View the file

Other files

File Type Posted
Am12_W912PL-12-R-0019.pdf PDF
Am11_W912PL-12-R-0019.pdf PDF
Am10_W912PL-12-R-0019.pdf PDF
Am8_W912PL-12-R-0019.pdf PDF
Am7_W912PL-12-R-0019.pdf PDF
Am6_W912PL-12-R-0019_Drawings.zip ZIP file
Am6_W912PL-12-R-0019_Specs.pdf PDF
Am5_W912PL-12-R-0019.pdf PDF
Am4_W912PL-12-R-0019.pdf PDF
Am3_W912PL-12-R-0019.pdf PDF
Am2_Spec_W912PL12R0019.pdf PDF
Am2_Drwgs_W912PL12R0019.pdf PDF
Am1_W912PL12R0019.pdf PDF
Dwgs1_Cover_Architectural_Misc.zip ZIP file
Spec_W912PL12R0019.pdf PDF
Dwgs3_Plumbing_Electrical.zip ZIP file
Dwgs2_Structural_HVAC.zip ZIP file
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICIATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPIRATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc. ) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION ( Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

1 97

0009 Jun 25, 2012

USACE, Los Angeles District Contracting Division, West Region branch 915 Wilshire Bl,14th Floor P.O. Box 532711 Los Angeles, CA 90053-2325

W912PL-12-R-0019

May 6, 2012

664-325 Expand Renovate Research Labs, VA San Diego Healthcare System, San Diego County, California.

The following Sections are amended with attached: Table of Contents; 01 00 00 General Requirements and Construction Signs and Forms.

The following Sections are replaced entirely with attached: 00110 Submission Requirements;

00120 Proposal Evaluation and Contract Award.

INSTRUCTIONS

Instructions for items other than those that are self-explanatory, are as follows:

Item 1 (Contract ID Code) . Insert the contract type identification code that appears in the title block of the contract being modified.

Item 3 (Effective date) .

(1)

(2)

(3)

(4)

(5)

For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.

For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.

For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.

For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.

For a modification confirming the contacting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.

(a)

(b)

(c)

(d)

(e)

(f)

Item 6 (Issued By) . Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.

Item 8 (Name and Address of Contractor) . For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.

Item 9, (Amendment of Solicitation No. - Dated), and 10, (Modification of Contract/Order No. - Dated ). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.

Item 12 (Accounting and Appropriation Data) .

When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries.

(2) Accounting classification Net decrease $

Include subject matter or short title of solicitation/contract where feasible.

Item 16B . The contracting officer's signature is not required on solicitation amendments. The contracting offier's signature is normally affixed last on supplemental agreements.

(i)

NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".

Item 13 . Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)

Item 14 (Description of Amendment/Modification) .

Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:

Total contract price increased by $

Total contract price decreased by $

Total contract price unchanged.

State reason for modification.

When removing, reinstating, or adding funds, identify the contract items and accounting classifications.

When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --

A reference to the letter determination; and

A statement of the net amount determined to be due in settlement of the contract.

(g)

(h)

(i)

(ii)

(1)

(2)

(3)

(4)

(5)

(6)

(i)

(ii)

(iii)

STANDARD FORM 30 (REV. 10-83) BACK

(1) Accounting classification Net increase $

664-325, Expand Renovate Research Labs W912PL-12-R-0019 VA San Diego Healthcare System San Diego County, CA

TABLE OF CONTENTS - 1

Amendment 9

TABLE OF CONTENTS

Section Title Amend#

DIVISION 00 – BIDDING REQUIREMENTS, CONTRACT FORMS AND CONTRACT CONDITIONS

Cover 664-325 EXPAND RENOVATE RESEARCH LABS

TOC Table of Contents (Am9) LOD List of Drawings (Am6) SF1442 Solicitation, Offer and Award (Am8)

00 010 Price Schedule 00 100 Instructions to Bidders (Am1) 00 110 Proposal Submission and Instruction (Am9) 00 120 Proposal Evaluation and Contract Award (Am9) 00 600 Representations and Certifications 00 700 Contract Clauses 00 800 Special Contract Requirements (Am6) 00 850 Wage Rates (Am6)

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements & Construction Signs & Forms (Am9) 01 00 01 Infection Control during Construction 01 00 02 VA Construction Standard 01 00 11 Special Requirements 01 21 00 GEMS Evaluation Survey 01 27 00 Measurement and Payment (Am6)

01 32 01 Project Schedule (Am6) 01 32 17 Network Analysis Schedules 01 33 00 Construction Submittal Procedures (Am6) 01 33 00a Submittal Register 01 33 23 Samples and Shop Drawings 01 35 26 Government Safety Requirements

01 42 19 Reference Standards 01 45 02 Quality Control System 01 45 10 Contractor Quality Control (Am6) 01 45 29 Testing Laboratory Services (Am6) 01 50 02 Temporary Construction Facilities 01 56 39 Temporary Tree and Plant Protection

01 56 80 Environmental Safety and Protection (Am6) 01 57 20 Environmental Protection 01 57 23 Storm Water Pollution Measures 01 58 16 Interior Signage 01 58 17 Exterior Signage 01 74 19 Construction Waste Management 01 74 19 Waste Debris Management Plan Spreadsheet (Am2) 01 78 00 Closeout Submittals 01 91 00 DELETED (Am7)

