New Orleans to Venice, Hurricane Protection Project, NOV-NF-W-06a3, West Pointe a La Hache to St. Jude Levee, Plaquemines Parish, Louisiana
Solicitation number
W912P8-15-B-0039
Issued by

About this file

Official Bid Abstract

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID ABSTRACT

For Bids Under Solicitation, W912P8-15-B-0039

New Orleans to Venice, Hurricane Protection System, NOV-NF-06a3, West Pointe a La Hache Plaquemines Parish, Louisiana

LINE

ITEM

NO. DESCRIPTION EST QTY UM UNIT PRICE AMOUNT

0001 Mobilization and Demobilization 1 JB 450,000 $450,000.00 0002 Truck Wash-Down Racks 1 JB 45,000.00 $45,000.00 0003 Traffic Control and Coordination 1 JB 70000 $70,000.00 0004 Clearing and Grubbing 1 JB 675,000 $675,000.00 0005 Embankment, Compacted Fill (Phase I) 400,000 CY 18 $7,200,000.00 0006 Surfacing

0006AA First 500 CY 500 CY 77 $38,500.00 0006AB All Over 500 CY 200 CY 77 $15,400.00

0007 Excavation - New Drainage Ditch 64200 CY 7.75 $497,550.00 0008 Silt Fence

0008AA First 10,500 LF 10500 LF 4 $42,000.00 0008AB All Over 10,500 LF 2500 LF 4 $10,000.00

0009 Seeding and Mulching (Phase I) 50 AC 3,200.00 $160,000.00 0010++ Lime Soil Amendment (Phase I) 50 TON 120 $6,000.00 0011++ Sulfur Soil Amendment (Phase I) 25 TON 700 $17,500.00

0012 Fertilizer (Phase I) 0012AA First 15,000 LBS 15,000 LBS 1.75 $26,250.00 0012AB All Over 15,000 LBS 7,500 LBS 1.75 $13,125.00

0013 Separator Geotextile 2,200 SY 2.5 $5,500.00 0014 Corrugated Metal Arch Pipes 1 JB 185,000.00 $185,000.00 0015 Asphaltic Pavement 1 JB 40,000.00 $40,000.00 0016 Pipeline Bridges 1 JB 16,000.00 $16,000.00

TOTAL BASE WORK $9,512,825.00

OPTIONAL WORK (OW)

0017 Clearing (Phase II) - OW 1 JB 25,000.00 $25,000.00 0018 Embankment, Compacted Fill (Phase II) - OW

0018AA First 25,000 CY 25,000 CY 27 $675,000.00 0018AB All Over 25,000 CY 10,000 CY 25 $250,000.00

0019 Seeding and Mulching (Phase II) 25 AC 3,200.00 $80,000.00 0020++ Lime Soil Amendment (Phase II) - OW 25 TON 120 $3,000.00 0021++ Sulfur Soil Amendment (Phase II) - OW 13 TON 700 $9,100.00

0022 Fertilizer (Phase II) - OW

BIS Services LLC - 1485 29th Street, Kenner, Louisiana 70062

0022AA First 7,500 LBS 7,500 LBS 1.75 $13,125.00 0022AB All Over 7,500 LBS 3,800 LBS 1.75 $6,650.00

TOTAL OPTIONAL

WORK $1,061,875.00

TOTAL BASE WORK+OPTION $10,574,700.00

LINE

ITEM

NO. DESCRIPTION EST QTY UM UNIT PRICE AMOUNT

0001 Mobilization and Demobilization 1 JB 1,130,000 $1,130,000.00 0002 Truck Wash-Down Racks 1 JB 25,000.00 $25,000.00 0003 Traffic Control and Coordination 1 JB 175000 $175,000.00 0004 Clearing and Grubbing 1 JB 700,000 $700,000.00 0005 Embankment, Compacted Fill (Phase I) 400,000 CY 21 $8,400,000.00 0006 Surfacing

0006AA First 500 CY 500 CY 76 $38,000.00 0006AB All Over 500 CY 200 CY 76 $15,200.00

0007 Excavation - New Drainage Ditch 64200 CY 15 $963,000.00 0008 Silt Fence

0008AA First 10,500 LF 10500 LF 5 $52,500.00 0008AB All Over 10,500 LF 2500 LF 5 $12,500.00

0009 Seeding and Mulching (Phase I) 50 AC 2,565.00 $128,250.00 0010++ Lime Soil Amendment (Phase I) 50 TON 102 $5,100.00 0011++ Sulfur Soil Amendment (Phase I) 25 TON 717 $17,925.00

