About this file

Amendment 0002

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

0011169121 AA1 00214-6

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to provide the answ ers to the questions submitted by a company.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 31-May-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912PF18R0006

X 9B. DATED (SEE ITEM 11)

23-Apr-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

31-May-2018

CODE

414TH CSB RCO ITALY SUBOFFICE LIVORNO

VIA AURELIA, EDIFICIO 5131

ZONA DEPOSITO

56128 TIRRENIA (PISA)

W912PF 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912PF18R0006

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

RFI

REQUEST FOR INFORMATION

1) QUESTION: Do you confirm that a PEHD conduit needs to be used for underground electrical power lines?

ANSWER: Yes, see requirements listed in parag. 13a-8.2 of technical specification

2) QUESTION: The marker tape that needs to be laid above the underground conduits (during the laying of conduits) have to be magnetic or non magnetic?

ANSWER: The marker tape shall be magnetic as required in parag. 3b-03.

3) QUESTION: - Can we re-fill our excavation area with the previously excavated material (in the same place)?

ANSWER: Yes.

4) QUESTION: Can we have the dwg files, about the drawings included in Solicitation?

ANSWER: No. Drawing file will not be given during the bidding phase; drawing files will be given only to the Contractor after the award, in order to provide the as built drawings.

5) QUESTION: The wood from the cut trees need to be picked up to dedicated places (like discarica) or can be left on in place (in Natural Reserve area)?

ANSWER: With reference to Section IIIa of Technical Specification, please assume that approximately 9 trees will need to be cut in the project, diameter varying from 15 to 60 cm.

The wood coming from branches less than 15 cm will be disposed out of base to dump, while the rest shall be treated in accordance with one of the last two alternatives in the Section.

6) QUESTION: In drawing CS101 (rif. Detail 04 - CS501) is shown an underground conduit for Optical Fiber line. Do we have to consider it as a predisposition or do we have to pull an optical fiber cable? If so, from where to where and please specify the type?

ANSWER: Only cable ducts is required to be installed; Contractor shall not install any fiber optic cable.

7) QUESTION: The required light fixtures will be ON-OFF only, or do you need dimmable lights? Do you need the virtual midnight set point or once the light is on is always 100%?

W912PF18R0006

ANSWER: The required lighting fixtures will be ON-OFF only.

8) QUESTION: Do you confirm that the new electrical light lines will be activated only by the 0-1 rotary selector that will be installed on the exterior side of each electrical substation (without any light sensor or timer)?

ANSWER: Confirmed

9) QUESTION :During the "UXO" (Unexploded Ordnance) verification/test, do we need to provide safety signs as per DETAIL#2 in drawing SC00 ? Or another kind of signposting/protection is required?

ANSWER: For the use of the mentioned drawing see also PSC, Section 9.3.

Additional requirements for the UXO search could come from the final project to be submitted to the 5th Reparto.

10) QUESTION: The BID GUARANTEE of 10% is required only based on ITEM 0001 or on the sum of ITEM0001 + ITEM0002 ?

ANSWER: The BID GUARANTEE is required on the sum of Item 0001+ Item 0002.

11) QUESTION: - Is the COR in charge for the presentation of the DIGGING PERMIT on this area, or is the contractor in charge for it?

ANSWER: The digging permit is requested by the Contractor to the COR who, in turn, routes it through the competent offices.

12) QUESTION: Are there any particular request for working in ASA area or not? If so, is the COR or the contractor in charge for get the approvals?

ANSWER: The particular requirements for the ASA are listed in the Enclosure to the Technical Specifications. Any kind of required approvals will ALWAYS need to be routed through the COR.

(End of Summary of Changes)