Questions and Answers.pdf

PDF 210 KB Posted

Attached to
Barkley Power Plant HVAC Replacement
Solicitation number
W912P525QA043-1
Issued by

About this file

This document is a Questions from Industry/Answers from Government file for a U.S. Army Corps of Engineers (USACE) project involving HVAC equipment. The document contains seven technical questions and corresponding government responses related to equipment specifications, including issues with the current Carrier product line, pipe sizing on drawing M-102, entering water temperature, condensing unit heat rejection, and building automation system requirements. Most answers direct bidders to refer to Amendment 0001 for detailed clarifications or instruct them to "bid as proposed," with one definitive response confirming that no building automation system integration is needed for this project.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions from Industry/ Answers from Government

Question 1: Since Carrier doesn’t make the product line any longer that is requested by the USACE and the USACE stated they don’t want a water source heat pump and 4.1 of the specifications states that the system should be from the same product line and manufacturer.

Please have your Engineer state the Product Line and Manufacturer that is your basis of design.

Answer 1: Addressed in Amendment 0001

Question 2: What is the entering water temperature?

Answer 2: Bid as proposed. (This temperature changes year-round.)

Question 3: Where will the condensing unit reject the heat off of the condenser fans to?

Answer 3: Addressed in Amendment 0001

Question 4: Is 3” pipe on M-102 necessary as the pipe that it is connected to is 2”?

Answer 4: Yes, bid as proposed.

Question 5: Does this need to tie into a building automation system? If so who is the contact for this work?

Answer 5: No.

Question 6: Please provide a new basis of design unit as the one that is in the plans is no longer made from what we can tell.

Answer 6: Addressed in Amendment 0001

Question 7: Please provide a refrigerant piping P&ID drawing for the refrigerant portion of the heat exchanger.

Answer 7: Bid as proposed.