This is an abstract of bids received in response to Solicitation Number W912P820B0042 issued by the Department of the Army Corps of Engineers Engineering District New Orleans. The solicitation was for construction work on the Mississippi River & Tributaries Project (MR&T) Carrollton Phase III District Floodwall in New Orleans, Louisiana.
The work includes clearing and grubbing, excavation and embankment, installation of steel sheet and H-piling, construction of reinforced concrete and deployable floodwalls, asphalt pavement, fencing, drainage structures and other related work. Eleven bids were received with values ranging from $8,942,388.84 to $23,453,728.88. The government estimate was $19,230,350. The apparent low bidder was APC Construction, LLC at $8,942,388.84. The solicitation was set aside for small businesses. The abstract provides bid tabulations listing unit prices and totals for various line items.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A21_W912P820B0042_Am_0005.pdf | ||
| A21_W912P820B0042_Am_0004.pdf | ||
| A21_W912P820B0042_Am_0003.pdf | ||
| A21_W912P820B0042_Am_0002.pdf | ||
| A21_W912P820B0042_Am_0001.pdf | ||
| A21_W912P820B0042_Plans.pdf | ||
| A21_W912P820B0042.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
APC Construction, LLC 8,942,388.84$ Harvey, LA
Shavers-Whittle Construction, LLC 11,941,512.00$ Mandeville, LA
Bucktown Contractors & Co. 13,700,993.65$ Kenner, LA
IGE 19,230,350.00$
Denotes a change in the bid price due to mathematical error on original bid
******* NOTE: OFFEROR NO. 10 - Dynamic Construction Group, LLC
Due to the numerous typographical errors throughout Dynamic Construction Group, LLC's bid, the Contracting Officer has deemed these numerous errors as omissions. Citing FAR 14.404.2, Rejection of Bids, the bid submitted by Dynamic Construction Group, LLC is hereby rejected by the Contracting Officer.
East Bank, Mississippi River Floodwall, Mississippi River and Tributaries Project (MR&T), Orleans Levee District Carrollton Phase III District Floodwall, Orleans Parish, Louisiana (ED 18-081)
Solicitation Number W912P820B0042
2. DATE ISSUED 3. DATE OPENED
2-Jun-20
DATE SIGNED
7A. ITEM 7C. EST. D. UNIT D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED
NO. QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
Mobilization and Demobilization 1 JOB $1,098,500.00 $1,098,500.00 $161,888.01 $161,888.01 $900,000.00 $900,000.00 $960,000.00 $960,000.00
0002 Video and Photographic Documentation 1 JOB $16,000.00 $16,000.00 $51,207.57 $51,207.57 $100,000.00 $100,000.00 $45,900.00 $45,900.00
0003 Traffic Control and Coordination
1 JOB $247,000.00 $247,000.00 $46,826.17 $46,826.17 $75,000.00 $75,000.00 $160,200.00 $160,200.00
0004 Silt Fence 520 LF $9.00 $4,680.00 $6.75 $3,510.00 $8,000.00 $4,160.00 $5.00 $2,600.00
0005 Truck Wash-Down Rack 1 JOB $173,000.00 $173,000.00 $10,666.68 $10,666.68 $25,000.00 $25,000.00 $58,750.00 $58,750.00
0006 Demolition 1 JOB $62,000.00 $62,000.00 $198,128.70 $198,128.70 $250,000.00 $250,000.00 $534,000.00 $534,000.00
0007 Reinforced Concrete Floodwall 1 JOB $3,141,500.00 $3,141,500.00 $1,612,398.93 $1,612,398.93 $2,310,000.00 $2,310,000.00 $3,200,000.00 $3,200,000.00
0008 Deployable Floodwalls 1,720 LF $1,610.00 $2,759,200.00 $732.86 $1,260,519.20 $1,300.00 $2,236,000.00 $908.00 $1,561,760.00
0009 Clearing and Grubbing 1 JOB $13,250.00 $13,250.00 $1,895.00 $1,895.00 $50,000.00 $50,000.00 $107,000.00 $107,000.00
East Bank, Mississippi River Floodwall, Mississippi River and Tributaries Project (MR&T), Orleans Levee District Carrollton Phase III District Floodwall, Orleans Parish, Louisiana (ED 18-081)