TABLE OF CONTENTS - 2

Section Title Amend#

DIVISION 02 – EXISTING CONDITIONS

02 41 00 DEMOLITION

02 82 11 CLASS I NEGATIVE PRESSURE ENCLOSURE ASBESTOS

ABATEMENT

DIVISION 03 – CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE

DIVISION 04 – MASONRY- NOT USED

DIVISION 05 – METALS

05 12 00 STRUCTURAL STEEL FRAMING

05 31 00 STEEL DECKING

05 36 00 COMPOSITE METAL DECKING

05 50 00 METAL FABRICATION

DIVISION 06 – WOOD,PLASTICS AND COMPOSITES

06 10 00 ROUGH CARPENTRY

06 20 00 FINISH CARPENTRY AND MILLWORK

DIVISION 07 THERMAL AND MOISTURE PROTECTION

07 21 13 THERMAL INSULATION

07 22 00 ROOF AND DECK INSULATION

07 54 19 POLYVINYL CHLORIDE ROOFING

07 54 23 THERMOPLASTIC POLYOLEFIN (TPO) ROOFING (Am3)

07 60 00 FLASHING AND SHEET METAL

07 81 05 SPRAYED-ON FIREPROOFING

07 84 00 FIRESTOPPING

07 92 00 SEALANTS AND CAULKING

DIVISION 08 OPENINGS

08 11 15 STEEL DOORS AND FRAMES AND STEEL WINDOW FRAME

08 21 00 WOOD DOORS (Am6)

08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS

08 44 13 GLAZED ALUMINUM CURTAIN WALLS

08 61 50 MANUAL SLIDING INTENSIVE CARE UNIT (ICU) DOORS

08 61 60 BIFOLDING INTENSIVE CARE UNIT (ICU) DOORS

08 71 00 DOOR HARDWARE

08 71 16 ELECTRO-MECHANICAL SWINGING DOOR OPERATORS

08 75 00 INSTALLATION OF DOORS AND HARDWARE

08 80 00 GLAZING

TABLE OF CONTENTS - 3

Section Title Amend#

DIVISION 09 – FINISHES

09 06 00 COLOR AND DESIGN

09 22 16 NON-STRUCTURAL FRAMING SYSTEMS

09 29 00 GYPSUM BOARD

09 30 13 CERAMIC TILING

09 51 00 ACOUSTICAL CEILING

09 65 16 RESILIENT SHEET FLOORING

09 68 20 CARPETING (WITHOUT CUSHION)

09 91 00 PAINTING

DIVISION 10 – SPECIALTIES

10 14 00 SIGNAGE

10 21 13 TOILET COMPARTMENTS

10 28 00 TOILET ACCESSORIES

10 28 25 PRE-FABRICATED SHOWER ENCLOSURES

10 44 13 FIRE EXTINGUISHER CABINETS

10 51 23 PLASTIC LAMINATE LOCKERS

DIVISION 11 – EQUIPMENT

11 53 13 LABORATORY FUME HOODS

11 72 11 WALK-IN COOLERS AND FREEZERS

11 72 14 LABORATORY CONTOLLED COLD ROOM OR WARM ROOMS

DIVISION 12 – FURNISHINGS

12 31 00 METAL CASEWORK

12 32 00 WOOD CASEWORK

12 34 63 ADAPTABLE LABORATORY FURNITURE SYSTEM

12 34 64 BENCH TOP UPRIGHT SYSTEM

12 34 66 WALL RAIL SYSTEM

DIVISION 13 - SPECIAL CONSTRUCTION – NOT USED

DIVISION 14– CONVEYING EQUIPEMENT – NOT USED

DIVISION 21- FIRE SUPPRESSION

21 05 11 COMMON WORK RESULTS FOR FIRE SUPPRESSION

21 13 13 WET-PIPE SPRINKLER SYSTEMS

TABLE OF CONTENTS - 4

Section Title Amend#

DIVISION 22 – PLUMBING

22 05 11 COMMON WORK RESULTS FOR PLUMBING

22 05 12 GENERAL MOTOR REQUIREMENTS FOR PLUMBING EQUIPMENT

22 05 19 METERS AND GAGES FOR PLUMBING PIPING

22 11 00 FACILITY WATER DISTRIBUTION

22 13 00 FACILITY SANITARY AND VENT PIPING

22 15 00 GENERAL SERVICE COMPRESSED-AIR SYSTEMS

22 40 00 PLUMBING FIXTURES

22 62 00 VACUUM SYSTEMS FOR LABORATORY AND HEALTHCARE FACILITIES

22 63 00 GAS SYSTEMS FOR LABORATORY AND HEALTHCARE FACILITIES

22 66 00 CHEMICAL-WASTE SYSTEMS FOR LABORATORY AND HEALTHCARE

FACILITIES

22 77 19 TYPE 2 WATER PURIFICATION SYSTEM

DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 05 11 COMMON WORK RESULTS FOR HVAC AND STEAM GENERATION

23 05 12 GENERAL MOTOR REQUIREMENTS FOR HVAC AND STEAM GENERATION

EQUIPMENT

23 05 41 NOISE AND VIBRATION CONTROL FOR HVAC PIPING AND EQUIPMENT

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 09 23 DIRECT -DIGITAL CONTROL SYSTEM FOR HVAC

23 11 23 FACILITY NATURAL-GAS PIPING

23 21 13 HYDRONIC PIPING

23 22 13 STEAM AND CONDENSATE HEATING PIPING

23 25 00 HVAC WATER TREATMENT

23 31 00 HVAC DUCTS AND CASINGS

23 34 00 HVAC FANS

23 36 00 AIR TERMINAL UNITS

23 37 00 AIR OUTLETS AND INLETS

23 40 00 HVAC AIR CLEANING DEVICES

23 73 00 INDOOR CENTRAL-STATION AIR-HANDLING UNITS

23 74 13 PACKAGED, OUTDOOR, CENTRAL-STATION AIR HANDLING UNITS

23 82 16 AIR COILS

DIVISION 25 – INTEGRATED AUTOMATION – NOT USED

DIVISION 26 – ELECTRICAL

26 05 11 REQUIREMENTS FOR ELECTRICAL INSTALLATIONS

26 05 21 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

(600 VOLTS AND BELOW)

