A02._Section_C_-_Locks_and_Dams_24_and_25_Fiber_Optic_Retermination.pdf
PDF 175 KB Posted
- Attached to
- Fiber Optic Cable Retermination
- Solicitation number
- W912P919T0042
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. ARMY CORPS OF ENGINEERS
LOCK AND DAM NOS. 24 AND 25
CLARKSVILLE AND WINFIELD, MISSOURI
FIBER OPTICE CABLE RETERMINATION
1 General
1.1 SCOPE
The Contractor shall furnish all labor, supervision, equipment, and supplies necessary for the installation of fiber optic patch panels and retermination of fiber optic communications cables between all remote I/O racks at Lock and Dam 24 and Lock and Dam
25. Individual locations for remote racks at each site can be found in drawings E-101, E-102, and E-103. Major items of work included in this service contract include:
Supply fiber optic cable
Supply and install new fiber optic patch panels
Reterminate and label fiber optic cables in patch panels
Provide all testing as specified herein
1.2 SITE VISIT
A pre-bid site visit is scheduled for July 31st 2019 at 9:00 a.m.
CST to see the location of the proposed project. Participants will meet at Lock and Dam 25, 10 Sandy Slough Road, Winfield, MO
63389. Please contact Contract Specialist Reid Drewes at
Reid.A.Drewes@usace.army.mil to confirm attendance for planning purposes.
1.3 DEFINITIONS
1.3.1 CONTRACTING OFFICER
The term “Contracting Officer” (KO) means the person executing this contract on behalf of the Government, and any officer or civilian employee who is properly designated
Contracting Officer. The term also includes, except as otherwise provided in this contract, the authorized representative of the Contracting Officer (COR) acting within the limits of his authority.
1.4 CODE AND SAFETY COMPLIANCE
All work shall be performed in accordance with the requirements of NFPA 70, IEEE C2, and EM 385-1-1.
1.5 SAFETY
All work shall be performed in accordance with the safety requirements set forth in the Corps of Engineers Manual, EM 385-
1-1, entitled “Safety and Health Requirements Manual”, 30
November, 2014; a copy is available at:
http://www.publications.usace.army.mil/Portals/76/Publications/En gineerManuals/EM_385-1-1.pdf
The Contractor shall be responsible for complying with the current edition and all changes posted on the web. The COR will notify the Contractor of any noncompliance with these provisions.
The Contractor shall, after receipt of such notice, immediately take corrective action. Such notice, when delivered to the mailto:Reid.A.Drewes@usace.army.mil http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf
Contractor, shall be deemed sufficient for the purpose. If the
Contractor fails or refuses to comply promptly, the COR may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to any such stop orders shall be made the subject of claim for extension of time or for excess cost or damages by the
Contractor. Compliance with the provisions of this clause by subcontractors will be the responsibility of the Contractor.
1.6 APPLICABLE PUBLICATIONS
The latest issues of the following publications, but referred to thereafter by basic designation only, form a part of the specifications to the extent indicated by the reference thereto.
Institute of Electrical and Electronics Engineers (IEEE).
C2 (2017) National Electrical Safety Code
National Fire Protection Association (NFPA).
70 (2017) National Electrical Code
National Electrical Manufacturers Association (NEMA).
250 (2018) Enclosures for Electrical Equipment
United States Army Corps of Engineers (USACE).
EM 385-1-1 (2014) Safety and Health Requirements
Telecommunications Industry Association (TIA).