1. SOLICITATION NUMBER W912P820B0042
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
SIGNATURE
4. ISSUING OFFICE
US ARMY ENGINEER DISTRICT, NOD
B. OFFEROR: Buck Town Contractor & Company, Kenner, LA.
5. PROJECT TITLE 8. GOVERNMENT ESTIMATE 9. OFFERS
7B. DESCRIPTION OF OFFERED
ITEM
(Check A, B or C and complete D, E, and F) NO. 1 NO. 2 NO. 3Solicitation Number W912P820B0042
B. BID SECURITY (Type and amount)
C. REASONABLE CONTRACT
(Including Profit)
C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED
B. REASONABLE CONTRACT
(Without Profit)
B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount)
23-Jul-20
NAME AND TITLE OF CERTIFYING OFFICIAL (TYPE)
6. NUMBER OF AMENDMENTS ISSUED
7400 Leake Avenue New Orleans, LA 70118
100% Small Business Set-Aside
A. HIRED LABOR A. OFFEROR: APC Construction, LLC., Harvey, LA
B. OFFEROR: Shavers-Whittle Construction, LLC., Mandeville, LA
Edith M. Brandon Contract Specialist
Christopher M. Nuccio Contracting Officer
DATE SIGNED
7A. ITEM 7C. EST. D. UNIT D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED
NO. QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
East Bank, Mississippi River Floodwall, Mississippi River and Tributaries Project (MR&T), Orleans Levee District Carrollton Phase III District Floodwall, Orleans Parish, Louisiana (ED 18-081)
1. SOLICITATION NUMBER W912P820B0042
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
SIGNATURE
4. ISSUING OFFICE
US ARMY ENGINEER DISTRICT, NOD
B. OFFEROR: Buck Town Contractor & Company, Kenner, LA.
5. PROJECT TITLE 8. GOVERNMENT ESTIMATE 9. OFFERS
7B. DESCRIPTION OF OFFERED
ITEM
(Check A, B or C and complete D, E, and F) NO. 1 NO. 2 NO. 3Solicitation Number W912P820B0042
B. BID SECURITY (Type and amount)
C. REASONABLE CONTRACT
(Including Profit)
C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED
B. REASONABLE CONTRACT
(Without Profit)
B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount)
23-Jul-20
NAME AND TITLE OF CERTIFYING OFFICIAL (TYPE)
6. NUMBER OF AMENDMENTS ISSUED
7400 Leake Avenue New Orleans, LA 70118
100% Small Business Set-Aside
A. HIRED LABOR A. OFFEROR: APC Construction, LLC., Harvey, LA
B. OFFEROR: Shavers-Whittle Construction, LLC., Mandeville, LA
0010 Embankment, Compacted Fill 1,400 CY $116.80 $163,520.00 $95.80 $134,120.00 $40.00 $56,000.00 $60.00 $84,000.00
0011 Piling, Steel Sheet, Z-Section 32,788 SF $79.25 $2,598,449.00 $31.08 $1,019,051.04 $33.75 $1,106,595.00 $39.50 $1,295,126.00
0012 Steel H-Piles 68,751 LF $87.00 $5,981,337.00 $36.21 $2,489,473.71 $42.00 $2,887,542.00 $49.15 $3,379,111.65
0013 Tension Connectors 1,077 EA $1,230.00 $1,324,710.00 $263.58 $283,875.66 $375.00 $403,875.00 $694.00 $747,438.00
0014* Granular Base Course $0.00
0014AA* First 1,083 CY 1,083 CY $102.50 $111,007.50 $139.83 $151,435.89 $110.00 $119,130.00 $69.00 $74,727.00
0014AB* All Over 1,083 CY 1,083 CY $102.50 $111,007.50 $139.83 $151,435.89 $110.00 $119,130.00 $69.00 $74,727.00
0015* Asphalt Concrete - Binder Course
487 TON $210.00 $102,270.00 $334.36 $162,833.32 $200.00 $97,400.00 $207.00 $100,809.00
Asphalt Concrete - Wearing Course $0.00
Edith M. Brandon Contract Specialist
DATE SIGNED
7A. ITEM 7C. EST. D. UNIT D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED
NO. QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
East Bank, Mississippi River Floodwall, Mississippi River and Tributaries Project (MR&T), Orleans Levee District Carrollton Phase III District Floodwall, Orleans Parish, Louisiana (ED 18-081)
