W912P520B0001 Solicitaion Amendment 0002 (f).pdf
PDF 461 KB Posted
- Attached to
- Lake Cumberland (Wolf Creek) O&M
- Solicitation number
- W912P520B0001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Abstract of Offers_W912P520B0001.pdf | ||
| Exhibits C-2.1 thru C-2.15.pdf | ||
| Exhibit C-3.1 thru C-3.4.pdf | ||
| Exhibit C-3.4 in Excel.XLSX | XLSX spreadsheet | |
| Site Visit Signed Sign In Sheet.pdf | ||
| Bid Schedule in Excel.xlsx | XLSX spreadsheet | |
| Solicitation Amendment 0001 (f).pdf | ||
| Exhibit B, Definitions.docx | DOCX document | |
| Exihibit D AHA CELRL Form 1259 Blank.pdf | ||
| Exhibit E DD1155.pdf | ||
| Exhibit C.xlsx | XLSX spreadsheet | |
| W912P520B0001_Solicitation.pdf | ||
| Exhibit F Delivery Order Cost Estimate.pdf | ||
| Exhibit 3.4 Location of Work.pdf | ||
| Exhibit A QASP.docx | DOCX document |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W38XDD91547920
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
PROJECT TITLE: Lake Cumberland (Wolf Creek) O&M Requirement
PURPOSE: The purpose of this amendment is to:
1. Revise answer number 26, and
2. FAR 52.252-3, Alterations in Solicitation, is updated There w ill be no further questions answered after this amendment.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 5
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 20-Dec-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P520B0001
X 9B. DATED (SEE ITEM 11)
21-Nov-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
20-Dec-2019
CODE
US ARMY CORPS OF ENGINEERS-CELRN-RC-N
DIRECTORATE OF CONTRACTING
110 9TH AVENUE SOUTH, RM A405
NASHVILLE TN 37203
W912P5 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P520B0001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
SUMMARY OF CHANGES
SECTION B - SUPPLIES OR SERVICES AND PRICES
The following have been modified:
QUESTIONS & ANSWERS
Question 1: Quality Control Plan: Is it the intent of the Government to have Quality Control inspections every day that duties are performed to include weekends.
Answer: Reference the Performance Work Statement (PWS) Paragraph C-1.18 Quality Control, which provides, in relevant part, that:
The Contractor shall have a Quality Control program to assure the requirements of the contract are provided as specified. The primary purpose of Quality Control is to identify and correct deficiencies in the quality of services performed before the level of performance is unacceptable.
The program shall include, but not be limited to the following:
a. An inspection system covering all the services stated in the contract specifications (this shall include inspection of services performed on weekends such as cleaning services and Section 5 non-routine work orders and any work performed by subcontractors). It must specify all areas to be inspected on both a scheduled or unscheduled basis and the individual(s) who shall do the inspection.
Question 2: Section C.2.4: Understanding that it is the contractor’s responsibility to cut downed trees to firewood length (18”-24”) and haul and stack wood to COR designated area, is it the responsibility of the contractor to split these pieces into smaller sizes deemed appropriate for campfires?
Answer: No.
Question 3: Section 3.2.G Dumpsters: During the site visit, we noticed many more dumpsters than what is listed in the current solicitation. Is the contractor financially responsible for all dumpsters needed outside of the areas in section 3.2.G.?
Answer: Each dumpster is ordered by issuance of a task order under CLINS 0036, 1036, 2036, 3026 and 4036.
There are multiple dumpsters at some campgrounds. The contractor is financially responsible for all dumpster quantities ordered on a per task order basis.
Question 4: Section C.9 Boundary Line Marking Being familiar with the difficult terrain in the area and the labor intensiveness of walking the terrain with supplies due to the lack of roadways or paths for clearing and marking the boundary line. Will the USACE furnish a boat for areas that are more easily reached via water?
Answer: No, the Government will not provide a boat for the work associated with this section.
Question 5: Section C.3.2.T Can the Government furnish an estimated amount of acreage that annual leaf removal will take place?
Answer: Please reference PWS Section C-2.2 for mowing acreage. Leaf removal is the park in its entirety.
Question 6: Award Selection Basis: Will unbalanced or unreasonably low bids be omitted? I.E. bids that are found to be far below the internal Government Estimate or deemed too low for the contractor to satisfactorily perform the scoped duties.
Answer: The Contracting Officer may only reject individual bids for the reasons listed in FAR 14.404-2, which includes materially unbalanced bids. In determining price reasonableness, the Contracting Officer may only determine whether a bidder’s price is fair and reasonable to the Government and may not reject a bid for being too low. The Government will prepare a responsibility determination for the apparent low bidder, which will determine whether the bidder can perform the contract requirements.
Question 7: 1.11 Definitive Responsibility Criteria: Do we submit the Definitive Responsibility Criteria with our proposals or at the request of the government?
Answer: Reference Instructions to Bidders, Paragraph 1.11b. (last paragraph), “Bidders are not required to submit additional documentation related to these criteria at the time of bid. Instead, within four (4) days after the date of bid opening, the Government will request supporting documentation from the apparent low bidder to include points of contact for their submitted projects.”
Question 8: C-4, Janitorial Services: Could we get the square footage of the Visitor Center, Resource Managers Office and the Contract Admin Building?
Answer: Visitor Center and Resource Managers Office – 5000 sq. ft.
Contract Admin Building/Facility Management Office – 7503 sq. ft.
Question 9: Reference list of Exhibits: There are references to the following Exhibits which were not included in the solicitation packaged. Could you please provide?
C-3.1 Description of the Areas and Facilities Upon Which Work is Performed C-3.2 Playground Sites C-3.3 Indicates Which Areas have Ramps Answer: Reference Amendment 0001, specifically Exhibit C-3.1 thru C-3.4, which are provided as attachments to the Amendment.