TIA-455-104 (2016b) Standard for FOTP-104 Fiber Optic
Cable Cyclic Flexing Test
TIA-455-13 (1996a; R 2012) FOTP-13 Visual and
Mechanical Inspection of Fiber Optic
Components, Devices, and Assemblies
TIA-455-177 (2003b) FOTP-177 IEC-60793-1-43:
Measurement Methods and Test Procedures -
Numerical Aperture
TIA-455-58 (2001b) FOTP-58 Core Diameter Measurement of Graded-Index Optical Fibers
TIA-455-78-B (2002) FOTP-78 Optical Fibres – Part 1-
40: Measurement Methods and Test
Procedures - Attenuation
TIA-455-91 (1986; R 1996) FOTP-91 Fiber Optic Cable
Twist-Bend Test
TIA/EIA-455-171 (2001a) FOTP-171 - Attenuation by
Substitution Measurement for Short-Length
Multimode Graded-Index and Single-Mode
Optical Fiber Cable Assemblies
TIA/EIA-455-204 (2000) Standard for Measurement of
Bandwidth on Multimode Fiber
TIA/EIA-455-25 (2016d) FOTP-25 Impact Testing of Optical
Fiber Cables
TIA/EIA-455-41 (1993a; R 2013) FOTP-41 Compressive
Loading Resistance of Fiber Optic Cables
TIA/EIA-455-88 (2001) FOTP-88 Fiber Optic Cable Bend
Test
1.7 ORDER AND COORDINATION OF WORK
The Contractor shall start and complete work in such order and sequence as specified in this contract and in compliance with the following paragraphs.
1.7.1 This effort will be coordinated with lock closures
scheduled for additional work by others. The closures are scheduled to start at both locks on 15 Dec 2019. The
Contractor’s work must be coordinated with the Government as they are responsible for demolition of equipment in the existing enclosures on the lock and dam. Termination of the fiber optic cable at Miter Gate No. 4 will be delayed until the other Contractor completes their concrete work and re-installs the fiber optic cable to the enclosure.
1.7.2 The Contractor shall coordinate all work with the
Contracting Officer’s Representative and the Lockmaster.
1.7.3 All work required in this contract, including proper
containment and disposal of debris, shall be accomplished in place at Contractor’s expense.
1.7.4 The Contractor shall furnish all electrical power or other required utilities required for construction activities. No temporary hookups to existing lock facilities will be allowed unless stated otherwise in this specification.
1.7.5 At least thirty (30) days prior to mobilization, the
Contractor shall submit the plan for storage of materials and equipment at the site to the Contracting Officer for approval.
1.7.6 Construction limits shall extend as shown on the drawings.
Contractor personnel may cross the main lock upper and/or lower miter gate when the gates are closed, the incomplete auxiliary lock using the closed miter gate, and dam using the service bridge to gain access to the construction limits at both sites. Only hand carried equipment shall be brought across the miter gates and the dam by Contractor personnel.
1.7.7 The Contractor’s employees shall park personal vehicles outside of Government Property.
1.7.8 Potable water and portable toilet facilities for Contractor use shall be provided by the Contractor.
1.7.9 Security fencing and hand railing may be removed in work areas during construction as long as safety and security is maintained and replacement made to its original location and condition, including an approved method and type of touch up painting as necessary. Contractor proposals for modifying fencing and handrails shall meet requirements in
EM 385-1-1 and be submitted for approval.
1.7.10 All elevations and dimensions shall be verified in the field before work begins. The Contractor is responsible for confirming all dimensions prior to shop drawings preparation and material fabrication.
1.7.11 Access to the dam across the overflow spillway will not be permitted at either site.
1.7.12 The staging area for the contract shall be coordinated with the projects. No loading or unloading of materials and supplies shall be permitted from the lock walls or guide walls.
1.7.13 The Contractor shall provide the Contracting Officer and the Lockmaster at each location or the designated representatives a minimum of a two (2) week initial notification and a final 48 hour advance notice prior to commencement of any work. The Contractor shall also coordinate access to the construction area with the
Contracting Officer and Lockmaster or designated representatives at the contact information provided below:
Tony Reis, Lockmaster, Lock and Dam 25
10 Sandy Slough Road
Winfield, MO 63389
636-566-8120
Ryan Lee, Lockmaster, Lock and Dam 24
350 North 1st Street
Clarksville, MO 63336
535-242-3524
1.7.14 “As-Built” Contract Drawings. The Contractor shall maintain a separate set of full-size contract drawings, marked up in red, to indicate as-built conditions. Each as-built contract drawing shall include the Contract Number associated with the contract. These drawings shall be maintained in a current condition at all times until completion of the work and shall be available for review by
Government personnel at all times. All variations from the contract drawings, for whatever reason, including those occasioned by modifications, optional materials, and the required coordination between trades, shall be indicated.
