DEPARTMENT OF THE ARMY

U.S. ARMY GARRISON LIVORNO

DIRECTORATE OF PUBLIC WORKS

APO AE 09613

Project

MS 00276-5

REPAIR BUILDING 5092 AND CONVERT TO DRESSING/SHOWER FACILITY

S&M AREA, CAMP DARBY, LIVORNO, ITALY

TECHNICAL SPECIFICATIONS

Consisting of 229 pages and of 0 enclosed plans

PAOLO SERRAGLINI

Chief, Engineering Services Branch

Prepared by:

Director of Public Works

THE OK DESIGN GROUP S.r.l.

ARCHITECTS – PLANNERS

CONSULTING ENGINEERS

VIA ANGELO BARGONI, 78

00153 ROME, ITALY

on May 2018 APPROVAL DATE ________________

TABLE OF CONTENTS

SECTION TITLE No PAGES

Ia GENERAL PROVISIONS

Ib QUALITY CONTROL BY CONTRACTOR

IIa DESCRIPTION OF WORK

IIIa DEMOLITION AND REMOVAL

IIIb EXCAVATION AND BACKFILLING

IIId EXTERIOR SANITARY SEWER SYSTEM

IIIe EXTERIOR WATER SYSTEM

IIIf ROAD PAVEMENTS

IIIg TURF

IVa CONCRETE WORK

IVc STEEL WORK

Vc LIGHT EXPANDED CLAY MASONRY

Ve FLASHING AND MISCELLANEOUS METAL WORK

Vf JOINT SEALANTS

VIb FLOOR AND WALL GRES PORCELAIN TILE

VIIb PLASTERING

VIIc PAINTING

VIId EPOXY PAINT COATING

VIIe INTERIOR RIGID THERMAL INSULATION

VIIf EXTERIOR INSULATION AND PLASTIC COATING

VIIIb ROOF INSULATION AND WATERPROOFING

MS 00276-5

- 1 -

SECTION TITLE No PAGES

VIIIc ROOF MEMBRANE MATERIALS

IXa ALUMINUM DOORS AND WINDOWS

IXb WOOD DOORS

IXc STEEL DOORS AND FRAMES

IXd GLAZING

IXe DOOR HARDWARE

Xa NATURAL STONE WORK

Xb SUSPENDED CEILING IN ACOUSTICAL TILES

Xe FINISH CABINETRY

Xf VENETIAN BLINDS

Xg TOILET ACCESSORIES

Xh TOILET PARTITIONS

XIIa PLUMBING

XIIb PLUMBING FIXTURES AND FIXTURE TRIMMINGS

XIIc HEATING SYSTEM

XIIe THERMAL INSULATION FOR MECHANICAL SYSTEMS

XIIf AIR CONDITIONING SYSTEM

XIIIa ELECTRICAL SYSTEMS

XIIIb TELECOMMUNICATION SYSTEM

XIIIc FIRE DETECTION AND ALARM SYSTEMS

XIIId MASS NOTIFICATION SYSTEM

- 2 -

SECTION Ia

GENERAL PROVISIONS

1a-01 WORK PHASING.

a. Work Schedule. Whenever the nature of the contract and the work location are such that the work is to be performed in an area assigned to activities and services that cannot be interrupted, work shall be scheduled with concurrence of COR in such a manner as to cause the least possible inconvenience to the normal operations of mentioned activities and services. Contractor shall submit his proposed work schedule to the COR at the time of the pre-construction conference. Work start shall be contingent upon schedule approval.

b. Utilities Cut-Offs. As a rule, cut-off of power and other utilities (water, sewage, heating system, etc.) is not allowed. All temporary connections necessary to insure continuous power distribution shall be provided. If cut-offs are necessary, they shall not exceed the period of time strictly needed to make the temporary connections. Cut-off shall be scheduled with the COR not less than 15 days ahead of time.

c. Alarm, Telephone and Televisions Systems. Deenergizing of alarm, telephone and television systems is strictly prohibited. Should these systems, which may not appear on the drawing interfere with the contract work, they shall be temporarily diverted and fed by means of temporary connections to be adequately protected. Written approval must be obtained from COR prior to doing any temporary work.

d. System Reactivating. At the completion of the work, all existing systems, including water, electrical and heating systems, shall be reactivated and placed in their original locations.

e. Temporary Protections. Floors, carpets, and equipment that cannot be removed shall be adequately protected by temporary tarpaulins to be furnished and installed at no cost to the US Government. In addition, temporary protections shall be furnished and installed in some particular areas so as to allow performance of activities that cannot be interrupted or transferred. Also, the Contractor shall be responsible for removing, protecting, and reinstalling all furniture, shelves and furnishings that may interfere with the work course.

A wrong or no evaluation of all requirements specified above does not constitute grounds for a request for additional compensation.

1a-02 JOBSITE CLEAN UP AND DUST CONTROL. The contractor shall have sufficient trash/waste bins on site, and shall clean the worksite so that all discarded materials, debris and trash are placed in these bins at the end of each workday, and not left or allowed to accumulate anywhere else on the jobsite. These waste bins shall not be allowed to overflow with debris, and shall be emptied as soon as they become full. Haul roads shall be watered sufficiently to prevent excessive dust.

