These are construction phasing plans showing 8 phases of construction for a new Critical Care Center (CCC), Central Utility Plant (CUP), and Logistics Transportation Hub (LTH) at the West Los Angeles VA Medical Center campus. The drawings detail the sequence of construction activities, including site preparation, building construction, utility work, and site improvements across multiple buildings and areas.
Key phases include: Phase 1 (Make Ready) involves PV panel removal, temporary loading dock construction, and contractor mobilization; Phase 2-4 show construction of buildings B600 (CCC), B601 (LTH), and B602 (CUP); Phase 5 includes pedestrian spine construction and utility work; Phase 6 covers building commissioning; Phase 7 involves moving inpatient programs from B500 to B600; and Phase 8 includes B500 renovations, guard house construction, and perimeter security fence installation. The plans emphasize maintaining access to existing facilities, protecting building air intakes, fire department access, and utility services throughout construction. Detailed notes address dust control, temporary barriers, fire protection requirements, and contractor parking areas.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Industry Day Sign-In Roster 12 Feb 25.pdf | ||
| Question and Answer Session.docx | DOCX document | |
| Industry Day Presentation 20250212.pdf | ||
| Parking Shuttle Service.pdf | ||
| 691-408.000.SITE.DRAWINGS.zip | ZIP file | |
| 691-408-2HOSP.METHANE DWGS.zip | ZIP file | |
| 691-408.8AGVLD-B500.DRAWINGS.zip | ZIP file | |
| 691-408.602.CUP.DRAWINGS.zip | ZIP file | |
| 691-408-2HOSP.DRAWINGS.VOL 3.zip | ZIP file | |
| 691-408-2HOSP.DRAWINGS.VOL 5.zip | ZIP file | |
| 691-408-2HOSP.DRAWINGS.VOL 4.zip | ZIP file | |
| 691-408-2HOSP.DRAWINGS.VOL 2.zip | ZIP file | |
| Industry Day - Site Map.pptx | PPTX presentation | |
| 691-408-2HOSP.DRAWINGS.VOL 1.zip | ZIP file | |
| 691-408.000.PHASING.pdf |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STOP
STOP
STOP
BUMP
BUMP
V .A
B
U S O
N L Y
P A
T
IE
N T
-V A
N
PED PED
XING XING
BUMP
BU M
P
ENTER
M O
T O
R C
Y C
L E
S O
N L
Y
H C
H C
H C
H C
H C
H C
H C
STOP
STOP
STOP
STOP
STOP
STOP
STOP
STOP
BUMP
BUMP
KEEP
CLEAR
STOP
HC
NO
PA
RKING
HC
NO
PA
RKING
NO
P
A
RK
IN
G
NO
PA
RKING
NO
PA
RKINGNO
P A
RK
IN
G
NO
P A
RK
IN
G
PARKING
NO
PARKINGPARKINGPARKING
PARKING PARKING PARKINGNO NO NO
NONONO
PARKING
NO
FI R E LA N E
PARKINGPARKINGPARKINGPARKINGPARKINGPARKINGPARKING
PARKING
NO
NONONONONONONO
NO PARKINGNO PARKING
FIRE LANE
BUMP
BUMP
STOP
S T
OP
S T
OP
S T
OP
STOPSTOP
STOP
STO
P
HCHC
S
TO
P S
T O
P
HC
STOP
HC
N O
PA
R
KI
NG
N O
PA
R
KI
NG
N O
PA
R
KI
NG
HCHCHCHCHCHCHC
HC HC HCHCHCHCHCHCHCHCHCHC
S TOP
ST O
P
STOP
N O
P A
R K
IN
G
NO PARKING
NO PARKING
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
NO PARKING
NO PARKINGNO PARKING
NO PARKING NO PARKING
BU M
P
LAUNDRY
NO PARKING
BUMP
NO PARKING
N O
P A
R K
IN
G
NO PARKING
NO PARKING
N O
P A
R K
IN
G
HC HC
HC
HC
HCHC
STO
P
NO PARKING
NO PARKING
STOP
STO
P
S TOP
BU M
P
LAUNDRY
NO PARKING
BUMP
IN
O
U T
DO
NOT
ENTER
E
XIT
STOP
STOP
EXIT
EXIT
S T
OP
HCHC HC HC HC HC HC
HCHCHCHCHCHCHCHCHC
NO PARKING NO PARKINGNO PARKING
TSTS
TS
TS
TS
TS
TS
TS
TS
TS
TS
TS
TS
PED
STOP
STO
P
STOP
U T
U T
U T
U T
H H
H H
U T
U T
H H
U T
D
E
D
D
E
D
D
M W M W M W
D
E
D
D
E
E
E
D
E
D
D
D
M W
M W M W
D E
D
D
M WM W
D
M W
M W
P B
D
M W
D
D
D
M W
D D
M W
D
D
M W
M W
D
D
M W
T
T T
T
T
T
T
P B
P B
D
E
D
PHASE 1 - CONTRACTOR MOBILIZATION / MAKE READY
1.a REMOVE PV PANELS AND CLEAR SITE. MAKE READY FOR GRADING.
FENCE AREA OF CONSTRUCTION.
1.b REMOVE PV PANELS. SALVAGE PV SUPPORT STRUCTURE FOR
REINSTALLATION AT LOT 5. CLEAR SITE. MAKE READY FOR
GRADING. FENCE AREA OF CONSTRUCTION.
1.c REMOVE PV PANELS. GRADE AND PAVE AREA. PREPARE AREA FOR
CONTRACTOR USE AS CONSTRUCTION STAGING, TRAILER, AND/OR
PARKING. ERECT FENCE TO SECURE AREA. VERIFY ALL REQURIED
CLEARANCES WITH ACTIVE HELIPAD SITE. NOTE: CONTRACTOR TO
SECURE THEIR OWN POWER SOURCE AND ALL REQUIRED
CONNECTIONS.
1.d RELOCATE OXYGEN YARD TO TEMPORARY LOCATION.
1.e CONSTRUCT TEMPORARY LOADING DOCK. RELOCATE
UNDERGROUND UTILITIES AS REQUIRED FOR TEMPORARY
LOADING DOCK WORK. ROUGH-IN NEW UTILITIES AS REQUIRED TO
MAINTAIN ACCESS TO THE TEMPORARY DOCK DURING
CONSTRUCTION. MAINTAIN ACCESS TO EXISTING LOADING DOCK
UNTIL TEMPORARY LOADING DOCK IS COMPLETE.
1.f GRADE AND PAVE AREA FOR CONTRACTOR USE. PROIVDE DIRECT
ENTRANCE FROM OHIO AVENUE. ERECT FENCE TO SECURE AREA.
1.g ABOVE-GROUND FUEL TANKS. MAINTAIN TRUCK ACCESS TO
TANKS.
1.h EDISON SUBSTATION EXPECTED TO BE UNDER CONSTRUCTION.
1.i PROTECT BUILDING AIR INTAKES FROM DUST AND OTHER
CONSTRUCTION DEBRIS, TYPICAL.
1.j PROVIDE ACCESS TO EXISTING ENTRANCES DURING
CONSTRUCTION.
1.k PROVIDE FIRE DEPARTMENT ACCESS DURING CONSTRUCTION.
1.l MAINTAIN CLEARANCE AT AMBULANCE ENTRY.
1.m INSTALL ELECTRICAL DUCTBANK TO BACKFEED B501.
1.n INSTALL STORM DRAIN PIPING.
CONTRACTOR
CONTROLLED LAYDOWN &
CONSTRUCTION TRAILERS
(LAYDOWN AND TRAILER
LAYOUTS SHOWN FOR
REFERENCE ONLY)
KITCHEN
LOADING DOCK
1.b
1.f
1.c
1.d
1.l
1.a
TEMP.
KITCHEN
GENERATOR
1.g1.e
LOT A
LOT B
LOT 6
LOT 6
B608
PARKING
GARAGE
LOT F
B501
CUP
B500
HOSPITAL
B304
B402 B401
B345
B527 A.R.C.
B507
B522
B318
B312 B311
B23 B307
B308
B309
B91
B90
B104
B310
U.S. ARMY
CALIFORNIA
NATIONAL GUARD
U.S. AIR FORCE
PROPERTY
B105
EDISON
SUBSTATION
LOT 5
B607
PATRIOT
HOUSE
B606
FISHER HOUSE
B605
KITCHEN
B603
BOILER
METRO STATION
SUBSTATION
LOT 42
LOT C
LOT 2
S
A W
T E
L L
E
B
O U
L E
V A
R D
D O
W L E
N D
R I V
E
D O
W L
E N
D R
I V
W I L S H I R E V O U L E V A R D
O H I O A V E N U E
1.h
1.i
1.j
1.k
1.i
1.m
1.m
AMBULANCE
ENTRY
1.c
B527
PARKING
LOT
1.n
HELIPAD
CONTRACTOR
CONTROLLED PARKING
(PARKING LAYOUT SHOWN
FOR REFERENCE ONLY)
EXISTING
DOCK AREA
1. PROVIDE EGRESS ACCESS FROM EXISTING BUILDING
EXITS AND AREAS OF NEW WORK DURING
CONSTRUCTION.
2. PHASING IS SCHEMATIC AND NOT INTENDED TO BE
SEQUENTIAL
3. ENSURE DUST CONTROL PLAN IS IN PLACE. SEE
SUSTAINABLE CONSTRUCTION REQUIREMENTS
SPECIFICATION.
4. PROTECT EXISTING BUILDING AIR INTAKES FROM
DUST AND OTHER CONSTRUCTION DEBRIS.
5. PROVIDE FIRE DEPARTMENT ACCESS TO BUILDINGS
DURING CONSTRUCTION.
6. SEE LOGISTICS TRANSPORTATION HUB DRAWINGS
FOR PHASING INFORMATION AT B500.
7. FOR FULL EXTENTS OF AREAS OF WORK, SEE CIVIL
DEMOLITION PLANS.
8. CONTRACTOR SHALL NOT ENTER AREAS WHICH ARE
NOT IN CONTRACT. IF ACCESS TO THESE AREAS ARE
NEEDED, GC TO COORDINATE ACCESS WITH
CONTRACTING OFFICER REPRESENTATIVE.
9. PROVIDE TEMPORARY CONSTRUCTION BARRIERS TO
SEPARATE AREAS OF WORK FROM OTHER AREAS.
10. REFER TO THE SPECIFICATIONS AND FIRE
PROTECTION DESIGN MANUAL SECTION 1.4 FOR FIRE
PROTECTION REQUIREMENTS DURING
CONSTRUCTION.
11. USE ONLY THE CONTRACTOR'S PERSONNEL PARKING
AS INDICATED ON PHASING PLANS.
12. MAINTAIN CIRCULATION AREAS FREE OF BARRIERS
TO EMERGENCY VEHICLES.