These variations shall be shown in the same general detail utilized in the contract drawings. One set of marked-up hard copy drawings and one electronic copy of the marked-up drawings in pdf format shall be furnished to the
Contracting Officer prior to acceptance of the work.
1.8 CABLE SCHEDULES
The cables schedules provided for each facility identify the fiber optic cables to be terminated or reterminated by the
Contractor. The Government will be replacing two 6-fiber cables used on the lock with a single 12-fiber cable. The Government will also be replacing the 6-fiber cables between the Central
Control House and the two Control Shelters. The Contractor shall terminate all fibers in the cable.
1.9 DELIVERY AND STORAGE
Items specified in this section comprised of all fiber optic cables, patch panels, and appurtenances shall be scheduled for shipment to arrive on the job site no more than seven days prior to its scheduled installation date. Upon delivery at the work site, the Contractor is responsible for unloading, storing, and protecting all items in accordance with the manufacturer’s written recommendations. Deliveries should be scheduled M-F 0700-
1600hrs. No deliveries will be accepted on weekends or federal holidays. A 48 hour notification is required for all deliveries.
The Government will not be liable for any additional delivery fees due to not following the listed delivery times and requirements. Shipping Addresses are as follows:
Lock and Dam 24
Attn: Fiber Optic Retermination
350 North 1st Street
Clarksville, MO 63336
Lock and Dam 25
Attn: Fiber Optic Retermination
10 Sandy Slough Road
Winfield, MO 63389
1.10 BIDDING SCHEDULE
See Section B – Bidding Schedule. This solicitation will contain multiple bid line items. See Bidding Schedule notes for detailed information.
1.11 POINTS OF CONTACT
All questions in regards to this solicitation should be directed to the following Point Of Contact:
Reid Drewes
U.S. Army Corps of Engineers, St. Louis District
314-331-8384
Reid.A.Drewes@usace.army.mil
Questions when working onsite may be directed to the Site POCs.
Dan Portwood
U.S. Army Corps of Engineers
Lock and Dam 24 Electronic Integrated System Mechanic
573-242-3524
Carl.D.Portwood@usace.army.mil
Steve Lovell
U.S. Army Corps of Engineers
Lock and Dam 25 Electronic Integrated System Mechanic
636-566-8120
Steven.D.Lovell@usace.army.mil
2 BASE WORK TO BE PERFORMED BY CONTRACTOR
2.1 SUPPLY FIBER OPTIC CABLE FOR LOCK AND DAM 24 AND 25
2.1.1 The Contractor shall supply fiber optic cable for each
facility in the quantities shown on the bid schedule.
2.1.2 Optical Fibers
2.1.2.1 General. Coat optical fibers with a suitable material to preserve the intrinsic strength of the glass. The mailto:Carl.D.Portwood@usace.army.mil mailto:Steven.D.Lovell@usace.army.mil outside diameter of the glass-cladded fiber is nominally 125 microns, and concentric with the fiber core. Ensure optical fibers meet TIA-455-78-B, and
TIA-455-177.
2.1.2.2 62.5 Micron Multimode Fibers. Use conductors that are multimode, graded index, solid glass waveguides with a nominal core diameter of 62.5 microns. Ensure the fiber has transmission windows centered at 850 and
1300 nanometer wavelengths, with a numerical aperture minimum of 0.275. The attenuation at 850 nanometers is 3.5 dB/Km or less. The attenuation at 1300 nanometers is 1.5 dB/Km or less. The minimum bandwidth is 160 MHz-Km at 850 nanometers and 500
MHz-Km at 1300 nanometers. Certify FO cable to meet
TIA/EIA-455-204 and TIA-455-58.
