This document provides details for federal contract opportunity number W912PF-20-R-0003 to construct a softball field at Camp Darby in Livorno, Italy. The project includes designing and building the softball field, including an optional lighting system and required irrigation system. The design phase will be followed by construction of all approved project elements. Design and construction must comply with applicable Italian and U.S. laws and regulations. The estimated value is between $250,000 and $500,000. Interested offerors must have an active System for Award Management registration and valid DUNS and NCAGE codes. A non-mandatory site visit will be held on April 7, 2020, and offerors must RSVP by March 4 with specified contact and identification information. The anticipated performance period is 135 days for design and 150 days for construction, or up to 315 total days if lighting is included. The solicitation is expected to be posted to SAM.gov in the coming weeks.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912PF20R0003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

REQUESTS FOR INFORMATION

Requests for information #1

1) In accordance with RFQ - Section L Factors, page 67 there are multiple questionnaires:

- Technical Factor I DESIGN EXPERIENCE - Attachment7 Design Exp. Questionnaire;

- Technical Factor II CONSTRUCTION EXPERIENCE - Attachment8 Constr. Exp. Questionnaire;

- Non-Price Factor IV PAST PERFORMANCE - Attachment9 Past Per. Questionnaire.

The second and the third point seem to repeat the same Past Performances. Therefore, we kindly ask to confirm if questionnaire for the second line could be duplicated to satisfy the third line requirement or they should report different experiences. In the second case, there will be at least four (4) experiences plus the Design Experiences.

Gover CONSTRUCTION EXPERIENCE technical factor has been removed, subsequently Sections M and L have been modified, see the Summary of changes for details.

2) In accordance with RFQ - Section L - Factors - Technical Factor I DESIGN EXPERIENCE (page 67 and 81), the past design projects must have been performed by the design firm signing the letter of intent as required by Section L of the solicitation. After more than one reading we could not identify the Letter of Intent that should be signed by the Design Firm, except the SF 1442 which will be signed by the Offeror. We kindly ask further clarification about which letter of intent shall be signed by the Design Firm.

The letter of intent should clearly state, both in English and in Italian, that there is a binding agreement between the Vendor and the design firm/ an authorized agent of the Architect and Engineering firm, and should be bilaterally written by the parties, signed and dated. The past design projects must have been performed by the design firm signing the letter of intent. If the design work will be performed in-house by the prime Contractor, a letter must be submitted stating this fact.

3) At page 82 is reported: "For Past Performance to be considered relevant, the offeror shall submit information about at least two (2) recent and relevant projects completed during the last five years from the

The only form in the solicitation is the SF 1442. We kindly ask to clarify if this is a typo or there is a missing document.

This is to confirm that there is a typo, the current SF is 1442, not 1449.

4) On the irrigation system, why is requested Dynamic spriklers "NON pop up", what is the use of this sprinklers? In addition, Is neccesary to design and install a sprinkler system to irrigate the diamond area?

SOW requires "Dynamic sprinklers" + "Dynamic AND pop up sprinklers".

5) Probably, to perform a flat area (with a maximum slope of 0.3%) and install ready lawn it is neccesary to excavate 0.15m of existing material. Could be distributed in the area all this surplus of material? Or it must be dispose? Provably There is a big quantity of surplus material, which will impact a lot in the price of the bid.

The excavated surplus soil shall be characterized and if analytical results will be in compliance with the regulation DPR 120/2017 the excavated surplus soil shall be moved in the Ammunition Storage Area where indicated by the COR. Soil characterization is included in the contractor scope of work: Contractor can assume that analytical results of the characterization will be in compliance with the regulation DPR 120/2017. If the soil will result contaminated, an addendum to the contract could be issued to bring it to disposal.

6) In the abovementioned solicitation, bidders are requested to submit 2 "Past Performance Questionnaire" forms and "Design Experience Questionnaire" forms attesting the performance of similar work in scope and amount.

We are a construction company, qualified SOA OG1 class IV, but we cannot submit this statements.

