This document is an amendment to a federal solicitation for construction services related to flood protection infrastructure along the Mississippi River in New Orleans, Louisiana. The amendment provides responses to contractor questions, specification and drawing changes, and revised bid opening information. Key details include construction of a steel sheet and H-pile floodwall with concrete scour protection and deployable floodwall sections. Incidental work includes clearing, grubbing, excavation, backfill, concrete work, fencing, pavement, and turf establishment. Staging areas will be available for field offices and materials storage. The bid opening remains on July 23, 2020 at 1:00 PM CST via an audio teleconference with call-in information provided.

View the file

Other files

File Type Posted
B01_Bid Abstract_W912P820B0042(s).pdf PDF
A21_W912P820B0042_Am_0004.pdf PDF
A21_W912P820B0042_Am_0003.pdf PDF
A21_W912P820B0042_Am_0002.pdf PDF
A21_W912P820B0042_Am_0001.pdf PDF
A21_W912P820B0042_Plans.pdf PDF
A21_W912P820B0042.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The subject solicitation for East Bank, Mississippi River Floodw all, Mississippi River andTributaries Project (MR&T), Orleans Levee District, Carrolton Phase III - District Floodw all Project Orleans Pariish, LA is hereby amended as follow s:

1. To answ er contractors questions.(See attached)

2. To provide specif ication and draw ing changes as stated in the attached continuation.

3. To provide revised audio teleconference bid opening information as show n in continuation.

4. This w ill be the final response to questions and no futher questions w ill be accepted.

NOTE: The bid opening date of Thursday, 23 July 2020 at 1:00 pm local time remains unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 8

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P820B0042

X 9B. DATED (SEE ITEM 11)

02-Jun-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

16-Jul-2020

CODE

USACE, CONTRACTING DIVISION

ATTN: CEMVN-CT, ROOM 172

7400 LEAKE AVE.

NEW ORLEANS LA 70118-3651

W912P8 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

16 Jul 20

W912P820B0042

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

(End of Summary of Changes)

The following items are applicable to this modification:

Carrollton Phase III: District Floodwall Solicitation W912P820-B-0042

Contractor Questions & USACE Responses

1. Staging Area 1 shown on Drawing C-100 has a significant slope that may make it unsuitable for field office use.

The slope at Staging Area 1 may also limit materials that can be stored at Staging Area 1 as the slope is unsuitable for crane operations. Staging Area 2 shown on Drawing C-101 indicates that it is for “Materials Storage Only”. Please clarify if field offices can be located at Staging Area 2. Alternatively, please provide a suitable location for field offices at the project site.

Staging Areas 1 or 2 will be available for field office use.

2. What is the frequency of use of the Helipad located near Staging Area 1?

The helipad is used sparingly outside of hurricane season. Government will coordinate with Contractor when the helipad is to be used and what actions need to take place.

3. What is the voltage of the high-voltage electric lines running adjacent to Staging Area 1?

13.8kV 3 Phase

4. After viewing the construction site, there are numerous trees and other landscape features that will need to be removed for construction. Paragraph 3.1.2 under specification 01 57 20.00 12, Environmental Protection, requires the contractor to replace landscape features damaged during construction utilizing the services of a licensed arborist. There are no landscape plans included in the solicitation. Please clarify if the contractor will be required to replace any of the trees, shrubs, or other landscape features (other than Seeding and Mulching under the Bid Schedule) that will be affected by construction. If so, please provide a landscape plan and schedule.

The Contractor shall replace any trees, shrubs or landscape features damaged by his activity beyond what is required to be removed for the construction of the floodwall. Per paragraph 3.1.2., the Contractor shall coordinate with the New Orleans' District Landscape Architect and secure the services of a licensed arborist to assess any damage to trees that occur as a result of construction activities. This project will not address replacement of landscaping that was removed as a result of the construction of the floodwall.

5. Will a licensed arborist be required for the tree removal and tree trimming required for overhead access and construction of the new floodwall?

Yes, as stated in Paragraph 3.1.2 under specification 01 57 20.00 12

6. Note 6 under Sequencing and Recommended Construction Section Notes on Drawing C-103 states that heavy equipment and crane placement for construction is not permitted on the flood side of the monoliths between PI- 4 thru PI-5 and PI-8 thru PI-11. However, at monoliths DM29 thru DM31 (in front of the main building entrance roundabout) there are walls, a flagpole, and other landscape features/structures prohibiting construction operations on the land side of the monoliths. Additionally, a 4 – 5 feet excavation is required in this area for the floodwall construction that will impact some of these land side landscape features. If the structures and landscape features are to be demolished for access at this location and reconstructed afterwards, please provide details of structures so contractors can estimate the cost of this work. It is not apparent how deep the walls and other concrete structures extend, or if they contain footings or foundations. Alternatively, please provide details regarding construction and construction access at this location.

Landside features will be removed and restored to their original location, such as the flagpole and bell statue.

Contractor shall minimize the amount of walls to be removed for the construction of the floodwall.

Unfortunately there are no as-built plans for the walls around the flagpoles. Contractor shall assume these walls are soil-founded with a 1-ft thick x 5-ft wide base, buried 1-ft under the ground line.

7. Note 6 under Sequencing and Recommended Construction Section Notes on Drawing C-103 states that heavy equipment and crane placement for construction is not permitted on the flood side of monoliths between PI-4 thru PI-5 and PI-8 thru PI-11. However, at monoliths DM53 thru DM55 there is a building less than 20’ from the land side edge of these monoliths. Additionally, a 4 – 5 feet excavation is required at this location for floodwall construction which will not provide adequate landside access and may encroach on the building foundation. Please provide details regarding construction and construction access at this location. Likewise, there are no details of the building or building foundation included in the plans. Please provide details regarding excavation and any shoring requirements in the area adjacent to the existing building.

Contractor shall be allowed to drive piling from the riverside of monoliths DM53 thru DM70 at the approval of the government. The Contractor shall be allowed to work in this area only when the river is between elevations

6.0 and 11.0 at the Carrollton Gage. Contractor shall submit anticipated crane loadings and measures that can be taken to reduce the loading surface pressures for government approval.

8. The existing building located adjacent to monoliths DM53 thru DM55 is very close to the floodwall piling.

Please clarify how the piling will be installed in this area if the vibrations at the building exceed those listed in paragraph 19 under specification section 01100.

Vibration monitoring and subsequent adjustments to the pile driving operation if the limits are exceeded is the responsibility of the Contractor.

9. Amendment 0001 states that the bid opening date of 07 July 2020 at 11:00am local time remains unchanged.

However, the original solicitation indicates a bid opening time of 1:00pm. Please clarify.

A new bid opening date was established in amendment 004.

10. 13 30 25, 1.8 Warranty. The section reads “Warrant the deployable floodwall system for a period of 5 years, and warrant materials for 3 years.” Can you clarify the difference between these two warranty coverages?”

Section 1.8 has been revised per current amendment.

Revised audio teleconference bid opening information is as follows:

The Bid Opening is currently scheduled for Thursday, 23 July 2020 at 1 :00 PM CST. The Contracting Officer and Contract Specialist will begin downloading bids at 12:30 PM CST, which is the bid receipt cutoff time. All bids received after 12:30 PM CST on Thursday, 23 July 2020 will be considered late.

Audio Teleconference Bid Opening Information:

Bid Opening will be held on Thursday, 23 July 2020 at 1 :00 PM CST. Please use the following call-in information to attend the meeting:

Toll-Free: 844-867-6169 Access Code: 1766324

NOTE: All other Electronic Submission of Bids information remains unchanged.

File details come from the government source that posted it. Updated .