Ia-1

The work area shall be swept regularly to prevent accumulation of debris. Equipment, construction materials and excavated soil shall be stored in a safe and orderly manner on the jobsite, in accordance with the contractor's approved area use plan.

1a-03 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT. The contractor is considered the waste generator of all salvage, re-usable, re-cyclable and disposable materials derived from the demolition and removal works included in this contract and shall handle these materials as hereinafter indicated.

a. Salvage Material. All salvage end items that the COR will have considered in good operating conditions shall be disassembled without damage, cleared of all dirt and scaling and then transported to the DPW Warehouse, Building 5156, Depot, where they shall be handled over undamaged.

b. Re-usable Material. End items removed during contract accomplishment which cannot be re-utilized in future construction but which still have a commercial value shall be delivered to the DRMO, through DD Form 1348-1a. This material includes, but it is not limited to, canvas, textile consisting of scrap clothing, scrap aluminum including doors, windows and frames, copper, brass, bronze, and stainless steel, cables, electric motors, light and heavy metals in different sizes and thicknesses that the DRMO contractor can handle (3-4 m long), electrical and electronic equipment, and kitchen appliances. All the above material must be free of hazardous property and need to be segregated. The scraps generated in the Supply & Maintenance Area shall be transported to the DRMO yard only on Monday and Tuesday from 08:00 am to 15:00 pm by appointment through the COR. The scraps generated from other installations must be kept in place. DRMO will arrange the removal. However, the contractor shall request a pre-inspection of the material by DRMO through the COR.

c. Recyclable Material. All construction and demolition recyclable waste material shall be delivered to authorized treatment facilities by the contractor.

d. Special Waste. All special waste, either hazardous or not hazardous, shall be delivered by the contractor to authorized disposal facilities.

e. Waste Storage. Construction and demolition waste shall be stored in waste specific containers provided by the contractor. Containers will be in good conditions, free from severe rusting, bulging, or structural defects. Containers shall be placed in area identified by COR. Containers shall be removed once full or on COR’s decision.

f. Certificates and Authorizations.

(1) Recyclable Materials. As regards to recyclable materials, the Contractor shall submit copy of the authorization of the treatment facility which they are delivered to and will certify that waste have been removed in compliance with applicable law requirements.

Ia-2

(2) Disposable Materials. As regards to material delivery to disposal facilities, the contractor will provide the COR and DPW Environmental Office with copies of the following documents:

• Authorization to transport construction and demolition waste;

• Authorization of the landfill;

• 4th copy of Formulario di Identificazione del Rifiuto.

(3) Waste Manifest. All transported waste will be accompanied by the

Formulario di Identificazione del Rifiuto (waste manifest) to ensure a complete audit trail from point of origin to ultimate disposal. The waste manifest must be completed in quadruplet, all dated and signed by the waste generator and countersigned by the transporter. The first copy of the manifest will remain with the waste generator; of the remaining three copies, (countersigned and dated by the receiver), the second copy will remain with the transporter, the third copy will remain with the receiver, and the fourth copy must be returned by the transporter to the waste generator within 3 months of delivery of the waste to the disposal/treatment facility.

g. Costs. All operations included in this paragraph shall be carried out by the contractor with no additional cost to the US Government.

1a-04 AUTHORIZATION FOR INSTALLATION OF MATERIAL AND EQUIPMENT. Before installing any material or equipment mentioned in the specifications, approval shall be obtained from the COR. Contractor shall submit material samples, shop drawings, manufacturer's literature, etc., to the COR 10 days prior to installation and shall proceed with installation only after receiving written approval from the COR. All material installed without COR's approval shall be removed.

1a-05 ISPESL AND CEI STANDARDS. All work described in these specifications shall be accomplished in strict compliance with the ISPESL (Superior Institute of Prevention and Assurance of Work) and CEI (Italian Electrotechnical Committee) standards. In particular, if the work under contract, such as roof repairs, building painting, etc., may cause Contractor's personnel or other individuals to come in contact with non insulated electric lines, these shall be temporarily protected by use of appropriate spiral plastic tubes available on the market.

1a-06 TRANSLATION AND TITLE ABBREVIATION. The terms COR and "Direzione dei Lavori" used in the Italian version of these specifications are equivalent to the American term "Contracting Officer's Representative," which in the English version is indicated by the letters

COR.

1a-07 DIGGING PERMIT. The Contractor shall obtain a digging permit for all work areas affected by this contract (to insure that all the as-built information for underground services is received). This permit and related drawings must be received by the Contractor prior to starting any work. After receipt of the digging permit, the Contractor shall immediately notify, in writing the Contracting Officer of the permit receipt. The Contractor will be held responsible for any damages caused to existing services, as indicated on the digging permit and related drawings, and will repair such damages at his own expense.

Ia-3

1a-08 ASBESTOS. No handling of asbestos containing material is included in this project. Use of asbestos containing materials is forbidden.

1a-09 PARTICULAR REQUIREMENT FOR WORK IN HEATING PLANTS. When the contract requires the work to be performed inside heating plants, the contractor shall provide a new cylinder in the door lock and shall deliver two keys of the new cylinder and the removed cylinder to the personnel in charge of the maintenance. At the work end the contractor shall restore the lock to the original conditions and the temporary cylinder will remain his own property.