2.1.3 Cable Construction
2.1.3.1 General. The number of fibers in each cable is twelve
(12). Protect each fiber by a protective tube. Ensure cables have a jacketed strength member, and an exterior jacket. Ensure cable and fiber protective covering are free from holes, splits, blisters, and other imperfections. Insulation and jacketing material for interior cables cannot contain any polyvinyl chloride (PVC) compounds. Use a covering that is flame retardant, moisture resistant, non-nutrient to fungus, ultraviolet light resistant as specified, and nontoxic. Do not transmit mechanical stress present in cable to the optical fibers. Ensure strength members are non-metallic and an integral part of the cable construction. Ensure the combined strength of all the strength members is sufficient to support the stress of installation and to protect the cable in service. For exterior cables, select a minimum storage temperature range of minus 40 to plus
75 degrees C minus 104 to plus 167 degrees F. A minimum storage temperature of minus 10 to plus 75 degrees C plus 14 to plus 167 degrees F is required for interior cables. Ensure all optical fiber cables and all optical fiber raceways furnished meet the requirement of NFPA 70. Apply a flooding compound into the interior of the fiber tubes, into the interstitial spaces between the tubes, to the core covering, and between the core covering and jacket of all cable to be installed aerially, underground, and in locations susceptible to moisture. Ensure flooded cables comply with TIA/EIA-455-81 and TIA-455-82.
Provide cables from the same manufacturer, of the same cable type, of the same size, and of the same optical characteristics. Ensure each fiber and protective coverings is continuous with no factory splices. Certify by the manufacturer, optic cable assemblies, including jacketing and fibers, to have a minimum life of 30 years. Ensure cables meet UL 1666.
Certify FO cable to meet the following: TIA-455-13, TIA/EIA-455-25, TIA/EIA-455-41, TIA-455-177, TIA-455-
78-B, TIA/EIA-455-88, TIA-455-91, TIA-455-104, and
TIA/EIA-455-171.
2.1.3.2 Exterior Cable. Surround the optical fibers by a tube buffer, contained in a channel or otherwise loosely packaged to provide clearance between the fibers and inside of the container, and extruded from a material having a coefficient of friction sufficiently low to allow the fiber free movement. Select cable with the following characteristics:
a. Cable outer jacket: Medium density polyethylene material with orange pigment added for ease of identification.
b. Tensile strength: Withstand an installation tensile load of not less than 608 pounds and not less than 135 pounds continuous tensile load.
c. Impact and Crush resistance: Withstand an impact of 1.7 lbs/in as a minimum, and have a crush resistance of 317 psi as a minimum.
Fiber optic cables shall be Corning ALTOS® Loose Tube, Gel-Free, All-Dielectric Cable with FastAccess®
Technology, or an approved equal.
2.2 SUPPLY FIBER OPTIC PATCH PANELS FOR LOCK AND DAM 25
2.2.1 The Contractor shall provide patch panels for all remote racks and building locations at Lock and Dam 25 as identified in drawings E-101 and E-103 with sufficient patch panel capacity to terminate all optical fibers in each enclosure. Quantities of optical fibers to terminate in each remote rack enclosure are as follows:
MCC1, MCC3, RR-MG4, RR-TG17 (4 enclosures):
12 fibers per enclosure
All other enclosure racks (19 enclosures):
24 fibers per enclosure
Central Control House, U/S Landwall Control Shelter, D/S Landwall Control Shelter (3 Locations):
12 fibers per location
2.2.2 Patch panels shall be of type Corning SPH-01P or
equivalent, as required by each patch panel location.
Contractor shall be responsible for field-verifying that proposed patch panel(s) will work at each location. Any proposed patch panel not specified in this contract must be approved by the Government. Any purchasing of unusable patch panels shall be at the expense of the contractor.
2.2.3 Patch panels for use in the Central Control House, U/S
Landwall Control Shelter, and D/S Landwall Control Shelter shall be of type Corning WPH-02P or equivalent, as required by each patch panel location. Contractor shall be responsible for field-verifying that proposed patch panel(s) will work at each location. Any proposed patch panel not specified in this contract must be approved by the Government. Any purchasing of unusable patch panels shall be at the expense of the contractor.
2.2.4 Contractor shall also supply appropriate CCH (Closet
Connector Housing) panels for each patch panel. Each CCH panel shall be of type SC, capable of patching through 12 multimode, 62.5-micron, SC-terminated fibers. Contractor shall install CCH panels in patch panels as directed by the manufacturer.