The question is: is it possible to build a temporary Joint Venture (Raggruppamento Temporaneo di Imprese) with a company qualified in this kind of design and construction, using their experience for design and past performance questionnaire and our credentials (DUNS, CAGE, SOA etc.) for the solicitation?

It is not allowed to participate through Joint venture/ATI.

7) With reference to the above-mentioned solicitation, we submit to you the following question:

field are also included in the scope. The construction of the lighting system will be optional, but its design will be pa lighting in option item. Could you please indicate us which of the two is correct?

This amendment #0001 deletes the design informational note contained under Line tem #0002; therefore, the design portion should be considered entirely included under Line Item #0001.

8) With reference to the above-mentioned solicitation, we submit to you the following question:

system for the new field are also included in the scope. The construction of the lighting system will be optional, but its design will be part of the price of the design for softball field lighting in option item.

The informational Design Note under Line Item 0002 of the standard form 1442 has been removed.

SECTION A - SOLICITATION/CONTRACT FORM

The required response date/time has changed from 27-Jul-2020 12:00 PM to 07-Aug-2020 11:00 AM.

SECTION B - SUPPLIES OR SERVICES AND PRICES

CLIN 0002

The CLIN extended description has changed from:

The Contractor shalll furnish all labor, equipment, material and transportationnecessary for the accomplishment of the work in strict accordance with theScope of Work for Project ED 00165-7, "Construct softball field Darby South, Darby Military Community, Italy" dated February 3, 2020, and consisting of 15 pages, and IAW attached Area for Construction, consisting of two (2) sheets; Geo Survey, consisting of two (2) sheets, dated August 1999; Plan of the

Area, consisting of one (1) sheets, dated February 3, 2020; Wiring Diagram Panel, consisting of seven (7) sheets, dated October 29, 2010.NOTE: Vendors are required to indicate the cost of the design of the abovementioned project FOR INFORMATION ONLY: EURO _______________

To:

The Contractor shalll furnish all labor, equipment, material and transportationnecessary for the accomplishment of the work in strict accordance with theScope of Work for Project ED 00165-7, "Construct softball field Darby South, Darby Military Community, Italy" dated February 3, 2020, and consisting of 15 pages, and IAW attached Area for Construction, consisting of two (2) sheets; Geo Survey, consisting of two (2) sheets, dated August 1999; Plan of the Area, consisting of one (1) sheets, dated February 3, 2020; Wiring Diagram Panel, consisting of seven (7) sheets, dated October 29, 2010.

SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

The following have been modified:

ATTACHED DOCUMENTATION

ATTACHED DOCUMENTATION

The following documents are part of this solicitation:

1) Attachment # 1 - Statement of Work consisting of 15 pages dated February 3, 2020;

2) Attachment # 2 - Area for Construction, consisting of two (2) sheets;

3) Attachment #3 - Geo Survey, consisting of two (2) sheets, dated August 1999;

4) Attachment #4 Self-certification for Antimafia Communication;

5) Attachment #5 Plan of the Area, consisting of one (1) sheets, dated February 3, 2020;

6) Attachment #6 Wiring Diagram Panel, consisting of seven (7) sheets, dated October 29, SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS

The following have been modified:

SECTION L

SECTION L

A. Each offeror shall provide a lump sum price in Euro currency and without IVA tax for all contract line item(s) in the bid schedule.

B. An authorized official of the firm shall sign:

- The SF 1442.

C. To be awarded a government contract you MUST have DUNS (Dun & Bradstreet) (http://fedgov.dnb.com/webform) and NCAGE (www.dlis.dla.mil/Forms/Form_AC135.asp) numbers and be registered in SAM Registration ((https://www.sam.gov).