1a-10 ANTI-TERRORISM TRAINING. The Contractor shall comply with the following security requirements:

a. AT Level I Training. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date.

The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR within 10 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website: httQ://jko.jten.mil.

b. OPSEC Training. According to AR 530-1, new contractor employees must complete Level I OPSEC training within 30 calendar days after they report for duty. All contractor employees must complete annual OPSEC awareness training.

The contractor will develop an OPSEC standing operating procedure (SOP)/plan within 90 calendar days after the contract is awarded, to be reviewed and approved by the responsible Government OPSEC officer, according to AR 530-1. This SOP/plan will include the Government’s critical information, why it needs to be protected, where it is located, who is responsible for it, and how to protect it. The contractor will ensure this individual becomes OPSEC Level II certified according to AR 530-1.

c. Access And General Protection/Security Policy And Procedures. Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office.

Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

Ia-4

d. iWATCH Training. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO).This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 40 calendar days after contract award.

1a-11 ENVIRONMENTAL PROTECTION SYSTEM. The contractor will provide the following information semi-annually to be used by the Government to address environmental performance relative to the goals of the USAG Vicenza Environmental Management System.

Please note that the amounts reported are those used/generated by the contractor regardless of source (private purchase or government furnished). Reports for January – June will be submitted by 15 July and reports for July-December will be submitted by 15 January each year.

Media Report Element #1 Report Element #2

Non-Hazardous Solid Waste

Total Waste Generated (Kg)

Amount of Waste Diverted from Landfill (Kg)

Construction Debris/Demolition Materials

Total Waste Generated (Kg)

Amount of Waste Diverted from Landfill (Kg)

Compostable/Organic Material

Total Waste Generated (Kg)

Amount of Waste Diverted from Landfill (Kg)

Hazardous Materials Total Used (Kg) Hazardous Waste Total Generated (Kg) Total Recycled (Kg) Energy Consumption - Electricity

Total Energy Consumed (MBtu)

Energy Consumption - Fuel

Total Fuel Consumed (L)

Renewable/Alternative Energy

Total Consumed

(MW)

Facility Construction/Renovation

Number of Buildings LEED Certified Silver or Higher

SqFt of buildings LEED Certified

Ia-5

SECTION Ib

QUALITY CONTROL BY CONTRACTOR

1b-01 GENERAL. The Contractor shall establish and maintain an effective quality control system to implement the requirements of contract clause entitled "Inspection of Construction (July 1986)". The quality control system shall comprise plans, schedules, and organization necessary to provide materials, equipment, workmanship, manufacture, construction, and operations which comply with contract requirements and shall identify personnel and forms to be used. The system shall cover construction operations, both indoors and outdoors, and shall be in accordance with the proposed construction sequence.

1b-02 COORDINATION MEETING. As soon as practicable after receipt of Notice to Proceed and before start of construction, the Contractor shall meet with the Contracting Officer's Representative (COR) and discuss the Contractor's quality control (CQC) system. During the meeting a mutual understanding of the system details shall be developed including the forms for recording the CQC operations, control activities, testing, administration of the system for both indoors and outdoors construction, and the interrelationship of Contractor's inspection and control with the Government's inspection. Minutes of the meeting will be prepared by the COR and forwarded to the Contracting Officer who will make them a part of the contract file. There may also be other subsequent meetings will be called to reconfirm understandings.

Minutes of these meetings will also be forwarded to the Contracting Officer.

1b-03 QUALITY CONTROL PLAN.

a. Prior to starting the construction, the Contractor shall furnish his CQC plan through the COR to the Contracting Officer for acceptance. Construction will be permitted to begin only after acceptance of the CQC plan or approval of that portion of the plan applicable to the particular feature of the work to be started. The QC plan proposed by the Contractor shall identify personnel, procedures, instructions, records and forms, and, as a minimum, shall include:

(1) A description of the quality management organization.

(2) The names, qualifications, duties, responsibilities, and authorities of each person assigned a quality control (QC) function.

(3) A copy of the letter to the QC manager, signed by an authorized official of the firm, which describes the responsibilities and delegates the authorities of the QC manager.

Ib-1

(4) Procedures to perform QC over other activities including subcontractors, manufacturers, and suppliers.

(5) Control testing procedures for each specific test.

(6) Reporting procedures for QC including proposed reporting formats.

b. After approval of the QC plan the Contractor shall notify the Contracting Officer in writing of any proposed change to his QC plan. Proposed changes are subject to acceptance by Contracting Officer.

c. The acceptance of the QC plan is conditional and will be predicated on a satisfactory performance during the construction. If it is determined that the QC plan, personnel, instructions, controls, tests or records are not providing a construction conforming to contract requirements, the Government will reserve the right to require the Contractor to make changes in his QC plan and operations, as deemed necessary to obtain the specified quality. Any changes required to the plan will be made at no cost to the Government.

1b-04 QUALITY CONTROL ORGANIZATION.

a. The Contractor shall identify an individual within his organization at the site of the work who shall be responsible for overall management of CQC and have the authority to act in all CQC matters for the Contractor.

b. A staff shall be maintained under the direction of the system manager to perform all QC activities. The actual strength of the staff during any specific work period may vary to cover work phase needs, shifts and rates of placement. The personnel of his staff shall be fully qualified by experience and technical training to perform their assigned tasks, and shall be directly hired by and work for the prime Contractor.