13. MAINTAIN UTILITY SERVICES AT AND TO FACILITIES AT
ALL TIMES. IF INTERRUPTIONS ARE NECESSARY,
RECEIVE ADVANCE APPROVAL FROM COR.
14. MAINTAIN EXISTING FIRE EXITS OPEN AND FREE
FROM DEBRIS AND OBSTACLES.
15. MAINTAIN FIRE ALARM DETECTION AND SUPPRESSION
SYSTEMS. PROVIDE TEMPORARY INTERIM SYSTEMS
WHEN PERMANENT SYSTEMS CANNOT BE USED.
16. PROVIDE AND MAINTAIN PORTABLE FIRE
SUPPRESSION EQUIPMENT WHERE REQUIRED.
EXISTING BUILDING
PROPERTY LINE
UNDERGROUND STORAGE TANKS
LIMITS OF WORK (ACTIVE WORK AREA)
AREA EXPECTED TO BE UNDER
CONSTRUCTION BY OTHER PROGRAM
CONTRACTOR PARKING/ STAGING/
TRAILER AREAS
NEW BUILDING
UTILITY TUNNEL CONNECTIONS
AGV (AUTOMATED GUIDED VEHICLE)
TUNNEL CONNECTIONS
PEDESTRIAN PATH ACCESS
PATH OF EGRESS
PROPOSED LOCATION OF FUTURE
EXPANSION
N TRUE
NORTH
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
A u to d e s k D o c s /0
-1
-0
V A
W
L A
-C C
C C
U P
S it e
U ti ls
R e n o o f_ B
/6
-4
.0
.A
R C
H .r v t
/2
/2
:5
:0
P
M
GI201
PHASING PLAN - PHASE 1 - MAKE
READYLEO A DALY COMPANY
LOS ANGELES, CA 90071
(213) 629-0100
NICOS KATSELLIS
WEST LA MEDICAL CENTER
SITE INFRASTRUCTURE AND
UTILITIES
WEST LOS ANGELES, CA
691-408
N/A
2.16.24 KT
CONSTRUCTION
DOCUMENTS
550 SOUTH HOPE STREET, 27TH FLOOR
SCALE:1 : 1440
F1
SITE PLAN OVERALL - PHASE 1
SYMBOL LEGEND
GENERAL NOTES
SCALE : 1" = 120'-0"
0 120' 240'
Revisions: Date:
FOR REFERENCE ONLY
NOT FOR CONSTRUCTION
FOR REFERENCE ONLY - NOT FOR CONSTRUCTION : QUANTITIES AND DESIGNS CAN, AND LIKELY WILL, CHANGE. BY USING THESE DRAWINGS, YOU AGREE LEO A DALY IS RELEASED AND HELD HARMLESS FOR ANY AND ALL DAMAGES OR CLAIMS RELATED TO OR ARISING FROM SUCH USE
STOP
STOP
BUMP
BUMP
V .A
B
U S O
N L Y
P A
T
IE
N T
-V A
N
PED PED
XING XING
BUMP
BU M
P
ENTER
M O
T O
R C
Y C
L E
S O
N L
Y
H C
H C
H C
H C
H C
H C
H C
STOP
STOP
STOP
STOP
STOP
STOP
STOP
STOP
BUMP
BUMP
KEEP
CLEAR
STOP
HC
NO
PA
RKING
HC
NO
PA
RKING
NO
P
A
RK
IN
G
NO
PA
RKING
NO
PA
RKING
NO
P
A
RK
IN
G
NO
P
A
RK
IN
G
PARKING
NO
PARKINGPARKINGPARKING
PARKING PARKING PARKINGNO NO NO
NONONO
PARKING
NO
FI R E LA N E
PARKINGPARKINGPARKINGPARKINGPARKINGPARKINGPARKING
PARKING
NO
NONONONONONONO
NO PARKINGNO PARKING
FIRE LANE
BUMP
BUMP
STOP
S T
OP
S T
OP
S T
OP
STOPSTOP
STOP
STO
P
HCHC
S
TO
P S
T O
P
HC
STOP
HC
N O
PA
R
KI
NG
N O
PA
R
KI
NG
N O
PA
R
KI
NG
HCHCHCHCHCHCHC
HC HC HCHCHCHCHCHCHCHCHCHC
S TOP
ST O
P
STOP
N O
P A
R K
IN
G
NO PARKING
NO PARKING
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
NO PARKING
NO PARKINGNO PARKING
NO PARKING NO PARKING
BU M
P
LAUNDRY
NO PARKING
BUMP
NO PARKING
N O
P A
R K
IN
G
NO PARKING
NO PARKING
N O
P A
R K
IN
G
HC HC
HC
HC
HCHC
STO
P
NO PARKING
NO PARKING
STOP
STO
P
S TOP
BU M
P
LAUNDRY
NO PARKING
BUMP
IN
O
U T
DO
NOT
ENTER
E
XIT
STOP
EXIT
EXIT
S T
OP
HCHC HC HC HC HC HCHCHCHCHCHCHCHCHCHC
NO PARKING NO PARKINGNO PARKING
TSTS
TS
TS
TS
TS
TS
TS
TS
TS
TS
TS
TS
PED
STOP
STO
P
STOP
U T
U T
U T
U T
H H
H H
U T
U T
H H
U T
D
E
D
D
E
D
D
M W M W M W
D
E
D
D
E
E
E
D
E
D
D
D
M W
M W M W
D E
D
D
M WM W
D
M W
M W
P B
D
M W
D
D
D
M W
D D
M W
D
D
M W
M W
D
D
M W
T
T T
T
T
T
T
P B
P B
D
E
D
KITCHEN
LOADING DOCK
PHASE 2 - CONSTRUCTION
2.a GRADE SITE. BEGIN CONSTRUCTION OF B601 OVER EXISTING
UTILITY TUNNEL BETWEEN B500 AND B501.
2.b BEGIN EXCAVATION AND CONSTRUCTION OF B601
ELEVATORS STRUCTURE.
2.c GRADE SITE. BEGIN EXCAVATION AND CONSTRUCTION OF B600 AND B602.
2.d MAINTAIN ACCESS TO B605 AND B603.
2.e TEMPORARY LOADING DOCK IS OPERATIONAL.
2.f TEMPORARY LOADING DOCK ACCESS ROAD ALONG SAWTELLE
BLVD. MAINTAIN ALL REQUIRED CONSTRUCTION CLEARANCES
FROM FUTURE B600.
2.g EDISON SUBSTATION EXPECTED TO BE UNDER CONSTRUCTION.
2.h ABOVE-GROUND FUEL TANKS. MAINTAIN TRUCK ACCESS TO TANKS.
2.i CONSTRUCTION OF BOILER B603 IS COMPLETE.
TEMPORARILY RELOCATED
OXYGEN YARD
2.b
EXISTING UTILITY TUNNEL
2.c 2.c
2.d
2.a
2.f
2.g
2.h
TEMP.
KITCHEN
GENERATOR
TEMP
LOADING
DOCK
2.e
B527
PARKING
LOT
S A
W T
E L
U L
E V
A R
D
D O
W L E
N D
R I V
E
D O
W L
E N
D R
LOT A
LOT B
LOT 6
LOT 6
B608
PARKING
GARAGE
LOT F
B501
CUP
B500
HOSPITAL
B304
B402 B401
B345
A.R.C.
B507
B522
B318
B312 B311
B23 B307
B308
B309
B91
B90
B104
B310
U.S. ARMY
CALIFORNIA
NATIONAL GUARD
U.S. AIR FORCE
PROPERTY
B105
EDISON
SUBSTATION
LOT 5
B607
PATRIOT
HOUSE
B606
FISHER HOUSE
B605
KITCHEN
B603
BOILER
METRO STATION
SUBSTATION
LOT 42
LOT C
B601
(B601 - LOADING DOCK/LOGISTICS TRANSPORTATION HUB - LTH)
(B602 - CENTRAL UTILITY PLANT - CUP)
(B600 - CRITICAL CARE CENTER - CCC)
2.i
B600
CCC
B602
CUP
HELIPAD
1. PROVIDE EGRESS ACCESS FROM EXISTING BUILDING
EXITS AND AREAS OF NEW WORK DURING
CONSTRUCTION.
2. PHASING IS SCHEMATIC AND NOT INTENDED TO BE
SEQUENTIAL
3. ENSURE DUST CONTROL PLAN IS IN PLACE. SEE
SUSTAINABLE CONSTRUCTION REQUIREMENTS
SPECIFICATION.
4. PROTECT EXISTING BUILDING AIR INTAKES FROM
DUST AND OTHER CONSTRUCTION DEBRIS.
5. PROVIDE FIRE DEPARTMENT ACCESS TO BUILDINGS
DURING CONSTRUCTION.
6. SEE LOGISTICS TRANSPORTATION HUB DRAWINGS
FOR PHASING INFORMATION AT B500.
7. FOR FULL EXTENTS OF AREAS OF WORK, SEE CIVIL
DEMOLITION PLANS.
8. CONTRACTOR SHALL NOT ENTER AREAS WHICH ARE
NOT IN CONTRACT. IF ACCESS TO THESE AREAS ARE
NEEDED, GC TO COORDINATE ACCESS WITH
CONTRACTING OFFICER REPRESENTATIVE.
9. PROVIDE TEMPORARY CONSTRUCTION BARRIERS TO
SEPARATE AREAS OF WORK FROM OTHER AREAS.
10. REFER TO THE SPECIFICATIONS AND FIRE
PROTECTION DESIGN MANUAL SECTION 1.4 FOR FIRE
PROTECTION REQUIREMENTS DURING
CONSTRUCTION.
11. USE ONLY THE CONTRACTOR'S PERSONNEL PARKING
AS INDICATED ON PHASING PLANS.
12. MAINTAIN CIRCULATION AREAS FREE OF BARRIERS
TO EMERGENCY VEHICLES.
13. MAINTAIN UTILITY SERVICES AT AND TO FACILITIES AT
ALL TIMES. IF INTERRUPTIONS ARE NECESSARY,
RECEIVE ADVANCE APPROVAL FROM COR.
14. MAINTAIN EXISTING FIRE EXITS OPEN AND FREE
FROM DEBRIS AND OBSTACLES.
15. MAINTAIN FIRE ALARM DETECTION AND SUPPRESSION
SYSTEMS. PROVIDE TEMPORARY INTERIM SYSTEMS
WHEN PERMANENT SYSTEMS CANNOT BE USED.
16. PROVIDE AND MAINTAIN PORTABLE FIRE
SUPPRESSION EQUIPMENT WHERE REQUIRED.