All offerors must be submitted to the Contracting Officer no later than 11:00 a.m (local time, Rome, Italy) on August 07 2020. All offers shall be submitted in English and include the company point of contact, phone number, and email address. The Point of Contact for this contract is:

Elisa Orsini 414th Contracting Support Brigade RCO Livorno Sub-Office Email: elisa.orsini2.ln@mail.mil Telephone: (39) 050-548367

The Alternate Point of Contact and address for this contract is

Cristina Pancaccini 414th Contracting Support Brigade Email: cristina.pancaccini2.ln@mail.mil Telephone: (39) 050-548365

Only E-Mail offers will be accepted. Quotes shall include one scanned copy of the dated offer signed by an official fully authorized to bind the quoter. The documents shall be submitted in Adobe Acrobat (PDF) format.

E-Mail Submission Instructions: offerors shall submit their solicitation via E-Mail using the subject line uired to submit all solicitation attachments, offerors shall indicate in the Email number at the end of the subject (i.e. for the first of 3 E-Mails,

- iple E-

Mails to submit, ALL E-Mails shall be submitted prior to the time listed above. E-Mails received after shall be considered late and the offer will be rejected. (NOTE: Recommended maximum file(s) size per email is no larger than 5MB. If solicitation documents exceed 5MB, submit in multiple emails).

Offerors shall include the names and number of attachments in the body of each E-Mail. E-mail submissions shall be sent to both of the above email addresses. Be advised that the Government does not provide automatic notification of receipt; contact the POC via telephone to receive confirmation.

I DOCUMENTATION REQUIRED FOR THE EVALUATION

1. Failure to address all the mandatory requirements may cause the offer to be disqualified from further consideration.

2. The offeror is responsible for submitting a well-written offeror, with adequately detailed information, which clearly demonstrates compliance with the solicitation requirements.

FACTORS:

Technical Factor I DESIGN EXPERIENCE

The offeror shall demonstrate recent and relevant experience in scope, complexity and price. The Government will evaluate the information concerning at least two (2) recent and relevant projects provided by the offeror on the

The technical factor will be rated on an acceptable/unacceptable basis.

In order to be considered relevant the value of each project shall be at least Euro 50,000.00 ($58,227.55). In addition, each project shall be of similar scope, size and complexity, to the attached Scope of Work (i.e. Outdoor sport/recreation plants construction/upgrade; outdoor works consisting in installation or repair of green areas for recreational use, for example the construction/repair of facilities including green areas with benches or playgrounds etc.).

In order to be considered recent the design contracts must be completed within five (5) years from the date of this solicitation identified on Page 1, Block 3.

The past design projects must have been performed by the design firm signing the letter of intent as required by Section L of this solicitation. A letter of intent signed by an authorized agent of the Architect and Engineering firm that will be performing the design portion -

TECHNICAL FACTOR II SOA CERTIFICATION

The offeror shall demonstrate their capability by providing proof of their specified Societa Organismi di Attestazione (SOA) qualification level. Offerors shall submit certification for:

SOA OG1 Classification II, or OS24, Classification II.

NON-PRICE FACTOR III PAST PERFORMANCE

The offeror shall submit the information as required on Attachment #9 - Past Performance Questionnaire showing past performance of Outdoor sport/recreation plants construction/upgrade. The offeror shall provide at least two (2) recent and relevant projects. Relevant means work of similar scope, size and complexity to the attached Scope of Work (i.e. Outdoor sport/recreation plants construction/upgrad; outdoor works consisting in installation or repair of green areas for recreational use, for example the construction/repair of facilities including green areas with benches or playgrounds etc.).

Recent means work was completed during the last five years from the date of this RFQ (as shown in block no. 6 of the SF 1442).

Offerors are encouraged to submit past performance information with evidence of customer satisfaction such as performance evaluation, special commendation, recognition, letters of appreciation, "certificato di regolare

FACTOR V PRICE

Offerors shall fill in the lump sum prices for CLINs 0001, 0002 and 7500 without IVA tax.

II. ADDITIONAL DOCUMENTATION REQUIRED BY THE SOLICITATION

a.Self Certification Anti Mafia The offeror shall fill in the Attachment #7 entitled " Self-Certification for Anti-mafia Communication".