1b-05 SUBMITTALS.

a. The Contractor shall develop procedures for purchasing materials and equipment, subcontracting, and processing shop drawings, samples, certificates, and other submittals. This procedure shall include the establishment of responsibilities to assure, at each level, adequate review and approval, timely delivery including verification procedures, and proper storage. Submittals of the shop drawings and/or manufacturer's data shall be, as specified, in accordance with contract clauses entitled "Materials and Workmanship" and "Shop Drawings."

Ib-2

b. Actions shall be taken to ensure that only materials and equipment which comply with contract requirements are purchased and delivered to the job site or used in off site fabrication, unless specific deviations are approved, as specified hereinafter. The COR may request a copy of the document of transportation of the provided material.

c. The Contractor shall review the contract requirements and verify that submittals are confirming to contract compliance. Within 10 days after receipt of notice to proceed, the Contractor shall submit a submittal control document listing and scheduling all submittal items required in the contract. This document shall be in duplicate and shall be addressed through the COR to the Contracting Officer. The control document shall include such items as construction schedules, monthly progress reports, shop drawings, manufacturer's literature, certificates of compliance, material samples, and guarantees. The document shall schedule for each item the dates of submittals. The scheduling of submittals shall be coordinated with the approved progress schedule; the information contained therein shall be reviewed and updated at each schedule update. Adequate time shall be allowed to the US Government for approval of submittals. The Contractor shall review the listing at each progress schedule update and copies of updated documents shall be submitted through the COR to the Contracting Officer in the specified quantity. Payments to the Contractor will not be made for material or equipment which does not comply with the Contract requirements.

d. The CQC organization shall be responsible for certifying that all submittals are in compliance with the contract requirements. Submittals to the Contracting Officer without evidence of the certification will be returned for resubmission.

e. The Contractor shall submit copies of all submittals through the COR to the Contracting Officer.

f. Delays in the approval process shall not be the basis for consideration of a time extension when such delay is the result of the Contractor's failure to make proper and timely submittal, or make corrections in accordance with the specifications or the Contracting Officer's comments, or is a result of a resubmittal which is required because of an unsatisfactory original submittal. Approval action by the Contracting Officer will not relieve the Contractor of his responsibility for compliance with the contract but will indicate only that the general method of construction and detailing is satisfactory.

Ib-3

g. All proposed deviations from contract requirements shall be submitted in writing for approval by the Contracting Officer.

1b-06 CONTROL. Quality control is the means by which the Contractor assures himself that his construction complies with the requirements of the contract plans and specifications. The QC system shall include at least the following three phases of control and management for all definitive features of work:

(1) Preparatory. This control phase shall be performed before beginning work on each definable feature of work. It shall include a review of contract requirements to assure that materials, sample, and equipment conform to contract requirements and that control testing procedures are finalized. The control shall also include examination of the work area to verify that structures over which new work is to be placed conform to contract requirements; Contractor shall also verify that the required materials be on hand and properly stored. The COR shall be notified at least 24 hours in advance of each preparatory activity.

(2) Initial. This phase of control must be accomplished as soon as a representative portion of the particular feature of work has been accomplished and shall include examination of the quality of workmanship and a review of control testing for compliance with contract requirements, identification of defective or damaged materials, omission, and dimensional requirements. The COR shall be notified at least 24 hours in advance of the initial inspection and such inspection shall be made a matter of record in the CQC documentation.

(3) Follow-Up. The follow-up phase shall be performed continuously to verify that control procedures are providing an end product which complies with contract requirements.

Adjustments to control procedures may be required based upon the results of this phase.

(4) Completion. At the completion of all work or any increment, the CQC representative shall conduct a joint review with the COR. During this review the work shall be examined, quality control shall be examined, and a list shall be developed of work not properly completed or not conforming to plans and specifications. This list shall be included in the quality control documentation with an estimated date for correction of each deficiency.

The Contractor shall make sure that deficiencies be corrected prior to the contract completion date. Payment will be withheld for defective or deficient features until they are satisfactorily corrected except as otherwise provided in the contract.

Ib-4

1b-07 TESTS.

a. The Contractor shall perform tests specified or required to verify that control measures are adequate to provide a product which conforms to contract requirements. The Contractor shall procure the services of an industry recognized testing laboratory or he may establish an approved testing laboratory at the project site. A list of tests which Contractor believes necessary shall be furnished to the COR. The list shall give the test name, specification paragraph containing the test requirements, and the personnel and laboratory responsible for each type of test. The Contractor shall perform the following activities and provide the following data:

(1) Verify that the testing procedures comply with contract requirements.

(2) Verify that facilities and testing equipment are available and comply with testing standards.

(3) Check test instrument calibration data against certified data.

(4) Verify that recording forms including all pertaining documentation have been prepared.

b. Testing.

(1) The Contracting Officer reserves the right to check laboratory equipment in the proposed laboratory for compliance with the standards set forth in the contract specifications and to check the laboratory technician's testing procedures and techniques.