0012 Fertilizer (Phase I) 0012AA First 15,000 LBS 15,000 LBS 1.45 $21,750.00 0012AB All Over 15,000 LBS 7,500 LBS 1.45 $10,875.00

0013 Separator Geotextile 2,200 SY 3.6 $7,920.00 0014 Corrugated Metal Arch Pipes 1 JB 365,000.00 $365,000.00 0015 Asphaltic Pavement 1 JB 20,000.00 $20,000.00 0016 Pipeline Bridges 1 JB 50,000.00 $50,000.00

TOTAL BASE WORK $12,138,020.00

OPTIONAL WORK (OW)

0017 Clearing (Phase II) - OW 1 JB 20,000.00 $20,000.00 0018 Embankment, Compacted Fill (Phase II) - OW

0018AA First 25,000 CY 25,000 CY 21 $525,000.00 0018AB All Over 25,000 CY 10,000 CY 21 $210,000.00

0019 Seeding and Mulching (Phase II) 25 AC 2,500.00 $62,500.00

Williams Group LLC, 9070 Highway 33, Boligee, AL 35443

0020++ Lime Soil Amendment (Phase II) - OW 25 TON 100 $2,500.00 0021++ Sulfur Soil Amendment (Phase II) - OW 13 TON 700 $9,100.00

0022 Fertilizer (Phase II) - OW 0022AA First 7,500 LBS 7,500 LBS 1.4 $10,500.00 0022AB All Over 7,500 LBS 3,800 LBS 1.4 $5,320.00

TOTAL OPTIONAL

WORK $844,920.00

TOTAL BASE WORK+OPTION $12,982,940.00

LINE

ITEM

NO. DESCRIPTION EST QTY UM UNIT PRICE AMOUNT

0001 Mobilization and Demobilization 1 JB 160,000 $160,000.00 0002 Truck Wash-Down Racks 1 JB 60,000.00 $60,000.00 0003 Traffic Control and Coordination 1 JB 125000 $125,000.00 0004 Clearing and Grubbing 1 JB 650,000 $650,000.00 0005 Embankment, Compacted Fill (Phase I) 400,000 CY 26 $10,400,000.00 0006 Surfacing

0006AA First 500 CY 500 CY 85 $42,500.00 0006AB All Over 500 CY 200 CY 85 $17,000.00

0007 Excavation - New Drainage Ditch 64200 CY 9 $577,800.00 0008 Silt Fence

0008AA First 10,500 LF 10500 LF 4.5 $47,250.00 0008AB All Over 10,500 LF 2500 LF 3.75 $9,375.00

0009 Seeding and Mulching (Phase I) 50 AC 3,150.00 $157,500.00 0010++ Lime Soil Amendment (Phase I) 50 TON 100 $5,000.00 0011++ Sulfur Soil Amendment (Phase I) 25 TON 725 $18,125.00

0012 Fertilizer (Phase I) 0012AA First 15,000 LBS 15,000 LBS 1.5 $22,500.00 0012AB All Over 15,000 LBS 7,500 LBS 1.5 $11,250.00

0013 Separator Geotextile 2,200 SY 2.3 $5,060.00 0014 Corrugated Metal Arch Pipes 1 JB 105,000.00 $105,000.00 0015 Asphaltic Pavement 1 JB 11,000.00 $11,000.00 0016 Pipeline Bridges 1 JB 25,000.00 $25,000.00

TOTAL BASE WORK $12,449,360.00

OPTIONAL WORK (OW)

0017 Clearing (Phase II) - OW 1 JB 160,000.00 $160,000.00 0018 Embankment, Compacted Fill (Phase II) - OW

Tikigaq Construction LLC, 701 S. Knik Goose Bay Road, Suite M, Wasilla, AK 99654

0018AA First 25,000 CY 25,000 CY 52 $1,300,000.00 0018AB All Over 25,000 CY 10,000 CY 30 $300,000.00

0019 Seeding and Mulching (Phase II) 25 AC 3,000.00 $75,000.00 0020++ Lime Soil Amendment (Phase II) - OW 25 TON 125 $3,125.00 0021++ Sulfur Soil Amendment (Phase II) - OW 13 TON 800 $10,400.00

0022 Fertilizer (Phase II) - OW 0022AA First 7,500 LBS 7,500 LBS 1.7 $12,750.00 0022AB All Over 7,500 LBS 3,800 LBS 1.7 $6,460.00