1. SOLICITATION NUMBER W912P820B0042
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
SIGNATURE
4. ISSUING OFFICE
US ARMY ENGINEER DISTRICT, NOD
B. OFFEROR: Buck Town Contractor & Company, Kenner, LA.
5. PROJECT TITLE 8. GOVERNMENT ESTIMATE 9. OFFERS
7B. DESCRIPTION OF OFFERED
ITEM
(Check A, B or C and complete D, E, and F) NO. 1 NO. 2 NO. 3Solicitation Number W912P820B0042
B. BID SECURITY (Type and amount)
C. REASONABLE CONTRACT
(Including Profit)
C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED
B. REASONABLE CONTRACT
(Without Profit)
B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount)
23-Jul-20
NAME AND TITLE OF CERTIFYING OFFICIAL (TYPE)
6. NUMBER OF AMENDMENTS ISSUED
7400 Leake Avenue New Orleans, LA 70118
100% Small Business Set-Aside
A. HIRED LABOR A. OFFEROR: APC Construction, LLC., Harvey, LA
B. OFFEROR: Shavers-Whittle Construction, LLC., Mandeville, LA
0016AA First 3,500 SY 3,500 SY $22.80 $79,800.00 $22.93 $80,255.00 $22.00 $77,000.00 $23.00 $80,500.00
0016AB All Over 3,500 SY 3,500 SY $22.80 $79,800.00 $22.93 $80,255.00 $22.00 $77,000.00 $23.00 $80,500.00
0017 Cold Planning 6,670 SY $13.20 $88,044.00 $7.53 $50,225.10 $6.00 $40,020.00
$8.50 $56,695.00
0018 Curbs and Gutters 1,250 LF $12.20 $15,250.00 $33.94 $42,425.00 $45.00 $56,250.00 $52.00 $65,000.00
0019 Pavement Markings 1 JOB $29,500.00 $29,500.00 $41,076.00 $41,076.00 $40,000.00 $40,000.00 $37,400.00 $37,400.00
Chain Link Fencing
200 LF $47.50 $9,500.00 $73.94 $14,788.00 $58.00 $11,600.00 $40.00 $8,000.00
Seeding and Mulching
2 AC $8,000.00 $16,000.00 $6,633.71 $13,267.42 $6,500.00 $13,000.00 $13,900.00 $27,800.00
Fertilizer
$0.00
0022AA
First 300 LBS
300 LBS $2.50 $750.00 $2.33 $699.00 $2.00 $600.00 $5.00 $1,500.00
0022AB All Over 300 LBS 300 LBS $2.50 $750.00 $2.33 $699.00 $1.70 $510.00 $5.00 $1,500.00
Edith M. Brandon Contract Specialist
DATE SIGNED
7A. ITEM 7C. EST. D. UNIT D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED
NO. QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
East Bank, Mississippi River Floodwall, Mississippi River and Tributaries Project (MR&T), Orleans Levee District Carrollton Phase III District Floodwall, Orleans Parish, Louisiana (ED 18-081)
1. SOLICITATION NUMBER W912P820B0042
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
SIGNATURE
4. ISSUING OFFICE
US ARMY ENGINEER DISTRICT, NOD
B. OFFEROR: Buck Town Contractor & Company, Kenner, LA.
5. PROJECT TITLE 8. GOVERNMENT ESTIMATE 9. OFFERS
7B. DESCRIPTION OF OFFERED
ITEM
(Check A, B or C and complete D, E, and F) NO. 1 NO. 2 NO. 3Solicitation Number W912P820B0042
B. BID SECURITY (Type and amount)
C. REASONABLE CONTRACT
(Including Profit)
C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED
B. REASONABLE CONTRACT
(Without Profit)
B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount)
23-Jul-20
NAME AND TITLE OF CERTIFYING OFFICIAL (TYPE)
6. NUMBER OF AMENDMENTS ISSUED
7400 Leake Avenue New Orleans, LA 70118
100% Small Business Set-Aside
A. HIRED LABOR A. OFFEROR: APC Construction, LLC., Harvey, LA
B. OFFEROR: Shavers-Whittle Construction, LLC., Mandeville, LA
0023++ Lime Soil Amendment 2 TON $1,375.00 $2,750.00 $2,203.02 $4,406.04 $1,650.00 $3,300.00 $350.00 $700.00
0024++ Sulfur Soil Amendment 1 TON $1,750.00 $1,750.00 $2,498.77 $2,498.77 $1,900.00 $1,900.00 $1,000.00 $1,000.00