26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

26 05 33 RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS

26 24 16 PANELBOARDS

26 27 26 WIRING DEVICES

26 29 21 DISCONNECT SWITCHES

TABLE OF CONTENTS - 5

Section Title Amend#

DIVISION 26 – ELECTRICAL - CONTINUED

26 51 00 INTERIOR LIGHTING

DIVISION 27 – COMMUNICATIONS

27 05 11 REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS

27 31 31 VOICE COMMUNICATIONS SWITCHING AND ROUTING

EQUIPMENT – EXTENSION

27 54 81 OFFICE OF INFORMATION & TECHNOLOGY (OI&T) CABLING

STANDARDS AND CRITERIA (Am3)

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY – NOT USED

DIVISION 31 – EARTHWORK – NOT USED

DIVISION 32 – EXTERIOR IMPROVEMENTS – NOT USED

DIVISION 33 – UTILITIES – NOT USED

End of Table of Contents

00110 - 1

AMENDMENT 09

SECTION 00110

SUBMISSION REQUIREMENTS AND INSTRUCTIONS

1.1. GENERAL SUBMISSION REQUIREMENTS

1.2. GENERAL INSTRUCTIONS:

1.3. WHERE TO SUBMIT:

1.4. SUBMISSION DEADLINE:

1.5 PROPOSAL COVER SHEET:

1.6. SPECIFIC INSTRUCTIONS FOR THE PRICE PROPOSAL (VOLUME I):

1.7 SPECIFIC INSTRUCTIONS FOR THE TECHNICAL PROPOSAL (VOLUME II):

1.8 REQUIRED DATA FOR TECHNICAL PROPOSAL SUBMISSION

00110 - 2

SECTION 00110

SUBMISSION REQUIREMENTS AND INSTRUCTIONS

1.1. GENERAL SUBMISSION REQUIREMENTS

1.1.1. In order to effectively and equitably evaluate all offers, the Contracting Officer must receive information sufficiently detailed that clearly responds to all the solicitation requirements, including but not limited to the technical and price proposal submission requirements.

1.1.2. Each Offeror must submit both a Technical Proposal and a Price Proposal. The Technical Proposal and a Price Proposal must be submitted as separate, physically distinct volumes. Both the Technical Proposal and a Price Proposal must be received by the closing date and time set for receipt of proposals.

1.1.3. No dollar amounts and/or price information from the Price Proposal are to be included in the Technical Proposal.

1.1.4. All information intended by the Offeror to be evaluated as part of the Technical Proposal must be submitted as part of the Technical Proposal. Do not merely cross-reference similar material from the Price Proposal.

1.2. GENERAL INSTRUCTIONS:

1.2.1. All written portions: Use only 8 ½ by 11 inch paper, unless another size is specifically authorized elsewhere in this section. Do not use a font size smaller than 10, an unusual font style such as script, or condensed print.

1.2.2. Three-ring binders are preferred. Do not use spring clamps or exceed the recommended capacity of the fastener or binder.

1.2.3. “Confidential” projects cannot be submitted to demonstrate capability unless all of the information required for evaluation as specified herein can nonetheless be provided to the Government as part of the Offeror’s technical proposal. Offerors that include in their proposals information that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, must be clearly marked in accordance with the instructions at FAR 52.215-1, “Instructions to Offeror—Competitive Acquisition”, paragraph (3), “Restriction on disclosure and use of data”.

1.2.4. The Corps of Engineers recognizes that submittals by the Offeror may contain confidential or proprietary information; however, the Government reserves the right to make inquiries into the information disclosed. The submission of false or misleading information may be grounds for disqualification of the proposal.

1.3. WHERE TO SUBMIT:

1.3.1. Offeror(s) shall submit their proposal packages to the Los Angeles District Corps of Engineers (COE) as directed in Section 00100.

1.4. SUBMISSION DEADLINE:

1.4.1. Offers shall be received by the Los Angeles District COE no later than the time and date specified on the SF-1442, Block 13A, as amended.

00110 - 3

1.5 PROPOSAL COVER SHEET:

1.5.1. Format for the Proposal Cover Sheet: The proposal cover sheet is required by FAR 52.215- 1(c)(2). This provision, titled “Instructions to Offerors—Competitive Acquisition,” has been provided in full text in Section 00100.

A summary of the format is as follows:

PROPOSAL COVER SHEET

1. Solicitation Number:

2. The name, address, and telephone and facsimile numbers of the Offeror and electronic address (if available):

3. A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item.

4. Names, titles, and telephone and facsimile numbers (and electronic addresses if available) of persons authorized to negotiate on the Offeror’s behalf with the Government in connection with this solicitation:

5. Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent’s authority, unless that evidence has been previously furnished to the issuing office.

1.6. SPECIFIC INSTRUCTIONS FOR THE PRICE PROPOSAL (VOLUME I):

1.6.1. Number of Sets of the Price Proposal: Submit the original and one copy.

1.6.2. Format and Contents of the Price Proposal/List of Tabs: The Price Proposal shall be appropriately labeled as such and shall be organized as indicated in the following chart.

TAB CONTENTS OF THE PRICE PROPOSAL

TAB #1

From Section 00010: SF 1442, entitled “Solicitation, Offer and Award” front and back; Certificate of Corporate Principal, completed as applicable, including corporate seal, if any.