2.3 SUPPLY FIBER OPTIC PATCH PANELS FOR LOCK AND DAM 24
2.3.1 The Contractor shall provide patch panels for all remote racks and building locations at Lock and Dam 24 as identified in drawings E-102 and E-103 with sufficient patch panel capacity to terminate all optical fibers in each enclosure. Quantities of optical fibers to terminate in each remote rack enclosure are as follows:
MCC1, MCC3, RR-MG4, RR-TG15 (4 enclosures):
12 fibers per enclosure
All other enclosure racks (17 enclosures):
24 fibers per enclosure
Central Control House, U/S Landwall Control Shelter, D/S Landwall Control Shelter (3 Locations):
12 fibers per location
2.3.2 Patch panels shall be of type Corning SPH-01P or
equivalent, as required by each patch panel location.
Contractor shall be responsible for field-verifying that proposed patch panel(s) will work at each location. Any proposed patch panel not specified in this contract must be approved by the Government. Any purchasing of unusable patch panels shall be at the expense of the contractor.
2.3.3 Patch panels for use in the Central Control House, U/S
Landwall Control Shelter, and D/S Landwall Control Shelter shall be of type Corning WPH-02P or equivalent, as required by each patch panel location. Contractor shall be responsible for field-verifying that proposed patch panel(s) will work at each location. Any proposed patch panel not specified in this contract must be approved by the Government. Any purchasing of unusable patch panels shall be at the expense of the contractor.
2.3.4 Contractor shall also supply appropriate CCH (Closet
Connector Housing) panels for each patch panel. Each CCH panel shall be of type SC, capable of patching through 12 multimode, 62.5-micron, SC-terminated fibers. Contractor shall install CCH panels in patch panels as directed by manufacturer.
2.4 INSTALL PATCH PANELS IN MCCS AND LOCK AT LOCK AND DAM 25
2.4.1 The Government will be responsible for demolition of old
PLC and fiber equipment. The Government will also be responsible for any replacement of old fiber optic cables.
2.4.2 Contractor shall supply all labor, supervision, parts, and equipment to install patch panels for each MCC (Motor
Control Center) in the electrical equipment room and remote
I/O rack enclosure on the lock at Lock and Dam 25.
Placement of patch panel(s) within each remote rack shall be coordinated with the Government.
2.4.3 Contractor shall supply all labor, supervision, parts, and equipment to terminate all optical fibers in patch panels with type SC connectors, with the exception of any cable designated “CONNECTION FOR LAPTOP” in R-001. Cables designated as such will be removed or abandoned, at the discretion and as the responsibility of the Government.
Contractor shall provide fan-out kits as necessary.
2.4.4 The Government will be responsible for providing and
installing patch cables from the patch panels to the devices in the remote racks.
2.5 INSTALL PATCH PANELS IN MCCS AND LOCK AT LOCK AND DAM 24
2.5.1 The Government will be responsible for demolition of old
PLC and fiber equipment. The Government will also be responsible for any replacement of old fiber optic cables.
2.5.2 Contractor shall supply all labor, supervision, parts, and equipment to install patch panels for each MCC (Motor
Control Center) in the electrical equipment room and remote
I/O rack enclosure on the lock at Lock and Dam 24.
Placement of patch panel(s) within each remote rack shall be coordinated with the Government.
2.5.3 Contractor shall supply all labor, supervision, parts, and equipment to terminate all optical fibers in patch panels with type SC connectors, with the exception of any cable designated “CONNECTION FOR LAPTOP” in R-002. Cables designated as such will be removed or abandoned, at the discretion and as the responsibility of the Government.
Contractor shall provide fan-out kits as necessary.
2.5.4 The Government will be responsible for providing and
installing patch cables from the patch panels to the devices in each remote rack.
2.6 INSTALL PATCH PANELS ON DAM AT LOCK AND DAM 25
2.6.1 The Government will be responsible for the demolition of old PLC and fiber equipment.
2.6.2 Contractor shall supply all labor, supervision, parts, and equipment to install patch panels for each remote I/O rack enclosure on the dam at Lock and Dam 25. Placement of patch panel(s) within each remote rack shall be coordinated with the Government.