Utility Modifications
1 JOB $411,000.00 $411,000.00 $639,037.84 $639,037.84 $500,000.00 $500,000.00 $400,000.00 $400,000.00
Sewer Lift Station
1 JOB $79,750.00 $79,750.00 $82,656.44 $82,656.44 $125,000.00 $125,000.00 $187,000.00 $187,000.00
0027 Sewer Line 1 JOB $155,750.00 $155,750.00 $61,142.12 $61,142.12 $93,000.00 $93,000.00 $160,000.00 $160,000.00
0028 Concrete Scour Protection 750 SY $182.70 $137,025.00 $90.74 $68,055.00 $150.00 $112,500.00 $135.00 $101,250.00
0029* Temporary Retaining Structures 1 JOB $205,500.00 $205,500.00 $21,637.34 $21,637.34 $50,000.00 $50,000.00 $106,000.00 $106,000.00
$19,230,350.00 $8,942,388.84 $11,941,512.00 $13,700,993.65TOTAL
Edith M. Brandon Contract Specialist
2-Jun-20 Page 6 of 11
DATE SIGNED
7A. ITEM 7C. EST. D. UNIT D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED
NO. QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
Mobilization and Demobilization 1 JOB $1,098,500.00 $1,098,500.00 $1,500,000.00 $1,500,000.00 $1,027,560.40 $1,027,560.40 $795,000.00 $795,000.00
0002 Video and Photographic Documentation 1 JOB $16,000.00 $16,000.00 $80,000.00 $80,000.00 $43,000.00 $43,000.00 $125,000.00 $125,000.00
0003 Traffic Control and Coordination
1 JOB $247,000.00 $247,000.00 $150,000.00 $150,000.00 $150,000.00 $150,000.00 $100,000.00 $100,000.00
0004 Silt Fence 520 LF $9.00 $4,680.00 $5.00 $2,600.00 $5.00 $2,600.00 $8.00 $4,160.00
0005 Truck Wash-Down Rack 1 JOB $173,000.00 $173,000.00 $75,000.00 $75,000.00 $55,000.00 $55,000.00 $30,000.00 $30,000.00
0006 Demolition 1 JOB $62,000.00 $62,000.00 $150,000.00 $150,000.00 $600,000.00 $600,000.00 $300,000.00 $300,000.00
0007 Reinforced Concrete Floodwall
1 JOB $3,141,500.00 $3,141,500.00 $2,254,000.00 $2,254,000.00 $4,200,000.00 $4,200,000.00 $3,900,000.00 $3,900,000.00
0008 Deployable Floodwalls 1,720 LF $1,610.00 $2,759,200.00 $1,500.00 $2,580,000.00 $850.00 $1,462,000.00 $900.00 $1,548,000.00
0009 Clearing and Grubbing 1 JOB $13,250.00 $13,250.00 $50,000.00 $50,000.00 $100,000.00 $100,000.00 $60,000.00 $60,000.00
0010 Embankment, Compacted Fill 1,400 CY $116.80 $163,520.00 $45.00 $63,000.00 $56.00 $78,400.00 $60.00 $84,000.00
0011 Piling, Steel Sheet, Z-Section 32,788 SF $79.25 $2,598,449.00 $50.00 $1,639,400.00 $36.45 $1,195,122.60 $45.00 $1,475,460.00
0012 Steel H-Piles 68,751 LF $87.00 $5,981,337.00 $50.00 $3,437,550.00 $46.00 $3,162,546.00 $55.00 $3,781,305.00
0013 Tension Connectors 1,077 EA $1,230.00 $1,324,710.00 $250.00 $269,250.00 $634.00 $682,818.00 $550.00 $592,350.00
0014* Granular Base Course
0014AA* First 1,083 CY 1,083 CY $102.50 $111,007.50 $90.00 $97,470.00 $65.00 $70,395.00 $100.00 $108,300.00
0014AB* All Over 1,083 CY 1,083 CY $102.50 $111,007.50 $90.00 $97,470.00 $65.00 $70,395.00 $100.00 $108,300.00
B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount)
(Without Profit)
C. AMENDMENTS ACKNOWLEDGED
(Including Profit)
7B. DESCRIPTION OF OFFERED ITEM
6. NUMBER OF AMENDMENTS ISSUED C. REASONABLE CONTRACT C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED
5. PROJECT TITLE 8. GOVERNMENT ESTIMATE 9. OFFERS
Solicitation Number W912P820B0042 (Check A, B or C and complete D, E, and F) NO. 4 NO. 5 NO. 6 A. HIRED LABOR A. OFFEROR: B&K Construction Co, LLC
Mandeville, LA B. OFFEROR: Tarpan Construction, LLC Cottonport, LA
B. OFFEROR: CAYO, LLC
Fort Worth, TX
B. REASONABLE CONTRACT