TAB #2

From Section 00010: Pricing Schedule, completed with the Offeror’s proposed contract line item prices inserted in the appropriate spaces.

TAB #3

Bid Guarantee, executed as per FAR 28. 101 and clause FAR 52.228-1 (Standard Form

SF-24)

TAB #4 Section 00600 entitled, “Representations and Certifications,” completed as applicable

TAB #5

If the Offeror is a Joint Venture (JV), include a copy of the JV Agreement. If the JV is competing as an 8(a) concern, indicate if the JV Agreement has been approved by the Small Business Administration. If so, furnish documentation thereof.

00110 - 4

1.7 SPECIFIC INSTRUCTIONS FOR THE TECHNICAL PROPOSAL (VOLUME II):

1.7.1. Number of Sets of the Technical Proposal: Submit the original and 5 copies of the written Technical Proposal. In addition, submit complete copy of the technical proposal on Compact Disk (CD) using a searchable “.pdf” file format. The Technical Proposal shall be in 8-1/2” x 11” format, bound as a single document, with single-sided or double-sided pages being acceptable. Condensed print is not permitted. The Proposals shall be separated with section tabs, and the tabs shall clearly identify the contents of each section. Maximum number of pages for Technical Proposal is fifty (50). Each page shall be sequentially numbered for that section. Pages from the Owner/Client Past Performance Survey will not count against the page limit. Information on surveys will solely be used for evaluation in Factor #2, Past Performance.

1.7.1.1. Format and Contents of the Technical Proposal/List of Tabs: The original and all copies of the technical proposal will be appropriately labeled as such. Each set shall be organized using the tabs specified in the following chart. The main tabs directly correlate to the evaluation factors identified in Section 00120.

1.7.1.2. Detailed Submission Requirements for the Technical Proposal: A detailed description of the information to be submitted under each of the above tabs follows.

TAB CONTENTS OF THE TECHNICAL PROPOSAL

TAB #1

TECHNICAL NARRATIVE ON THE FOLLOWING: EXPERIENCE ON

SIMILAR PROJECTS, SPECIFICALLY ON HOSPITAL AND/OR CLINIC

ENVIRONMENT; INFECTION CONTROL PROCESSES

TAB #2 PAST PERFORMANCE ON SIMILAR PROJECTS, SPECIFICALLY ON

HOSPITAL AND/OR CLINIC ENVIRONMENTS.

TAB #3 TECHNICAL APPROACH, METHODS AND PROCEDURES AND

SCHEDULE

TAB #4

TECHNICAL NARRATIVE ON THE FOLLOWING:

CORPORATE/MANAGEMENT STRUCTURE; CAPABILITY TO MANAGE

AND CONTROL PROJECTS; KEY PERSONNEL; PRESENT WORKLOAD

1.8 REQUIRED DATA FOR TECHNICAL PROPOSAL SUBMISSION: See attached formats at end of this section and Section 00120, List of Evaluation Factors, for more details.

00110 - 5

PROJECT EXPERIENCE FORM

(TAB 1)

Control No.: W912PL-12-R-0019

OFFEROR’S NAME: ____________________________________________________________

Provide a completed form for each project for which experience is being claimed.

Experience provided for (check more than one box if applicable):

[ ] Offeror: ____________________________________________________________________

[ ] Key Construction Subcontractor:_________________________________________________

Was project a firm-fixed-price contract (Y/N)? ____ If No, what type was it?

Project Name: __________________________________________________________________

Project Location:________________________________________________________________

Owner/Client: __________________________________________________________________

For this project for which experience is being claimed, firm(s) worked as the [ ] prime contractor; or [ ] Subcontractor. If experience is provided for more than one firm, check more than one box as appropriate for each firm listed.

Brief description of project (Include, as applicable, how project is similar in scope and magnitude to the work required in this RFP)

00110 - 6

Construction Contract Amount or Design Fee (for Designer): ________________________

Original Contract Completion Date: ________________________

Final Contract Completion Date: ________________________

Actual Completion Date: ________________________

Percent of Completion (if project is currently under construction) _________________________

Explanation of any Late Finish:

Was the project terminated early or were cure/show cause letters received? ___Yes ___No

Explain early termination (default/convenience) or cure/show cause letters

Safety record: ____Injuries with Lost Workdays*, ____Injuries without Lost Workdays* (*Use the number reported on OSHA Form No. 200 or equivalent)

List and explain any customer concerns or dissatisfaction. Explain how you responded.

SMALL BUSINESS SUBCONTRACTING (Complete for Offeror (Prime Contractor) only):

Large Business Offerors Only: What were the various small business percentage goals in the original contract, if applicable (see FAR 52.219-9)? SDB: _______ WOB: _______ Small Business: _______ Veteran-owned: _______ HUBZone: _______

What was the actual percent achieved at contract completion? SDB: _______ WOB: _______ Small Business: _______ Veteran-owned: _______ HUBZone: _______

Explanation—If goals were not met:

00110 - 7

Large and Small Business Offerors: Percent of contract and types of work subcontracted to small businesses (see FAR 52.219-8, Utilization of Small Business Concerns).

