16 June 2020
ADDENDUM N. 0001 TO THE STATEMENT OF WORK OF
PROJECT ES 00299-9 WATER WELLS DEPOT
With reference to comma “4 (Drawing and documents provided to Contractor)” of paragraph III
“Phase 1 (Design) Description”, the sentence:
“The following drawings are provided to the contractor with the purpose of showing the consistency of the facility where the work is planned. There is, however, no guarantee that the situation shown in the drawings exactly reflects the existing conditions. The drawings are provided in tif or pdf format and will be available in CAD format (unless otherwise indicated):
- Allegato- ubicazione CTR (map)
- Allegato- Relazione idrogeologica
- Allegato A- relazione idrogeologica-Integrazione
- Reference drawings – existing industrial water system.”
is replaced by
“The following documents are provided to the contractor. Reference drawing is provided to the contractor with the purpose of showing the consistency of the facility where the work is planned, however there is no guarantee that the situation shown in the drawing exactly reflects the existing conditions.
- Autorizzazione regione Toscana
- Allegato – Ubicazione CRT (map)
- Allegato –Relazione idrogeologica
- Allegato A –relazione idrogeologia – Integrazione
- Reference drawings – existing industrial water system (available also in CAD)
All works must be done in accordance with the documents “Autorizzazione regione Toscana”, “Relazione idrogeologica”, and “Relazione idreogeologica – integrazione”, whose requirements must be considered as part of this scope of work and included in the design.
All documents to be sent to Regione Toscana or other Authorities shall be sent through the COR.
Contractor is not authorized to contact any Authority without the approval of the COR.”
GIANLUCA LUCETTI, PE
Chief, Engineering Services Branch
| 2020-06-18T08:21:55+0200 | |