W912P822R0006 Am10.pdf
PDF 838 KB Posted
- Attached to
- Atchafalaya River Levees, St. Mary Levee District. Charenton Floodgate - Replacement. St. Mary, Louisiana
- Solicitation number
- W912P822R0006
About this file
This document contains an amendment to a solicitation for the replacement of the Charenton Floodgate in St. Mary Parish, Louisiana. The amendment provides responses to questions from offerors and confirms the proposal submission date of July 18, 2022 at 11:00 am local time. Key details include that the work involves clearing and grubbing, structural excavation, installation of sheet piling, H-piling and pipe piling, construction of 380 feet of new flood wall and a new sector gate structure, placement of geotextile and levee embankment, and other miscellaneous metal work, painting and scour protection. The estimated construction value is between $25-100 million. The solicitation is full and open competition issued by the Department of the Army Corps of Engineers New Orleans District for NAICS code 237990.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ED 21-019
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The above numbered solicitation for Atchafalaya River Levees, St. Mary Levee District, Charenton Floodgate, Replacement, St. Mary Parish, Louisiana (ED 21-019) is hereby amended as follow s:
1) Provides Government responses to Offeror(s) questions.
2) The proposal submission date and time of Monday, July 18, 2022, at 11:00 am local time, remains the same.
1. CONTRACT ID CODE PAGE OF PAGES
1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 13-Jul-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P822R0006
X 9B. DATED (SEE ITEM 11)
14-Jan-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
13-Jul-2022
CODE
USACE, CONTRACTING DIVISION
ATTN: CEMVN-CT, ROOM 172
7400 LEAKE AVE.
NEW ORLEANS LA 70118-3651
W912P8 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
X 1
W912P822R0006
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0010
1. All in regards to the response to Question #13 from Phase 1 of the Solicitation:
a. Please clarify the 72,000lb load limit provided for the levee. Is this the load limit for the temporary access bridge support on the levee, or is this the axel load limit for haul vehicles?
Does this load limit only apply at the temporary access to the borrow? Construction of the gate structure will require equipment well in excess of the 72,000lbs.
Response: The 72,000 pound load limit refers to a HS-20 44 truck loading and is the maximum design load for the existing bridge and access route. Truck loads in excess of this limit for other areas of the job site will require approval of the Contracting Officer.
b. Will soil stabilization of the levee be permitted in order to support crane and equipment loadings for construction of the gate structures?
Response: The Contractor is responsible for demonstrating that his means and methods will not be detrimental to the work, subject to the approval of the Contracting Officer.
c. Is the load limit of the bridge across the existing structure due to the condition of the span or due to concerns with the condition of the walls/foundations the span is on?
Response: It is due to both.
2. Paragraph 3.3.7 of Spec Section 03 31 00.00 12 states that all T-walls, bases, and stems, and gatebay monolith require special thermal treatment, treating these structures as mass concrete. Some of these sections are as thin as 2 ft, whereas the LADOTD defines mass concrete as “a structural concrete placement having a least dimension of 48 inches or greater.” Will the Government consider revising this requirement so that it is only applicable to structures that have a minimum dimension of 48 inches or greater?
Response: No. Thermal analysis of the mix design will determine if controls are required
3. Is all embedded material to Hot Dip Galv. Coated, including Pipe Pile Tension Connectors & HP Tension Pile Connectors? General Note, Line 8.
Response: The pile tension connectors are not required to be galvanized.
4. Is the vertical rolled corner protection embeds CRS? See S-514, detail B5.
Response: Items designated as CRS shall be furnished as CRS, all other embedded metals shall be hot dip galvanized as per Steel Notes No. 8 on Sheet S-001.
5. Is all L 6 x 6 x 5/8 embed angle and L3 x 2 1/2 x 3/8 embed frame CRS? See S-517.
Response: Items designated as CRS shall be furnished as CRS, all other embedded metals shall be hot dip galvanized as per Steel Notes No. 8 on Sheet S-001.
6. Is Embedded plates in section A1 & A3 on S-517 CRS material?
Response: Items designated as CRS shall be furnished as CRS, all other embedded metals shall be hot dip galvanized as per Steel Notes No. 8 on Sheet S-001.
7. HP Piles are to be driven on a pitch and the drawings show the tension connectors to follow suit. Is this the case? If so, what is the degree or pitch on the piles?
Response: All non-vertical piles shall be installed at the batters shown on the drawings.
8. Equipment Cover Embeds shown as CRS with aluminum checker plate covers, is this correct?
Response: Yes, this is correct.
9. Per Section 05 59 20_Fabrication of Hydraulic Steel Structures Subsection 1.7.3, the assembly of the sector gate onsite shall be by the same fabricator that fabricated the gate offsite. Would the USACE allow the fabricator that fabricated the gate offsite to instead provide a certified supervisor to oversee the assembly of the gate by another contractor onsite rather than assemble the gate onsite themselves? It has been very hard trying to find a fabricator with the required certifications to do the offsite fabrication and the onsite assembly.
Additionally, per the same section, the gate fabricator must be certified under AISC in either of the two categories: Major Bridge Fabrication, having AISC fracture critical endorsement or Metal Hydraulic Fabrication. Is the certification Major Bridge the same as Bridge Fabricator – Advanced or Bridge Fabricator – Intermediate? A list of the AISC certifications are listed below. There are no Bridge Fabricator – Advanced in Louisiana and very few in the surrounding states that include the fracture control endorsement.
Response: As stated in Section 05 59 20, Section 1.7.3, AISC certification is required for both shop and field fabrication. This is necessary to comply with AWS and USACE requirements for fabrication of hydraulic steel structures and fracture critical members.
AISC is in the process of updating their certification categories. Fabricators may be certified as either IBR, Certified Bridge Fabricator – Intermediate with facture critical endorsement or ABR – Certified Bridge Fabricator – Advanced with fracture critical endorsement.
10. It calls for the contractor to fill the pipe pile with concrete to the mudline. Can you provide the anticipated depth of the pipe pile mudline in order for all contractors to bid the same depth?
Response: For consistency in bidding, contractors shall assume the top 10-ft of the pipe pile shall be filled with concrete. The remainder of the void (mudline to concrete) shall be filled with sand. All costs associated with filling the pipe pile shall be included in the applicable contract unit price and/or job price for which the work is incidental thereto.
The following have been deleted:
AMENDMENT 0008
(End of Summary of Changes)