Name, address, FAX and telephone number of the owner:

Name and telephone number of a representative of your firm who is knowledgeable of this project and can readily be contacted:

Name, address, FAX and telephone number of a representative of the owner who is knowledgeable of this project and can be readily contacted:

Name, address, FAX and telephone number of the Contracting Officer if project was for Federal Government:

00110 - 8

OWNER/CLIENT PAST PERFORMANCE SURVEY

(TAB 2)

The U.S. Army Corps of Engineers, Los Angeles District, is interested in your assessment of the named company's “past performance". Past performance refers to the company's record of conforming to contract requirements and to standards of good workmanship; the company's record of forecasting and controlling costs; the company's adherence to contract schedules including the administrative aspects of performance; the company's history of reasonable and cooperative behavior and commitment to customer satisfaction; and the company’s general business-like concern for the interest of the customer.

These questions relate to the work performed by

(Name of Contractor) at (Name and Location of Project)

1. Is the information provided by the contractor in the attached Project Experience Form accurate and correct to the best of your knowledge?

Yes No Why Not?

2. How would you rate the following performance of this Contractor on the subject project?

a. Conformance to contract requirements.

Excellent Good Satisfactory Fair Unsatisfactory

b. Adherence to contract schedules.

c. Overall satisfaction with project quality.

d. Reasonable and cooperative behavior and commitment to customer satisfaction.

e. Conformance to contract safety requirements.

f. Contractor’s price, in terms of initial price and control of changes or claims.

g. Execution of effective quality control procedures.

00110 - 9

OWNER/CLIENT PAST PERFORMANCE SURVEY (CONTINUED)

CONTRACTOR’S NAME: ___________________________________________________

3. Were there any significant problems encountered by the Contractor? Yes No ____ If yes, state the problem(s), what corrective actions were taken by the Contractor, and indicate whether you consider these corrective actions to be effective?

4. Additional Comments:_________________________________________________________________

Name ______________________________________________________

Title _______________________________________________________

Telephone ___________________________________________________

Fax _________________________________________________________

E-Mail Address _______________________________________________

Date ________________________________________________________

Return to: U.S. Army Corps of Engineers, Los Angeles District Contracting Division, Attn: Julie Ayala P.O. Box 532711 Los Angeles, CA 90053-2325

Ph: (213) 452-3241 FAX: (213) 342-4187 EMAIL: Julie.Ayala@usace.army.mil

THANK YOU FOR YOUR TIME IN PREPARING THIS SURVEY!

00110 - 10

PERSONNEL RESUME FORM

(TAB 4)

Check applicable block:

KEY PERSONNEL:

[ ] Construction Project Manager [ ] Construction Site Superintendent [ ] Contractor Quality Control Manager [ ] Safety Manager

Name of Individual: _____________________________________________________________________

Employed by: __________________________________________________________________________

Number of years with firm: _______________________________________________________________

Number of years as practicing professional in your current field __________________________________

Education (degree(s)/year/ specialization): ___________________________________________________

Achievements, Special Recognition, and Honors: ______________________________________________

Experience: (most recent to earliest)

Project: _________________________________Company _____________________________________

Dates: From ________________________ to Present

Type of Construction:

Duties & Responsibilities:

00110 - 11

Project: ________________________________Company _____________________________________

Dates: From _______________ to ___________________

Project: ________________________________Company ______________________________________

Project: ________________________________Company_______________________________________

00120 - 1

SECTION 00120

PROPOSAL EVALUATION AND CONTRACT AWARD

1. ELIGIBILITY FOR CONTRACT AWARD

2. SOURCE SELECTION USING LOWEST PRICE TECHNICALLY ACCEPTABLE

3. LIST OF EVALUATION FACTORS (VOLUME II) AND SPECIFIC TECHNICAL

EVALUATION CRITERIA

4. EVALUATION OF PRICE PROPOSAL

5. INTENT TO AWARD WITHOUT DISCUSSIONS

6. PROPOSAL SUBMITTAL

7. PROPOSAL EXPENSE AND PREAWARD COSTS

00120 - 2

SECTION 00120

PROPOSAL EVALUATION AND CONTRACT AWARD

1. ELIGIBILITY FOR CONTRACT AWARD

In accordance with the FAR, no contract shall be entered into unless the contracting officer ensures that all requirements of law, executive orders, regulations, and all other applicable procedures, including clearances and approvals, have been met. This includes the FAR requirement that no award shall be made unless the contracting officer makes an affirmative determination of responsibility. To be determined responsible, a prospective contractor must meet the general standards in Part FAR 9 and any special standards set forth in the solicitation.

2. SOURCE SELECTION USING LOWEST PRICE TECHNICALLY ACCEPTABLE

(a) The Government will make award to the Offeror submitting the lowest priced technically acceptable proposal. The Government will first review unpriced technical proposals to determine which proposals are acceptable to the Government. Offers that are determined to be technically “Acceptable” will be evaluated on the basis of price.

Offers that are determined to be “Non-Acceptable” will not receive further consideration.

(b) Responses that the Offeror understands, or will comply with the specifications, statements paraphrasing the specifications, and general or overly broad responses such as “standard procedures will be employed” or “well known techniques will be used”, will be rated “non-acceptable”.

(c) The objective of the Government is to award a contract to the Offeror who submits a proposal that when evaluated is determined to meet or exceed the acceptability levels established in the solicitation for non-price evaluation factors. Each non-price evaluation technical factor will receive a rating of Acceptable/Non-Acceptable. The award will be made to the technically acceptable proposal with the lowest evaluated proposed price.

3. LIST OF EVALUATION FACTORS (VOLUME II) AND SPECIFIC TECHNICAL

EVALUATION CRITERIA.