EXISTING BUILDING
PROPERTY LINE
UNDERGROUND STORAGE TANKS
LIMITS OF WORK (ACTIVE WORK AREA)
AREA EXPECTED TO BE UNDER
CONSTRUCTION BY OTHER PROGRAM
CONTRACTOR PARKING/ STAGING/
TRAILER AREAS
NEW BUILDING
UTILITY TUNNEL CONNECTIONS
AGV (AUTOMATED GUIDED VEHICLE)
TUNNEL CONNECTIONS
PEDESTRIAN PATH ACCESS
PATH OF EGRESS
PROPOSED LOCATION OF FUTURE
EXPANSION
N TRUE
NORTH
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
A u to d e s k D o c s /0
-1
-0
V A
W
L A
-C C
C C
U P
S it e
U ti ls
R e n o o f_ B
/6
-4
.0
.A
R C
H .r v t
/2
/2
:5
:0
P
M
GI202
PHASING PLAN - PHASE 2 -
CONSTRUCTIONLEO A DALY COMPANY
LOS ANGELES, CA 90071
(213) 629-0100
NICOS KATSELLIS
WEST LA MEDICAL CENTER
SITE INFRASTRUCTURE AND
UTILITIES
WEST LOS ANGELES, CA
691-408
N/A
2.16.24
CONSTRUCTION
DOCUMENTS
550 SOUTH HOPE STREET, 27TH FLOOR
SCALE:1 : 1440
F1
SITE PLAN OVERALL - PHASE 2
SYMBOL LEGEND
GENERAL NOTES
SCALE : 1" = 120'-0"
0 120' 240'
Revisions: Date:
FOR REFERENCE ONLY
FOR REFERENCE ONLY - NOT FOR CONSTRUCTION : QUANTITIES AND DESIGNS CAN, AND LIKELY WILL, CHANGE. BY USING THESE DRAWINGS, YOU AGREE LEO A DALY IS RELEASED AND HELD HARMLESS FOR ANY AND ALL DAMAGES OR CLAIMS RELATED TO OR ARISING FROM SUCH USE
STOP
STOP
BUMP
BUMP
V .A
B
U S O
N L Y
P A
T
IE
N T
-V A
N
PED PED
XING XING
BUMP
BU M
P
ENTER
M O
T O
R C
Y C
L E
S O
N L
Y
H C
H C
H C
H C
H C
H C
H C
STOP
STOP
STOP
STOP
STOP
STOP
STOP
STOP
BUMP
BUMP
KEEP
CLEAR
STOP
HC
NO
PA
RKING
HC
NO
PA
RKING
NO
P
A
RK
IN
G
NO
PA
RKING
NO
PA
RKINGNO
P A
RK
IN
G
NO
P A
RK
IN
G
PARKING
NO
PARKINGPARKINGPARKING
PARKING PARKING PARKINGNO NO NO
NONONO
PARKING
NO
FI R E LA N E
PARKINGPARKINGPARKINGPARKINGPARKINGPARKINGPARKING
PARKING
NO
NONONONONONONO
NO PARKINGNO PARKING
FIRE LANE
BUMP
BUMP
STOP
S T
OP
S T
OP
S T
OP
STOPSTOP
STOP
STO
P
HCHC
S
TO
P S
T O
P
HC
STOP
HC
N O
PA
R
KI
NG
N O
PA
R
KI
NG
N O
PA
R
KI
NG
HCHCHCHCHCHCHC
HC HC HCHCHCHCHCHCHCHCHCHC
S TOP
ST O
P
STOP
N O
P A
R K
IN
G
NO PARKING
NO PARKING
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
NO PARKING
NO PARKINGNO PARKING
NO PARKING NO PARKING
BU M
P
LAUNDRY
NO PARKING
BUMP
NO PARKING
N O
P A
R K
IN
G
NO PARKING
NO PARKING
N O
P A
R K
IN
G
HC HC
HC
HC
HCHC
STO
P
NO PARKING
NO PARKING
STOP
STO
P
S TOP
BU M
P
LAUNDRY
NO PARKING
BUMP
IN
O
U T
DO
NOT
ENTER
E
XIT
STOP
EXIT
EXIT
S T
OP
HCHC HC HC HC HC HC
HCHCHCHCHCHCHCHCHC
NO PARKING NO PARKINGNO PARKING
TSTS
TS
TS
TS
TS
TS
TS
TS
TS
TS
TS
TS
PED
STOP
STO
P
STOP
U T
U T
U T
U T
H H
H H
U T
U T
H H
U T
D
E
D
D
E
D
D
M W M W M W
D
E
D
D
E
E
E
D
E
D
D
D
M W
M W M W
D E
D
D
M WM W
D
M W
M W
P B
D
M W
D
D
D
M W
D D
M W
D
D
M W
M W
D
D
M W
T
T T
T
T
T
EXISTING PARKING STRUCTURE
T
P B
P B
D
E
D
PHASE 3 - CONSTRUCTION
3.a CONSTRUCTION CONTINUES AT B600, B601 AND B602.
3.b ABOVE-GROUND FUEL TANKS. MAINTAIN ALL TRUCK ACCESS TO TANKS.
3.c CONSTRUCT UNDERGROUND STORAGE TANKS.
3.d INSTALL UNDERGROUND UTILITIES BETWEEN B600 AND B602.
3.e CONSTRUCTION BEGINS ON AGV TUNNEL BETWEEN B601 AND B605.
3.f EDISON SUBSTATION EXPECTED TO BE UNDER CONSTRUCTION.
3.g BEGIN INSTALLATION OF UNDERGROUND UTILITIES BETWEEN
B600, B602 AND B603.
KITCHEN
LOADING DOCK
3.a
3.a 3.a
3.d
3.e
3.b
TEMP.
KITCHEN
GENERATOR
TEMP
LOADING
DOCK
3.f
S A
W T
E L
U L
E V
A R
D
D O
W L E
N D
R I V
E
D O
W L
E N
D R
B600
CCC B602
CUP
B601
LTH
3.g
3.c
B527
PARKING
LOT
LOT A
LOT B
LOT 6
LOT 6
B608
PARKING
GARAGE
LOT F
B501
CUP
B500
HOSPITAL
B304
B402 B401
B345
A.R.C.
B507
B522
B318
B312 B311
B23 B307
B308
B309
B91
B90
B104
B310
U.S. ARMY
CALIFORNIA
NATIONAL GUARD
U.S. AIR FORCE
PROPERTY
B105
EDISON
SUBSTATION
LOT 5
B607
PATRIOT
HOUSE
B606
FISHER HOUSE
B605
KITCHEN
B603
BOILER
METRO STATION
SUBSTATION
LOT 42
LOT 2
HELIPAD
3.c
1. PROVIDE EGRESS ACCESS FROM EXISTING BUILDING
EXITS AND AREAS OF NEW WORK DURING
CONSTRUCTION.
2. PHASING IS SCHEMATIC AND NOT INTENDED TO BE
SEQUENTIAL
3. ENSURE DUST CONTROL PLAN IS IN PLACE. SEE
SUSTAINABLE CONSTRUCTION REQUIREMENTS
SPECIFICATION.
4. PROTECT EXISTING BUILDING AIR INTAKES FROM
DUST AND OTHER CONSTRUCTION DEBRIS.
5. PROVIDE FIRE DEPARTMENT ACCESS TO BUILDINGS
DURING CONSTRUCTION.
6. SEE LOGISTICS TRANSPORTATION HUB DRAWINGS
FOR PHASING INFORMATION AT B500.
7. FOR FULL EXTENTS OF AREAS OF WORK, SEE CIVIL
DEMOLITION PLANS.
8. CONTRACTOR SHALL NOT ENTER AREAS WHICH ARE
NOT IN CONTRACT. IF ACCESS TO THESE AREAS ARE
NEEDED, GC TO COORDINATE ACCESS WITH
CONTRACTING OFFICER REPRESENTATIVE.
9. PROVIDE TEMPORARY CONSTRUCTION BARRIERS TO
SEPARATE AREAS OF WORK FROM OTHER AREAS.
10. REFER TO THE SPECIFICATIONS AND FIRE
PROTECTION DESIGN MANUAL SECTION 1.4 FOR FIRE
PROTECTION REQUIREMENTS DURING
CONSTRUCTION.
11. USE ONLY THE CONTRACTOR'S PERSONNEL PARKING
AS INDICATED ON PHASING PLANS.
12. MAINTAIN CIRCULATION AREAS FREE OF BARRIERS
TO EMERGENCY VEHICLES.
13. MAINTAIN UTILITY SERVICES AT AND TO FACILITIES AT
ALL TIMES. IF INTERRUPTIONS ARE NECESSARY,
RECEIVE ADVANCE APPROVAL FROM COR.
14. MAINTAIN EXISTING FIRE EXITS OPEN AND FREE
FROM DEBRIS AND OBSTACLES.
15. MAINTAIN FIRE ALARM DETECTION AND SUPPRESSION
SYSTEMS. PROVIDE TEMPORARY INTERIM SYSTEMS
WHEN PERMANENT SYSTEMS CANNOT BE USED.
16. PROVIDE AND MAINTAIN PORTABLE FIRE
SUPPRESSION EQUIPMENT WHERE REQUIRED.