(2) The Contracting Officer reserves the right to utilize the Contractor's control testing laboratory and equipment to make assurance tests and to check Contractor's testing procedures, techniques, and test results at no additional cost to the Government.

(3) Cost incidental to the transportation of samples or materials will be borne by the Contractor.

1b-08 DEFECTIVE WORK. The Contractor shall not build upon or conceal a defective work.

1b-09 DOCUMENTATION.

a. The Contractor shall maintain current records, on an appropriate form, of quality control operations, activities and tests performed including the work of suppliers and subcontractors.

Ib-5

These records shall include factual evidence that the required activities or tests have been performed, including but not limited to the following:

(1) Type and number of control activities and tests involved.

(2) Results of control activities or tests.

(3) Nature of defects, causes for rejection, etc.

(4) Proposed remedial action.

(5) Corrective actions taken.

b. These records shall cover both conforming and defective or deficient features and shall include a statement saying that supplies and materials incorporated in the work comply with the contract. Legible copies of these records shall be furnished to the COR weekly. The records shall cover work performed during the time period for which the records are furnished and shall be verified by persons designated by the Contractor.

Ib-6

SECTION IIa

DESCRIPTION OF WORK

2a-01 STATEMENT OF WORK. Contractor shall furnish all plants, labor, equipment, material and transportation necessary for the accomplishment of the work described in these specifications and shown on drawings, both of which are an integral and binding part of the contract.

2a-02 DESCRIPTION OF THE WORK. Work included in this project MS 00276-5 “Repair Building 5092 and Convert to Dressing/Shower Facility”, in Camp Darby will consist of the following main items of work:

ARCHITECTURAL

- Complete demolition of the existing building including foundation, except the exterior appendix boiler room that remain on site. Contractor will provide a Demolition Plan to the Contracting Officer and to the “Coordinatore Della Sicurezza in Fase di Esecuzione” for approval.

In the existing Boiler Room will be provided the following works:

- Replace existing precast concrete chimney stack with a new stainless steel one as indicated on mechanical drawings, work includes flashings, sealing and bracings;

- Replace existing boiler’s concrete pad with a new one 20cm high, dimensions suitable with a new boiler;

- Patch-up existing slab on grade and provide a new oil resistant proofing on floor and 20cm high base;

- Patch-up plaster and paint;

- Enamel paint on existing door and frame including all exposed existing metal item previous rust inhibitive treatment;

- New copper flashing on roof edges;

- New copper joint cover flashing between existing mechanical roof and new building’s wall;

- Replace existing waterproofing membrane with new one. The new waterproofing is made of 2 ply bituminous membrane 4mm thick each with the top layer protected by slate chips;

- Continuous sealant between existing mechanical and new building walls;

IIa-1

In the new replaced building the main works include:

- Roof finish package including: 2 ply of 4mm thick each of bituminous waterproofing membranes, 12cm thick high density rock wool thermal insulation, bituminous vapor barrier and primer. Natural finish copper flashings and gutters are included.

- Roof accessories as: three operators simultaneous life safety line, two simultaneous operators anchoring points, Galvanized steel ladder with security lockable hinged panel, raised precast pavers around solar panels.

- Exterior skin as: painted synthetic coating on 9cm thick high density rock wool thermal insulation on concrete wall, prepainted galvanized steel louvers with bird screen, prepainted galvanized insulated hollow steel doors and frames including hardware, prepainted aluminium windows and door with insulated laminated glass and hardware, insect screens and venetian blinds on operable windows.

- 8/12cm thick floor to ceiling Interior plastered light expanded clay masonry partitions and gypsum board on metal furring lining on perimeter concrete walls;

- Interior finish as: non slip 30x30cm gres porcelain floor tiles, concrete floor finish with epoxy resin, glazed 30x30cm porcelain wainscot tiles in toilet/shower areas, 60x60cm acoustical tiles suspended ceilings, water resistant where indicated, paint on walls and ceilings as indicated.

- Interior wood doors finished with plastic laminated and metal frames including hardware and aluminium transom grilles where indicated;

- HPL toilet partitions, toilet accessories as scheduled, wood kitchen, agglomerate quartz lavatory counter tops, extinguisher hooks and cabinets and door signs.

STRUCTURAL

New building

The new structure is made of reinforced concrete frames and perimeter walls dimensions as indicated on drawings.

- The excavation for foundations will be dept about 100cm under ground level where the existing foundation should be made;

- The main structural elements consist of:

- 18cm thick sloped reinforced concrete roof slab supported by 60cm high reinforced concrete beams.

- 10cm thick reinforced concrete slab on grade cast-in rigid thermal insulation with interposed an polyethylene sheet;

IIa-2

- 20cm thick reinforced concrete perimeter walls flush with interior face of columns in the East and West sides, while they are flush with exterior feces of columns in the North and South sides.

- The perimeter columns have the dimensions 40x40cm while the central ones are 40x50cm.

- The roof beams are all rectangular shape 40x60cm height, except the ridge beam that is 50cm wide and 60cm height. The two head building beams have a variable height from 60 to 90cm at roof.

- The foundations are made of isolated reinforced concrete plinths connected by beams.

Existing boiler Room

- Construction of 20cm high reinforced concrete pad and slab on grade.