East Bank, Mississippi River Floodwall, Mississippi River and Tributaries Project (MR&T), Orleans Levee District Carrollton Phase III District Floodwall, Orleans Parish, Louisiana (ED 18-
1. SOLICITATION NUMBER W912P820B0042
New Orleans, LA 70118
23-Jul-20
NAME AND TITLE OF CERTIFYING OFFICIAL (TYPE)
100% Small Business Set-Aside
SIGNATURE
4. ISSUING OFFICE
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
US ARMY ENGINEER DISTRICT, NOD
7400 Leake Avenue
Edith M. Brandon Contract Specialist
0015* Asphalt Concrete - Binder Course
487 TON $210.00 $102,270.00 $350.00 $170,450.00 $194.00 $94,478.00 $200.00 $97,400.00
Asphalt Concrete - Wearing Course
0016AA First 3,500 SY 3,500 SY $22.80 $79,800.00 $30.00 $105,000.00 $21.50 $75,250.00 $25.00 $87,500.00
0016AB All Over 3,500 SY 3,500 SY $22.80 $79,800.00 $30.00 $105,000.00 $21.50 $75,250.00 $25.00 $87,500.00
0017 Cold Planning 6,670 SY $13.20 $88,044.00 $10.00 $66,700.00 $8.00 $53,360.00
$22.00 $146,740.00
0018 Curbs and Gutters 1,250 LF $12.20 $15,250.00 $45.00 $56,250.00 $45.00 $56,250.00 $45.00 $56,250.00
0019 Pavement Markings 1 JOB $29,500.00 $29,500.00 $50,000.00 $50,000.00 $35,000.00 $35,000.00 $45,000.00 $45,000.00
Chain Link Fencing
200 LF $47.50 $9,500.00 $75.00 $15,000.00 $37.00 $7,400.00 $50.00 $10,000.00
Seeding and Mulching
2 AC $8,000.00 $16,000.00 $6,000.00 $12,000.00 $13,000.00 $26,000.00 $9,000.00 $18,000.00
Fertilizer
0022AA
First 300 LBS
300 LBS $2.50 $750.00 $1.50 $450.00 $5.00 $1,500.00 $2.50 $750.00
0022AB All Over 300 LBS 300 LBS $2.50 $750.00 $1.50 $450.00 $5.00 $1,500.00 $2.50 $750.00
0023++ Lime Soil Amendment 2 TON $1,375.00 $2,750.00 $500.00 $1,000.00 $330.00 $660.00 $2,400.00 $4,800.00
0024++ Sulfur Soil Amendment 1 TON $1,750.00 $1,750.00 $1,800.00 $1,800.00 $990.00 $990.00 $2,700.00 $2,700.00
Utility Modifications
1 JOB $411,000.00 $411,000.00 $350,000.00 $350,000.00 $350,000.00 $350,000.00 $670,000.00 $670,000.00
Sewer Lift Station
1 JOB $79,750.00 $79,750.00 $150,000.00 $150,000.00 $106,000.00 $106,000.00 $70,000.00 $70,000.00
0027 Sewer Line 1 JOB $155,750.00 $155,750.00 $100,000.00 $100,000.00 $127,000.00 $127,000.00 $85,000.00 $85,000.00
0028 Concrete Scour Protection 750 SY $182.70 $137,025.00 $120.00 $90,000.00 $115.00 $86,250.00 $140.00 $105,000.00
0029* Temporary Retaining Structures 1 JOB $205,500.00 $205,500.00 $100,000.00 $100,000.00 $95,000.00 $95,000.00 $120,000.00 $120,000.00
$19,230,350.00 $13,819,840.00 $14,091,725.00 $14,619,265.00
NSN 7540-01-150-0981 501419-101 NOTE: If more than two offers are received, continue on OF 1419A. OPTIONAL FORM 1419 (11-88) Prescribed by GSA - FAR (48 CFR) 53.236-1
TOTAL
2-Jun-20 Page 8 of 11
DATE SIGNED
7A. ITEM 7C. EST. D. UNIT D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED
NO. QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
Mobilization and Demobilization 1 JOB $ 1,098,500.00 $ 1,098,500.00 $1,500,000.00 $1,500,000.00 $1,547,821.00 $1,547,821.00 $600,000.00 $600,000.00
0002 Video and Photographic Documentation 1 JOB $ 16,000.00 $ 16,000.00 $80,000.00 $80,000.00 $5,000.00 $5,000.00 $20,000.00 $20,000.00
0003 Traffic Control and Coordination
1 JOB $ 247,000.00 $ 247,000.00 $233,100.00 $233,100.00 $19,900.00 $19,900.00 $75,000.00 $75,000.00
0004 Silt Fence 520 LF $ 9.00 $4,680.00 $9.60 $4,992.00 $10.00 $5,200.00 $11.00 $5,720.00