TOTAL OPTIONAL

WORK $1,867,735.00

TOTAL BASE WORK+OPTION $14,317,095.00

LINE

ITEM

NO. DESCRIPTION EST QTY UM UNIT PRICE AMOUNT

0001 Mobilization and Demobilization 1 JB 1,016,000 $1,016,000.00 0002 Truck Wash-Down Racks 1 JB 90,000.00 $90,000.00 0003 Traffic Control and Coordination 1 JB 48000 $48,000.00 0004 Clearing and Grubbing 1 JB 1,550,000 $1,550,000.00 0005 Embankment, Compacted Fill (Phase I) 400,000 CY 28.45 $11,380,000.00 0006 Surfacing

0006AA First 500 CY 500 CY 65 $32,500.00 0006AB All Over 500 CY 200 CY 65 $13,000.00

0007 Excavation - New Drainage Ditch 64200 CY 6.75 $433,350.00 0008 Silt Fence

0008AA First 10,500 LF 10500 LF 3 $31,500.00 0008AB All Over 10,500 LF 2500 LF 3 $7,500.00

0009 Seeding and Mulching (Phase I) 50 AC 3,080.00 $154,000.00 0010++ Lime Soil Amendment (Phase I) 50 TON 300 $15,000.00 0011++ Sulfur Soil Amendment (Phase I) 25 TON 600 $15,000.00

0012 Fertilizer (Phase I) 0012AA First 15,000 LBS 15,000 LBS 1.5 $22,500.00 0012AB All Over 15,000 LBS 7,500 LBS 1.5 $11,250.00

0013 Separator Geotextile 2,200 SY 1.3 $2,860.00 0014 Corrugated Metal Arch Pipes 1 JB 147,000.00 $147,000.00 0015 Asphaltic Pavement 1 JB 36,000.00 $36,000.00 0016 Pipeline Bridges 1 JB 11,850.00 $11,850.00

TOTAL BASE WORK $15,017,310.00

Clark Construction Enterprises LLC, 108 East Berms St., St. Martinville, LA 70582

OPTIONAL WORK (OW)

0017 Clearing (Phase II) - OW 1 JB 100,000.00 $100,000.00 0018 Embankment, Compacted Fill (Phase II) - OW

0018AA First 25,000 CY 25,000 CY 31 $775,000.00 0018AB All Over 25,000 CY 10,000 CY 30 $300,000.00

0019 Seeding and Mulching (Phase II) 25 AC 3,080.00 $77,000.00 0020++ Lime Soil Amendment (Phase II) - OW 25 TON 600 $15,000.00 0021++ Sulfur Soil Amendment (Phase II) - OW 13 TON 300 $3,900.00

0022 Fertilizer (Phase II) - OW 0022AA First 7,500 LBS 7,500 LBS 1.5 $11,250.00 0022AB All Over 7,500 LBS 3,800 LBS 1.5 $5,700.00

TOTAL OPTIONAL

WORK $1,287,850.00

TOTAL BASE WORK+OPTIONA $16,305,160.00

LINE

ITEM

NO. DESCRIPTION EST QTY UM UNIT PRICE AMOUNT

0001 Mobilization and Demobilization 1 JB 1,500,000 $1,500,000.00 0002 Truck Wash-Down Racks 1 JB 25,000.00 $25,000.00 0003 Traffic Control and Coordination 1 JB 30000 $30,000.00 0004 Clearing and Grubbing 1 JB 400,000 $400,000.00 0005 Embankment, Compacted Fill (Phase I) 400,000 CY 30 $12,000,000.00 0006 Surfacing

0006AA First 500 CY 500 CY 100 $50,000.00 0006AB All Over 500 CY 200 CY 100 $20,000.00

0007 Excavation - New Drainage Ditch 64200 CY 12 $770,400.00 0008 Silt Fence

0008AA First 10,500 LF 10500 LF 4 $42,000.00 0008AB All Over 10,500 LF 2500 LF 4 $10,000.00

0009 Seeding and Mulching (Phase I) 50 AC 1,800.00 $90,000.00 0010++ Lime Soil Amendment (Phase I) 50 TON 500 $25,000.00 0011++ Sulfur Soil Amendment (Phase I) 25 TON 500 $12,500.00

0012 Fertilizer (Phase I) 0012AA First 15,000 LBS 15,000 LBS 2 $30,000.00 0012AB All Over 15,000 LBS 7,500 LBS 2 $15,000.00