The Technical Proposal will be evaluated based on the following technical evaluation factors and standards:

FACTOR 1, TECHNICAL NARRATIVE ON THE FOLLOWING: EXPERIENCE ON SIMILAR

PROJECTS, SPECIFICALLY ON HOSPITAL AND/OR CLINIC ENVIRONMENT;

INFECTION CONTROL PROCESSES

FACTOR 2, PAST PERFORMANCE ON SIMILAR PROJECTS, SPECIFICALLY ON

HOSPITAL AND/OR CLINIC ENVIRONMENTS

FACTOR 3, TECHNICAL APPROACH, METHODS AND PROCEDURES AND SCHEDULE

00120 - 3

FACTOR 4, NARRATIVE ON THE FOLLOWING: CORPORATE/MANAGEMENT STRUCTURE;

CAPABILITY TO MANAGE AND CONTROL PROJECTS; KEY PERSONNEL;

PRESENT WORKLOAD.

In order to be considered technically acceptable, proposals must meet ALL of the following requirements listed in the factors below:

FACTOR 1: TECHNICAL NARRATIVE ON THE FOLLOWING: EXPERIENCE ON SIMILAR

PROJECTS, SPECIFICALLY ON HOSPITAL AND/OR CLINIC ENVIRONMENT; INFECTION

CONTROL PROCESSES

Offeror shall identify at least three projects of similar scope, magnitude (projects no less than $3,000,000) and complexity as the RFP requirement it and/or its proposed team (i.e., predecessor companies, key personnel who have relevant experience or subcontractors that will perform major or critical aspects of the requirement) has/have successfully completed within the past five years and provide a technical narrative of those projects identified with the following:

experience on similar projects, specifically on hospital and/or clinic environment involving infection control processes. Projects referenced in Factor 1 are required to be reference in Factor 2.

EXPERIENCE ON SIMILAR PROJECTS, SPECIFICALLY ON HOSPITAL AND/OR CLINIC

ENVIRONMENT.

The Offeror and its proposed team will be evaluated by identifying at least three successfully completed projects within the past five years in a functioning, operational Department of Veterans Affairs Hospital and/or clinic or other hospital and/or clinic environment and providing a narrative of experience on similar projects, specifically on hospital and/or clinic environment. The narrative shall include a description of the project; total dollar value of the project at the time of award and at the time of completion, the Offeror’s role in the project (i.e., as a prime or a subcontractor), and the name, address and telephone number of the owner. In the case of a federal, state or local government project, provide the name, address and telephone number of the contracting officer. Offeror may include projects completed by predecessor companies. Offeror must include a general description of the infectious control processes involved in the projects. Offeror must explain why it believes the proffered projects are similar in scope, magnitude and complexity to the RFP requirement. When relying on the specific, relevant experience of key personnel, and/or major subcontractor, the description must include, in addition to all the above information, and explanation of what role the key person or subcontractor played in the former project, and what specific role that company, key person or subcontractor would perform in this project.

INFECTION CONTROL PROCESSES.

The Offeror will be evaluated by providing a technical narrative of demonstrated knowledge and experience performing construction projects requiring strict adherence to stringent Infection Control Requirements.

Standard for Acceptability: This standard is met when the Offeror can provide a technical narrative of construction experience in three or more completed projects within the past five years; similar in scope, 00120 - 4 magnitude (no less than $3 million) and complexity on the following:

experience on similar projects, specifically on hospital and/or clinic environment involving infection control processes. Experience of predecessor companies, key personnel, and major subcontractors may be used to qualify for this factor so long as the key person and/or major subcontractor will participate in this project in a meaningful way.

Projects referenced in Factor 1 are required to be referenced in Factor 2.

FACTOR 2: PAST PERFORMANCE ON SIMILAR PROJECTS, SPECIFICALLY ON

HOSPITAL AND/OR CLINIC ENVIRONMENTS.

For each project identified in Factor 1, provide a customer survey describing the scope of the work, contract price at the time of award, project cost growth during contract performance, and contract price at the time of completion. Describe the contract performance period set forth in the contract, time growth during contract performance, if any, and the number of days from the start of the project to acceptance by the owner/government agency. Provide a general description of the safety protocols employed and the number of safety-related incidents or accidents, if any, and if there were infectious control protocols involved, a description of any breach events and how they were resolved. Identify and describe any warranty issues raised by the owner, and how the problems were resolved. If no warranty issues were raised, Offerors should so state. Offerors may provide information on problems encountered on the projects and the Offeror’s corrective action. Identify and include results, if any of litigation regarding the project.

The Government may consider any and all sources of information about the projects, including, but not limited to, contacting the owner or contracting officer of the project, and the CCASS rating system. Firms who have a less than satisfactory performance evaluation should explain from the perspective what happened and lessons learned from the experience. This factor will evaluate how well an Offeror has performed on projects of a similar scope, magnitude, and complexity, and is an indicator of the likelihood of completion of the project in terms of time, cost and quality of work. Past performance must be demonstrated within a functioning, operational Department of Veterans Affairs Hospital and/or Clinic, or other Hospital and/or Clinic environment.

In addition, the Government will consider Client’s Overall Satisfaction with Project. A Past Performance Questionnaire to be submitted by Offeror’s current/former client/customer is included for your use;

refer to Section 00110. The Offeror must provide its client information, as described in Factor 4. The Offeror’s Client will be contacted. The clients’ responses to the following questions will be considered:

(1) Where Key Personnel responsive to Client’s needs?

(2) Did Key Personnel have the authority to meet the project objectives?

(3) Were Key Personnel responsive to Client’s requested changes?

(4) Was the Client satisfied with technical knowledge of Key

00120 - 5

Personnel?

(5) Would the Client use this company again?

(6) Was the staffing level consistent with the project size and complexity?

(7) Was communication of schedule and/or project issues adequate and consistent?

(8) Was the team’s response time to Client’s questions acceptable?