EXISTING BUILDING
PROPERTY LINE
UNDERGROUND STORAGE TANKS
LIMITS OF WORK (ACTIVE WORK AREA)
AREA EXPECTED TO BE UNDER
CONSTRUCTION BY OTHER PROGRAM
CONTRACTOR PARKING/ STAGING/
TRAILER AREAS
NEW BUILDING
UTILITY TUNNEL CONNECTIONS
AGV (AUTOMATED GUIDED VEHICLE)
TUNNEL CONNECTIONS
PEDESTRIAN PATH ACCESS
PATH OF EGRESS
PROPOSED LOCATION OF FUTURE
EXPANSION
N TRUE
NORTH
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
A u to d e s k D o c s /0
-1
-0
V A
W
L A
-C C
C C
U P
S it e
U ti ls
R e n o o f_ B
/6
-4
.0
.A
R C
H .r v t
/2
/2
:5
:1
P
M
GI203
PHASING PLAN - PHASE 3 -
CONSTRUCTIONLEO A DALY COMPANY
LOS ANGELES, CA 90071
(213) 629-0100
NICOS KATSELLIS
WEST LA MEDICAL CENTER
SITE INFRASTRUCTURE AND
UTILITIES
WEST LOS ANGELES, CA
691-408
N/A
2.16.24 KHOI
CONSTRUCTION
DOCUMENTS
550 SOUTH HOPE STREET, 27TH FLOOR
SCALE:1 : 1440
F1
SITE PLAN OVERALL - PHASE 3
SYMBOL LEGEND
GENERAL NOTES
SCALE : 1" = 120'-0"
0 120' 240'
Revisions: Date:
FOR REFERENCE ONLY
FOR REFERENCE ONLY - NOT FOR CONSTRUCTION : QUANTITIES AND DESIGNS CAN, AND LIKELY WILL, CHANGE. BY USING THESE DRAWINGS, YOU AGREE LEO A DALY IS RELEASED AND HELD HARMLESS FOR ANY AND ALL DAMAGES OR CLAIMS RELATED TO OR ARISING FROM SUCH USE
STOP
STOP
BUMP
BUMP
V .A
B
U S O
N L Y
P A
T
IE
N T
-V A
N
PED PED
XING XING
BUMP
BU M
P
ENTER
M O
T O
R C
Y C
L E
S O
N L
Y
H C
H C
H C
H C
H C
H C
H C
STOP
STOP
STOP
STOP
STOP
STOP
STOP
STOP
BUMP
BUMP
KEEP
CLEAR
STOP
HC
NO
PA
RKING
HC
NO
PA
RKING
NO
P
A
RK
IN
G
NO
PA
RKING
NO
PA
RKINGNO
P A
RK
IN
G
NO
P A
RK
IN
G
PARKING
NO
PARKINGPARKINGPARKING
PARKING PARKING PARKINGNO NO NO
NONONO
PARKING
NO
FI R E LA N E
PARKINGPARKINGPARKINGPARKINGPARKINGPARKINGPARKING
PARKING
NO
NONONONONONONO
NO PARKINGNO PARKING
FIRE LANE
BUMP
BUMP
STOP
S T
OP
S T
OP
S T
OP
STOPSTOP
STOP
STO
P
HCHC
S
TO
P S
T O
P
HC
STOP
HC
N O
PA
R
KI
NG
N O
PA
R
KI
NG
N O
PA
R
KI
NG
HCHCHCHCHCHCHC
HC HC HCHCHCHCHCHCHCHCHCHC
S TOP
ST O
P
STOP
N O
P A
R K
IN
G
NO PARKING
NO PARKING
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
N O
P A
R K
IN
G
NO PARKING
NO PARKINGNO PARKING
NO PARKING NO PARKING
BU M
P
LAUNDRY
NO PARKING
BUMP
NO PARKING
N O
P A
R K
IN
G
NO PARKING
NO PARKING
N O
P A
R K
IN
G
HC HC
HC
HC
HCHC
STO
P
NO PARKING
NO PARKING
STOP
BU M
P
LAUNDRY
NO PARKING
BUMP
IN
O
U T
DO
NOT
ENTER
E
XIT
STOP
EXIT
EXIT
S T
OP
HCHC HC HC HC HC HCHCHCHCHCHCHCHCHCHC
NO PARKING NO PARKINGNO PARKING
TSTS
TS
TS
TS
TS
TS
TS
TS
TS
TS
TS
TS
PED
STOP
STO
P
STOP
U T
U T
U T
U T
H H
H H
U T
U T
H H
U T
D
E
D
D
E
D
D
M WM W
M W
D
E
D
D
E
E
E
D
E
D
D
D
M W
M W M W
D E
D
D
M WM W
D
M W
M W
P B
D
M W
D
D
D
M W
D D
M W
D
D
M W
M W
D
D
M W
T
T T
T
T
T
T
P B
P B
D
E
D
PHASE 4 - CONSTRUCTION
4.a CONSTRUCT TELECOM DUCTBANK.
4.b CONSTRUCTION CONTINUES ON B600.
4.c B602 BUILDING CONSTRUCTION IS COMPLETE. BEGIN
COMMISSIONING OF BUILDING B602.
4.d CONSTRUCT FISHER HOUSE DRIVEWAY & SITE IMPROVEMENTS.
MAINTAIN PEDESTRIAN ACCESS FROM PARKING GARAGE B608
TO KITCHEN B604.
4.e CONTINUE INSTALLATION OF UNDERGROUND UTILITIES
BETWEEN B600, B602 AND B603.
4.f RELOCATE OXYGEN YARD TO PERMANENT LOCATION.
4.g EDISON SUBSTATION WORK EXPECTED TO BE COMPLETE.
REWORK AREA OF FORMER PARKING LOT F.
4.h ABOVE-GROUND FUEL TANKS. MAINTAIN TRUCK ACCESS TO
TANKS.
4.i B601 CONSTRUCTION COMPLETE. COMMISSION B601.
4.j CONSTRUCT NEW PARKING AREAS.
4.k CONSTRUCTION OF AGV TUNNEL CONTINUES.
4.d
4.b
KITCHEN
LOADING DOCK
4.g
OXYGEN YARD RELOCATED TO
PERMANENT LOCATION
4.a
TEMP.
KITCHEN
GENERATOR
4.h
TEMP
LOADING
DOCK 4.i
B601
LTH
LOT A
LOT B
LOT 6
LOT 6
B608
PARKING
GARAGE
LOT F
B500
HOPSPITAL
B304
B402 B401
B345
A.R.C.
B507
B522
B318
B312 B311
B23 B307
B308
B309
B91
B90
B104
B310
U.S. ARMY
CALIFORNIA
NATIONAL GUARD
U.S. AIR FORCE
PROPERTY
B105
EDISON
SUBSTATION
LOT 5
B607
PATRIOT
HOUSE
B606
FISHER HOUSE
B605
KITCHEN
B603
BOILER
METRO STATION
SUBSTATION
LOT 42
S A
W T
E L
U L
E V
A R
D
D O
W L E
N D
R I V
E
D O
W L
E N
D R
4.k
B501
CUP
LOT C
4.j
4.c
B600
CCC
B602
CUP
HELIPADHELIPAD
4.e
4.f
1. PROVIDE EGRESS ACCESS FROM EXISTING BUILDING
EXITS AND AREAS OF NEW WORK DURING
CONSTRUCTION.
2. PHASING IS SCHEMATIC AND NOT INTENDED TO BE
SEQUENTIAL
3. ENSURE DUST CONTROL PLAN IS IN PLACE. SEE
SUSTAINABLE CONSTRUCTION REQUIREMENTS
SPECIFICATION.
4. PROTECT EXISTING BUILDING AIR INTAKES FROM
DUST AND OTHER CONSTRUCTION DEBRIS.
5. PROVIDE FIRE DEPARTMENT ACCESS TO BUILDINGS
DURING CONSTRUCTION.
6. SEE LOGISTICS TRANSPORTATION HUB DRAWINGS
FOR PHASING INFORMATION AT B500.
7. FOR FULL EXTENTS OF AREAS OF WORK, SEE CIVIL
DEMOLITION PLANS.
8. CONTRACTOR SHALL NOT ENTER AREAS WHICH ARE
NOT IN CONTRACT. IF ACCESS TO THESE AREAS ARE
NEEDED, GC TO COORDINATE ACCESS WITH
CONTRACTING OFFICER REPRESENTATIVE.
9. PROVIDE TEMPORARY CONSTRUCTION BARRIERS TO
SEPARATE AREAS OF WORK FROM OTHER AREAS.
10. REFER TO THE SPECIFICATIONS AND FIRE
PROTECTION DESIGN MANUAL SECTION 1.4 FOR FIRE
PROTECTION REQUIREMENTS DURING
CONSTRUCTION.
11. USE ONLY THE CONTRACTOR'S PERSONNEL PARKING
AS INDICATED ON PHASING PLANS.
12. MAINTAIN CIRCULATION AREAS FREE OF BARRIERS
TO EMERGENCY VEHICLES.
13. MAINTAIN UTILITY SERVICES AT AND TO FACILITIES AT
ALL TIMES. IF INTERRUPTIONS ARE NECESSARY,
RECEIVE ADVANCE APPROVAL FROM COR.
14. MAINTAIN EXISTING FIRE EXITS OPEN AND FREE
FROM DEBRIS AND OBSTACLES.
15. MAINTAIN FIRE ALARM DETECTION AND SUPPRESSION
SYSTEMS. PROVIDE TEMPORARY INTERIM SYSTEMS
WHEN PERMANENT SYSTEMS CANNOT BE USED.
16. PROVIDE AND MAINTAIN PORTABLE FIRE
SUPPRESSION EQUIPMENT WHERE REQUIRED.
EXISTING BUILDING
PROPERTY LINE
UNDERGROUND STORAGE TANKS
LIMITS OF WORK (ACTIVE WORK AREA)
AREA EXPECTED TO BE UNDER
CONSTRUCTION BY OTHER PROGRAM
CONTRACTOR PARKING/ STAGING/
TRAILER AREAS
NEW BUILDING
UTILITY TUNNEL CONNECTIONS
AGV (AUTOMATED GUIDED VEHICLE)
TUNNEL CONNECTIONS
PEDESTRIAN PATH ACCESS
PATH OF EGRESS
PROPOSED LOCATION OF FUTURE
EXPANSION
N TRUE
NORTH
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
A u to d e s k D o c s /0
-1
-0
V A
W
L A
-C C
C C
U P
S it e
U ti ls
R e n o o f_ B
/6
-4
.0
.A
R C
H .r v t
/2
/2
:5
:1
P
M
GI204
PHASING PLAN - PHASE 4 -
CONSTRUCTIONLEO A DALY COMPANY
LOS ANGELES, CA 90071
(213) 629-0100
NICOS KATSELLIS
WEST LA MEDICAL CENTER
SITE INFRASTRUCTURE AND
UTILITIES
WEST LOS ANGELES, CA
691-408
N/A
2.16.24
CONSTRUCTION
DOCUMENTS
550 SOUTH HOPE STREET, 27TH FLOOR
SCALE : 1" = 120'-0"
0 120' 240'
SCALE:1 : 1440
F1
SITE PLAN OVERALL - PHASE 4
SCALE : 1" = 120'-0"
0 120' 240'
SYMBOL LEGEND
GENERAL NOTES
Revisions: Date:
FOR REFERENCE ONLY
FOR REFERENCE ONLY - NOT FOR CONSTRUCTION : QUANTITIES AND DESIGNS CAN, AND LIKELY WILL, CHANGE. BY USING THESE DRAWINGS, YOU AGREE LEO A DALY IS RELEASED AND HELD HARMLESS FOR ANY AND ALL DAMAGES OR CLAIMS RELATED TO OR ARISING FROM SUCH USE
S T
OP
STOP
STOP
BUMP
BUMP
V .A
B
U S O
N L Y
P A
T
IE
N T
-V A
N
PED PED
XING XING
BUMP
BU M
P
ENTER
M O
T O
R C
Y C
L E
S O
N L
Y
H C
H C
H C
H C
H C
H C
H C
STOP
STOP
STOP
STOP
STOP
STOP
STOP
STOP
BUMP
BUMP
KEEP
CLEAR
STOP
HC
NO
PA
RKING
HC
NO
PA
RKING
NO
P
A
RK
IN
G
NO
PA
RKING
NO
PA
RKING
NO
P
A
RK
IN
G
NO
P
A
RK
IN
G
PARKING
NO
PARKINGPARKINGPARKING
PARKING PARKING PARKINGNO NO NO
NONONO
PARKING
NO
FI R E LA N E
PARKINGPARKINGPARKINGPARKINGPARKINGPARKINGPARKING
PARKING
NO
NONONONONONONO
NO PARKINGNO PARKING
FIRE LANE
BUMP
BUMP
STOP
S T
OP
S T
OP
S T
OP
STOPSTOP
STOP
STO
P
HCHC
S
TO
P S
T O
P
HC
STOP
HC
YI ELD
N O
PA
R
KI
NG
N O
PA
R
KI
NG
N O
PA
R
KI
NG
VAN
VAN VAN
VANVAN
VANVANVAN
VANVANVAN
VAN
278.69
BFP/3"IP
S T
OP
HCHC HC HC HC HC HCHCHCHCHCHCHCHCHCHC
NO PARKING NO PARKINGNO PARKING
PED
STOP
STO
P
STOP
D
E
D
D
E
D
D
D
E
D
D
E
E
E
D
D
D
E D
D
D
D
D
D
D
D D
D
D
D
D
PHASE 5 - CONSTRUCTION
5.a EXPAND CONSTRUCTION FENCE TO ENCLOSE AREAS OF
CONSTRUCTION.