MECHANICAL

- Removal of the entire existing HVAC systems including the existing aboveground fuel oil storage tank and associated fuel oil piping, boiler/burner, chimney stack and breeching, circulating pumps, expansion tank, unit heaters, radiators, roof exhaust fan, ductwork, registers, heating hot water piping, fittings, insulation, hangers, controls and accessories;

- Complete removal of the existing plumbing systems including fixtures with faucets, cold and hot water piping, electric water heater and sanitary waste and vent piping;

- Complete removal of existing compressed air piping including valves, fittings, supports and accessories;

- Provision of a new HVAC system including boiler/burner, chimney stack and breeching, sectional type primary air unit with integral heat recovery section, hot water radiators, split-type heat pump air conditioning units, circulating pumps, expansion tank, ductwork, registers, grilles, louvers, dampers, piping, fittings, insulation, hangers, controls and accessories;

- Provision of a new aboveground UL 2085 protected type fuel oil tank and associated fuel oil piping complete with valves, fittings and accessories. Fuel oil tank will be complete with stepladder, leak detection system (also for buried fuel oil piping), and level monitoring;

IIa-3

- Provision of a new water make-up system for the HVAC system including piping with valves, fittings, insulation and supports, backflow preventer device, cartridge filter and accessories;

- Provision of a new solar panel system including solar panels with supporting structure, vertical type domestic hot water generator with two heat exchangers and electric resistance, circulating pumps, expansion tank, piping, valves, fittings, insulation, controls and accessories;

- Provision of new plumbing systems including fixtures with faucets, pulse type water meter, backflow preventer assembly, thermostatic mixing valve, hot water recirculating pump, expansion tank, cold, hot and recirculating domestic water piping, waste and vent piping, fittings, valves, insulation, controls and accessories.

ELECTRICAL

- Removal of the existing lighting and power systems;

- Removal of the existing special systems;

- Use of spare automatic circuit breaker and miscellaneous work in the existing substation bldg#5099 for new 400V connection;

- Provision of new feeder cable and cable duct from existing substation;

- Rerouting and reconnection of existing communication cables from existing exterior manhole;

- Provision and installation of new lighting and power systems in the building;

- Reinstallation and reconnection of existing energy meter;

- Provision and installation of new grounding system;

- Provision and installation of new communication system;

- Provision and installation of new fire alarm and mass notification system;

- Miscellaneous works as indicated on drawings.

CIVIL

- Demolition and replacement of existing asphalt and , concrete pavement demolition of ramps;

IIa-4

- Removal of underground pipes including earthwork;

- Removal of existing fuel oil tank concrete base, and metal skin

- Construction of water line including pipes, valves, thrust blocks, earthwork;

- Construction of sanitary sewer pipeline including pipes, manholes, earthwork;

- Grading, topsoiling and grass seeding;

- Construction of new fuel oil tank concrete pad including steel ladder, fence and gate.

- All other items of demolition, removal, repair and construction work as necessary and as indicated on drawings and specifications.

2a-03 SAFETY DURING CONSTRUCTION. The project is performed assuming the possible presence of more than one firm, also not at the same time, on the work place, as per paragraphs 3 and 4 of art. 90 of Legislative Decree 81/2008. The “Piano di Sicurezza e Coordinamento” (safety and coordination plan) is included as part of the contract documentation. The Contractor shall provide his/her own “Piano Operativo di Sicurezza” (operational safety plan) and comply with the requirements of the mentioned Law in all applicable parts.

2a-04 EMERGENCY SITUATIONS. Contractor will maintain the following documentation available and usable at the work site, to be provided by the COR:

- A copy of the Camp Darby Emergency Plan, to which contractor will refer in the case of the emergency conditions indicated in the plan itself.

- Base Grid Coordinates layout, with the work site highlighted.

- List of emergency telephone numbers.

2a-05 PROJECT IDENTIFICATION SIGN. The contractor shall supply and install a sign identifying the project. The sign shall be of high-resistant plywood for outdoor installation, white painted. The dimensions shall be 1200x2400x12 mm. The letters of the wording shall be uppercase, black color, 5 cm high, except the letters of the project title which shall be 10

cm. The sign shall be fixed to a structure made of any material provided it is lasting and in compliance with all safety requirements.

IIa-5

The sign shall be well visible, with the lower side at 1.2 m from ground level.

IIa-6

SECTION IIIa

DEMOLITION AND REMOVAL

3a-01 Before starting the demolition work, Contractor must submit to Contracting Officer and Coordinatore della Sicurezza in Corso d’Opera a Demolition Plan in according to Piano di Sicurezza e Coordinamento as indicated in Dls n 81/2008.

During the inspection, exposed asbestos was not found. If during the demolitions, containing asbestos materials will be found, the works must be stopped and they will start again only after disposal, which will be carried out by specialized personnel in accordance with current legislation.