0005 Truck Wash-Down Rack 1 JOB $ 173,000.00 $ 173,000.00 $25,300.00 $25,300.00 $115,489.00 $115,489.00 $87,000.00 $87,000.00
0006 Demolition 1 JOB $ 62,000.00 $ 62,000.00 $147,400.00 $147,400.00 $249,874.00 $249,874.00 $174,000.00 $174,000.00
0007 Reinforced Concrete Floodwall
1 JOB $ 3,141,500.00 $ 3,141,500.00 $4,289,250.00 $4,289,250.00 $4,254,535.00 $4,254,535.00 $4,920,000.00 $4,920,000.00
0008 Deployable Floodwalls 1,720 LF $ 1,610.00 $ 2,759,200.00 $1,205.65 $2,073,718.00 $1,178.00 $2,026,160.00 $1,387.00 $2,385,640.00
0009 Clearing and Grubbing 1 JOB $ 13,250.00 $ 13,250.00 $15,800.00 $15,800.00 $5,000.00 $5,000.00 $110,000.00 $110,000.00
0010 Embankment, Compacted Fill 1,400 CY $ 116.80 $ 163,520.00 $64.90 $90,860.00 $77.00 $107,800.00 $79.00 $110,600.00
0011 Piling, Steel Sheet, Z-Section 32,788 SF $ 79.25 $ 2,598,449.00 $42.00 $1,377,096.00 $50.00 $1,639,400.00 $68.00 $2,229,584.00
0012 Steel H-Piles 68,751 LF $ 87.00 $ 5,981,337.00 $55.70 $3,829,430.70 $61.00 $4,193,811.00 $74.00 $5,087,574.00
0013 Tension Connectors 1,077 EA $ 1,230.00 $ 1,324,710.00 $544.80 $586,749.60 $600.00 $646,200.00 $335.00 $360,795.00
0014* Granular Base Course
0014AA* First 1,083 CY 1,083 CY $ 102.50 $ 111,007.50 $117.70 $127,469.10 $149.00 $161,367.00 $92.00 $99,636.00
0014AB* All Over 1,083 CY 1,083 CY $ 102.50 $ 111,007.50 $151.00 $163,533.00 $149.00 $161,367.00 $92.00 $99,636.00
6. NUMBER OF AMENDMENTS ISSUED C. REASONABLE CONTRACT C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED
(Including Profit)
B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount)
(Without Profit)
7B. DESCRIPTION OF OFFERED ITEM
5. PROJECT TITLE 8. GOVERNMENT ESTIMATE 9. OFFERS
Solicitation Number W912P820B0042 (Check A, B or C and complete D, E, and F) NO. 7 NO.8 NO. 9 A. HIRED LABOR A. OFFEROR: Greenup Industries, LLC
Kenner, LA B. OFFEROR:OCCI, Inc.
Fulton, MO
B. OFFEROR: Southern Contracting, LLC Newbern, TN
B. REASONABLE CONTRACT
SIGNATURE
100% Small Business Set-Aside
East Bank, Mississippi River Floodwall, Mississippi River and Tributaries Project (MR&T), Orleans Levee District Carrollton Phase III District Floodwall, Orleans Parish, Louisiana (ED 18-
1. SOLICITATION NUMBER W912P820B0042
23-Jul-20
4. ISSUING OFFICE
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
NAME AND TITLE OF CERTIFYING OFFICIAL (TYPE)
US ARMY ENGINEER DISTRICT, NOD
7400 Leake Avenue New Orleans, LA 70118
Edith M. Brandon Contract Specialist
487 TON $ 210.00 $ 102,270.00 $323.20 $157,398.40 $299.00 $145,613.00 $250.00 $121,750.00
Asphalt Concrete - Wearing Course
0016AA First 3,500 SY 3,500 SY $ 22.80 $ 79,800.00 $35.05 $122,675.00 $30.00 $105,000.00 $25.00 $87,500.00
0016AB All Over 3,500 SY 3,500 SY $ 22.80 $ 79,800.00 $35.05 $122,675.00 $30.00 $105,000.00 $23.00 $80,500.00
0017 Cold Planning 6,670 SY $ 13.20 $ 88,044.00 $13.75 $91,712.50 $15.00 $100,050.00
$15.00 $100,050.00
0018 Curbs and Gutters 1,250 LF $ 12.20 $ 15,250.00 $76.00 $95,000.00 $92.00 $115,000.00 $84.00 $105,000.00
0019 Pavement Markings 1 JOB $ 29,500.00 $ 29,500.00 $47,000.00 $47,000.00 $15,000.00 $15,000.00 $40,000.00 $40,000.00
Chain Link Fencing
200 LF $ 47.50 $ 9,500.00 $150.00 $30,000.00 $60.00 $12,000.00 $40.00 $8,000.00
Seeding and Mulching
2 AC $ 8,000.00 $ 16,000.00 $15,000.00 $30,000.00 $19,854.00 $39,708.00 $7,500.00 $15,000.00