0013 Separator Geotextile 2,200 SY 5 $11,000.00 0014 Corrugated Metal Arch Pipes 1 JB 50,000.00 $50,000.00 0015 Asphaltic Pavement 1 JB 50,000.00 $50,000.00

TKTMJ, INC., 100 Harbor Circle, New Orleans, LA 70126

0016 Pipeline Bridges 1 JB 30,000.00 $30,000.00

TOTAL BASE WORK $15,160,900.00

OPTIONAL WORK (OW)

0017 Clearing (Phase II) - OW 1 JB 200,000.00 $200,000.00 0018 Embankment, Compacted Fill (Phase II) - OW

0018AA First 25,000 CY 25,000 CY 30 $750,000.00 0018AB All Over 25,000 CY 10,000 CY 30 $300,000.00

0019 Seeding and Mulching (Phase II) 25 AC 1,800.00 $45,000.00 0020++ Lime Soil Amendment (Phase II) - OW 25 TON 500 $12,500.00 0021++ Sulfur Soil Amendment (Phase II) - OW 13 TON 500 $6,500.00

0022 Fertilizer (Phase II) - OW 0022AA First 7,500 LBS 7,500 LBS 1 $7,500.00 0022AB All Over 7,500 LBS 3,800 LBS 1 $3,800.00

TOTAL OPTIONAL

WORK $1,325,300.00

TOTAL BASE WORK+OPTIONA $16,486,200.00

LINE

ITEM

NO. DESCRIPTION EST QTY UM UNIT PRICE AMOUNT

0001 Mobilization and Demobilization 1 JB 755,000 $755,000.00 0002 Truck Wash-Down Racks 1 JB 234,000.00 $234,000.00 0003 Traffic Control and Coordination 1 JB 100,000.00 $100,000.00 0004 Clearing and Grubbing 1 JB 1,580,000 $1,580,000.00 0005 Embankment, Compacted Fill (Phase I) 400,000 CY 29.2 $11,680,000.00 0006 Surfacing

0006AA First 500 CY 500 CY 70 $35,000.00 0006AB All Over 500 CY 200 CY 70 $14,000.00

0007 Excavation - New Drainage Ditch 64200 CY 4.5 $288,900.00 0008 Silt Fence

0008AA First 10,500 LF 10500 LF 4.4 $46,200.00 0008AB All Over 10,500 LF 2500 LF 4.4 $11,000.00

0009 Seeding and Mulching (Phase I) 50 AC 3,600.00 $180,000.00 0010++ Lime Soil Amendment (Phase I) 50 TON 600 $30,000.00 0011++ Sulfur Soil Amendment (Phase I) 25 TON 940 $23,500.00

0012 Fertilizer (Phase I) 0012AA First 15,000 LBS 15,000 LBS 1.5 $22,500.00 0012AB All Over 15,000 LBS 7,500 LBS 1.5 $11,250.00

0013 Separator Geotextile 2,200 SY 6.5 $14,300.00

LECON, Inc. 4302 Creekmont Drive, Houston, TX 77091

0014 Corrugated Metal Arch Pipes 1 JB 122,000.00 $122,000.00 0015 Asphaltic Pavement 1 JB 28,000.00 $28,000.00 0016 Pipeline Bridges 1 JB 17,000.00 $17,000.00

TOTAL BASE WORK $15,192,650.00

OPTIONAL WORK (OW)

0017 Clearing (Phase II) - OW 1 JB 540,000.00 $540,000.00 0018 Embankment, Compacted Fill (Phase II) - OW

0018AA First 25,000 CY 25,000 CY 43 $1,075,000.00 0018AB All Over 25,000 CY 10,000 CY 43 $430,000.00

0019 Seeding and Mulching (Phase II) 25 AC 3,600.00 $90,000.00 0020++ Lime Soil Amendment (Phase II) - OW 25 TON 600 $15,000.00 0021++ Sulfur Soil Amendment (Phase II) - OW 13 TON 940 $12,220.00

0022 Fertilizer (Phase II) - OW 0022AA First 7,500 LBS 7,500 LBS 1.5 $11,250.00 0022AB All Over 7,500 LBS 3,800 LBS 1.5 $5,700.00