5.b GRADE AREA WEST OF B600 AND CONSTRUCT THE PEDESTRIAN
SPINE.
5.c REMOVE HARDSCAPE AND LANDSCAPE IN AREA BETWEEN B500 &
B304. CONSTRUCT NORTH DRIVE AND PARKING LOTS.
CONTRACTOR TO DEVELOP MICRO-PHASING PLANS, INCLUDING
POTENTIAL TEMPORARY MEASURES, TO ASSURE CONTINUED
CROSS CAMPUS ACCESS.
5.d AREA TO THE EAST OF B600 WORK: AFTER TEMPORARY ACCESS
FROM SOUTHEAST SIDE OF B500 TO B501 IS ESTABLISHED,
REWORK UTILITIES AND CONSTRUCT AMBULANCE DRIVEWAY &
DROP-OFF AT EAST SIDE OF B600. COMPLETE INSTALLATION OF
BURIED UTILITIES BEYWEEN B600 AND B602. COMPLETE AGV
TUNNEL CONNECTION TO KITCHEN.
5.e CONSTRUCT LANDSCAPE, DRIVEWAYS, AND WALKWAYS AROUND
B602 AND B603.
5.f COMMISSIONING OF B601 IS COMPLETE. LOADING DOCK. IS
OPERATIONAL.
5.g BEGIN SITE WORK AT FITNESS TRAIL. TEMPORARY KITCHEN
GENERATOR REMAINS OPERABLE.
5.h CONTINUE COMMISSIONING OF B602
5.i INSTALL SALVAGED SOLAR PANEL SUPPORT STRUCTURE. INSTAL
SOLAR PANELS.
5.j PROVIDE PEDESTRIAN ACCESS TO AND EGRESS FROM OCCUPIED
BULDINGS DURING CONSTRUCTION.
5.k COMPLETE CONSTRUCTION OF B600.
5.l TEMPORARY DOCK IS REMOVED AND TEMPORARY ACCESS TO
B501 AND ABOVE GROUND FUEL TANKS IS ESTABLISHED.
5.m SWITCH UTILITY SERVING B603 AND B605 FROM B501 TO B602.
- PHASE THE 2 POWER FEEDS SERVING B603 AND THE 2 POWER
FEEDS SERVING B605 AS REQUIRED TO MAKE THE TRANSITION
TO CUP B602.
5.n CONSTRUCT ELEVATOR AT B605.
5.b
5.d
5.a
5.c
5.e
5.g
5.h
KITCHEN
LOADING DOCK
TEMP.
KITCHEN
GENERATOR
5.i
5.f
5.k
S A
W T
E L
U L
E V
A R
D
D O
W L E
N D
R I V
E
D O
W L
E N
D R
5.l
5.j
5.j
5.j
5.j
5.j
5.j
5.m
TEMP
ELECTRICAL
SWITCHGEAR
FEEDING
BOILER B603
LOT A
LOT B
LOT 6
LOT 6
B608
PARKING
GARAGE
B500
HOPSPITAL
B304
B402 B401
B345
A.R.C.
B507
B522
B318
B312 B311
B23 B307
B308
B309
B91
B90
B104
B310
U.S. ARMY
CALIFORNIA
NATIONAL GUARD
U.S. AIR FORCE
PROPERTY
B105
LOT D
EDISON
SUBSTATION
LOT 5
B607
PATRIOT
HOUSE
B606
FISHER HOUSE
B605
KITCHEN
B603
BOILER
METRO STATION
SUBSTATION
LOT 42
5.d
5.d
5.n
B501
CUP
LOT C
B602
CUP
HELIPADHELIPAD
B601
LTH
B600
CCC
LOADING
DOCK
1. PROVIDE EGRESS ACCESS FROM EXISTING BUILDING
EXITS AND AREAS OF NEW WORK DURING
CONSTRUCTION.
2. PHASING IS SCHEMATIC AND NOT INTENDED TO BE
SEQUENTIAL
3. ENSURE DUST CONTROL PLAN IS IN PLACE. SEE
SUSTAINABLE CONSTRUCTION REQUIREMENTS
SPECIFICATION.
4. PROTECT EXISTING BUILDING AIR INTAKES FROM
DUST AND OTHER CONSTRUCTION DEBRIS.
5. PROVIDE FIRE DEPARTMENT ACCESS TO BUILDINGS
DURING CONSTRUCTION.
6. SEE LOGISTICS TRANSPORTATION HUB DRAWINGS
FOR PHASING INFORMATION AT B500.
7. FOR FULL EXTENTS OF AREAS OF WORK, SEE CIVIL
DEMOLITION PLANS.
8. CONTRACTOR SHALL NOT ENTER AREAS WHICH ARE
NOT IN CONTRACT. IF ACCESS TO THESE AREAS ARE
NEEDED, GC TO COORDINATE ACCESS WITH
CONTRACTING OFFICER REPRESENTATIVE.
9. PROVIDE TEMPORARY CONSTRUCTION BARRIERS TO
SEPARATE AREAS OF WORK FROM OTHER AREAS.
10. REFER TO THE SPECIFICATIONS AND FIRE
PROTECTION DESIGN MANUAL SECTION 1.4 FOR FIRE
PROTECTION REQUIREMENTS DURING
CONSTRUCTION.
11. USE ONLY THE CONTRACTOR'S PERSONNEL PARKING
AS INDICATED ON PHASING PLANS.
12. MAINTAIN CIRCULATION AREAS FREE OF BARRIERS
TO EMERGENCY VEHICLES.
13. MAINTAIN UTILITY SERVICES AT AND TO FACILITIES AT
ALL TIMES. IF INTERRUPTIONS ARE NECESSARY,
RECEIVE ADVANCE APPROVAL FROM COR.
14. MAINTAIN EXISTING FIRE EXITS OPEN AND FREE
FROM DEBRIS AND OBSTACLES.
15. MAINTAIN FIRE ALARM DETECTION AND SUPPRESSION
SYSTEMS. PROVIDE TEMPORARY INTERIM SYSTEMS
WHEN PERMANENT SYSTEMS CANNOT BE USED.
16. PROVIDE AND MAINTAIN PORTABLE FIRE
SUPPRESSION EQUIPMENT WHERE REQUIRED.
EXISTING BUILDING
PROPERTY LINE
UNDERGROUND STORAGE TANKS
LIMITS OF WORK (ACTIVE WORK AREA)
AREA EXPECTED TO BE UNDER
CONSTRUCTION BY OTHER PROGRAM
CONTRACTOR PARKING/ STAGING/
TRAILER AREAS
NEW BUILDING
UTILITY TUNNEL CONNECTIONS
AGV (AUTOMATED GUIDED VEHICLE)
TUNNEL CONNECTIONS
PEDESTRIAN PATH ACCESS
PATH OF EGRESS
PROPOSED LOCATION OF FUTURE
EXPANSION
N TRUE
NORTH
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
A u to d e s k D o c s /0
-1
-0
V A
W
L A
-C C
C C
U P
S it e
U ti ls
R e n o o f_ B
/6
-4
.0
.A
R C
H .r v t
/2
/2
:5
:1
P
M
GI205
PHASING PLAN - PHASE 5 -
CONSTRUCTIONLEO A DALY COMPANY
LOS ANGELES, CA 90071
(213) 629-0100
NICOS KATSELLIS
WEST LA MEDICAL CENTER
SITE INFRASTRUCTURE AND
UTILITIES
WEST LOS ANGELES, CA
691-408
N/A
2.16.24
CONSTRUCTION
DOCUMENTS
550 SOUTH HOPE STREET, 27TH FLOOR
SCALE:1 : 1440
F1
SITE PLAN OVERALL - PHASE 5
SYMBOL LEGEND
GENERAL NOTES
SCALE : 1" = 120'-0"
0 120' 240'
Revisions: Date:
FOR REFERENCE ONLY
FOR REFERENCE ONLY - NOT FOR CONSTRUCTION : QUANTITIES AND DESIGNS CAN, AND LIKELY WILL, CHANGE. BY USING THESE DRAWINGS, YOU AGREE LEO A DALY IS RELEASED AND HELD HARMLESS FOR ANY AND ALL DAMAGES OR CLAIMS RELATED TO OR ARISING FROM SUCH USE
S T
OP
STOP
BUMP
BUMP
BU M
P
ENTER
M O
T O
R C
Y C
L E
S O
N L
Y
H C
H C
H C
H C
H C
H C
H C
STOP
STOP
STOP
STOP
STOP
STOP
STOP
STOP
BUMP
BUMP
KEEP
CLEAR
HC
NO
PA
RKING
HC
NO
PA
RKING
NO
P
A
RK
IN
G
NO
PA
RKING
NO
PA
RKING
NO
P
A
RK
IN
G
NO
P
A
RK
IN
G
PARKING
NO
PARKINGPARKINGPARKING
PARKING PARKING PARKINGNO NO NO
NONONO
PARKING
NO
FI R E LA N E
PARKINGPARKINGPARKINGPARKINGPARKINGPARKINGPARKING
PARKING
NO
NONONONONONONO
NO PARKINGNO PARKING
FIRE LANE
BUMP
BUMP
STOP
S T
OP
S T
OP
S T
OP
STOPSTOP
STOP
STO
P
HCHC
S
TO
P S
T O
P
HC
STOP
HC
YI ELD
N O
PA
R
KI
NG
N O
PA
R
KI
NG
N O
PA
R
KI
NG
V A N
V A N
VAN
VAN VAN
VANVAN
VANVANVAN
VANVANVAN
VAN
278.69
BFP/3"IP
S T
OP
HCHC HC HC HC HC HCHCHCHCHCHCHCHCHCHC
NO PARKING NO PARKINGNO PARKING
PED
STOP
STO
P
STOP
D
E
D
D
E
D
D
D
E
D
E
E
E
D
D
D
E D
D
D
D
D
D
D D
D
D
D
D
STOP
BUMP
V .A
B
U S O
N L Y
P A
T
IE
N T
-V A
N
PED PED
XING XING
D
D
STOP
STOP
BU M
P
BUMP
BU M
P
BUMP
STOP
PHASE 6 - CONSTRUCTION
6.a B600 CONSTRUCTION IS COMPLETE. COMMISSION B600.
