0011169121 AA1 00214-6
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
1.The purpose of this amendment is to change the performance schedule ( see continuation sheets for detail)
2. The closing date of this solicitation has been changed from 24 May 2018 to 18 June 2018 at 12:00 hrs
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 23-May-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912PF18R0006
X 9B. DATED (SEE ITEM 11)
23-Apr-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
23-May-2018
CODE
414TH CSB RCO ITALY SUBOFFICE LIVORNO
VIA AURELIA, EDIFICIO 5131
ZONA DEPOSITO
56128 TIRRENIA (PISA)
W912PF 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912PF18R0006
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 24-May-2018 12:00 PM to 18-Jun-
2018 12:00 PM.
The contractor period of performance end date has increased by 20 days from 210 days to 230 days.
SECTION B - SUPPLIES OR SERVICES AND PRICES
CLIN 7500 is added as follows:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
7500 1 Each
CMR
FFP
Contract Manpower Report (CMR) - The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the subject contract via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: http://www.ecmra.mil/ Default .aspx.
Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year, beginning with 2018.
Contractors may direct questions to the help desk by clicking on “Send an email” which is located under the Help Resources ribbon on the right side of the login page of the applicable Service/Component’s CMR website.
FOB: Destination
PSC CD: N056
NET AMT
SECTION E - INSPECTION AND ACCEPTANCE
The following Acceptance/Inspection Schedule was added for CLIN 7500:
INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
Destination Government Destination Government
SECTION F - DELIVERIES OR PERFORMANCE
The following Delivery Schedule item for CLIN 0001 has been changed from:
DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
210 dys. ADC 1 W582RR USAG ITALY
N/A
USAG ITALY, DARBY MILITARY
COMMUNITY VIA AUR
TIRRENIA (PISA)
N/A
W582RR
To:
DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
230 dys. ADC 1 W582RR USAG ITALY
N/A
USAG ITALY, DARBY MILITARY
COMMUNITY VIA AUR
TIRRENIA (PISA)
N/A
The following Delivery Schedule item for CLIN 0002 has been changed from:
CAGE
90 dys. ADC 1 W582RR USAG ITALY
N/A
USAG ITALY, DARBY MILITARY
COMMUNITY VIA AUR
TIRRENIA (PISA)
N/A
To:
CAGE
70 dys. ADC 1 W582RR USAG ITALY N/A
USAG ITALY, DARBY MILITARY
COMMUNITY VIA AUR
TIRRENIA (PISA)
N/A
The following Delivery Schedule for CLIN 7500 has been added:
CAGE
300 dys. ADC 1 W582RR USAG ITALY
N/A
USAG ITALY, DARBY MILITARY
COMMUNITY VIA AUR
TIRRENIA (PISA)
N/A
The following have been modified:
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 230 calendar days from the issuance of the notice to proceed ( Basic project). The time stated for completion shall include final cleanup of the premises.
(End of clause)
NOTE : The performance period for option item (CLIN 0002) is 70 calendar days