equipment shall be cleaned using water under pressure, and hand tools shall be thoroughly cleaned by brushing or other means to remove all soil. In addition, all construction equipment and hand tools used for this USACE contract shall be thoroughly cleaned by the Contractor before they are removed from this job site. The Contractor shall consult with the USDA jurisdictional office for additional cleaning requirements that may be necessary.

(End of Clause)

SECTION 01 10 00.10 38 Page 11

1.16 PUBLIC CONVENIENCE AND SAFETY

1.16.1 Roads To Be Closed

No road shall be closed to the public by the Contractor until construction of the new facilities infringe upon the public safety or until construction of the new facilities obliterate the existing facilities. The Contractor shall obtain the Contracting Officer's approval before closing any roads.

Barricades, danger, warning and detour signs, as required, shall be erected before closing any roads.

1.16.2 Storage of Materials

Materials and equipment shall not be stored within roadway rights-of-way or in such a manner as to pose possible danger or obstruction to the traveling public.