Fertilizer
0022AA
First 300 LBS
300 LBS $ 2.50 $ 750.00 $7.00 $2,100.00 $50.00 $15,000.00 $3.00 $900.00
0022AB All Over 300 LBS 300 LBS $ 2.50 $ 750.00 $7.00 $2,100.00 $50.00 $15,000.00 $2.00 $600.00
0023++ Lime Soil Amendment 2 TON $ 1,375.00 $ 2,750.00 $300.00 $600.00 $2,000.00 $4,000.00 $2,500.00 $5,000.00
0024++ Sulfur Soil Amendment 1 TON $ 1,750.00 $ 1,750.00 $900.00 $900.00 $3,000.00 $3,000.00 $2,500.00 $2,500.00
Utility Modifications
1 JOB $ 411,000.00 $ 411,000.00 $281,250.00 $281,250.00 $749,823.00 $749,823.00 $350,000.00 $350,000.00
Sewer Lift Station
1 JOB $ 79,750.00 $ 79,750.00 $82,500.00 $82,500.00 $171,283.00 $171,283.00 $82,000.00 $82,000.00
0027 Sewer Line 1 JOB $ 155,750.00 $ 155,750.00 $122,100.00 $122,100.00 $99,851.00 $99,851.00 $65,000.00 $65,000.00
0028 Concrete Scour Protection 750 SY $ 182.70 $ 137,025.00 $197.50 $148,125.00 $147.00 $110,250.00 $190.00 $142,500.00
0029* Temporary Retaining Structures 1 JOB $ 205,500.00 $ 205,500.00 $21,250.00 $21,250.00 $50,000.00 $50,000.00 $250,000.00 $250,000.00
19,230,350.00$ $15,902,084.30 16,994,502.00 $17,821,485.00TOTAL
NSN 7540-01-150-0981 501419-101 NOTE: If more than two offers are received, continue on OF 1419A. OPTIONAL FORM 1419 (11-88) Prescribed by GSA - FAR (48 CFR) 53.236-1
2-Jun-20 Page 10 of 11
DATE SIGNED
7A. ITEM 7C. EST. D. UNIT D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED
NO. QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
Mobilization and Demobilization 1 JOB $ 1,098,500.00 $ 1,098,500.00 1 $2,250,000.00 $2,261,224.87 $2,261,224.87
0002 Video and Photographic Documentation 1 JOB $ 16,000.00 $ 16,000.00 1 $18,000.00 $301,496.65 $301,496.65
0003 Traffic Control and Coordination
1 JOB $ 247,000.00 $ 247,000.00 1 $360,000.00 $150,748.32 $150,748.32
0004 Silt Fence 520 LF $ 9.00 $4,680.00 520 $2,600.00 $9.04 $4,700.80
0005 Truck Wash-Down Rack 1 JOB $ 173,000.00 $ 173,000.00 1 $825,000.00 $226,122.49 $226,122.49
0006 Demolition 1 JOB $ 62,000.00 $ 62,000.00 1 $200,000.00 $753,741.62 $753,741.62
0007 Reinforced Concrete Floodwall
1 JOB $ 3,141,500.00 $ 3,141,500.00 1 $4,660,000.00 $7,085,171.24 $7,085,171.24
0008 Deployable Floodwalls 1,720 LF $ 1,610.00 $ 2,759,200.00 1720 $1,685,600.00 $1,409.50 $2,424,320.00
0009 Clearing and Grubbing 1 JOB $ 13,250.00 $ 13,250.00 1 $250,000.00 $15,074.83 $15,074.83
0010 Embankment, Compacted Fill 1,400 CY $ 116.80 $ 163,520.00 1400 $84,000.00 $97.99 $137,186.00
0011 Piling, Steel Sheet, Z-Section 32,788 SF $ 79.25 $ 2,598,449.00 32788 $1,442,672.00 $60.30 $1,977,116.40
0012 Steel H-Piles 68,751 LF $ 87.00 $ 5,981,337.00 68751 $3,850,056.00 $58.79 $4,041,871.29
0013 Tension Connectors 1,077 EA $ 1,230.00 $ 1,324,710.00 1077 $581,580.00 $1,281.36 $1,380,024.72
0014* Granular Base Course
0014AA* First 1,083 CY 1,083 CY $ 102.50 $ 111,007.50 1083 $158,118.00 $45.22 $48,973.26
0014AB* All Over 1,083 CY 1,083 CY $ 102.50 $ 111,007.50 1083 $158,118.00 $45.22 $48,973.26
6. NUMBER OF AMENDMENTS ISSUED C. REASONABLE CONTRACT C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED
(Including Profit)
B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount)
(Without Profit)
7B. DESCRIPTION OF OFFERED ITEM
5. PROJECT TITLE 8. GOVERNMENT ESTIMATE 9. OFFERS
Solicitation Number W912P820B0042 (Check A, B or C and complete D, E, and F) NO. 10 NO. 11 NO.