6.b CONTINUE CONSTRUCTION OF PERSTRIAN SPINE.
6.c CONTINUE HARDSCAPE AND LANDSCAPRE WORK.
6.d COMPLETE THE COMMISSIONING OF B602
6.e COMPLETE INTERIOR WORK AT KITCHEN B605.
6.f DEMOLISH TEMPORARY KITCHEN GENERATOR AND COMPLETE
LANDSCAPE OF FITNESS TRAIL.
6.g UTILITIES AND DRIVE WORK IS COMPLETE.
6.h DEMOLISH TEMPORARY ELECTRICAL SWITCHGEAR AND
ENCLOSURE.
KITCHEN
LOADING DOCK
TEMP.
KITCHEN
GENERATOR
D O
W L E
N D
R I V
E
D O
W L
E N
D R
6.a
6.e
LOADING
DOCKB601
LTH
B600
CCC
B602
CUP
LOT A
LOT B
LOT 6
LOT 6
B608
PARKING
GARAGE
LOT F
B500
HOPSPITAL
B304
B402 B401
B345
A.R.C.
B507
B522
B318
B312 B311
B23 B307
B308
B309
B91
B90
B104
B310
U.S. ARMY
CALIFORNIA
NATIONAL GUARD
U.S. AIR FORCE
PROPERTY
B105
LOT D
EDISON
SUBSTATION
LOT 5
B607
PATRIOT
HOUSE
B606
FISHER HOUSE
B605
KITCHEN
B603
BOILER
METRO STATION
SUBSTATION
LOT 42
B501
CUP
HELIPADHELIPAD
LOT C
6.c
6.b
6.d6.c
6.f
6.h
6.g
1. PROVIDE EGRESS ACCESS FROM EXISTING BUILDING
EXITS AND AREAS OF NEW WORK DURING
CONSTRUCTION.
2. PHASING IS SCHEMATIC AND NOT INTENDED TO BE
SEQUENTIAL
3. ENSURE DUST CONTROL PLAN IS IN PLACE. SEE
SUSTAINABLE CONSTRUCTION REQUIREMENTS
SPECIFICATION.
4. PROTECT EXISTING BUILDING AIR INTAKES FROM
DUST AND OTHER CONSTRUCTION DEBRIS.
5. PROVIDE FIRE DEPARTMENT ACCESS TO BUILDINGS
DURING CONSTRUCTION.
6. SEE LOGISTICS TRANSPORTATION HUB DRAWINGS
FOR PHASING INFORMATION AT B500.
7. FOR FULL EXTENTS OF AREAS OF WORK, SEE CIVIL
DEMOLITION PLANS.
8. CONTRACTOR SHALL NOT ENTER AREAS WHICH ARE
NOT IN CONTRACT. IF ACCESS TO THESE AREAS ARE
NEEDED, GC TO COORDINATE ACCESS WITH
CONTRACTING OFFICER REPRESENTATIVE.
9. PROVIDE TEMPORARY CONSTRUCTION BARRIERS TO
SEPARATE AREAS OF WORK FROM OTHER AREAS.
10. REFER TO THE SPECIFICATIONS AND FIRE
PROTECTION DESIGN MANUAL SECTION 1.4 FOR FIRE
PROTECTION REQUIREMENTS DURING
CONSTRUCTION.
11. USE ONLY THE CONTRACTOR'S PERSONNEL PARKING
AS INDICATED ON PHASING PLANS.
12. MAINTAIN CIRCULATION AREAS FREE OF BARRIERS
TO EMERGENCY VEHICLES.
13. MAINTAIN UTILITY SERVICES AT AND TO FACILITIES AT
ALL TIMES. IF INTERRUPTIONS ARE NECESSARY,
RECEIVE ADVANCE APPROVAL FROM COR.
14. MAINTAIN EXISTING FIRE EXITS OPEN AND FREE
FROM DEBRIS AND OBSTACLES.
15. MAINTAIN FIRE ALARM DETECTION AND SUPPRESSION
SYSTEMS. PROVIDE TEMPORARY INTERIM SYSTEMS
WHEN PERMANENT SYSTEMS CANNOT BE USED.
16. PROVIDE AND MAINTAIN PORTABLE FIRE
SUPPRESSION EQUIPMENT WHERE REQUIRED.
EXISTING BUILDING
PROPERTY LINE
UNDERGROUND STORAGE TANKS
LIMITS OF WORK (ACTIVE WORK AREA)
AREA EXPECTED TO BE UNDER
CONSTRUCTION BY OTHER PROGRAM
CONTRACTOR PARKING/ STAGING/
TRAILER AREAS
NEW BUILDING
UTILITY TUNNEL CONNECTIONS
AGV (AUTOMATED GUIDED VEHICLE)
TUNNEL CONNECTIONS
PEDESTRIAN PATH ACCESS
PATH OF EGRESS
PROPOSED LOCATION OF FUTURE
EXPANSION
N TRUE
NORTH
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
A u to d e s k D o c s /0
-1
-0
V A
W
L A
-C C
C C
U P
S it e
U ti ls
R e n o o f_ B
/6
-4
.0
.A
R C
H .r v t
/2
/2
:5
:2
P
M
GI206
PHASING PLAN - PHASE 6 -
CONSTRUCTIONLEO A DALY COMPANY
LOS ANGELES, CA 90071
(213) 629-0100
NICOS KATSELLIS
WEST LA MEDICAL CENTER
SITE INFRASTRUCTURE AND
UTILITIES
WEST LOS ANGELES, CA
691-408
N/A
2.16.24
CONSTRUCTION
DOCUMENTS
550 SOUTH HOPE STREET, 27TH FLOOR
SCALE:1 : 1440
F1
SITE PLAN OVERALL - PHASE 6
SYMBOL LEGEND
GENERAL NOTES
SCALE : 1" = 120'-0"
0 120' 240'
Revisions: Date:
FOR REFERENCE ONLY
FOR REFERENCE ONLY - NOT FOR CONSTRUCTION : QUANTITIES AND DESIGNS CAN, AND LIKELY WILL, CHANGE. BY USING THESE DRAWINGS, YOU AGREE LEO A DALY IS RELEASED AND HELD HARMLESS FOR ANY AND ALL DAMAGES OR CLAIMS RELATED TO OR ARISING FROM SUCH USE
DNDN
CRAWL SPACE
ACCESS
ELEVATOR
MACHINE ROOM
124 ELEV. #1
EL101LOBBY
CRAWL SPACE
CS101
CORRIDOR
C101
LOUNGE
CONFERENCE
COST CLERK
ELECTRICAL
ROOM
STAIR #1
ST101
275' - 0"
271' - 0"
275' - 0"
271' - 0"
MEN'S STAFF
FACILITIES
SECRETARY
IT/FMS
ON-LINE
TRAINING
DIETITIAN
NSF ASSISTANT
NSF ASSISTANT
NSF CHIEF
CLINICAL ADMIN
SERVICE SYS
MGR
INTERN
DIRECTOR
CORRIDOR
C102
MECHANICAL
ELEV. #2
EL202
STAIR #2
ST102
MEN'S TOILET
122A
WOMEN'S TOILET
121A
WOMEN'S STAFF
FACILITIES
HOUSEKEEPING
MEN'S
WOMEN'S
DIETETIC
INTERNS
MAINTAIN ACCESS TO EXITS
DURING CONSTRUCTION
AREA OF NEW WORK
ELEV. #1
EL101
RECYCLE/
GARBAGE
CLEANING
SUPPLY
WOMEN'S TOILET
MEN'S TOILET
ELECTRICAL
HAZARDOUS
SUPPLY
CORRIDOR
C203
LOADING
DOCK-SOILED
LOBBY
289' - 6"
ELEV. #2
EL202
IT/FMS
FOOD SERVICE
FOREMEN
COMM. CENTER
ELECTRICAL
FOOD PREP
FOOD PREP
DRY STORAGE
NON-FOOD DRY
STORAGE
ELECTRICAL
RECEIVING
NOURISH PREP
STORAGE
216A
NOURISH PREP
TRAY ASSEMBLY
TRAY RETHERM
CART HOLDING
SUPERVISOR
TRAY LINE
CLEAN CART
TRAYLINE
COOLER
SUPERVISOR
WAREWASH
DISH WASH/ POT
WASH
SOILED/ WASH
CART
EXTERIOR
STORAGE
STAIR #1
ST201
LOADING
DOCK-CLEAN
CORRIDOR
C201
CORRIDOR
C202
STAIR #2
ST202
SHAFT
SH101
AREA OF NEW WORK
EXISTING TO REMAIN
LIMITS OF WORK (ACTIVE WORK AREA)
PATH OF EGRESS
275' - 0"
271' - 0"
275' - 0"
LOCATION OF
NEW ELEVATOR PIT
CRAWL SPACE
ACCESS
ELEVATOR
MACHINE ROOM
124 ELEV. #1
EL101LOBBY
CRAWL SPACE
CS101
CORRIDOR
C101
LOUNGE
CONFERENCE
COST CLERK
ELECTRICAL
ROOM
STAIR #1
ST101
MEN'S STAFF
FACILITIES
SECRETARY
IT/FMS
ON-LINE
TRAINING
DIETITIAN
NSF ASSISTANT
NSF ASSISTANT
NSF CHIEF
CLINICAL ADMIN
SERVICE SYS
MGR
INTERN
DIRECTOR
CORRIDOR
C102
MECHANICAL
STAIR #2
ST102
MEN'S TOILET
122A
WOMEN'S TOILET
121A
WOMEN'S STAFF
FACILITIES
HOUSEKEEPING
MEN'S
WOMEN'S
DIETETIC
INTERNS
COORDINATE NEW
AGV TUNNEL WORK
WITH WORK AT B605
EXISTING WALL
MAINTAIN ACCESS TO EXITS
DURING CONSTRUCTION
TEMPORARY CONSTRUCTION
BARRIER
289' - 6"
289' - 6"
ELEV. #1
EL101
RECYCLE/
GARBAGE
CLEANING
SUPPLY
WOMEN'S TOILET
MEN'S TOILET
ELECTRICAL
HAZARDOUS
SUPPLY
CORRIDOR
C203
LOADING
DOCK-SOILED
LOBBY
ELEV. #2
EL202
IT/FMS
FOOD SERVICE
FOREMEN
COMM. CENTER
ELECTRICAL
FOOD PREP
FOOD PREP
DRY STORAGE
NON-FOOD DRY
STORAGE
ELECTRICAL
RECEIVING
NOURISH PREP
STORAGE
216A
NOURISH PREP
TRAY ASSEMBLY
TRAY RETHERM
CART HOLDING
SUPERVISOR
TRAY LINE
CLEAN CART
TRAYLINE
COOLER
SUPERVISOR
WAREWASH
DISH WASH/ POT
WASH
SOILED/ WASH
CART
EXTERIOR
STORAGE
STAIR #1
ST201
LOADING
DOCK-CLEAN
CORRIDOR
C201
RECEIVING
STAIR #2
ST202
SHAFT
SH101
MAINTAIN ACCESS TO ROOMS
DURING CONSTRUCTION
TEMPORARY CONSTRUCTION
BARRIER. ASSURE
CONSTRUCTION DUST AND
DEPRIS IS CONTAINED AND
DOES NOT INFILTRATE
OTHER AREAS
MAINTAIN ACCESS TO EXITS
DURING CONSTRUCTION
AREA OF NEW WORK
N TRUE
NORTH
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
A u to d e s k D o c s /0
-1
-0
V A
W
L A
-C C
C C
U P
S it e
U ti ls
R e n o o f_ B
/6
-4
.0
.A
R C
H .r v t
/2
/2
:5
:3
P
M
GI207A
SUBPHASING PLAN - PHASE 7A -
KITCHEN B605 ELEVATORLEO A DALY COMPANY
LOS ANGELES, CA 90071
(213) 629-0100
NICOS KATSELLIS
WEST LA MEDICAL CENTER
SITE INFRASTRUCTURE AND
UTILITIES
WEST LOS ANGELES, CA
691-408
N/A
2.16.24
CONSTRUCTION
DOCUMENTS
550 SOUTH HOPE STREET, 27TH FLOOR
Revisions: Date:
SYMBOL LEGEND
GENERAL NOTES
SCALE: 1/16" = 1'-0"
F5
PHASING PLAN - B605 LEVEL 1
SCALE: 1/16" = 1'-0"
D5
PHASING PLAN - B605 LEVEL 2
1. PROVIDE EGRESS PATHWAYS FROM EXISTING
BUILDING EXITS AND AREAS OF NEW WORK DURING
CONSTRUCTION. PROVIDE ACCESS TO EXISTING
BUILDINGS DURING CONSTRUCTION.