B. POOL OF FIRMS (CONSORZIO STABILE): Any Permanent Pool of Firms (Consorzio Stabile) shall provide with the proposal the here below listed required document/certificate otherwise its proposal will be rejected as not in compliance with the requirement of the solicitation, if a determination is made to award the contract based on initial proposals without discussion.

A copy certified of the notarized legal document that established the Permanent Pool of Firms (Consorzio Stabile).

The name and addresses of all the associated firms. The associated firms are NOT allowed to submit their individual proposals under this solicitation otherwise the proposal of the Permanent Pool of Firms (Consorzio Stabile) and the proposal of any associated firm will be rejected. The names and the addresses of the associated firms proposed to perform the work.

III. DOCUMENTATION REQUIRED FOR THE DETERMINATION OF RESPONSIBILITY

The U.S. Government requires the offeror to submit the following documentation/certification to be satisfied that a prospective contractor currently meets the applicable standards in Federal Acquisition Regulation 9.104 Standards.

The offeror shall provide with the proposal a copy certified and NOT older than ninety (90) days at the time set forth for the receipt of the offer of the DURC. -certifications are allowed. However, if the offeror has submitted a certified DURC to the issuing office (RCO Sub Office Livorno) within 90 days from the due date of this proposal, then the offeror may submit a copy of the previously certified DURC. The document MUST include the following statement otherwise the proposal will be rej

B. CERTIFICATE OF THE CHAMBER OF COMMERCE (CERTIFICATO DI ISCRIZIONE ALLA CAMERA

DI COMMERCIO) (ORDINARIO)

The offeror shall provide with the proposal a copy certified and NOT older than two (2) months at the time set forth for the receipt of the offer of the Chamber of Commerce Certificate of Membership (Certificato di Iscrizione alla Camera di Commercio). Self-certifications are not allowed. However, if the offeror has submitted a certified Chamber of Commerce Certificate of Membership to the issuing office (RCO Sub Office Livorno) within 90 days from the due date of this proposal, then the offeror may submit a copy of the previously certified Chamber of Commerce Certificate of Membership. The certificate must include the following statement otherwise the proposal

Maggio 1965, n. 575 e successive essa dalla C.C.I.A.A. utilizzando il collegamento telematico con il sistema informativo utilizzato dalla Prefettura di Roma."

C. EXTRACT OF THE REGISTRATION BOOK (ISTITUZIONE DEL LIBRO UNICO)

The offeror shall provide with the proposal a copy or a photocopy of the Extract Registration Book (ISTITUZIONE DEL LIBRO UNICO) listing the employees presently employed by the offeror.

D. EQUIPMENT LIST

The offeror shall provide with the proposal a list of all the major equipment presently in its possession.

E. BANK REFERENCE

The offeror shall provide a bank reference that discusses whether or not the offeror has an adequate financial resource to successfully complete the resultant contract.

F. PROFESSIONAL TECHNICAL CAPABILITY IN ACCORDANCE WITH DLGS NO. 81/2008

ATTACHMENT XVII (SAFETY LAW).

In order to verify compliance with the Italian DLGS No. 81/2008, Enclosure XVII (Safety Law), the offeror shall provide the below required documentation/certification. If the offeror has submitted the below information to the issuing office (RCO Sub Office Livorno) within 90 days from the due date of this proposal, then the offeror may reference that submission instead of submitting duplicate information. In its proposal, the offeror must reference the request for proposal number for which the information was previously submitted.

trade related to the typology of the contract;

2. Evaluation of risks document as in Art. 17, Para. 1, Sub-Para. a), or self-certification as in Art. 29, Para. 5, of the same DLGS;

3. Specific documentation showing that machinery, equipment and provisional clauses are in conformance with what required by the DLGS;

4. List/s of individual safety/protective equipment issued to employees;

5. Appointment of a safety manager responsible for the implementation of preventive and protective safety measures; of the individuals responsible for the fire prevention and fire-fighting measures, the evacuation procedures, for the management of emergencies, and qualified medical physician (doctor) when required;

7. Qualification certificates of the above mentioned individuals and employees as prescribed by the DLGS;

they are medically fit, as required by the DLGS;

9. Photocopy of the record of social security contributions (DURC), as prescribed in D.M. 24 Oct 2007; and

10. Statement that no interim orders, negative administrative provisions or suspensions exists as specified in the Art.

14 of the DLGS no. 81/2008.

