This is Amendment 0003 to Solicitation W912PF26QA011, issued by the U.S. Army Corps of Engineers (0414 AQ HQ Contract Directorate). The amendment, effective 30 June 2026, extends the response due date from 30 June 2026 to 20 July 2026 to allow the government additional time to address a request for information received.

The amendment modifies the period of performance for multiple contract line items (CLINs) and option line items. The base contract CLINs 0001 through 0005 and all option line items (1001-1005, 2001-2005, 3001-3005, and 4001-4005) shift their performance periods from July-June fiscal year cycles to September-September cycles. Specifically, base CLINs change from "01 Jul 2026 to 30 Jun 2027" to "14 Sep 2026 to 13 Sep 2027," with corresponding adjustments for all option periods through 2031. The solicitation involves Building 5156 cleaning services and includes required attachments: a 137-page Performance Work Statement dated 22 April 2026, facility planography, risk assessment documentation, first aid plans, hazard lists, anti-mafia certification, and a company experience questionnaire. Offerors must acknowledge receipt of this amendment prior to the extended deadline of 20 July 2026 by completing the amendment form, acknowledging receipt on offer copies, or sending separate written communication referencing the solicitation and amendment numbers.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Solicitation/Contract Form Continuation

The following changes have been made:

INFORMATION FROM TO

Response Due Date

30 Jun 2026 20 Jul 2026

Continuation of Deliveries or Performance

The delivery information for the following CLIN(s) / SLIN(s) / ELIN(s) were modified:

INFORMATION FROM TO

Period of Performance

01 Jul 2026 to 30 Jun 2027 14 Sep 2026 to 13 Sep 2027

INFORMATION FROM TO

Period of Performance

01 Jul 2026 to 30 Jun 2027 14 Sep 2026 to 13 Sep 2027

INFORMATION FROM TO

Period of Performance

01 Jul 2026 to 30 Jun 2027 14 Sep 2026 to 13 Sep 2027

W912PF26QA0110003

INFORMATION FROM TO

Period of Performance

01 Jul 2026 to 30 Jun 2027 14 Sep 2026 to 13 Sep 2027

INFORMATION FROM TO

Period of Performance

01 Jul 2029 to 30 Jun 2030 14 Sep 2026 to 13 Sep 2027

Option Line Item 1001

INFORMATION FROM TO

Period of Performance

01 Jul 2027 to 30 Jun 2028 14 Sep 2027 to 13 Sep 2028

Option Line Item 1002

INFORMATION FROM TO

Period of Performance

01 Jul 2027 to 30 Jun 2028 14 Sep 2027 to 13 Sep 2028

Option Line Item 1003

INFORMATION FROM TO

Period of Performance

01 Jul 2027 to 30 Jun 2028 14 Sep 2027 to 13 Sep 2028

Option Line Item 1004

INFORMATION FROM TO

Period of Performance

01 Jul 2027 to 30 Jun 2028 14 Sep 2027 to 13 Sep 2028

Option Line Item 1005

Period of Performance

01 Jul 2027 to 30 Jun 2028 14 Sep 2027 to 13 Sep 2028

Option Line Item 2001

INFORMATION FROM TO

Period of Performance

01 Jul 2028 to 30 Jun 2029 14 Sep 2028 to 13 Sep 2029

Option Line Item 2002

INFORMATION FROM TO

Period of Performance

01 Jul 2028 to 30 Jun 2029 14 Sep 2028 to 13 Sep 2029

Option Line Item 2003

INFORMATION FROM TO

Period of Performance

01 Jul 2028 to 30 Jun 2029 14 Sep 2028 to 13 Sep 2029

Option Line Item 2004

INFORMATION FROM TO

Period of Performance

01 Jul 2028 to 30 Jun 2029 14 Sep 2028 to 13 Sep 2029

Option Line Item 2005

Period of Performance

01 Jul 2028 to 30 Jun 2029 14 Sep 2028 to 13 Sep 2029

Option Line Item 3001

INFORMATION FROM TO

Period of Performance

01 Jul 2029 to 30 Jun 2030 14 Sep 2029 to 13 Sep 2030

Option Line Item 3002

INFORMATION FROM TO

Period of Performance

01 Jul 2029 to 30 Jun 2030 14 Sep 2029 to 13 Sep 2030

Option Line Item 3003

INFORMATION FROM TO

Period of Performance

01 Jul 2029 to 30 Jun 2030 14 Sep 2029 to 13 Sep 2030

Option Line Item 3004

INFORMATION FROM TO

Period of Performance

01 Jul 2029 to 30 Jun 2030 14 Sep 2029 to 13 Sep 2030

Option Line Item 3005

INFORMATION FROM TO

Period of Performance

01 Jul 2029 to 30 Jun 2030 14 Sep 2029 to 13 Sep 2030

Option Line Item 4001

Period of Performance

01 Jul 2030 to 30 Jun 2031 14 Sep 2030 to 13 Sep 2031

Option Line Item 4002

INFORMATION FROM TO

Period of Performance

01 Jul 2030 to 30 Jun 2031 14 Sep 2030 to 13 Sep 2031

Option Line Item 4003

INFORMATION FROM TO

Period of Performance

01 Jul 2030 to 30 Jun 2031 14 Sep 2030 to 13 Sep 2031

Option Line Item 4004

INFORMATION FROM TO

Period of Performance

01 Jul 2030 to 30 Jun 2031 14 Sep 2030 to 13 Sep 2031

Option Line Item 4005

INFORMATION FROM TO

Period of Performance

01 Jul 2030 to 30 Jun 2031 14 Sep 2030 to 13 Sep 2031

List of Contract Documents, Exhibits, or Attachments

Miscellaneous text in this section has been modified to:

The following documents are made part of this Request for Quotation:

Attachment #1 - Performance Work Statement consisting of 137 pages dated 22 April 2026

Attachment #2 - Building 5156 Cleaning Area Planography

Attachment #3 - Single Document for the Assessment of Interferial Risk (DUVRI: Documento di Valutazione dei Rischi di Interferenza) consisting of 13 pages dated 20 December 2024

Attachment #4 - First Aid Plan Review Oct20 (English)

Attachment #5 - Piano di Primo Intervento Aggiornamento Ott20

Attachment #6 - Hazard General List (English & Italian) dated July 2008

Attachment #7 - Self Certification for Anti-mafia Communication

Attachment #8 - Company Experience Questionnaire

IDCode: J
Page: 1
Pages: 7
AmendNo: 0003
EffDate: 30 JUN 2026
ReqNo:
ProjNo:
IssCode: W912PF
AdmCode:
IssuedBy: 0414 AQ HQ CONTRACT AUG

KO DIRECTORATE OF CONTRACTING, UNIT 31423 BOX 77

APO, AE 09630

UNITED STATES

SONIA ZANOBINI, EMAIL: SONIA.ZANOBINI2.LN@ARMY.MIL TELEPHONE: 314-645-8762

AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: W912PF26QA011
SolDate: 29 APR 2026
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: 1
OffrNoEx: Off
NoCopies: 1
ApprData: SEE CONTINUATION
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: The purpose of this amendment is as follows:

- to change the period of performance

- To postpone the he due date from 30 June 2026 3PM to 20 July 2026 3PM. This is to allow the Government additional time to answer the request for information received.

ContNameTitle:
CoNameTitle: BRENDAN A. DELUCA
ContDate:
CODate: 30 JUN 2026

File details come from the government source that posted it. Updated .