Question 10: L.2.1.3 Completed Bid Schedule: Is it possible to get the Bid Schedule in an excel format?
Answer: Yes, Excel spreadsheet version of the Bid Schedule will be added as an attachment.
Question 11: Section C-6.2a – Septic Tanks: Can the government please provide the size of the listed tanks or have the unit of measure in the pricing as gallons?
Answer: Halcomb’s Landing 2 each – 500 gallons Fall Creek 2 each – 500 gallons Mill Springs 1 each – 250 gallons Waitsboro 1 each – 1000 gallons Waitsboro 2 each – 500 gallons
Question 12: Can the government please provide the current staffing levels and associated positions?
Answer: No, this is a firm-fixed price performance based acquisition in which work is described in terms of the required results rather than either “how” the work is to be accomplished or the number of hours to be provided.
Question 13: Does the government have a greenwaste recycling area available for leaves, branches, and all other organic matter, or will the contractor be required to haul this material offsite?
Answer: No, The Governement does not have a greenwaste area, the contractor is required to haul offsite.
Question 14: Section C-1.14 – Supervision: Can the QCIs assigned to each crew be working members of the crew or do they have to be stand-alone quality personnel?
Answer: Reference PWS Section C-1.14 to C-1.19. The QCI should be a stand-alone member and not a working member of the crew.
Question 15: Could the government provide past procurement history for previous year's contract? Specifically, how many times each line item was ordered the most previous contract year?
Answer: Quantities ordered on previous contracts could vary significantly from what is ordered in subsequent contracts, therefore this information will not be provided. Reference the PWS Paragraph C-1.2 “Quantities and/or the work to be performed is described herein and listed on separate sheets as Exhibits. These quantities are approximate and are provided as information only to assist in the preparation of bids. The quantities shown are the not-to-exceed (NTE) quantities; actual quantities may be less than shown but shall not exceed them. They are not guaranteed.”
Question 16: Can the government provide previous award's contract number?
Answer: Contract No. W912P5-15-D-0003.
Question 17: Can the government provide an excel ELINS of the bid schedule?
Answer: See the Government’s Response to Question No. 10.
Question 18: Can the government provide a copy of the sign in sheet of the site visit?
Answer: The sign in sheet will be added as an attachment.
Question 19: Once a mowing is ordered, how long does the contractor have to complete each location?
Answer: Reference PWS Section C-2.3 for mowing requirements.
Question 20: At the site visit, it was observed that several locations could require edging along sidewalks etc. Could the government confirm if edging is required, and if so a rough quantity of edging required?
Answer: Reference PWS Section C-2.3 for trimming/edging requirements.
Question 21: Are there any irrigation maintenance requirements by the contractor?
Answer: No.
Question 22: Can the government provide a square footage estimate of space to have insecticide and janitorial services applied?
Answer: Janitorial insecticide approximately 12,503 sq. feet Insecticide approximately 13,882 sq. feet
Question 23: Can the government clarify that the mowing is NOT to be done down to the water line?
Answer: Reference Amendment 0001, specifically Exhibits C-2.1 thru C-2.15.
Question 24: Can the government provide mowing maps?
Answer: See the Government’s Response to Question No. 23.
Question 25: C-9, Boundary line marking - Can the government provide the last time the boundary line within the scope of work has been marked?
Answer: Lake Cumberland has 1255 miles of shoreline on an average year we complete 75 to 100 miles per year.
With an additional 120 performed by the Rangers in residential areas.
Question 26: Can the government provide sizes and capacities for the septic tanks to be pumped?
Answer: See answer to question number 11.
Question 27: Is the contractor responsible for major cleaning/ drift wood cleaning after a major weather event, such as the flooding event at Waitsboro, or will additional funds be allocated for the rehab?
Answer: Yes, routine task orders will be issued under normal weather conditions and non-routine task orders will be negotiated for unusually severe weather conditions.
Question 28: Will leaf removal require complete removal offsite, or will mulching and blowing throughout the tree line be acceptable?
Answer: Reference PWS Section C-3.2.t for leaf removal requirements.
Question 29: On the Bid Schedule Section C-5 in the Wolf Creek Solicitation #W912P520B0001 it shows items # 0065-0086 shall be Service Contract Labor Standards and items #0087-0114 shall be based on Construction Wage
Rate. But Section C-5.3 states that Service Contract Labor will be limited to items # 0070-0090 and Construction work will be limited to items #0091-0117.
Answer: The bid schedule is correct the PWS has been corrected to reflect the change in C-5.3.
SECTION M - EVALUATION FACTORS FOR AWARD
The following have been modified:
52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)
Portions of this solicitation are altered as follows:
Solicitation Amendment 0002
PROJECT TITLE: Lake Cumberland (Wolf Creek) O&M Requirement
PURPOSE: The purpose of this amendment is to:
1. Revise answer number 26, and
2. FAR 52.252-3, Alterations in Solicitation, is updated
There will be no further questions answered after this amendment.
Solicitation Amendment 0001
PROJECT TITLE: Lake Cumberland (Wolf Creek) O&M Requirement
PURPOSE: The purpose of this amendment is to:
1. Provide the Site Visit Sign in Sheet from the Pre-Bid Site Visit held 03 December 2019.
2. Provide answers to questions asked during solicitation question period.
3. Provide revised Exhibit C-3.1 thru C-3.4 and add new Exhibit C-2.1 thru C-2.15.
4. Extend the bid closing date to from December 23, 2019 to January 07, 2020, and
5. C-5.3 in the PWS has been revised
(End of Summary of Changes)