SECTION M - EVALUATION FACTORS FOR AWARD

The following have been modified:

BASIS FOR AWARD

BASIS OF AWARD

A. AWARD OF CONTRACT

The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factor(s) considered using the Lowest Price Technically Acceptable source selection process pursuant to FAR 15 procedures. Offerors are put on notice that:

1. The non-price factors will be evaluated on an acceptable/unacceptable basis

2. The non-price factors are evaluated for acceptability and NOT ranked

3. There is no relative order of importance of factors. Award will be made to the lowest price offer that meets or exceeds all the minimum mandatory criteria for the non-price evaluation factors.

In order to be considered awardable, there must be an acceptable rating in every non-price factor. A proposal -price factor will not be eligible for award. The offeror is responsible for submitting a well-written proposal, with adequately detailed information, which clearly demonstrates compliance with the solicitation requirements.

The Government reserves the right to discuss aspects of proposals with Offerors. Offerors are advised that the U.S.

Government intends to evaluate proposals and award a contract without discussions, clarifications, or any contact concerning the proposals received. Offerors may be asked to clarify some issues regarding the technical factors and non-price factors to enhance U.S. Government understanding. Such clarifications shall not be used to cure proposal deficiencies or material omissions, and/or otherwise revise the proposal. Offerors shall submit their best offer;

proposals shall be submitted initially on the most favorable terms from a price and technical standpoint. Offerors shall not assume they will be contacted or afforded an opportunity to clarify, discuss, or revise their proposals.

If discussions are determined necessary upon completing the evaluation of all proposals, the Contracting Officer will establish a competitive range and conduct discussions only with those Offerors within the competitive range. Upon conclusion of discussions, the Contracting Officer will request final proposal revisions from Offerors remaining in the competitive range, and may, upon receipt of final proposal revisions, proceed to select the most highly qualified offerors without further discussions or notice.

B. FACTORS

The solicitation provides for the following factors:

I) Technical Factor I Design Experience II) Technical Factor II SOA Certification III) Non-price Factor Past Performance IV) Price Factor

C. EVALUATION OF THE NON-PRICE FACTORS

Phase One. The Contract Specialist will screen each proposal for completeness to ensure that all mandatory requirements for this solicitation have been addressed. This level of evaluation does not include an in-depth reading meets the requirements of the solicitation. Failure to address all the mandatory requirements may be grounds to disqualify the proposal from further review.

Phase Two. In this phase, the evaluation team evaluates the technical factors.

TECHNICAL FACTOR I DESIGN EXPERIENCE

The Government will evaluate recent and relevant experience which is similar in scope, complexity and price to the requirements of this solicitation. The Government will evaluate the information concerning at least two (2) recent and relevant projects

The technical factor will be rated on an acceptable/unacceptable basis using the following ratings:

Acceptable Proposal clearly meets the minimum requirements of the solicitation Unacceptable Proposal clearly does not meet the minimum requirements of the solicitation

In order to be considered relevant the value of each project shall be at least EURO 50,000.00 ($58,227.55). In addition, each project shall be of similar scope, size and complexity, to the attached Scope of Work (i.e. Outdoor sport/recreation plants construction/upgrade; outdoor works consisting in installation or repair of green areas for recreational use, for example the construction/repair of facilities including green areas with benches or playgrounds etc.).

In order to be considered recent the past contracts must be completed within five (5) years from the date of this solicitation identified on Page 1, Block 3.

The past design projects must have been performed by the design firm signing the letter of intent as required by Section L of this solicitation.