2. ENSURE DUST CONTROL PLAN IS IN PLACE. SEE
SUSTAINABLE CONSTRUCTION REQUIREMENTS
SPECIFICATION.
3. PHASING IS SCHEMATIC AND NOT INTENDED TO BE
SEQUENTIAL.
4. PROTECT EXISTING BUILDING AIR INTAKES FROM
DUST AND OTHER CONSTRUCTION DEBRIS.
5. FOR FULL EXTENTS OF AREAS OF WORK, SEE
ARCHITECTURAL DEMOLITION PLANS.
6. CONTRACTOR SHALL NOT ENTER AREAS WHICH ARE
NOT IN CONTRACT. IF ACCESS TO THESE AREAS
ARE NEEDED, GC TO COORDINATE ACCESS WITH
CONTRACTING OFFICER REPRESENTATIVE.
7. PROVIDE TEMPORARY CONSTRUCTION BARRIERS
TO SEPARATE AREAS OF WORK FROM OTHER
AREAS PER SPECIFICATIONS.
8. REFER TO THE SPECIFICATIONS AND FIRE
PROTECTION DESIGN MANUAL SECTION 1.4 FOR
FIRE PROTECTION REQUIREMENTS DURING
CONSTRUCTION.
9. USE ONLY THE CONTRACTOR'S PERSONNEL
PARKING AS INDICATED ON PHASING PLANS.
10. MAINTAIN UTILITY SERVICES AT ALL TIMES. IF
INTERRUPTIONS ARE NECESSARY, RECEIVE
ADVANCE APPROVAL FROM COR.
11. MAINTAIN EXISTING FIRE EXITS OPEN AND FREE
FROM DEBRIS AND OBSTACLES.
12. MAINTAIN FIRE ALARM DETECTION AND
SUPPRESSION SYSTEMS. PROVIDE TEMPORARY
INTERIM SYSTEMS WHEN PERMANENT SYSTEMS
CANNOT BE USED.
13. PROVIDE TEMPORARY PARTITIONS THAT ARE
SMOKE-TIGHT AND FIRE RATED AS APPROPRIATE.
14. PROVIDE AND MAINTAIN PORTABLE FIRE
SUPPRESSION EQUIPMENT.
SCALE: 1/16" = 1'-0"
F1
PHASING PLAN - B605 EXISTING LEVEL 1
SCALE: 1/16" = 1'-0"
D1
PHASING PLAN - B605 EXISTING LEVEL 2
FOR REFERENCE ONLY
FOR REFERENCE ONLY - NOT FOR CONSTRUCTION : QUANTITIES AND DESIGNS CAN, AND LIKELY WILL, CHANGE. BY USING THESE DRAWINGS, YOU AGREE LEO A DALY IS RELEASED AND HELD HARMLESS FOR ANY AND ALL DAMAGES OR CLAIMS RELATED TO OR ARISING FROM SUCH USE
S T
OP
STOP
STOP
BUMP
BUMP
V .A
B
U S O
N L Y
P A
T
IE
N T
-V A
N
PED PED
XING XING
BUMP
BU M
P
ENTER
M O
T O
R C
Y C
L E
S O
N L
Y
H C
H C
H C
H C
H C
H C
H C
STOP
STOP
STOP
STOP
STOP
STOP
STOP
STOP
BUMP
BUMP
KEEP
CLEAR
STOP
HC
NO
PA
RKING
HC
NO
PA
RKING
NO
P
A
RK
IN
G
NO
PA
RKING
NO
PA
RKING
NO
P
A
RK
IN
G
NO
P
A
RK
IN
G
PARKING
NO
PARKINGPARKINGPARKING
PARKING PARKING PARKINGNO NO NO
NONONO
PARKING
NO
FI R E LA N E
PARKINGPARKINGPARKINGPARKINGPARKINGPARKINGPARKING
PARKING
NO
NONONONONONONO
NO PARKINGNO PARKING
FIRE LANE
BUMP
BUMP
STOP
S T
OP
S T
OP
S T
OP
STOPSTOP
STOP
STO
P
HCHC
S
TO
P S
T O
P
HC
STOP
HC
YI ELD
N O
PA
R
KI
NG
N O
PA
R
KI
NG
N O
PA
R
KI
NG
V A N
V A N
VAN
VAN VAN
VANVAN
VANVANVAN
VANVANVAN
VAN
278.69
BFP/3"IP
S T
OP
HCHC HC HC HC HC HCHCHCHCHCHCHCHCHCHC
NO PARKING NO PARKINGNO PARKING
PED
STOP
STO
P
STOP
D
E
D
D
E
D
D
D
E
D
D
E
E
E
D
D
D
E D
D
D
D
D
D
D
D D
D
D
D
D
1. PROVIDE EGRESS ACCESS FROM EXISTING BUILDING
EXITS AND AREAS OF NEW WORK DURING
CONSTRUCTION.
2. PHASING IS SCHEMATIC AND NOT INTENDED TO BE
SEQUENTIAL
3. ENSURE DUST CONTROL PLAN IS IN PLACE. SEE
SUSTAINABLE CONSTRUCTION REQUIREMENTS
SPECIFICATION.
4. PROTECT EXISTING BUILDING AIR INTAKES FROM
DUST AND OTHER CONSTRUCTION DEBRIS.
5. PROVIDE FIRE DEPARTMENT ACCESS TO BUILDINGS
DURING CONSTRUCTION.
6. SEE LOGISTICS TRANSPORTATION HUB DRAWINGS
FOR PHASING INFORMATION AT B500.
7. FOR FULL EXTENTS OF AREAS OF WORK, SEE CIVIL
DEMOLITION PLANS.
8. CONTRACTOR SHALL NOT ENTER AREAS WHICH ARE
NOT IN CONTRACT. IF ACCESS TO THESE AREAS ARE
NEEDED, GC TO COORDINATE ACCESS WITH
CONTRACTING OFFICER REPRESENTATIVE.
9. PROVIDE TEMPORARY CONSTRUCTION BARRIERS TO
SEPARATE AREAS OF WORK FROM OTHER AREAS.
10. REFER TO THE SPECIFICATIONS AND FIRE
PROTECTION DESIGN MANUAL SECTION 1.4 FOR FIRE
PROTECTION REQUIREMENTS DURING
CONSTRUCTION.
11. USE ONLY THE CONTRACTOR'S PERSONNEL PARKING
AS INDICATED ON PHASING PLANS.
12. MAINTAIN CIRCULATION AREAS FREE OF BARRIERS
TO EMERGENCY VEHICLES.
13. MAINTAIN UTILITY SERVICES AT AND TO FACILITIES AT
ALL TIMES. IF INTERRUPTIONS ARE NECESSARY,
RECEIVE ADVANCE APPROVAL FROM COR.
14. MAINTAIN EXISTING FIRE EXITS OPEN AND FREE
FROM DEBRIS AND OBSTACLES.
15. MAINTAIN FIRE ALARM DETECTION AND SUPPRESSION
SYSTEMS. PROVIDE TEMPORARY INTERIM SYSTEMS
WHEN PERMANENT SYSTEMS CANNOT BE USED.
16. PROVIDE AND MAINTAIN PORTABLE FIRE
SUPPRESSION EQUIPMENT WHERE REQUIRED.
EXISTING BUILDING
PROPERTY LINE
UNDERGROUND STORAGE TANKS
LIMITS OF WORK (ACTIVE WORK AREA)
AREA EXPECTED TO BE UNDER
CONSTRUCTION BY OTHER PROGRAM
CONTRACTOR PARKING/ STAGING/
TRAILER AREAS
NEW BUILDING
UTILITY TUNNEL CONNECTIONS
AGV (AUTOMATED GUIDED VEHICLE)
TUNNEL CONNECTIONS
PEDESTRIAN PATH ACCESS
PATH OF EGRESS
PROPOSED LOCATION OF FUTURE
EXPANSION
PHASE 7 - CONSTRUCTION
7.a MOVE INPATIENT PROGRAMS FROM B500 TO B600..
7.a
KITCHEN
LOADING DOCK
D O
W L E
N D
R I V
E
D O
W L
E N
D R
LOADING
DOCKB601
LTH
B600
CCC
B602
CUP
LOT A
LOT B
LOT 6
LOT 6
B608
PARKING
GARAGE
LOT F
B500
HOPSPITAL
B304
B402 B401
B345
A.R.C.