(9) Did the Offeror’s or Subcontractor’s performance conform to the terms of the contract?

Standard of Acceptability: This standard is met when the Offeror has demonstrated an overall satisfactory performance evaluation or higher, on similar contracts/projects within functioning, operational Hospital and/or Clinic, completed within the past five years. In the event that the Offeror does not provide a record of relevant past performance, the Offeror will not be rated favorably or unfavorably on this factor.

Consideration of Client Overall Satisfaction will be made. Projects referenced in Factor 1 must be referenced in Factor 2. Experience of predecessor companies, key personnel, and major subcontractors may be used to qualify for this factor so long as the key person and/or major subcontractor will participate in this project in a meaningful way.

The Government may will consider information submitted by the Offeror and the past performance surveys submitted by the owner/client along with any other relevant and reliable information that the Government may obtain from other sources (including information from Government personnel and databases).

FACTOR 3: TECHNICAL NARRATIVE ON TECHNICAL APPROACH, METHODS AND

PROCEDURES AND SCHEDULE

Proposals will be evaluated as to the Offeror’s ability to perform and to satisfy all contract requirements. Discuss the Offeror’s technical understanding of the work requirements , and the commitment to accomplish all the work in accordance with the solicitation requirements and schedule; the quality of the Offeror’s approach, methodology, plan for customer service, Quality Control procedures, and its approach for construction safety and infectious control protocols and procedures. Discuss the workability of the Offeror’s approach as well as the technical feasibility to successfully perform.

SCHEDULE. The Offeror shall provide a narrative that includes, as a minimum, discussion of proposed sequence of work, mandatory phasing, testing and balancing, interim and final acceptance. Offers shall include a bar chart reflecting the major construction activities with the completion period from the applicable contract Notice to Proceed (NTP). The proposal schedule shall be graphically presented, and may be on a maximum paper size of 11”x17”. The schedule shall reflect the major construction milestones, and the sequence of work required for this project. The schedule shall indicate start/finish dates of events, and durations. A detailed network analysis is not required as a proposal submittal item.

Offerors are cautioned that if they do not meet the project duration shown in Paragraph 52.211-10, Commencement, Prosecution and Completion

00120 - 6 of Work, of Section 00800, of this Request for Proposals, their response for Evaluation Factor 3 may be rated Non-Acceptable. Schedules showing Government submittal review durations to be shorter than are contractually mandated may be rated Non-Acceptable.

Standard of Acceptability: This standard is met when the Offeror demonstrates a commitment to accomplish all the work in accordance with the solicitation requirements, committing to meet scheduling requirements. The standard is met when the Offeror demonstrates an understanding of the work requirements has an adequate plan for customer service and the Quality Control, and has construction safety and infectious control protocols and procedures that are adequate for the work to be performed. The standard is met when the Offeror demonstrates technically feasible approach to meeting the Government’s requirements. This standard is met when the Offeror has demonstrated that it understands the project requirements and that the project will be completed within the contract performance period.

FACTOR 4: TECHNICAL NARRATIVE ON THE FOLLOWING - CORPORATE/MANAGEMENT

STRUCTURE; CAPABILITY TO MANAGE AND CONTROL PROJECTS; KEY PERSONNEL;

PRESENT WORKLOAD.

CORPORATE/MANAGEMENT STRUCTURE. The Offeror will be evaluated on their ability to satisfy all contract requirements within its Corporate/Management Structure. The Government will review the corporate decision-maker’s support for the contract execution team. In addition, the corporate structure should enhance communication flow within the corporation as well as with the customer.

CAPABILITY TO MANAGE AND CONTROL PROJECTS. The Offeror must demonstrate its capability to manage and control the project. Among other things, Offeror must show the corporate organization and reporting chain for key personnel. Specifically, the Offeror must demonstrate Project Management Experience by providing information for three completed projects within the past five years in functioning, operational Hospital and/or Clinic; similar in scope, magnitude and complexity to this project. For projects referenced, the following information must be provided:

• Project title, location, and brief project description including building use and contracting method (design-build, design-bid-build, etc.).

• Project owner, name and contract number of owner’s Contracting Officer.

• Project design architect, engineers and/or consultants, as applicable, and their name and contract number POC.

• Project statistics including start and completion dates, Original vs. Actual, for construction, and cost effectiveness between award amount and final contract amount. As applicable, provide pertinent information regarding change order history.

KEY PERSONNEL. The Offeror shall provide resumes for persons directly responsible for carrying out the day-to-day operations of this contract, including site superintendent, construction quality control

00120 - 7 manager, and the site safety and health officer. Resumes should specifically describe education, professional qualifications, and years of relevant experience and required training, if any. If the Offeror intends to have the site superintendant or the quality control manager assume the responsibilities of the site safety and health office, the key person must also meet the Level 4 qualification requirements, including the relevant Competent Person training. The education, professional qualifications, years of relevant experience and required training will all be assessed. Additionally, the Offeror’s site superintendent, construction quality control manager, and/or site safety and health officer must have the experience of at least one of the projects referenced in Factor 1 and must demonstrate relevant experience of key project personnel within functioning, operational Hospitals and/or Clinics, by providing the following information:

• Name of individual and company, position/title.

• Number of years with the company.

• Description of work experience with the projects of similar scope and complexity, specifying project experience at VA or other hospital/clinic facilities, if any.

• Position the individual will hold in regard to this contract/project team, description of duties, and what percentage of the individual’s time would be committed to this project.

• Describe job related educational experience, including degrees, certificates, etc., and granting institutions.

PRESENT WORKLOAD. The Offeror must provide a narrative/description on its present workload and the availability of a team to execute the contract.

