1. Question- Will all or portions of the 10,000LF of supplied fiber optic cable have to be installed by the contractor?
Answer- No, supply only.
2. Question- Is the Pre-Bid Mandatory? (the Government assumes this is referring to the Site Visit)
Answer- No.
3. Question- No Bid Submittal Instructions other than the Project Pricer Sheet are provided. Is this the only Bid Submittal Required?
Answer – Yes. The Bid Schedule (Section B) needs to be filled out completely.
4. Question- The Project Specific Davis- Bacon Wage Determination?
Answer- This is not considered a construction contract. Davis Bacon Wage Determinations don’t apply.
5. Question- Is a Bid Bond and Performance and Payment Bond Required with Bid Submittal?
Answer- No.
6. Question- Finally, the Preliminary Solicitation, indicates this is a Fiber Distribution Panel Installation, Splicing, And Testing Project only. Please confirm that the Switch Equipment, Racks, and Powering Equipment shown in the Project Diagrams, and all the Distribution Fiber is provided and installed by others.
Answer- Confirmed. The scope of the project only includes “Fiber Distribution Panel Installation, Splicing, and Testing.” Other equipment is existing or installed by others.