B507
B522
B318
B312 B311
B23 B307
B308
B309
B91
B90
B104
B310
U.S. ARMY
CALIFORNIA
NATIONAL GUARD
U.S. AIR FORCE
PROPERTY
B105
LOT D
EDISON
SUBSTATION
LOT 5
B607
PATRIOT
HOUSE
B606
FISHER HOUSE
B605
KITCHEN
B603
BOILER
METRO STATION
SUBSTATION
LOT 42
B501
CUP
HELIPADHELIPAD
LOT C
N TRUE
NORTH
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
A u to d e s k D o c s /0
-1
-0
V A
W
L A
-C C
C C
U P
S it e
U ti ls
R e n o o f_ B
/6
-4
.0
.A
R C
H .r v t
/2
/2
:5
:3
P
M
GI207
PHASING PLAN - PHASE 7 -
CONSTRUCTIONLEO A DALY COMPANY
LOS ANGELES, CA 90071
(213) 629-0100
NICOS KATSELLIS
WEST LA MEDICAL CENTER
SITE INFRASTRUCTURE AND
UTILITIES
WEST LOS ANGELES, CA
691-408
N/A
2.16.24
CONSTRUCTION
DOCUMENTS
550 SOUTH HOPE STREET, 27TH FLOOR
SYMBOL LEGEND
GENERAL NOTES
SCALE : 1" = 120'-0"
0 120' 240'
Revisions: Date:
SCALE:1 : 1440
F1
SITE PLAN OVERALL - PHASE 7
FOR REFERENCE ONLY
FOR REFERENCE ONLY - NOT FOR CONSTRUCTION : QUANTITIES AND DESIGNS CAN, AND LIKELY WILL, CHANGE. BY USING THESE DRAWINGS, YOU AGREE LEO A DALY IS RELEASED AND HELD HARMLESS FOR ANY AND ALL DAMAGES OR CLAIMS RELATED TO OR ARISING FROM SUCH USE
S T
OP
STOP
STOP
BUMP
BUMP
V .A
B
U S O
N L Y
P A
T
IE
N T
-V A
N
PED PED
XING XING
BUMP
BU M
P
ENTER
M O
T O
R C
Y C
L E
S O
N L
Y
H C
H C
H C
H C
H C
H C
H C
STOP
STOP
STOP
STOP
STOP
STOP
STOP
STOP
BUMP
BUMP
KEEP
CLEAR
STOP
HC
NO
PA
RKING
HC
NO
PA
RKING
NO
P
A
RK
IN
G
NO
PA
RKING
NO
PA
RKING
NO
P
A
RK
IN
G
NO
P
A
RK
IN
G
PARKING
NO
PARKINGPARKINGPARKING
PARKING PARKING PARKINGNO NO NO
NONONO
PARKING
NO
FI R E LA N E
PARKINGPARKINGPARKINGPARKINGPARKINGPARKINGPARKING
PARKING
NO
NONONONONONONO
NO PARKINGNO PARKING
FIRE LANE
BUMP
BUMP
STOP
S T
OP
S T
OP
S T
OP
STOPSTOP
STOP
STO
P
HCHC
S
TO
P S
T O
P
HC
STOP
HC
YI ELD
N O
PA
R
KI
NG
N O
PA
R
KI
NG
N O
PA
R
KI
NG
V A N
V A N
VAN
VAN VAN
VANVAN
VANVANVAN
VANVANVAN
VAN
278.69
BFP/3"IP
S T
OP
HCHC HC HC HC HC HCHCHCHCHCHCHCHCHCHC
NO PARKING NO PARKINGNO PARKING
PED
STOP
STO
P
STOP
D
E
D
D
E
D
D
D
E
D
D
E
E
E
D
D
D
E D
D
D
D
D
D
D
D D
D
D
D
D x xx x xx xxx x x x x x x x x x x x x x x x x x x x x x x x x xx xx xx x x x x x x xx x x i i i ii x x x x x x x x x x x x xx x x x x x x x x x x x x x
1. PROVIDE EGRESS ACCESS FROM EXISTING BUILDING
EXITS AND AREAS OF NEW WORK DURING
CONSTRUCTION.
2. PHASING IS SCHEMATIC AND NOT INTENDED TO BE
SEQUENTIAL
3. ENSURE DUST CONTROL PLAN IS IN PLACE. SEE
SUSTAINABLE CONSTRUCTION REQUIREMENTS
SPECIFICATION.
4. PROTECT EXISTING BUILDING AIR INTAKES FROM
DUST AND OTHER CONSTRUCTION DEBRIS.
5. PROVIDE FIRE DEPARTMENT ACCESS TO BUILDINGS
DURING CONSTRUCTION.
6. SEE LOGISTICS TRANSPORTATION HUB DRAWINGS
FOR PHASING INFORMATION AT B500.
7. FOR FULL EXTENTS OF AREAS OF WORK, SEE CIVIL
DEMOLITION PLANS.
8. CONTRACTOR SHALL NOT ENTER AREAS WHICH ARE
NOT IN CONTRACT. IF ACCESS TO THESE AREAS ARE
NEEDED, GC TO COORDINATE ACCESS WITH
CONTRACTING OFFICER REPRESENTATIVE.
9. PROVIDE TEMPORARY CONSTRUCTION BARRIERS TO
SEPARATE AREAS OF WORK FROM OTHER AREAS.
10. REFER TO THE SPECIFICATIONS AND FIRE
PROTECTION DESIGN MANUAL SECTION 1.4 FOR FIRE
PROTECTION REQUIREMENTS DURING
CONSTRUCTION.
11. USE ONLY THE CONTRACTOR'S PERSONNEL PARKING
AS INDICATED ON PHASING PLANS.
12. MAINTAIN CIRCULATION AREAS FREE OF BARRIERS
TO EMERGENCY VEHICLES.
13. MAINTAIN UTILITY SERVICES AT AND TO FACILITIES AT
ALL TIMES. IF INTERRUPTIONS ARE NECESSARY,
RECEIVE ADVANCE APPROVAL FROM COR.
14. MAINTAIN EXISTING FIRE EXITS OPEN AND FREE
FROM DEBRIS AND OBSTACLES.
15. MAINTAIN FIRE ALARM DETECTION AND SUPPRESSION
SYSTEMS. PROVIDE TEMPORARY INTERIM SYSTEMS
WHEN PERMANENT SYSTEMS CANNOT BE USED.
16. PROVIDE AND MAINTAIN PORTABLE FIRE
SUPPRESSION EQUIPMENT WHERE REQUIRED.
EXISTING BUILDING
PROPERTY LINE
UNDERGROUND STORAGE TANKS
LIMITS OF WORK (ACTIVE WORK AREA)
AREA EXPECTED TO BE UNDER
CONSTRUCTION BY OTHER PROGRAM
CONTRACTOR PARKING/ STAGING/
TRAILER AREAS
NEW BUILDING
UTILITY TUNNEL CONNECTIONS
AGV (AUTOMATED GUIDED VEHICLE)
TUNNEL CONNECTIONS
PEDESTRIAN PATH ACCESS
PATH OF EGRESS
PROPOSED LOCATION OF FUTURE
EXPANSION
PHASE 8 - CONSTRUCTION
8.a RELOCATION OF INPATIENT PROGRAMS TO B600 IS COMPLETE.
RENOVATE INTERIORS AT B500.
8.b CONSTRUCT NORTH VEHICULAR GUARD HOUSE AND CHECK
POINT.
8.c CONSTRUCT SOUTH VEHICULAR GUARD HOUSE AND CHECK
POINT.
8.d DEMOLISH TEMPORARY PARKING LOT AND CONSTRUCT
DETENTION BASIN.
8.f COMPLETE PERIMETER SECURITY FENCE.
KITCHEN
LOADING DOCK
D O
W L E
N D
R I V
E
D O
W L
E N
D R
8.d
LOADING
DOCKB601
LTH
B600
CCC
B602
CUP
LOT A
LOT B
LOT 6
LOT 6
B608
PARKING
GARAGE
LOT F
B500
HOPSPITAL
B304
B402 B401
B345
A.R.C.
B507
B522
B318
B312 B311
B23 B307
B308
B309
B91
B90
B104
B310
U.S. ARMY
CALIFORNIA
NATIONAL GUARD
U.S. AIR FORCE
PROPERTY
B105
LOT D
EDISON
SUBSTATION
LOT 5
B607
PATRIOT
HOUSE
B606
FISHER HOUSE
B605
KITCHEN
B603
BOILER
METRO STATION
SUBSTATION
LOT 42
B501
CUP
HELIPADHELIPAD
8.b
8.c 8.f
8.g 8.a
8.a
N TRUE
NORTH
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
A u to d e s k D o c s /0
-1
-0
V A
W
L A
-C C
C C
U P
S it e
U ti ls
R e n o o f_ B
/6
-4
.0
.A
R C
H .r v t
/2
/2
:5
:3
P
M
GI208
PHASING PLAN - PHASE 8 -
CONSTRUCTIONLEO A DALY COMPANY
LOS ANGELES, CA 90071
(213) 629-0100
NICOS KATSELLIS
WEST LA MEDICAL CENTER
SITE INFRASTRUCTURE AND
UTILITIES
WEST LOS ANGELES, CA
691-408
N/A
2.16.24
CONSTRUCTION
DOCUMENTS
550 SOUTH HOPE STREET, 27TH FLOOR
SYMBOL LEGEND
GENERAL NOTES
SCALE : 1" = 120'-0"
0 120' 240'
Revisions: Date:
SCALE:1 : 1440
F1
SITE PLAN OVERALL - PHASE 8
FOR REFERENCE ONLY
FOR REFERENCE ONLY - NOT FOR CONSTRUCTION : QUANTITIES AND DESIGNS CAN, AND LIKELY WILL, CHANGE. BY USING THESE DRAWINGS, YOU AGREE LEO A DALY IS RELEASED AND HELD HARMLESS FOR ANY AND ALL DAMAGES OR CLAIMS RELATED TO OR ARISING FROM SUCH USE
| Sheets |
| GI201 - PHASING PLAN - PHASE 1 - MAKE READY |
| GI202 - PHASING PLAN - PHASE 2 - CONSTRUCTION |
| GI203 - PHASING PLAN - PHASE 3 - CONSTRUCTION |
| GI204 - PHASING PLAN - PHASE 4 - CONSTRUCTION |
| GI205 - PHASING PLAN - PHASE 5 - CONSTRUCTION |
| GI206 - PHASING PLAN - PHASE 6 - CONSTRUCTION |
| GI207 - PHASING PLAN - PHASE 7 - CONSTRUCTION |
| GI207A - SUBPHASING PLAN - PHASE 7A - KITCHEN B605 ELEVATOR |
| GI208 - PHASING PLAN - PHASE 8 - CONSTRUCTION |
File details come from the government source that posted it. Updated .