A. HIRED LABOR A. OFFEROR:Dynamic Construction Group, LLC, Baton Rouge, LA ******* B. OFFEROR: Cherokee CRC, LLC Tulsa, OK
B. OFFEROR:
B. REASONABLE CONTRACT
SIGNATURE
100% Small Business Set-Aside
East Bank, Mississippi River Floodwall, Mississippi River and Tributaries Project (MR&T), Orleans Levee District Carrollton Phase III District Floodwall, Orleans Parish, Louisiana (ED 18-
1. SOLICITATION NUMBER W912P820B0042
23-Jul-20
4. ISSUING OFFICE
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
NAME AND TITLE OF CERTIFYING OFFICIAL (TYPE)
US ARMY ENGINEER DISTRICT, NOD
7400 Leake Avenue
Edith M. Brandon Contract Specialist
Christopher M. Nuccio
New Orleans, LA 70118
487 TON $ 210.00 $ 102,270.00 487 $97,400.00 $346.72 $168,852.64
Asphalt Concrete - Wearing Course
0016AA First 3,500 SY 3,500 SY $ 22.80 $ 79,800.00 3500 $77,000.00 $52.76 $184,660.00
0016AB All Over 3,500 SY 3,500 SY $ 22.80 $ 79,800.00 3500 $77,000.00 $52.76 $184,660.00
0017 Cold Planning 6,670 SY $ 13.20 $ 88,044.00 6670 $73,370.00 $15.07 $100,516.90
0018 Curbs and Gutters 1,250 LF $ 12.20 $ 15,250.00 1250 $75,000.00 $60.30 $75,375.00
0019 Pavement Markings 1 JOB $ 29,500.00 $ 29,500.00 1 $22,000.00 $218,585.07 $218,585.07
Chain Link Fencing
200 LF $ 47.50 $ 9,500.00 200 $10,000.00 $52.76 $10,552.38
Seeding and Mulching
2 AC $ 8,000.00 $ 16,000.00 2 $9,800.00 $12,059.87 $24,119.74
Fertilizer
0022AA
First 300 LBS
300 LBS $ 2.50 $ 750.00 300 $510.00 $9.04 $2,712.00
0022AB All Over 300 LBS 300 LBS $ 2.50 $ 750.00 300 $510.00 $9.04 $2,712.00
0023++ Lime Soil Amendment 2 TON $ 1,375.00 $ 2,750.00 2 $3,300.00 $3,014.97 $6,029.94
0024++ Sulfur Soil Amendment 1 TON $ 1,750.00 $ 1,750.00 1 $1,850.00 $3,316.46 $3,316.46
Utility Modifications
1 JOB $ 411,000.00 $ 411,000.00 1 $440,000.00 $904,489.95 $904,489.95
Sewer Lift Station
1 JOB $ 79,750.00 $ 79,750.00 1 $130,000.00 $263,809.57 $263,809.57
0027 Sewer Line 1 JOB $ 155,750.00 $ 155,750.00 1 $300,000.00 $90,448.99 $90,448.99
0028 Concrete Scour Protection 750 SY $ 182.70 $ 137,025.00 750 $82,500.00 $173.36 $130,020.00
0029* Temporary Retaining Structures 1 JOB $ 205,500.00 $ 205,500.00 1 $145,000.00 $226,122.49 $226,122.49
19,230,350.00$ $18,070,984.00 $23,453,728.88TOTAL
| Cover Sheet |
| Abstract |
| Sheet2 |
| Sheet3 |
| Sheet4 |
| 2020-07-24T16:37:29-0500 | |
| BRANDON.EDITH.M.1270826829 |
| 2020-07-24T16:38:27-0500 | |
| BRANDON.EDITH.M.1270826829 |
| 2020-07-24T16:39:00-0500 | |
| BRANDON.EDITH.M.1270826829 |
| 2020-07-24T16:39:37-0500 | |
| BRANDON.EDITH.M.1270826829 |
| 2020-07-24T16:40:19-0500 | |
| BRANDON.EDITH.M.1270826829 |
| 2020-07-24T16:40:56-0500 | |
| BRANDON.EDITH.M.1270826829 |
| 2020-07-24T16:41:29-0500 | |
| BRANDON.EDITH.M.1270826829 |
| 2020-07-24T16:49:54-0500 | |
| NUCCIO.CHRISTOPHER.1296631457 |
| 2020-07-24T16:50:25-0500 | |
| NUCCIO.CHRISTOPHER.1296631457 |
| 2020-07-24T16:50:56-0500 | |
| NUCCIO.CHRISTOPHER.1296631457 |
| 2020-07-24T16:51:29-0500 | |
| NUCCIO.CHRISTOPHER.1296631457 |
| 2020-07-24T16:52:03-0500 | |
| NUCCIO.CHRISTOPHER.1296631457 |
| 2020-07-24T16:52:41-0500 | |
| NUCCIO.CHRISTOPHER.1296631457 |
| 2020-07-24T16:53:23-0500 | |
| NUCCIO.CHRISTOPHER.1296631457 |
File details come from the government source that posted it. Updated .