3a-02 GENERAL. Breakups of predetermined dimensions and partial or total demolition of masonry and concrete surfaces, floor, etc., must be performed in a workmanlike manner, by taking the necessary precautions or by shoring the surfaces in order to avoid damages to the structures to be left in place, accidents, inconveniences or interference. Waste material shall not be thrown down, but rather, it shall be conveyed or guided downward, after wetting it to prevent raising dust. During demolition or removal work, the Contractor shall adopt every measure suitable to avoid deterioration of the items which may be reinstalled, or which, in the opinion of the COR, may be used at a later date. These items shall be cleaned, guarded, hauled and set neatly in the storage areas indicated by the COR. The demolition work shall be limited to the work, or to its parts, and to the dimensions specified. Reconstruction of structures demolished over and above the quantities indicated, as well as rehabilitation of work damaged as a result of lack or omission of precautions or shoring, shall be performed by the Contractor at his own expense. All waste material resulting from demolition and removal shall be handled by the contractor in accordance with para. 1a-02 of these specifications.

IIIa-1

SECTION IIIb

EXCAVATION AND BACKFILLING

3b-01 EXCAVATION.

a. General. During excavation, material suitable for backfilling shall be piled at a sufficient distance from the banks of the excavation to avoid backslides. All earthy material in excess or unsuitable for backfilling shall be delivered to the location indicated by the COR and within 10 km from work site. This does not apply to debris and rubble of all types, from which excavation material shall be rid of; these shall be disposed of at a dump, as prescribed at paragraph 1a-02. Ground water will be encountered; depending on seasonal variations the ground water nay be encountered from 0.80 to 1.50 m below grade. Contractor shall remove water by pumping or other methods to prevent the softening of surfaces exposed by excavation. Before excavation below ground water level, place the dewatering system into operation. Lower the water levels at least 30 cm below the bottom and side slopes of the excavation. Use screens and gravel packs as necessary on the dewatering devices to prevent the removal of fines from the soil. Operate the dewatering system continuously, 24 hours per day, 7 days per week until construction work below existing water levels is complete. Measure and record the performance of the dewatering system at the same time each day by use of observation wells and piezometers installed in conjunction with the dewatering system. After placement of initial slabs and backfilling, the water level may be allowed to rise but at no time allow it to rise higher than 30 cm below the prevailing level of excavation or backfill. Have a back-up system available for immediate use. Struts and shoring shall be placed as necessary for the protection of the work and for the safety of personnel. Adequate precautions shall be taken for the protection of existing underground pipelines or electrical cables. Before any excavation is started, plans showing the approximate location of underground utility lines shall be furnished to the Contractor, upon his request. The area of excavation shall be delimited by trestles, gangplanks, and warning signs visible during night and day, to prevent injuries to persons, as prescribed by the ISPESL standards.

b. Trenches. Trenches shall be of the necessary width for the proper laying of electric cables, and the banks shall be as nearly vertical as practicable. The bottom shall be accurately graded so as to provide bearing for the pipe on firm soil. The clear space between the pipe and the trenches wall shall not exceed 8" (20 cm.) on either side of the pipe.

IIIb-1

Further excavation will be required for housing and sealing of pipe joints. In proximity of buildings, existing underground utility lines, and wherever specifically requested in other sections of these specifications or on drawing notes, trenches shall be excavated manually.

c. Excavation for Foundation and Appurtenances. Excavation for manholes and similar structures shall be of sufficient dimensions as to leave a 12 inches (30 cm.) free space between their outer surfaces and the embankment or timber which may be used to hold the banks.

3b-02 BACKFILLING. Trenches shall not be backfilled until foundation, cables have been inspected and approved. Where, in the opinion of the COR, damage is likely to result from withdrawing of shoring, the latter shall be left in place. Trenches shall be backfilled with the excavated materials, if deemed suitable, free from large clods of earth, stones, and roots.

Backfilling material shall be deposited in 15 cm. (6") layers, thoroughly rammed until the trench is completely covered, and watered as necessary. Any material rejected by COR shall be replaced with material acceptable to the COR, coming from borrow pits located outside the US military base.

3b-03 REPAIRS. All crossings of existing paved or asphalt coated surfaces shall be cut neatly vertical and horizontal. At the completion of the work, pavement and sidewalks shall be restored to the original conditions. Damaged lawns shall be sown again and damaged plants shall be replaced with others of the same kinds. Any damage caused during the work progress shall be repaired by and at the expense of the Contractor. The Contractor shall be responsible also for injuries caused to persons as a result of non-compliance with prescribed ISPESL norms.

NOTE: In addition to above requirements, before starting the excavation, the Contractor must investigate with a metal detector furnished by himself the location of existing underground utility lines, e.g. electrical, communications, water, TV lines, or any other utility which may not be shown on the existing condition drawings, in order to prevent damaging or interrupting any existing utility. Investigation shall be done in the presence of the COR. Trial runs shall be done with the metal detector in the presence of the COR or his representative prior to the investigation. Investigation shall be done following COR approval of metal detector. The Contractor shall mark-up on a copy of the existing conditions the exact field location of the existing utility lines which are found during excavation. This copy shall then be submitted to the COR. Excavation work performed close to existing utility lines shall be done by hand within a 1 meter radius.

IIIb-2

SECTION IIId

EXTERIOR SANITARY SEWER SYSTEM

3d-01 RELATED REQUIREMENTS AND DESCRIPTION OF WORK. The work includes provision of new sanitary sewer system and related work. Provide the system complete and ready for operation.