TOTAL OPTIONAL

WORK $2,179,170.00

TOTAL BASE WORK+OPTIONA $17,371,820.00

LINE

ITEM

NO. DESCRIPTION EST QTY UM UNIT PRICE AMOUNT

0001 Mobilization and Demobilization 1 JB 330,000 $330,000.00 0002 Truck Wash-Down Racks 1 JB 115,158.00 $115,158.00 0003 Traffic Control and Coordination 1 JB 207,603.00 $207,603.00 0004 Clearing and Grubbing 1 JB 3,210,652 $3,210,652.00 0005 Embankment, Compacted Fill (Phase I) 400,000 CY 26.81 $10,724,000.00 0006 Surfacing

0006AA First 500 CY 500 CY 61.19 $30,595.00 0006AB All Over 500 CY 200 CY 69.83 $13,966.00

0007 Excavation - New Drainage Ditch 64200 CY 3.89 $249,738.00 0008 Silt Fence

0008AA First 10,500 LF 10500 LF 4.24 $44,520.00 0008AB All Over 10,500 LF 2500 LF 4.01 $10,025.00

0009 Seeding and Mulching (Phase I) 50 AC 5,093.20 $254,660.00 0010++ Lime Soil Amendment (Phase I) 50 TON 136.72 $6,836.00 0011++ Sulfur Soil Amendment (Phase I) 25 TON 854.52 $21,363.00

0012 Fertilizer (Phase I) 0012AA First 15,000 LBS 15,000 LBS 2.28 $34,200.00

Keystone Joint Venture, P.O. Box 1870, Titusville, FL 32781

0012AB All Over 15,000 LBS 7,500 LBS 2.28 $17,100.00 0013 Separator Geotextile 2,200 SY 5.99 $13,178.00 0014 Corrugated Metal Arch Pipes 1 JB 143,074.00 $143,074.00 0015 Asphaltic Pavement 1 JB 32,934.00 $32,934.00 0016 Pipeline Bridges 1 JB 18,117.00 $18,117.00

TOTAL BASE WORK $15,477,719.00

OPTIONAL WORK (OW)

0017 Clearing (Phase II) - OW 1 JB 1,830,085.00 $1,830,085.00 0018 Embankment, Compacted Fill (Phase II) - OW

0018AA First 25,000 CY 25,000 CY 25.75 $643,750.00 0018AB All Over 25,000 CY 10,000 CY 25.75 $257,500.00

0019 Seeding and Mulching (Phase II) 25 AC 5,515.20 $137,880.00 0020++ Lime Soil Amendment (Phase II) - OW 25 TON 136 $3,400.00 0021++ Sulfur Soil Amendment (Phase II) - OW 13 TON 854 $11,102.00

0022 Fertilizer (Phase II) - OW 0022AA First 7,500 LBS 7,500 LBS 2.28 $17,100.00 0022AB All Over 7,500 LBS 3,800 LBS 2.28 $8,664.00

TOTAL OPTIONAL

WORK $2,909,481.00

TOTAL BASE WORK+OPTIONA $18,387,200.00

LINE

ITEM

NO. DESCRIPTION EST QTY UM UNIT PRICE AMOUNT

0001 Mobilization and Demobilization 1 JB 1,287,100 $1,287,100.00 0002 Truck Wash-Down Racks 1 JB 369,250.00 $369,250.00 0003 Traffic Control and Coordination 1 JB 158,250.00 $158,250.00 0004 Clearing and Grubbing 1 JB 685,750 $685,750.00 0005 Embankment, Compacted Fill (Phase I) 400,000 CY 33.76 $13,504,000.00 0006 Surfacing

0006AA First 500 CY 500 CY 100.23 $50,115.00 0006AB All Over 500 CY 200 CY 100.23 $20,046.00

0007 Excavation - New Drainage Ditch 64200 CY 15.83 $1,016,286.00 0008 Silt Fence

0008AA First 10,500 LF 10500 LF 3.17 $33,285.00 0008AB All Over 10,500 LF 2500 LF 2.64 $6,600.00

0009 Seeding and Mulching (Phase I) 50 AC 4,905.75 $245,287.50 0010++ Lime Soil Amendment (Phase I) 50 TON 369.25 $18,462.50 0011++ Sulfur Soil Amendment (Phase I) 25 TON 923.13 $23,078.25

Hernandez Consulting, LLC, 3221 Tulane Ave., New Orleans, LA 70119

0012 Fertilizer (Phase I) 0012AA First 15,000 LBS 15,000 LBS 2.37 $35,550.00 0012AB All Over 15,000 LBS 7,500 LBS 2.37 $17,775.00