TECHNICAL FACTOR II SOA CERTIFICATION

The offeror shall submit the II SOA OG1, Classification II, or OS24, Classification. II

This technical factor will be rated on an acceptable/unacceptable basis using the following ratings:

Acceptable Proposal clearly meets the minimum requirements of the solicitation Unacceptable Proposal clearly does not meet the minimum requirements of the solicitation

The proposal clearly meets the minimum requirements if the offeror provides the required certificate as described in the factor above. The proposal does not clearly meet the minimum requirements if the offeror fails to provide the required certificate as described in the factor above.

NON PRICE FACTOR III - PAST PERFORMANCE

This factor will be rated acceptable or unacceptable based on whether the past performance submitted for consideration is recent and relevant and demonstrates successful past performance by the offeror, such as: no terminations for default, no ratings less than satisfactory by its customers/references, whether the quality of its work was satisfactory and completed in a timely manner and whether the offeror demonstrated reasonableness and cooperation during performance of the contracts. Past failure to apply sufficient tenacity and perseverance to perform acceptably is strong evidence of unacceptable past performance. In addition, failure to meet the quality requirements of a contract is a significant factor to consider in determining unsatisfactory performance. Offerors may be asked to clarify some issues regarding the aforementioned factors to enhance U.S. Government understanding. Such clarifications shall not be used to cure proposal deficiencies or material omissions, and/or otherwise revise the proposal.

Past Performance Evaluation Ratings - Rating Descriptions:

Acceptable Based on the offeror's performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort, or the offeror's performance record is unknown

Unacceptable Based on the offeror's performance record, the Government has no reasonable expectation that the offeror will be able to successfully perform the required effort.

Note: In the case of an offeror without a record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance (see FAR 15.305 (a) (2) (IV).

Therefore, the offeror shall be determined to have unknown past performance. In the context of

For Past Performance to be considered relevant, the offeror shall submit information about at least two (2) recent and relevant projects completed during the last five years from the date of this RFP (as shown in block no. 6 of the SF 1449). Relevant means work of similar scope, size and complexity to the attached Scope of Work (i.e. Outdoor sport/recreation plants construction/upgrade; outdoor works consisting in installation or repair of green areas for recreational use, for example the construction/repair of facilities including green areas with benches or playgrounds etc.).

The magnitude must be not less than Euro 50,000.00 ($58,227.55) per individual project.

The offeror is encouraged to submit past performance information with evidence of customer satisfaction such as

The Past Performance is considered to be not relevant if it is not similar in work and the magnitude is less than Euro 50,000.00 ($58,227.55) per individual project.

It will be considered not recent if it is not completed within the last five (5) years from the date of this solicitation (date shows at Block no. 3 of SF 1442).

The Government will conduct a past performance assessment on all contracts, at least two (2), submitted by the offeror on the Past Performance Questionnaire (Attachment #9). The Government will consider the recency and performance. The Government will consider the Past Performance Questionnaire information, as well as information obtained from any other sources.

FACTOR IV PRICE

1. A contract will be awarded to the Lowest Priced Technically Acceptable Offeror (LPTA). The total price indicated will be evaluated for fair and reasonableness and for unbalanced pricing. Unrealistic, unbalanced or unreasonable pricing may cause a proposal to be determined unacceptable. Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more contract line items is significantly overstated or understated as indicated by the application of cost or price analysis techniques. A proposal may be rejected if the Contracting Officer determines that the lack of balance poses an unacceptable risk to the Government. The U.S.

Government will evaluate the price proposals to ensure a fair and reasonable price by using one or more of the following price analysis techniques or any other price analysis techniques listed in FAR 15.404-1:

a. Comparison of proposed prices received in response to the solicitation; and/or

b. Comparison of proposed prices with the independent U.S. Government estimate; and/or

c. Comparison of proposed prices with available historical information; and/or

e. Obtaining information/reports from Defense Contract Audit Agency or other outside agencies as required.

2. Unrealistic or unreasonable pricing may cause a proposal to be determined unacceptable.

(End of Summary of Changes)