2.6.3 Contractor shall supply all labor, supervision, parts, and equipment to terminate all optical fibers in patch panel with type SC connectors. Contractor shall provide fan-out kits as necessary.
2.6.4 Contractor shall document the layout of the fibers
terminated in the patch panels at each panel and in separate documentation.
2.6.5 The Government will be responsible for providing and
installing patch cables from the patch panels to the devices in the remote racks.
2.7 INSTALL PATCH PANELS ON DAM AT LOCK AND DAM 24
2.7.1 The Government will be responsible for the demolition of old PLC and fiber equipment.
2.7.2 Contractor shall supply all labor, supervision, parts, and equipment to install patch panels for each remote I/O rack enclosure on the dam at Lock and Dam 25. Placement of patch panel(s) within each remote rack shall be coordinated with the Government.
2.7.3 Contractor shall supply all labor, supervision, parts, and equipment to terminate all optical fibers in patch panel with type SC connectors. Contractor shall provide fan-out kits as necessary.
2.7.4 Contractor shall document the layout of the fibers
terminated in the patch panels at each panel and in separate documentation.
2.7.5 The Government will be responsible for providing and
installing patch cables from the patch panels to the devices in each remote rack.
2.8 FIBER OPTIC CABLE TESTING
2.8.1 An optical time domain reflectometer test shall be
performed in accordance with the fiber optic test procedures of TIA-455-78-B on all fibers of each fiber optic cable prior to retermination with an optical time domain reflectometer calibrated to show anomalies of 0.2 dB as a minimum. Photographs of the traces shall be furnished to the Government. Documentation of any anomalies greater than 1 dB found prior to retermination work shall be furnished to the Government
2.8.2 An identical optical time domain reflectometer test shall again be performed on all fibers of each fiber optic cable after retermination work. If the optical time domain reflectometer test results show anomalies greater than 1 dB, the retermination work will be considered unacceptable to the Government. The unsatisfactory fibers shall be reterminated again until satisfactory. Photographs of the traces for each fiber shall be furnished to the Government prior to completion of the contract.
3 INSPECTION AND ACCEPTANCE
3.1 INSPECTION
All supplies shall be inspected upon delivery. No inspector is authorized to change any requirements of the contract.
3.2 WARRANTY AND O&M DOCUMENTATION
Contractor shall provide warranty documentation and any operation and maintenance documentation to the Government by the end of the project.
3.3 CONTRACTOR WASTE
Any Contractor generated waste, including parts and supplies being removed as part of this service shall be properly removed from Government property by the end of the project.
3.4 CONTRACT ADMINISTRATION DATA
Payment may be made by way of Government Visa for the work actually completed if in the Government’s best interest. Invoices shall contain the following information: Contractor’s name and address; contract number; contract description of supplies or services as specified in Section 4; quantities and extended totals, and upon submission to the Contracting Officer a complete accounting of all man-hours used to accomplish the job.
4 INSURANCE
4.1 REQUIRED INSURANCE
As required by the Contract Clause entitled “Insurance –
Work on a Government Installation”, the Contractor shall furnish to the Contracting Officer, prior to the commencement of work, a certificate or written statement as evidence of the minimum insurance listed below. The
Contractor shall procure and maintain such types and amounts of insurance during the entire period of performance under this contract. The Contractor shall assure that the certificate or written statement is in accordance with required wording indicated in paragraph b of the aforementioned Contract Clause.
Workmen’s Compensation – Amounts required by applicable jurisdiction statutes.
Employer’s Liability Insurance - $100,000.00
Comprehensive General Liability Insurance – (No property damage liability insurance is required.)
Bodily Injury - $500,000 per occurrence
Comprehensive Automobile Insurance –
Bodily Injury - $200,000.00 each person
$500,000.00 each accident
Certificates of Insurance shall be submitted to the following address:
Rivers Project Office
Attn: Figerald Garcia Ledesma
301 Riverlands Way
West Alton, MO 63386
File details come from the government source that posted it.