0013 Separator Geotextile 2,200 SY 4.22 $9,284.00 0014 Corrugated Metal Arch Pipes 1 JB 316,500.00 $316,500.00 0015 Asphaltic Pavement 1 JB 47,475.00 $47,475.00 0016 Pipeline Bridges 1 JB 21,100.00 $21,100.00

TOTAL BASE WORK $17,865,194.25

OPTIONAL WORK (OW)

0017 Clearing (Phase II) - OW 1 JB 63,300.00 $63,300.00 0018 Embankment, Compacted Fill (Phase II) - OW

0018AA First 25,000 CY 25,000 CY 61.19 $1,529,750.00 0018AB All Over 25,000 CY 10,000 CY 33.76 $337,600.00

0019 Seeding and Mulching (Phase II) 25 AC 4,905.75 $122,643.75 0020++ Lime Soil Amendment (Phase II) - OW 25 TON 369.25 $9,231.25 0021++ Sulfur Soil Amendment (Phase II) - OW 13 TON 922.07 $11,986.91

0022 Fertilizer (Phase II) - OW 0022AA First 7,500 LBS 7,500 LBS 2.37 $17,775.00 0022AB All Over 7,500 LBS 3,800 LBS 2.37 $9,006.00

TOTAL OPTIONAL

WORK $2,101,292.91

TOTAL BASE WORK+OPTION $19,966,487.16

LINE

ITEM

NO. DESCRIPTION EST QTY UM UNIT PRICE AMOUNT

0001 Mobilization and Demobilization 1 JB 1,988,000 $1,988,000.00 0002 Truck Wash-Down Racks 1 JB 284,800.00 $284,800.00 0003 Traffic Control and Coordination 1 JB 17,400.00 $17,400.00 0004 Clearing and Grubbing 1 JB 322,600 $322,600.00 0005 Embankment, Compacted Fill (Phase I) 400,000 CY 35.6 $14,240,000.00 0006 Surfacing

0006AA First 500 CY 500 CY 85.9 $42,950.00 0006AB All Over 500 CY 200 CY 85.9 $17,180.00

0007 Excavation - New Drainage Ditch 64200 CY 29.3 $1,881,060.00 0008 Silt Fence

0008AA First 10,500 LF 10500 LF 4.2 $44,100.00 0008AB All Over 10,500 LF 2500 LF 4.2 $10,500.00

0009 Seeding and Mulching (Phase I) 50 AC 3,678.00 $183,900.00

Independent Government Estimate (IGE)

0010++ Lime Soil Amendment (Phase I) 50 TON 880 $44,000.00 0011++ Sulfur Soil Amendment (Phase I) 25 TON 1170 $29,250.00

0012 Fertilizer (Phase I) 0012AA First 15,000 LBS 15,000 LBS 1.5 $22,500.00 0012AB All Over 15,000 LBS 7,500 LBS 1.5 $11,250.00

0013 Separator Geotextile 2,200 SY 2.9 $6,380.00 0014 Corrugated Metal Arch Pipes 1 JB 177,400.00 $177,400.00 0015 Asphaltic Pavement 1 JB 26,800.00 $26,800.00 0016 Pipeline Bridges 1 JB 14,700.00 $14,700.00

TOTAL BASE WORK $19,364,770.00

OPTIONAL WORK (OW)

0017 Clearing (Phase II) - OW 1 JB 46,300.00 $46,300.00 0018 Embankment, Compacted Fill (Phase II) - OW

0018AA First 25,000 CY 25,000 CY 44 $1,100,000.00 0018AB All Over 25,000 CY 10,000 CY 44 $440,000.00

0019 Seeding and Mulching (Phase II) 25 AC 3,470.00 $86,750.00 0020++ Lime Soil Amendment (Phase II) - OW 25 TON 880 $22,000.00 0021++ Sulfur Soil Amendment (Phase II) - OW 13 TON 1170 $15,210.00

0022 Fertilizer (Phase II) - OW 0022AA First 7,500 LBS 7,500 LBS 1.5 $11,250.00 0022AB All Over 7,500 LBS 3,800 LBS 1.5 $5,700.00

TOTAL OPTIONAL

WORK $1,727,210.00

TOTAL BASE WORK+OPTION $21,091,980.00

I certify that I have opened, read and recorded on this abstract all offers received in response to the solicitation.

Robin L. Green Bid Officer Vicksburg Contracting Office

Sheet1

2016-05-10T18:10:15-0500
GREEN.ROBIN.L.1059873683

File details come from the government source that posted it. Updated .