Standard for Acceptability: The standard is met when the Offeror has provided a narrative to demonstrate its capability to successfully staff, manage, and control the project; provide key personnel information; provide a narrative/description on its present workload.

4. EVALUATION OF PRICE PROPOSAL

The proposed price will be analyzed for reasonableness. It may also be analyzed to determine whether it is realistic for the work to be performed; reflects a clear understanding of the requirements; and is consistent with the Offeror’s Technical Proposal. All offers with separately priced line items or sub line items will be analyzed for unbalanced pricing.

5. INTENT TO AWARD WITHOUT DISCUSSIONS.

The Government intends to evaluate proposals and issue a Contract without discussions, but reserves the right to conduct discussions and receive revised proposals if later determined to be necessary.

00120 - 8

6. PROPOSAL SUBMITTAL.

The Offeror’s conformance with the specified format and submission requirements will be considered during the technical evaluation.

Material omission(s) may cause the technical proposal to be rejected as unacceptable.

The Offeror’s adherence to prescribed page and formatting limitations prescribed will be strictly adhered to and enforced. Information submitted which exceeds the specified limit will NOT be evaluated. For example, the Government will not evaluate excess information. If four pages are submitted in response to an item with a three page limitation, the information of the fourth page will not be evaluated.

The technical proposals will be reviewed for compliance with the technical specifications. Non-compliance with the technical specifications will be considered a deficiency and a Non-Acceptable adjectival rating will be assigned.

7. PROPOSAL EXPENSE AND PREAWARD COSTS.

The Request for Proposal does not commit the Government to pay any costs incurred in the preparation and submission of the initial and/or any subsequent proposals or for any other costs incurred prior to execution of the Contract.

--- END OF SECTION ---

664-325 Expand Renovate Research Labs W912PL-12-R-0019

01 00 00 - 1 Bold Italics Underlined denotes AMENDMENT 09

SECTION 01 00 00

GENERAL REQUIREMENTS

PART 1

1.1 GENERAL

A. WASTE AIR GAS SUCTION RESEARCH PROJECT

Construction Duration for WASTE AIR GAS SUCTION RESEARCH PROJECT is 30 calendar days.

PHASING: Upon completion of WASTE AIR GAS SUCTION RESEARCH PROJECT and acceptance by the Government, the Contractor shall allow Veterans Affairs 30 calendar days to vacate staff and equipment from 664-325 EXPAND RENOVATE RESEARCH LAB AREA and move staff and equipment in to WASTE AIR GAS SUCTION RESEARCH PROJECT. Contractor shall not begin construction including demolition work on 664-325 EXPAND RENOVATE RESEARCH LAB AREA until this phasing is completed.

WASTE AIR GAS SUCTION RESEARCH PROJECT work involves following rooms and related exhausts located on sixth floor of Building 1:

Room Exhaust

6152----FX 2.23

6174C---FX 2.24

6174F---FX 2.24

6181----FX 2.25

6184C---FX 2.25

6212----FX 2.30

All Tie-in’s and Room Installation’s are typical to drawings.

Waste Air Gas Suction Drawings are:

1-6I-H - PROJECT AREAS

1-6I-H.1 -NEW FUME WASTE EXHAUST PLAN

Room 6152 WAGS LAYOUT – ELEVATION VIEW ROOM 6152

1-DE FUME WASTE SUCTION DETAILS

HVAC

• All work will be performed in compliance with VA asbestos protocol which is provided in this solicitation.

• All workers are required to have current asbestos training and certificates. Containment and negative air machines are required when working above ceiling.

• All work will be performed after hours, 4:00pm-11:00pm on week days and 7:00am -4:00pm on Saturday and Sunday. This can be further determined by staff at preconstruction meeting.

01 00 00 - 2

• Shut down FX unit dedicated to room and tap into the main exhaust trunk line with approved duct work. Install exposed dual surface mount branch lines (4”) on wall as per Drawings provided and install balancing dampers at the main tap, to regulate suction.

PLUMBING & MEDICAL GAS

• Provide and install 2 surface mounted wall type Vacuum outlet,

• Provide and install 1-3/4” isolation valve at tape in.

• Provide and install 2 surface mounted wall type Oxygen outlet,

• Provide and install 1-3/4” isolation valve at tape in.

• Certify all Medical Gas installations.

B. 664-325 EXPAND RENOVATE RESEARCH LABS

SCOPE OF WORK: This project will renovate part of existing sixth floor south wing of Building 1. Work is identified and located as shown in specifications and drawings provided for this project at Veterans Affairs San Diego Medical Center, 3350 La Jolla Village Drive, San Diego, California 92161. Following is list of items that comprises construction scope.

CONSTRUCTION SUMMARY

Construction requirements for 6 South include:

• Provide all labor, materials, tools and equipment for renovation of part of existing Sixth Floor South Wing of Building 1.

• This project will build over two (2) existing light wells and building out to exterior balcony space capturing approximately 4,000 sq-ft of unusable space on 6th floor south wing.

• Majority of 6th floor south wing will be fully renovated and this will include about 14,520 sq-ft of remodeled space.

• Contractors are required to provide a work plan for the research remodel project 664-325 relating to work that will impact the DOU/ICU located on the floor directly below the project footprint.

This work includes but not limited to jack-hammering on the exterior decks, drilling or core drilling into the slab, demo of drain piping, installation of new drain piping etc. When this type of work is performed above this area, the rooms directly below will need to be vacated due to safety, noise and vibration.

No transiting or work can take place in the interstitial off the catwalks above any occupied area including corridors…