3d-02 PIPES. Shall be PVC solid wall pipes type SN8 SDR34, conforming to UNI EN 1401-1.

Fittings and flanges shall conform to UNI 7449. The joints shall be of the ball and spigot type with elastomeric seal.

3d-03 FRAMES, COVERS AND GRATES. Frames, covers and grates shall be made of ductile iron, Class ISO 1083, in accordance with standard UNI ISO EN 124, Class D400 unless indicated otherwise, with round cover, not ventilated, diameter as indicated, opening on rotula.

3d-04 MORTAR. Mortar for connections to other drainage structures shall be composed of one part by volume of Portland cement and two parts of sand. The quantity of water in the mixture shall be sufficient to produce a stiff workable mortar. Water shall be clean and free of harmful acids, alkalis, and organic impurities. Include with shrinkage additive in accordance with product manufacturer’s recommendations. The mortar shall be used within 30 minutes from the time the ingredients are mixed with water. The inside of the joint shall be wiped clean and finished smooth.

3d-05 BURIED UTILITY WARNING AND IDENTIFICATION TAPE. Provide detectable aluminum foil plastic-backed tape or detectable magnetic plastic tape manufactured specifically for warning and identification of buried piping. Tape shall be detectable by an electronic detection instrument. Provide tape in rolls, 7,5 cm minimum width, red-colored for the utility involved.

Use permanent coloring unaffected by moisture and other substances contained in trench backfill material. Bury tape at a depth of 30 cm below the top surface of earth or the top surface of the subgrade under pavements.

3d-06 SEWER STRUCTURES. Prefabricated concrete pits are acceptable upon submittal and approval of catalogs and shop drawings.

3d-07 INSTALLATION OF PIPE. Each pipe shall be carefully examined before being laid, and defective or damaged pipe shall not be used. Pipelines shall be laid to the grades and alignment indicated. Proper facilities shall be provided for lowering sections of pipe into trenches.

IIId-1

Under no circumstances shall pipe be laid in water, and no pipe shall be laid when trench conditions or weather are unsuitable for such work. All pipes in place shall have been approved before backfilling. Laying of pipes shall proceed upgrade with the spigot ends of bell-and-spigot pipe, and the tongue ends of tongue-and-groove pipe pointing in the direction of the flow.

3d-08 PIPELINE TESTING. Each straight run of pipeline shall be checked for gross deficiencies by holding a light in a manhole; it shall show a practically full circle of light through the pipeline when viewed from the adjoining end of the line.

3d-09 WATERPROOFING OF CONCRETE SURFACE. Shall consist of one coat of asphalt primer and one coat of oxidized asphalt.

a. Asphalt Primer. Shall consist of bituminous material of commercial type, conforming to UNI 4157, brush-applied on concrete surface which is free of dust, dry and smooth.

b. Oxidized Asphalt. Shall be based on bitumen from selected oils, processed to controlled oxidation.

IIId-2

SECTION IIIe

EXTERIOR WATER SYSTEM

3e-01 INSTALLATION. All pipes shall be installed complete with special parts of all kinds (elbows, runouts, sleeves, brass fittings, etc.) and with the necessary threading, mastic, hangers, ties, anchors and supports. Pipes layout shall be such as to avoid sharp curves or chokes.

3e-02 FINAL TEST. Pipeline shall not be backfilled until all piping have been cleaned and inspected for seal. Therefore, the water system shall be hydrostatically tested at a pressure of 14 kg/sq.cm. for not less than 4 hours. Leaks noted during final test shall be eliminated by replacing the pipe or fitting. Caulking of joints will not be permitted. After such replacements, tests shall be repeated until positive result is obtained. All tests will be conducted in presence of the COR, by Contractor's furnished equipment, at no additional cost to the US Government.

3e-03 DISINFECTION. Each unit of completed water service line shall be disinfected as specified herein. After pressure tests have been made, the unit to be disinfected shall be thoroughly flushed with water until all entrained dirt and mud have been removed before introducing the chlorinating material. The chlorinating material shall be either calcium hypochlorite or sodium hypochlorite. The chlorinating material shall provide a dosage of no less than 50 ppm and shall be introduced into the water lines in an approved manner. In no case will the agent be introduced into the line in a dry solid state. The treated water shall be retained in the pipe long enough to destroy all bacteria and spores bacteria. Except where a shorter period is approved, the retention time shall be at least 24 hours; no less than 10 ppm of chlorine shall result throughout the line at the end of the retention period. All valves on the lines being disinfected shall be opened and closed several times during the contact period. The line shall then be flushed with clean water until the residual chlorine is reduced to less than 1.0 ppm. The Contracting Officer will take samples of water from several points in the unit in proper sterilized containers for bacterial examination. The disinfection shall be repeated until tests indicated absence of pollution for at least 2 full days. The unit will not be accepted until satisfactory bacteriological results have been obtained.

3e-04 WORK ON MAIN DISTRIBUTION LINES. Gate valves operation on main water distribution lines will be performed by the maintenance personnel.

IIIe-1

Water supply interruptions shall be scheduled so as to minimize length. Maintenance personnel assistance shall be requested through the COR at least 3 working days ahead of time.

3e-05 MATERIALS AND EQUIPMENT.

1. Pipes. High…